R.H. SHEPPARD CO., INC. HANOVER, PA QUALITY BY DESIGN SUPPLIER QUALITY MANUAL NINTH EDITION
|
|
- Rodger Warren
- 6 years ago
- Views:
Transcription
1 R.H. SHEPPARD CO., INC. HANOVER, PA QUALITY BY DESIGN NINTH EDITION
2 TABLE OF CONTENTS TITLE PAGE 1. SUPPLIER QUALITY SYSTEM REQUIREMENTS 1 2. PURCHASE ORDERS, SPECIFICATIONS AND PRINTS 1 3. REQUESTS FOR PRINT CHANGES 1 4. REQUESTS FOR DEVIATIONS FROM PRINTS 2 5. PACKAGING 2 6. ON TIME DELIVERIES 3 7. PPAP REQUIREMENTS 3 & 4 8. MATERIAL COMPLAINT NOTICES (MCN) MCN ISSUE CORRECTIVE ACTION RESPONSE NOT REQUIRED CORRECTIVE ACTION RESPONSE REQUIRED SECOND NOTICE MCN 5 SAMPLE MCN S 6 & 7 Rev. 9, PAGE i
3 1. SUPPLIER S QUALITY SYSTEM REQUIREMENTS The minimum quality system required to do business with the R. H. Sheppard Company is ISO 9001:2008. Proof of certification to this standard must be available upon request. All ISO9001 certified suppliers are required to develop their quality systems to conform to the ISO/TS standard utilizing the AIAG standards listed below. These standards are necessary to provide the R.H. Sheppard Company with well documented PPAP s as required and assure the appropriate controls are in place. FMEA - Potential Failure Mode & Effects Analysis (Design & Process) MSA - Measurement Systems Analysis PPAP - Production Part Approval Process SPC - Statistical Process Control APQP - Advanced Product Quality Planning & Control Plan Current revisions of these manuals can be obtained from the Automotive Industry Action 2. PURCHASE ORDERS, SPECIFICATIONS AND PRINTS All confirmed purchase orders will be sent to the supplier with copies of the latest revisions of the applicable Sheppard prints, or Part Identification Sheets and specifications. The supplier should discard any previous revisions of these documents and use those provided with the Sheppard Purchase Order. 3. REQUESTS FOR PRINT CHANGES If it is determined by the supplier that a dimension or other print specification require changes, the supplier shall contact the Sheppard Purchasing Manager via and request a print change. The supplier shall provide all necessary details of the requested change to the Purchasing Department. Following RHSCo. review of the request, the Purchasing Department will inform the supplier of the decision in writing via . Rev. 9, Page 1 of 7
4 4. REQUEST FOR DEVIATION FROM PRINT (Prior to, During or Following Manufacturing) The supplier shall contact the Sheppard Purchasing Department via if a problem is discovered in complying with any print requirement and report the following information as a minimum: 1. Sheppard Part Number; 2. Sheppard Purchase Order Number; 3. Description of the problem; 4. Quantity of the parts involved; 5. Duration of this condition; 6. The proposed corrective action for preventing future occurrences of the reported condition. This information will be reviewed by Sheppard Purchasing, Quality and Engineering, as necessary. Following review, the supplier will be contacted by the Purchasing Department on the acceptance or rejection of the deviation request in writing via e- mail. 5. PACKAGING Unless otherwise stated in the Sheppard purchase order, all parts and material shall be packaged for shipment in accordance with the supplier s standard packaging procedures. The methods and materials used in packaging shall assure adequate protection against damage during handling and delivery. Rev. 9, Page 2 of 7
5 6. ON TIME DELIVERIES The R. H. Sheppard Co., requires 95 percent on time delivery performance from its suppliers. If the required delivery of parts as stated on the Sheppard Purchase Order cannot be met, the supplier shall immediately contact the Sheppard Purchasing Department to determine if the delay would have a negative affect on our production. The R. H. Sheppard Co., would be subject to very severe penalties from our customers if we caused delays or stoppages on any of our customers production lines due to poor delivery performance. The R. H. Sheppard Co., reserves the right to assess suppliers penalties and/or recoup related costs if a supplier causes a delay or stoppage on an assembly line. 7. PPAP REQUIREMENTS The below guide describes when a PPAP will be required and what level of PPAP should be performed, we have identified various conditions where a PPAP will be required, however, should you have a question on a different situation please contact R.H. Sheppard Purchasing or Quality Department for further direction. 7.1 No PPAP: This MAY be allowed for commercially available product from a catalog, must be approved by quality. 7.2 Level 1 PPAP: Is required when purchasing commercially available product. A PSW/Dimensional layout is required. 7.3 Level 1 PPAP: New Tooling (dies) a Level 1 PPAP along with a PSW and full dimensional layout is required. 7.4 Level 3 PPAP: MATERIAL CHANGES, all material changes must be submitted to Purchasing to receive authorization from Product Engineering to make parts and proceed with testing. A Level 3 PPAP is required and there is a 300 piece minimum PPAP run unless otherwise approved by Quality. Level 3 PPAP is required as defined by the AIAG Manual. Rev. 9, Page 3 of 7
