1 Monitoring for Environment and Security in Africa (MESA) MESA and PUMA Status of deployment, User support and warranty IMAGINE A SPACE APPLICATION REVOLUTION 12th EUMETSAT User forum - 13/09/ Kigali Philippe RIERA 1

2 Supply Contract highlights 2

3 Supply Contract highlights Telespazio France: Supply Contract Management System Design & Validation Hardware integration & PHST (Logistics) Installation management and monitoring Thales Alenia Space: System Design estation2 integration (from JRC) Meteo France International: Synergie upgrade & integration Deployment Teams: On-site deployments On-site training 3

4 Supply Contract highlights Deployment teams ECOWAS : Etienne KENNE (Cameroon) IGAD : Peter MUTAI (Kenya) SADC : Abay ASSEFA (Ethiopia) CEMAC : Freddy FALANGA (DR Congo) IOC : Telespazio France 4

5 Supply Contract highlights Figures and challenges: 178 stations: 116 MESA (full & partial) and 58 PUMA + 4 training centres 600 PCs to integrate, configure and test 50 tons of equipment to pack and ship 49 countries meaning 49 different situations in terms of administrative processes, shipment, packing, export control, customs, transit agent, etc. 5

6 Supply Contract highlights MESA Supply Contract (2015) STATIONS UPGRADE NEW STATIONS PUMA2010 to PUMA stations AMESD to MESA 55 stations PUMA/MESA Training Centres 4 centres PUMA stations MESA 61 stations 6

7 Name Duration Scheduled Date T0 MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY Project Milestones Real Date Supply Contract highlights 13/05/ /05/2015 Contract signature KOM 3 weeks 03/06/ /06/2015 FAT 4 months1/2 27/09/ /12/2015 VGF start 8 months 13/01/ /06/2016 VGF end 1 month 13/02/ /07/2016 Detail Review of activity, infrastructure documentation, function and specification Design validation and starting of deploiement of 7 references station Starting of validation of 7 references station with ISO 1.0,.3 version End validation of 7 references station and sending of the VGF report FPA 18 months 13/11/2016 Full Provisionall Aceptance End SW warrantly End HW warrantly 30 months 13/11/2017 End of software warrantly 36 months 13/11/2019 End of hardware warrantly 7

8 Deployment status - TULEAP 8

9 Pending issues Tax exemption and Customs clearance: Average time = 40 days Niger, Angola, Benin, South Africa 9

10 Pending issues Site surveys : 13 % missing RIC RETURNED PENDING TOTAL % Completed MOI % UoG % ICPAC % CICOS % AGRHYMET % BDMS-CSC % ACMAD % TOTAL % 10

11 Pending issues Antenna slabs : 57 % not built! RIC Slab Ready Slab Not Ready TOTAL % Completed MOI % UoG % ICPAC % CICOS % AGRHYMET % BDMS-CSC % ACMAD % TOTAL % 11

12 Status of Deployments 12

13 Deployment Schedule vs initial planning 13

14 Schedule Deployment schedule : September Cameroon (continued) DRC (continued) Equatorial Guinea Ethiopia (Continued) Gambia Ghana Guinée Conakry Kenya (continued) Namibia Rwanda Sao Tomé Sudan Swaziland Tanzania 14

15 Schedule Deployment schedule : October Benin Burkina Faso Chad Comoros Djibouti Ivory Coast Lesotho Malawi Madagascar Mauritania Nigeria RCA Senegal South Africa South Sudan Zimbabwe Sierra Leone Guinee Bissau 15

16 Deployment schedule : November MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY Schedule Angola Eritrea Gabon Liberia Mozambique Seychelles Somalia Uganda 16

17 Users support -Tuleap One single Point of Contact : EUMETSAT Helpdesk by at ops@eumetsat.int or by phone at /3770 One single source of information: TULEAP at 17

18 Users support -Tuleap Tuleap is an Open Source Suite for Application Lifecycle Management tailored to follow-up MESA status for : Documentation Anomalies MESA/PUMA2015 Stations status and configuration Deployment Schedule 18

19 Users support -Tuleap Users Accounts : Account Type Occurrences EO Focal Point 58 Eumetsat 4 Government and Ministers 8 other 139 REC Focal Point 2 RIC Focal Point 16 STATION ADMIN 18 STATION FOCAL POINT 10 STATION USER 2 TA representative 7 TA Thematic Expert 44 Trainer 9 UA representative 36 19

20 Users support -Tuleap Follow and update Station information 20

21 Users support -Tuleap 21

22 Users support -Tuleap NCR creation and follow-up 22

23 Users support -Tuleap 23

24 Users support -Tuleap 24

25 Warranty 1 year Software warranty covering: Sending of security updates (dissemination) NCRs fixing 3 years Hardware warranty covering: Support to diagnostic Handling of local repair when feasible Replacement of failing device if local repair is not possible 25

26 26