Implementation Status & Results Serbia CORRIDOR X HIGHWAY PROJECT (P108005)

Size: px
Start display at page:

Download "Implementation Status & Results Serbia CORRIDOR X HIGHWAY PROJECT (P108005)"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Serbia CORRIDOR X HIGHWAY PROJECT (P108005) Report : ISR1437 Operation Name: CORRIDOR X HIGHWAY PROJECT (P108005) Project Stage: Implementation Seq.: 3 Status: ARCHIVED Last Modified : 23-v-2010 Country: Serbia Approval FY: 2010 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): K10 D.O.O Key s Board Approval 09-Jul-2009 Original Closing Planned Mid Term Review 31-Dec-2012 Last Archived ISR 03-May-2010 Effectiveness 06-v-2009 Revised Closing Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to increase transport efficiency and improve traffic safety on the three project sections of Corridor X, between Nis and Dimitrovgrad and Grabovnica and Donji Neradovac respectively, and to improve road management and road safety in Serbia. Has the Project Development Objective been changed since Board Approval of the Project? Component(s) losure Authorized Public Disclosure Authorized Component Name Component Cost Component 1 - two sections of the E-75 (32km) Component 2- One section of the E-80 (8,67km) Component 3 -Road Safety TA and Goods/Equipment 2.90 Implementation Assistance and Institutional Support Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview Whilst good progress has been made in all areas since the last full implementation support mission in April 2010, some procurement activities remain behind the original schedule. The civil works contractor for Lots 1 and 2 on the E-80 commenced work in April 2010and has made good progress on the Dimitrovgrad Bypass in clearing the site, constructing the access roads, and commencing earthworks and the construction of the structures (bridges and culverts). Page 1 of 5

2 Report : ISR1437 However, some procurement activities, including the tunnels (Lot 3) on the E-80 and the works on the E-75, the consultant supervision of the civil works on the E-80, and the procurement of consultants to undertake independent supervision of the social and environmental aspects on both the E-80 and the E-75, have fallen behind, markedly in some cases, the originally agreed schedule. The Bank team impressed on counterparts the importance of staying on schedule from this point, and ensuring that all outstanding works contracts, on both the E-80 and the E-75, are signed as early as possible in the next construction season. Results Project Development Objective Indicators Road User costs for road section Nis-Dimitrovgrad v-2010 Construction ongoing 1.00 Road user costs for road section Grabovnica to Donji Neradovac v-2010 in Euro cents per veh-km 1.00 Reduce rate of road crash related death and serious injury for road section Nis Dimitrovgrad v-2010 in Euro Cents per veh-km Ten percent less at end of project. Page 2 of 5

3 Report : ISR1437 Reduced rate of road crash related death and serious injury for road section Grabovnica and Donji Neradovac Custom Indicator Number v-2010 Construction not started yet on this section Action Plan for Reform of PEPS adopted Custom Indicator / Procurement started to hire consultant to prepare reform action plan. National Road Safety Strategy developed and launched Custom Indicator / Component has not started yet. Intermediate Results Indicators Roads constructed, non-rural Core Indicator Kilometers 23-v Page 3 of 5

4 Report : ISR1437 Number of km constructed/upgraded for E-75 section Custom Indicator Kilometers 23-v Number of km constructed/upgraded for E-80 Custom Indicator Kilometers 23-v-2010 Construction ongoing Lead agency for road safety established and operational Custom Indicator / 01-Oct-2009 Lead Agency established under new Road Safety Law, but not fully operational. Two road safety pilot projects implemented Custom Indicator / Data on Financial Performance (as of 12-Jul-2010) Financial Agreement(s) Key s 01-Oct-2009 Component has not started yet. Project Loan. Status Approval Signing Effectiveness Closing Page 4 of 5

5 Report : ISR1437 Project Loan. Status Approval Signing Effectiveness Closing P IBRD Effective 09-Jul Jul v-2009 Disbursements (in Millions) Project Loan. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IBRD Effective USD Disbursement Graph Key Decisions Regarding Implementation There are no key decisions on project implementation at this time. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Page 5 of 5