6 7.5 Level 3 PPAP: Required for any parts manufactured to a RH Sheppard print/design. There is a 300 piece minimum PPAP run unless otherwise approved by Quality. Level 3 PPAP is required as defined by the AIAG Manual. 7.6 Level 3 PPAP: MOVING TO A NEW SUPPLIER required for any parts manufactured to a RH Sheppard print/design. A Level 3 PPAP is required as defined by the AIAG Manual. 7.7 Level 1 PPAP: FAMILY OF PARTS, when a part has a Level 3 PPAP performed and there are subsequent like parts, a Level 1 PPAP and PSW with dimensional layout is acceptable for any additional parts in that family. 7.8 Level 3 PPAP: MAKING ANY PROCESS/PLANT MOVES CHANGES required for any parts manufactured to a RH Sheppard print/design. There is a 300 piece minimum PPAP run unless otherwise approved by Quality. Level 3 PPAP is required as defined by the AIAG Manual. All procedures will work in conjunction with the AIAG PPAP Manual. Copies of this manual may be obtained by visiting: Rev. 9, Page 4 of 7
7 8. MATERIAL COMPLAINT NOTICE (MCN) PROCEDURE 8.1 MCN ISSUE A Material Complaint Notice (MCN) will be issued to the supplier for any discrepant shipment received at R. H. Sheppard. The Responsibility Description section of the MCN will contain instructions stating whether or not written corrective action is required. 8.2 CORRECTIVE ACTION RESPONSE NOT REQUIRED On the issued MCN if under responsibility a #2 is present, no corrective action response is required. It is recommended that the supplier investigate the reported condition(s) and implement necessary changes. 8.2 CORRECTIVE ACTION RESPONSE REQUIRED On the issued MCN if under responsibility a #1 is present, a corrective action response is required. A corrective action report, utilizing the 8D format, shall be completed by the supplier. This corrective action report shall contain as a minimum information on the following: The immediate containment action taken The root cause The proposed corrective action plan The implementation date of the permanent corrective action The verification of Corrective Action take for effectiveness The supplier shall submit the completed MCN response to the Sheppard Purchasing Department within 30 calendar days of receipt. Additional information concerning 8D response, Corrective Action format may be obtained from the American Society for SECOND MCN NOTICE If the initial corrective action response is not received at R. H. Sheppard within the required time, a Second Notice MCN will be issued. Included on the front page of the MCN will be a reminder note stating that the written corrective action report is overdue. A 30 calendar day response time from the day of receipt will be required on this notice. A LACK OF RESPONSE WILL HAVE A NEGATIVE EFFECT ON SUPPLIER RATINGS AND FUTURE BUSINESS WITH R.H. SHEPPARD. Rev. 9, Page 5 of 7
8 SAMPLE MATERIAL COMPLAINT NOTICE Requiring CAR: R. H. SHEPPARD CO., INC. Rev. 9, Page 6 of 7
9 SAMPLE MATERIAL COMPLAINT NOTICE Not Requiring CAR R. H. SHEPPARD CO., INC. Rev. 9, Page 7 of 7
Supplier Quality Manual (QQS )
Monticello Spring Corporation Quality Management System Supplier Quality Manual (QQS 100.00) 1.0 Introduction 1.1 Scope The details stipulated in this manual are the minimum mandatory requirements for
More informationSupplier Quality Standard
Supplier Quality Standard Sherex Industries & Sherex Fastening Solutions "First Time Quality at the Source" Through Teamwork Supplier Quality Standard Edition: Rel. September 6, 2007 This document is controlled
More informationProgressive Metal Forming, inc Hall Road Hamburg, MI 48139
SUPPLIER QUALITY MANUAL Progressive Metal Forming, inc. 10850 Hall Road Hamburg, MI 48139 www.pmfdraw.com Rev. 1/30/17 Page 1 of 11 TABLE OF CONTENTS 1.0 INTRODUCTION. 3 2.0 SUPPLIER QUALITY GUIDELINES...3
More informationSupplier Quality System Requirements Manual
Supplier Quality System Requirements Manual This manual available ON-LINE at www.axletech.com website Quality Policy "AxleTech International is committed to exceeding our customers expectations by continually
More informationEdition: Revision 09, February 19, This document is controlled by: Mayco International, LLC. Edited by
Working together as a team QUALITY AT THE SOURCE Page: 2 of 24 Supplier Quality Standard Edition: Revision 09, February 19, 2018 This document is controlled by: Mayco International, LLC Edited by Mayco
More informationSUPPLIER GUIDELINES MANUAL
1.0 INTRODUCTION 1.1 This guidelines manual defines the minimum requirements for Supreme Machined Products Co.; Inc. LTD (to be referenced as Supreme throughout the document) Supplier s and does not supersede
More informationSupplier Quality Requirements Manual
Supplier Quality Requirements Manual Revision D 05/31/2017 Page 1 1.0 Purpose The purpose of this manual is to communicate the quality requirements pertaining to the systems, processes, tools and procedures
More informationMetal Powder Products Company
Metal Powder Products Company Supplier Quality Manual Revision 1 Page 1 of 10 Introduction 1. Purpose: This manual has been created for Metal Powder Product s (MPP) Production, Prototype and Service Suppliers.
