1 (Part II The Paving Site) 36 th Annual Rocky Mountain Asphalt Conference & Equipment Show February 18-20, 2009
2 Use Common Sense Train for and Implement Best Practices Focus on Quality and Customer Service Include Employees Be Willing to do Things Differently!
3 Account for predictable traffic patterns in scheduling Know traffic patterns to job. Rush hours, special events, school and factory hours. Adjust routes and timing. On mill and fill projects, use delivery trucks to back haul RAP Save on trucking. May need release agent at paving site.
4
5
6 Mill different layers separately to allow more flexibility in RAP use Different layers may have different materials. E.g., milling surface layer with high friction aggregates will provide RAP for surface mixes. Evaluate costs of extra pass and separate stockpiles. Sort milling teeth by the amount of wear to reuse less worn teeth When replacing worn milling teeth, sort them by the wear. They can be used together to obtain smooth milling. Saves on number of teeth used each year.
7 Install weigh bridge on milling machine conveyor to maximize truck load Minimize the number of trucks during the day. Position trucks side-by-side in front of milling machine to keep continuous operation. Save time in truck exchange. Minimize water spray during milling to keep RAP dryer Minimizing cooling water reduces delays in re-filling tank and reduces moisture in the RAP, reducing plant fuel consumption.
8
9 Calibrate electronics on distributor truck every day Important to obtain proper coverage and quantity. Install plate at the end of distributor spray bar to avoid overspray of curb and gutter Avoids cleanup and keeps customers happy. Make sure each paving crew has a wooden level to check the screed (daily), transverse joints, and mat behind the screed Identify warped screeds, smooth transverse joints and proper drainage.
10 Install a bumper in back of the spray bar on distributor truck - Protects the spray bars, avoids down time. Investigate use of trackless tack Reduces the time for an emulsion tack to break. This can increase productivity and reduce tracking.
11
12 Attach a magnetic grade gauge on the back of the paver ($55 each) Provides a check of crossslope control on paver. Provide paving crew and roller operators with daily feedback on smoothness and density Allows the team to know the score. Share bonus with employees on bonus jobs, when successful Get buy-in from employees on the importance of quality.
13 Keep biodegradable release agent on board paver for tool and paver clean up - Keep tools and paver parts clean, saves time and avoids using diesel. Assign one member of crew to look after the electronics and store them in a dry, safe place - One person responsible for the care and storage of the electronics to avoid costly malfunctions..
14 Install hooks, buckets, and bins on pavers for tools (e.g. putty knives, wood level, 30 tape, 100 tape, gloves, 12 straight edge, whisk broom for tacking pavement edges) - Having all of the tools needed saves time. Tools should be inventoried, cleaned and placed back on the paver at the end of every shift.
15 Use MTV in places requiring hand work or when trucks can t get to paver - This helps to deliver mix to the paver in places where trucks cannot reach or stay in contact with the paver. It can also be helpful in depositing mix in areas requiring hand work. Cut off feeders and run augers to avoid piling at end of paver pulls Cutoff the feeders and run the augers properly to avoid piling mix at the end of the pull.
16
17 Use a paint marker system on pickup truck instead of string line Improves productivity by speeding job layout and improves safety by keeping employees away from traffic. Have auger and tunnel extensions available on site Auger and tunnel extensions reduce segregation and improve longitudinal joints. Waiting for them or proceeding without them hurts productivity or quality.
18
19 Check tire pressures on pneumatic rollers often Important to the ability of pneumatic rollers to obtain density. Purchase a vibe tachometer for each vibratory roller to ensure proper frequency ($500 each) Assures proper roller operation for compaction and smoothness. Always stop roller only on cool pavement at an angle Avoids bumps in the pavement for maximum smoothness and to avoid re-work.
20 Inspect scrapers, wipers, and cocoa mats on rollers and have spares available Keep drums and tires clean to avoid pick-up. Avoids mat blemishes and improves smoothness. Install small rubber bumpers on all perimeter frame rollers Protects the sheet metal from damage.
21 Fill roller water tanks and check the water spray system at the beginning of each shift All equipment should be fully functional prior to beginning paving to avoid time delays and quality issues. Stopping to fill or repair rollers may affect density and require stopping paving operations. Have welder wire available to clean roller water spray nozzles and have extra water spray nozzles available - Welder wire is an easy and cheap way to clean clogged nozzles. Nozzles should be checked periodically to avoid down time.
22 Install infrared sensors on rollers or equip operator with infrared gun and set temperature targets for each type of roller - Assures rolling temperatures are correct. It keeps the operators aware that they are working in the right temperature zone. Equip all rollers with high-intensity discharge xenon lights for night work - Important safety and quality issue.
23 Explore intelligent compaction for rollers This technology could help quality and productivity on paving jobs. Select rollers to match paver and planned production rates - Roller selection is part of the daily planning. The wrong type and number rollers can mean the difference between high production and quality, and wasted time.
