1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina AR B.A.URB.TSP (P39584) Operation Name: AR B.A.URB.TSP (P39584) Project Stage: Implementation Seq.No: 33 Status: ARCHIVED Last Modified : Country: Argentina Approval FY: 1997 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): Secretaria de Transporte Key s Board Approval Original Closing 31-Dec-23 Planned Mid Term Review Last Archived ISR 28-Nov-21 Effectiveness 18-Mar-1998 Revised Closing 3-Jun-211 Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) Help in developing integrated urban transport strategies in Argentina's largest Metropolitan Areas. Has the Project Development Objective been changed since Board Approval of the Project? Yes No losure Authorized Public Disclosure Authorized Page 1 of 5

2 Component(s) Component Name Component Cost METROVIAS CONCESSION 5. REHABILITATION OF SUBWAY LINE A 63. TRANSPORT SYSTEMS INTEGRATION 7.3 ENV. MONITORING & TRAFFIC SAFETY 15.1 INSTITUTIONAL FRAMEWORK HEALTH COMPONENT 5.25 TRANSPORT INTEGRATION (improvement works to 8 suburban railway stations in AMBA) 23.5 TRAFFIC SAFETY (7 road/rail crossings in AMBA) 36.8 REHABILITATION LINE A (minor works).7 INSTITUTIONAL STRENGTHENING 13.2 METROVIAS CONCESSION 5. REHABILITATION OF SUBWAY LINE A 63. TRANSPORT SYSTEMS INTEGRATION 7.3 ENV. MONITORING & TRAFFIC SAFETY 15.1 INSTITUTIONAL FRAMEWORK HEALTH COMPONENT 5.25 TRANSPORT INTEGRATION (improvement works to 8 suburban railway stations in AMBA) 23.5 TRAFFIC SAFETY (7 road/rail crossings in AMBA) 36.8 REHABILITATION LINE A (minor works).7 INSTITUTIONAL STRENGTHENING 13.2 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Implementation Status Overview The project has achieved its objectives despite having been traversed the difficult Argentine crisis of 21/22. The metro line A is fully rehabilitated, although some connexions in the signaling system will be finalized, these do not affect the functionality of the line. In fact, line A has increased its patronage despite the rolling stock not being renewed by the concessionaire. The support given to the metro concessionaire at the beginning of the project meant that the government complied with its obligations according to the concession agreement, contributing to the stable continuity of the concession. Page 2 of 5

3 The project has been extremely successful in improving safety and transport integration through the construction of a major transfer center in Moreno, facilitation transfer from the bus system to rail. In addition, to 12 road/rail underpasses that have improved traffic crossings at major rail road intersections. The Additional Finance of this loan helped enhance the above results, but also expanded them through the improvement of urban environment around more than thirty suburban railway stations. The effect has been significant in the access to the station and the upgrading of the urban environment. The full impact of these intervention is being assessed in an ex-post study. Additionally, the project has been very successful in developing a battery of data and instrument for transport planning in the Buenos Aires region supported and maintained by thirty well trained young professionals. This will be the basis of the planning team in the future metropolitan Transport Agency. Finally, the project has managed to support and develop, in some cases, in other Metropolitan Areas transport planning and urban transport support projects with a comon vision. The Metropolitan Areas include Rosario, Posadas, Cordoba, Mendoza and Tucum. Results Project Development Objective Indicators Regarding "Support the infrastructure improvements..." Completion of Line A rehabilitation as a % of Line A rehabilitation 1% Regarding the PDO "Assist in improving..." Replacement of at-grade road/rail crossings with grade separations (Number of grade separations completed) 12 Page 3 of 5

4 Regarding the DPO "Help in developing an integrated urban transport..." Carrying out a transport survey and building a rail/bus transfer center (Completion of subproject) OD Survey: completed Transfer Center: completed Intermediate Results Indicators Regarding "Support the private-public partnership..." Implementation of Basic Investment Program ( ) as a percentage of disbursement % 14-May-29 1% Data on Financial Performance (as of 8-Jun-211) Financial Agreement(s) Key s Project Loan No. Status Approval Signing Effectiveness Closing P39584 IBRD-4163 Closed 1-Dec Mar Jun-21 P39584 IBRD-7442 Effective 27-Mar Nov-27 9-Jan-28 3-Jun-211 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P39584 IBRD-4163 Closed USD P39584 IBRD-7442 Effective USD Disbursement Graph Page 4 of 5

5 Key Decisions Regarding Implementation The GOA through the PIU are committed to finishing all contracts that go beyond the loan closing date of June 3th 211 Restructuring History Board Approved on 27-Mar-27, Level two Approved on 1-May-21 Related Projects P14984-Buenos Aires Urban Transport -PTUBA - Additional Financing Page 5 of 5