More informationSUPPLIER QUALITY MANUAL For ISO/TS16949:2009 (Level 1)
1 of 8 General Introduction Standard Motor Products, Inc. Greenville Operations (SMP) is a registered TS-16949 facility. SMP has earned a reputation for providing products of consistent quality, competitive
More informationWestern Diversified Plastics, LLC. Supplier Requirements Manual
Western Diversified Plastics, LLC. Supplier Requirements Manual Revision Date: 12/10/2019 TABLE OF CONTENTS 1.0 Introduction.. 3 2.0 WDP Supplier Policy.. 4 3.0 Scope... 4 4.0 Launch Readiness Measures...
More informationSUPPLIER MANUAL SUPPLIER MANUAL
SUPPLIER MANUAL Rev.: 4, 01.11.2013 Page: 1 of 9 IER-QSF 003 TABLE OF CONTENTS PAGE 1. INTRODUCTION 2 2. SCOPE 3 3. REFERENCE MATERIAL 3 4. SUPPLIER APPROVAL PROCESS 3 5. PRODUCT APPROVAL PROCESS 5 6.
More informationSupplier Quality Manual
QP #: 8.4.1.2 Rev. #:0 Date Issued: 12/19/17 Date Revised: Page 1 of 8 Supplier Quality Manual Approved by: Mike Cornwell ( VP of Materials) Date: 12/19/17 1.0 Purpose: To provide Suppliers of BRC Rubber
More informationSection Table of Contents Page Number
Derby Fabricating Solutions Section Table of Contents Page Number 1.1 Introduction 2 1.2 Derby Quality Policy 2 1.3 Environmental Policy 2 1.4 Supplier Requirements Manual 2 1.5 Social Accountability 2
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL QD-SUPPLIER-QUALITYMANUAL 1 of 13 02.20.15 TABLE OF CONTENTS Page A. Goal 3 B. Purpose 3 C. Approach 3 D. Applicability 3 E. Implementation 3 F. Zero Defects Policy 3 Section 1:
More informationAgreement. Between. Cooper Standard. (Hereafter referred to as the CS ) And. (Hereafter referred to as the Supplier )
Global Supplier Quality Manual Revision 1 Agreement Between Cooper Standard (Hereafter referred to as the CS ) And (Hereafter referred to as the Supplier ) This agreement is made between the above named
More informationSUPPLIER MANUAL. Griffith Rubber Mills - HQ 2625 Northwest Industrial Street Portland, Oregon 97210
SUPPLIER MANUAL Griffith Rubber Mills - HQ 2625 Northwest Industrial Street Portland, Oregon 97210 TABLE OF CONTENTS Page Title 1... Introduction, Purpose, Scope Quality Policy, Certification & Exemptions
More informationJSP Supplier Quality Assurance Manual
Changes to the Supplier Quality Assurance Manual: The 2011 has been reviewed for updates and revisions needed to keep our forms, policies and procedures current. The updates will be communicated to suppliers
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL 2 TABLE OF CONTENTS PAGE 1. INTRODUCTION 3 2. SCOPE 4 3. REFERENCE MATERIAL 4 4. SUPPLIER APPROVAL PROCESS 4-6 5. PRODUCT APPROVAL PROCESS 6 6. ON-GOING PRODUCTION 6-7 7. SUPPLIER
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 6/26/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 8/2/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationSupplier Requirements Manual
Supplier Requirements Manual 1.0 Control Responsibility TABLE OF CONTENTS 1.1 Proprietary Information Sharing 1.2 Purpose & Approval 1.2.1 Scope 1.3 Quality Systems Management & Evaluation 1.3.1 QMS 1.3.2
More informationTRICO PRODUCTS PUR-C-P106-A
TRICO PRODUCTS PUR-C-P106-A October 9, 2009 Supplier Guide Page 1 of 14 TRICO PRODUCTS PUR-C-P106-A October 9, 2009 Page 2 of 14 NAME: TRICO Supplier Guide PURPOSE: The purpose of this document is to communicate
More informationVernay Quality System Supplier Quality Manual