24 Have a printed daily maintenance check list for equipment operators and truck drivers Avoids downtime and holds them accountable for the equipment they operate. Have parts uptime kits for pavers and rollers Have high wear and repair parts in stock or on site so they can be available at a moments notice. Install pre-cleaners in front of air filters on rollers and pavers Improves fuel economy, and improves engine and filter life.
25 Set start time for operations and meet it - Start time for paving crews should mean when the first truck dumps into the paver. There is a 20 to 30 minute lag (while the paver warms up and the crew gets ready) between the start time and when the pave starts moving. Stagger start times for crews on long days to avoid loss of momentum Not all employees need to start at same time. Different members of plant and paving crew can start and quit at different times.
26 Outline tools on tool racks in utility trucks so they are kept in the same place all the time Saves time when people know where to get the tool they need and when a tool is missing and needs to be replaced. Tape a list of tools contained in toolboxes and periodically inventory Saves time by knowing that key tools are available. Install ice machines for employees at each yard to avoid stopping to buy ice Crews stopping at convenience stores wastes time.
27 Install common key locks on all equipment to avoid waiting for lost keys Time can be lost looking for the correct key or waiting for someone to show up with it. Plan each day s production and paving in detail Every days production needs to be planned in every detail for maximum productivity.
28 Equip dump man, paver operator, and MTV operator with radio headsets, especially at night, for better communication. (one ear phone, not voice activated) - These are an inexpensive way to coordinate between the dump man, MTV operator and paver operator and can result in higher production and greater safety. Avoid unusually long shifts for employees Tired employees are more likely to make mistakes affecting quality and safety. Longer hours do not mean more productivity.
29 Keep cooler of water and electrolyte drinks with drinking cups on paver at all times This is a safety issue. Dehydration can reduce good judgment and result in heat exhaustion or heat stroke.
30 Enhance safety at every opportunity Improved safety reduces insurance costs and improves productivity. Examples: X on back of safety vests means I m not facing you, distinctive red headgear for new employees to indicate they are new, backup cameras on all trucks, reversible flashing arrows on front of tack truck to indicate direction for oncoming traffic, orange flags on the ends of distributor spray bars, flashing strobe lights on pavers, rollers and other equipment. Provide an incentive plan for employees for safety, quality and cleanliness Safety and quality affect your bottom line. Cleanliness can affect safety and presents a better image to your customers.
31 Establish a training program for paving company customers Value the customers and it will improve the quality of their work, reducing the number of bad jobs and conflicts. Provide attendance incentives such as food and giveaways. Keep them informed on future changes in company and industry, and emphasize the importance of best practices. Cross train people in critical positions If a critical employee does not show up, another should be trained to take their place.
32 Motivate employees to do the right things. Explain how it benefits them Use bonuses and commendations to motivate employees. Point out how quality affects the bottom line. Have a regular training program for employees Training affects quality and reduces employee turnover. Examples of training include: toolbox talks, regular training sessions, on-line training, equipment manufacturers schools, and using professional trainers. Provide train the trainer classes for superintendents and foremen This will make them more effective in teaching others how to do their jobs.
33 Have an employee appreciation day at least once a year Shows your employees that you value the work they do, improving morale and productivity.
34 Call on customers - Increases customer satisfaction and helps maintain repeat customers. Make sure job is done right the first time to avoid expensive call backs Never take shortcuts or accept marginal material to get the job down. It is much more expensive to remove and replace materials than it is to do it right the first time. Put paving crews in uniforms so they look and act professional This provides and better image to your customers and the general public. It can also instill pride in your workers.
35 Have a person responsible for site clean-up throughout the day This assures that the site is kept clean since one person is responsible. Provide accessible trash bags on pavers and other equipment to keep job site neat This portrays a better image to your customers and the general public. It may also prevent trash from ending up in the mat.
Flexible Pavement Preservation Treatment Construction Thin Functional and Maintenance Overlay Projects AT-TC3PP T1-JA01
Suggested Field Considerations The following field considerations are a guide for the important aspects of planning a thin functional overlay project. Thorough answers to these questions should be determined
More informationSuggested Best Practices for PAVER OPERATORS
Suggested Best Practices for PAVER OPERATORS Safety operates the paver using "Best Practices" procedures, to produce the highest-quality pavement possible. 1. Select a paving speed that balances delivery,
More informationFlexible Pavement Preservation Treatment Construction Ultra-thin, Hot Mixed Asphalt, Bonded Wearing Course AT-TC3PP T1-JA01
Suggested Field Considerations The following field considerations are a guide to the important aspects of applying a bonded wearing course (BWC). The below items should be considered to promote a successful
More informationMaterials 207: Troubleshooting Production Problems
Materials 207: Troubleshooting Production Problems A Contractor s Perspective Rocky Mountain Asphalt Conference Feb. 25, 2011 Bob Ekstrom Quality Control Manager United Companies of Mesa County Troubleshooting
More informationSection 409. Chip and Fog Seals
Section 409 Chip and Fog Seals PRECONSTRUCTION: Obtain from the contractor the supply sources for the chips, blotter material (if needed) and asphalt to be used on the project. Ensure the results of compatibility
More informationUsing Your Paver as it was Intended
Using Your Paver as it was Intended Presented by Todd Mansell, CAT Paving October 26, 2017 Role of the Paver To meet specifications for grade, texture & smoothness 1 What Is Grade & Slope? Grade (thickness)
More informationCooler Temperature Paving Using Modified Binders. Presented to the Association of Modified Asphalt Producers January 29, 2002
Cooler Temperature Paving Using Modified Binders Presented to the Association of Modified Asphalt Producers January 29, 2002 Cooler Temperatures? 1.) Am I talking about paving in cooler weather? Or 2.)