Table of Contents Revision: G Approvals: Manager, Quality Systems/Improvements NA Purchasing Manager Section A Overview Revision: G Page Approval 1 Table of Contents 2 Section A Section B Section C Section
More informationSupplier Quality Manual PREPARED AND MAINTAINED BY FIRESTONE INDUSTRIAL PRODUCTS COMPANY DIVISION OFFICE 250 W. 96 th Street INDIANAPOLIS, IN 46260
Supplier Quality Manual PREPARED AND MAINTAINED BY FIRESTONE INDUSTRIAL PRODUCTS COMPANY DIVISION OFFICE 250 W. 96 th Street INDIANAPOLIS, IN 46260 Firestone Industrial Products Quality Policy We will
More informationSupplier Quality Systems Requirements Manual
Supplier Quality Systems Requirements Manual Brink Towing Systems Version: 2.4 Date: 23-07-2018 Changed text in blue Page 1 / 9 Table of Contents 1. Introduction 3 1.1 Scope 3 1.2 Purpose 3 1.3 Background
More informationSUPPLIER QUALITY REQUIRMENTS MANUAL (SQRM)
SUPPLIER QUALITY REQUIRMENTS MANUAL (SQRM) 11/3/2008 Page 1 of 12 PURPOSE The purpose of this manual is to provide Suppliers with the DeltaTech Control (DTC) requirements for various items related to the
More informationGuideline for Suppliers: Initial Sampling
1. Purpose Regulation of the procedure for production process and product approval (initial sampling) with the goal to provide a documented proof that the requirements outlined and agreed upon in drawings,
More informationSTANDARD. S P-O Svedlund UTDH Markku Backholm. SDT Eva Ivrell Hedensjö UTDH Iréne Klingberg
1(13) SCANIA CUSTOMER SPECIFIC REQUIREMENTS Contents Changes from previous issue... 1 General... 1 1 General requirements... 2 2 Human rights... 2 3 REACH legislation... 3 4 Environmental protection...
More informationTable of Contents. 1.0 Introduction 1.1 Overview 1.2 Customer Responsibilities
1400 Lunar Drive Wapakoneta, OH 45895 Supplier Manual Table of Contents 1.0 Introduction 1.1 Overview 1.2 Customer Responsibilities 2.0 Supplier Quality Expectations 2.1 Quality System Requirements 2.2
More informationRevcor Supplier Quality Manual
Revcor Supplier Quality Manual Documentation The Revcor is governed by comprehensive documentation as referenced herein. Procedures, work instructions, practices, forms, drawings, and similar documentation
More informationSupplier Requirement Manual. Preface
1 Preface This manual has been created to assist our suppliers in understanding the purchasing expectations and quality requirements for products supplied to RCO Engineering. The manual is also a tool
More informationSupplier Quality Manual
Supplier Quality Manual Second Edition Issued: August 25, 2015 Meeting Our Customers Needs Through Business Excellence First Edition All rights reserved under the copyright laws. 1 Marion Body Works Inc.
More informationSupplier Quality Manual
Supplier Quality Manual February 2010 Page 1 of 6 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Supplier Assessments 5.0 Advance Product Quality Planning 6.0 First Article
More informationSP-Q-SG 002 Supplier Guidelines for the APCB. Production Part Approval Process (PPAP)
Supplier Guidelines for the APCB Production Part Approval Process (PPAP) These supplier guidelines complement and clarify the requirements defined in the AIAG PPAP manual and the APCB Customer Specific
More informationMERIT Customer Specific Requirements
MERIT Customer Specific Requirements For Use with ISO 9001:2015 And IATF16949:2016 Effective March 31, 2018 1 Table of Contents INTRODUCTION /BUSINESS PHILOSOPHY... 6 1. SCOPE... 7 1.1 Scope General...
More informationSupplier Quality System Survey
Supplier Division Address Date: Quality Contact: Reports to: Title: Title: Phone Fax e-mail Plant size (ft 2 ): Union: Contract expires: Total Employment: Direct Labor: Shifts: QA employees: This report
More informationSupplier Quality Assurance Manual
Supplier Quality Assurance Manual Revised: 0128 January Jul 2014 2010 1. Introduction The purpose of the Supplier Quality Assurance Manual is to straightforwardly communicate to our current and potential
More informationBlue Chip Engineered Products Supplier Quality Manual
Blue Chip Engineered Products Supplier Quality Manual Revision Date 07/09/2013 Page 1 Table of Contents A. Goal B. Purpose C. Approach D. Applicability E. Implementation F. Zero Defects Policy Section
More informationIATF - International Automotive Task Force IATF 16949:2016 Frequently Asked Question (FAQ)
:2016 Frequently Asked Question (FAQ) :2016 1 st Edition was published in October 2016. In response to questions from the IATF recognized certification bodies and stakeholders, the following questions
More informationALCO Plastics, Incorporated SUPPLIER QUALITY SYSTEM REQUIREMENTS MANUAL
INTRODUCTION Revision Level: A 5/3/06 Revision Level: This manual is provided to the Suppliers of ALCO Plastics, Inc. to communicate the Quality System Requirements and Assessment process. Purchased materials
More informationMetric Manufacturing Supplier Manual
Metric Manufacturing Supplier Manual This Manual applies to all suppliers of Metric Manufacturing Co. Compliance to all requirements within this manual, as well as the general terms and conditions, are
More informationVisteon Corporation. Customer Specific Requirements Fifth Edition. For Use with ISO/TS 16949:2009
Visteon Corporation Customer Specific Requirements Fifth Edition For Use with ISO/TS 16949:2009 SP-WW-SG-1007 Page 1 of 9 Printed Copies of this I. Introduction Quality professionals from Visteon collaboratively
More informationSupplier Quality Manual
Classification: QMS Created By: Jeff Teel 06/07/2016 Document No.: Mark "X" where applies Firestone Controlled Document New First Issue Published: Revision X Supersedes Issue Published: 01/12/2007 Three-Year
More informationVU Manufacturing Supplier Quality Manual
Supplier Quality Manual Revision 08, February 26, 2018 Table of Contents Section Preface Page 3 A. Quality System Page 4 B. Advanced Quality Planning Page 4 C. Continuous Improvement Page 5 D. Production
More informationSupplier Quality Requirements FSQ01
Supplier Quality Requirements FSQ01 1 Change Revision Level Date Introduced 0 25/06/2013 2 1. Scope 2. Code of Conduct 3. Acronyms and Definitions 4. Prohibited and Restricted Materials Policy 5. Quality
More informationCUSTOMER SPECIFIC REQUIREMENTS FOR ISO/TS APPLICABLE TO FIASA/POWERTRAIN SUPPLIERS
Betim, July 27 th, 2012. CUSTOMER SPECIFIC REQUIREMENTS FOR ISO/TS 16949 APPLICABLE TO FIASA/POWERTRAIN SUPPLIERS Updates and replaces, from 08/06/2012, the "LETTER OF SPECIFIC REQUIREMENTS" from FIASA
More informationSupplier Quality Assurance Manual
Supplier Quality Assurance Manual Note: This manual is electronically controlled. The most current revision can be obtained on line through the TASUS website link www.tasus.com Click downloads Hardcopies
More informationSupplier Quality Requirements Guide
Supplier Quality Requirements Guide CVTECH-IBC INC., 300 LABONTÉ, DRUMMONDVILLE, QC J2C 6X9, CANADA TEL: (819) 477-3232 FAX: (819) 477-4705 TABLE OF CONTENTS 1- Introduction... Page 3 1.1 Purpose... Page
More informationSUPPLIER MANUAL Released 5/16/2012 Revised 11/12/2016
SUPPLIER MANUAL Released 5/16/2012 Revised 11/12/2016 TABLE OF CONTENTS 1.0 Introduction 1.1 Purpose of Supplier Requirements 1.2 Scope 2.0 Quoting 3.0 Advance Product Quality Planning (APQP) 3.1 APQP
More informationSUPPLIER QUALITY MANUAL
Global Supplier of Automotive Tire Products & Refrigeration Components SUPPLIER QUALITY MANUAL Air Controls Products, LLC Oxford, NC Air Controls Products maintains sole control rights to the master copy
More informationGENERAL QUALITY REQUIREMENTS
SUPPLIER QUALITY MANUAL Ref.: 05.04 LIR Ind. : 3 Date : 07.11.2012 Page : 1 / 10 Modified by : Dumitrita DALEA Validated by : Gelu MATEESCU Verified by : Adina Halinga GENERAL QUALITY REQUIREMENTS This
More informationIts purpose is to define the approval process of new or revised parts, or parts resulting from new or significantly revised production methods.
SUPPLIER PPAP HANDBOOK NORTH AMERICA Revision D May 24, 2018 Table of Contents Table of Contents 1 Foreword.. 2 Production Part approval Process (PPAP) Purpose.. 3 When is a Submission Required?. 3 Significant
More informationSupplier Quality Manual
Supplier Quality Manual Table of Contents Challenge Quality Policy... 4 Challenge Objectives... 4 Expectations & Philosophy... 5 SECTION 1- Introduction... 6 A. Policy and Vision... 6 B. Purpose... 6 C.
More informationSUPPLIER QUALITY REQUIREMENTS MANUAL
SUPPLIER QUALITY REQUIREMENTS MANUAL Manufacturing Locations: Nyloncraft Nyloncraft 616 W. McKinley Ave. 1640 East Chicago Road Mishawaka, IN 46545 Jonesville, MI 49250 (574) 256-1521 (517) 849-9911 Document
More informationSupplier Quality Manual
Supplier Quality Manual SC-002 Revision: 09/24/2018 Table of Contents Challenge Quality Policy. 3 Challenge Quality Objectives..3 Expectations and Philosophy...4 Section 1- Introduction.... 5-6 A. Policy
More informationGlobal Supplier Quality Process Manual. Quality Processes for Suppliers to Merkle-Korff Industries. Abstract
Global Supplier Quality Process Manual Quality Processes for Suppliers to Merkle-Korff Industries Abstract This document contains quality requirements for suppliers to Merkle-Korff Industries and provides
More informationSupplier Quality Expectations for 2011
Supplier Quality Expectations for 2011 May 2, 2011 FXI Quality Policy The FXI Team is committed to do our jobs right the first time every time in order to obtain the highest level of customer delight.
More informationSupplier. Quality. Manual
DEPARTMENT: Quality Assurance Title: Supplier - Quality Manual ISSUED ON: 29-Jul-09 PAGE 1 of 12 Supplier Quality Manual Distribution to: Electronically controlled. If this document is in hard copy it
More informationGlobal Supplier Quality Manual. Revision 4
Global Supplier Quality Manual Revision 4 Introduction 1. Purpose: This manual has been created for Cooper Standard s (CS) Production, Prototype and Service Suppliers. The manual includes all CS locations
More informationSupplier Quality Requirements Manual
Supplier Quality Requirements Manual ISO-020-1 Revision G January 20, 2012 ISO-020-1 Rev G 01/20/12 Page 1 of 17 Table of Contents Quality Commitment and Expectations... 3 SECTION 1- Introduction... 4
More informationTable of Contents. 1.0 Purpose. 2.0 Scope. 3.0 Quality System Requirements. 4.0 Approved Supplier List. 5.0 Supplier Assessments
Issued 2/6/2009 Revision: 2/13/2017 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Approved Supplier List 5.0 Supplier Assessments 6.0 Advance Product Quality Planning (APQP)
More informationSupplier Quality Assurance Manual (SQAM)
Supplier Quality Assurance Manual (SQAM) March 2018 Edition Page 1 of 18 ***When printed this is copy only, Electronic version is Master*** FD 700392 Rev: 03/15/2018 Table of Contents 1. Introduction Pg.
More informationDaimlerChrysler (Chrysler Group) Customer-Specific Requirements
DaimlerChrysler (Chrysler Group) Customer-Specific Requirements For Use With ISO/TS 16949 Second Edition September, 2005 1. Scope ISO/TS 16949 and this document define fundamental quality system requirements
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL LM-QU-PA-008 Revision Date:7/13/18 LM-QU-PA-008 Revision Date:7/13/18 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Approved Supplier List 5.0 Supplier
More informationSupplier Manual Rev /15
Supplier Manual Rev. 01-05/15 www.kamax.com Operations Europe KAMAX GmbH & Co. KG Petershütter Allee 29, 37520 Osterode am Harz, Germany Dr.-Rudolf-Kellermann-Str. 2, 35315 Homberg/Ohm, Germany Am Kreuzweg
More informationGlobal Supplier Development & Guidelines Manual
Carr. Qro-SLP Km 28.5 Lote 25-2 Mz. 1 Parque Industrial Querétaro Qro +011-52-442-211-3700 www.narmco.com Global Supplier Development & Guidelines Manual Rev. 3 Page 1 of 25 INTRODUCTION The Global Supplier
More informationHow to perform PPAP Level 1 Level 2 Level 3 Level 4 Level 5
How to perform PPAP The process of completing a PPAP submission is complex. This detailed process is a collection of key elements that must be completed to verify that the production process will produce
More informationPPAP Process Checklist \ Sign Off Sheet Instructions
Global Supply Management PPAP Process Checklist \ Sign Off Sheet Instructions In addition to these requirements, you must meet all Nexteer Automotive Supplier Requirements noted in the Nexteer Automotive
More informationGLB QM 02. Supplier Quality Manual 05. 3/2/18 Supplier Quality 1 of 19. Issue Date Issuing Department Page
3/2/18 Supplier Quality 1 of 19 3/2/18 Supplier Quality 2 of 19 Table of Contents 1.0 Introduction 3 2.0 Manual 4 2.1 Application 4 2.2 Quality Management System of the Supplier 4 2.3 Quality Management
More informationCustomer Specific Requirements. For Use with ISO/TS16949 And ISO 9001
Customer Specific Requirements For Use with ISO/TS16949 And ISO 9001 Effective: October 9, 2015 Introduction This document contains BWI companion requirements to the current revision of ISO/TS16949. Each
More informationMANUAL SUPPLIER S QUALITY MANUAL
MANUAL Rába Automotive Component Manufacturing Ltd Identification 1.3 1/8 Coming into force 28. 01. 2009 SUPPLIER S QUALITY MANUAL Prepared by Checked by Approved by Name Signature Date János KENYERES
More informationSupply Chain Supplier Quality Manual. Creation Date: 19 th September 2012 Last Updated: February 16, 2016 Revision Number: 03 Document Number: AQM005
Supply Chain Supplier Quality Manual Creation Date: 19 th September 2012 Last Updated: February 16, 2016 Revision Number: 03 Document Number: AQM005 1 Introduction Policy Statement Analogic suppliers have
More informationSUPPLIER MANUAL Quality Policy
SUPPLIER MANUAL Quality Policy Prettl, Kurz Kasch is committed to providing our Customers with quality products. We will develop, maintain and continually improve our quality systems to ensure Customer
More informationSuppliers Quality Assurance Manual
Suppliers Quality Assurance Manual Revision: 10 Issued Date: 9 July 2018 2016 Marketing Plan Avenida 5 de Febrero 2115 Fracc. Industrial Benito Juárez Santiago de Querétaro, Querétaro C.P. 76120 Tel: +52
More informationCustomer Specific Requirements. For Use with ISO/TS16949 And ISO 9001
Customer Specific Requirements For Use with ISO/TS16949 And ISO 9001 Rev. 13 - Effective Date: Oct. 27, 2017 Introduction This document contains BWI companion requirements to the current revision of ISO/TS16949.
More informationSupplier Quality Specification 3DS Document P14 Rock Hill, South Carolina Revision A
Supplier Quality Specification 3DS Document 51000-P14 Rock Hill, South Carolina Revision A Revision History Change Description Revision Date All New Release 6/26/16 A Updated supplier classification section,
More informationAnnex 1. Customer Specific Requirements For Use With ISO/TS16949
Annex 1. Customer Specific Requirements For Use With ISO/TS16949 Issue: July 2015 CONTENTS I. Introduction... 3 II. Customer Specific Requirements Document Structure... 3 III. Reference Documents... 3
More informationTable of Contents. 1 P age. Page
11/22/16 / Rev B Table of Contents Page 1.0 Overview 3 1.1 Application and Approach 3 1.2 Distribution 4 1.3 Introduction 4 1.3.1 Scope 4 1.3.1.1 Off The Shelf Items 4 1.3.1.2 Expected Quality System of
More informationSUPPLIER QUALITY MANUAL
Work Instruction Standard Locknut, LLC Supplier Quality Manual Doc. No. SQM-01 Page 1 of 11 Initial Date 11/1/2009 Rev. 4 Prepared By Dwight Beaty Revised By Shannon Smith Rev. Date 9/12/12 Approvals Purchasing
More informationMontaplast of North America, Inc.
Montaplast of North America, Inc. Supplier Quality Manual Page 1 of 20 Table of Contents 1.0 Purpose pg. 3 2.0 Scope pg. 3 3.0 Quality System Requirements pg. 3 4.0 Approved Supplier List pg. 4 5.0 Supplier
More informationSTANDARD. Date SP Jan F Visscher UTMS Michaela Bundschuh
1(19) Distribution: Scania, Suppliers SCANIA CUSTOMER SPECIFIC REQUIREMENTS Contents Changes from previous issue... 1 1 General... 2 2 Supplier Portal... 2 3 Scania Standards... 2 4 Customer Property...
More informationWorks Standard. PPAP - Production Part Approval Process
Works Standard PPAP - Production Part Approval Process WN 50 020 1 AREA OF APPLICATION AND PURPOSE This works standard contains the general, basic requirements for the approval of vendor parts for production.
More informationConMet Supplier Quality Manual
ConMet Supplier Quality Manual Revision: 11/2/17 Uncontrolled Copy Page 1 Table of Contents Title Page Introduction 3 Supplier Quality Systems Requirements 4 Supplier Social Responsibility 4 Confidentiality
More informationSUPPLIERS MANUAL. Revision: Copyright Interconnect Product Assembly AS Printed NB! Paper copies are uncontrolled documents
1 (20) 1.0 Purpose and function of this manual 1.1. Vision It is IPA's goal to develop a working relationship with our suppliers that mirrors the Vision and Guiding Principles on which IPA s business philosophy
More informationSupplier Quality Manual
Supplier Quality Manual 1 1. Introduction Scope Purpose Application Implementation 2. Purchasing Expectations Terms and Conditions Engineering / Technical Support Customer Support Resources Pricing Consistent
More informationSUPPLIER QUALITY ASSESSMENT
Supplier Organization Name: Supplier Number: Street Address: Date of This Audit: City, State, Zip Code: Date of Last Audit: Country: of Employees: Main Phone Number: of Buildings/Size: Fax Number: Principal
More informationConsolidated Metco, Inc. Supplier Quality Manual
Consolidated Metco, Inc. Supplier Quality Manual Revision: 12/20/17 Uncontrolled Copy Page 1 Table of Contents Title Page Introduction 3 Supplier Quality Systems Requirements 4 Supplier Social Responsibility
More informationMANUAL SUPPLIER S QUALITY MANUAL
MANUAL Raba Automotive Components Ltd Identification 50MR23003 1.8 Page 1/9 Coming into force 10.09.2015 SUPPLIER S QUALITY MANUAL Prepared/ Modified by Checked by Approved by Name Signature Date János
More informationINTRODUCTION. New Mather Metal Incorporated specializes in manufacturing quality stabilizer bars for suspension systems for the automotive industry.
INTRODUCTION Welcome to, New Mather Metal Inc. (NMMI) New Mather Metal Incorporated specializes in manufacturing quality stabilizer bars for suspension systems for the automotive industry. You can view
More information10/24/18. Printed document is uncontrolled after 10/24/2018, unless in a controlled book
10/24/18 Table of Contents Description Page CTA Acoustics Expectations 1 How to submit samples 2 How to process Corrective Action 3-7 How to request a temporary or permanent change 8-9 How your performance
More informationSupplier Quality Requirements Manual
Supplier Quality Requirements Manual 1 TABLE OF CONTENTS Page Number 1.0 Forward 3 2.0 Introduction 4 3.0 Supplier Selection Requirements 5 4.0 Supplier Development 5 5.0 Supplier Quality Rating System
More informationPrepared by: Checked by: Released by: Department LOQL Wagner LO-E Doelker LOQL Nuding Date Signature
Page 1 of 9 Prepared by: Checked by: Released by: Department LOQL Wagner LO-E Doelker LOQL Nuding Date Signature Page 2 of 9 Revision status 4 Copies to: LOQ; LOQL; LO-E; Supplier Contents: Page 1. Purpose...
More informationTorque Transfer Solutions
SUPPLIERS QUALITY ASSURANCE MANUAL TREMEC 5F/ PE Level 9 Issued Date March 02 nd, 2015 Revision Date May 17 th, 2017 - Page 1 of 135 Dear Supplier: In these times of global markets, it is not longer enough
More informationCUSTOMER SPECIFIC REQUIREMENTS RELATED TO ISO/TS APPLIED TO FIASA/Powertrain SUPLLIERS
Betim, October 7 th 2013. CUSTOMER SPECIFIC REQUIREMENTS RELATED TO ISO/TS 16949 APPLIED TO FIASA/Powertrain SUPLLIERS This letter updates and replaces, from 12/02/2013 on, the previous Customer Specific
More informationLOTUS SUPPLIER HANDBOOK rev14 09/05/2018. Supplier Handbook
rev14 09/05/2018 Supplier Handbook Issue 14 May 2018 SECTION 0.0 Foreword to Issue 14 The LOTUS Supplier Handbook Issue 14 was issued with revisions to the following: Chapters re-organised Section 2.0
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL 2018 I N D E X Paragraph Subject Page 1.0 Introduction 3 2.0 Quality System Requirements Specific to JVS 3 2.1 ISO 14001:2015 Compliance Requirements 2.2 IATF16949:2016/ISO9001:2015
More informationCharleston Metals Products, Inc.
350 Grant Street Waterloo, IN. 46793 (260) 837-8211 Charleston Metals Products, Inc. Revision 6 December 18 th, 2017 Table of Contents Charleston Metal Products, Inc. Charleston Metal Products Policy...
More informationPURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe
Page 1 of 12 DOCUMENT TITLE Supplier Quality Assurance Manual PURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe REVISION HISTORY Revision Change
More information4. RELATED DOCUMENTS AND FORMS 4.1. AS ISO Cambridge Valley Machining, Inc. QMS procedures, including, but not limited to:
Approved By: Purchasing Manager Candice Lane (signature on file) Date: 5/26/17 Approved By: Process Owner James D. Moore (signature on file) Date: 5/26/17 1. PURPOSE 1.1. To define Cambridge Valley Machining,
More informationISO/TS16949:2002 The Automotive Quality Management Business System
ISO/TS16949:2002 The Automotive Quality Management Business System Background ISO/TS 16949:2002 is an ISO Technical Specification. The International Automotive Task Force (IATF), which consists of an international
More information