More informationSection 505. CHIP SEALS
Section 505. CHIP SEALS 505.01. Description. This work consists of preparing the pavement surface and providing and placing a single chip seal, double chip seal, or shoulder chip seal. 505.02. Materials.
More informationCity of Regina Standard Construction Specification SECTION 2350 PLACEMENT OF ASPHALTIC CONCRETE SURFACE 1.0 GENERAL. 1.1 Scope
1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of placing asphaltic concrete to a compacted thickness conforming to the lines, grades, and cross-sections as shown on the plan or as designated
More informationSpecial Specification 3005 Scrub Seal Treatment
Special Specification 3005 Scrub Seal Treatment 1. DESCRIPTION 2. MATERIALS 3. EQUIPMENT Construct a surface treatment consisting of 1 or more applications of a single layer of asphalt emulsion that is
More informationFlexible Pavement Preservation Treatment Construction Micro-surfacing AT-TC3PP T1-JA01. Suggested Field Considerations
Suggested Field Considerations These field considerations are guides to the important aspects of performing a micro-surfacing project. Thorough answers to these questions should be determined, as required,
More informationAsphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007
Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION March 22, 2007 Description: This work consists of furnishing and applying asphalt rubber binder followed by an application of treated cover aggregate
More informationEverything you need to know about Chip Seals and Fog Seals
1 Everything you need to know about Chip Seals and Fog Seals March 22-24, 2016 Nashville, TN www.worldofasphalt.com Preventive maintenance treatments Time or traffic Rehabilitate 1 The right treatment
More informationGUIDELINE FOR HOT MIX ASPHALT PAVEMENT PRE PAVING MEETING AGENDA
GUIDELINE FOR HOT MIX ASPHALT PAVEMENT PRE PAVING MEETING AGENDA November 2013 This document was developed by the Colorado Asphalt Pavement Association (CAPA). It is intended to be used as a resource in
More informationITEM 342 PLANT MIX SEAL
ITEM 342 PLANT MIX SEAL 342.1. Description. This Item shall govern for the construction of a wearing surface composed of a compacted mixture of aggregate and asphalt cement mixed hot in a mixing plant,
More informationThe Right Fit - Joint Construction. Presented by: Todd Mansell, Sakai America, Inc.
The Right Fit - Joint Construction Presented by: Todd Mansell, Sakai America, Inc. Why joints? The weakest link in a pavement structure Raveling along longitudinal joints Ride quality on transverse joints
More informationConstruction Specification for Tack Coat
Engineering and Construction Services Division Standard Specifications for Road Works TS 3.20 April 2014 for Table of Contents TS 3.20.01 SCOPE... 2 TS 3.20.02 REFERENCES... 2 TS 3.20.03 DEFINITIONS Not
More informationSECTION 315 ASPHALT CONCRETE PAVEMENT. Materials shall be furnished by the Contractor in accordance with Section 200.
SECTION 315 ASPHALT CONCRETE PAVEMENT I. GENERAL 1.1. DESCRIPTION OF WORK The Contractor shall furnish all labor, supervision, material (except as herein provided), tools, equipment, supplies, and services;
More informationChip Seal Best Practices Chip Seal Introduction AT-TC3PP T1-JA02. Chip Seal Application Checklist
Chip Seal Application Checklist This checklist is a guide for State and local highway maintenance and inspection staff in the use of innovative pavement preventive maintenance processes. Note that some
More information5-02 BITUMINOUS SURFACE TREATMENT
5-02 BITUMINOUS SURFACE TREATMENT 5-02 BITUMINOUS SURFACE TREATMENT 5-02.1 Description This Work shall consist of constructing a single or multiple course bituminous the lines and cross-sections shown
More informationNight Lighting Best Practices to Ensure Safety. Fred Beaudry
Night Lighting Best Practices to Ensure Safety Fred Beaudry Night Work Safety Work Zones Safe work practices for night work consist of much more than just PPE. It s our whole attitude and approach to the
More informationPavement Maintenance Best Practices. Thomas J. Wood
Pavement Maintenance Best Practices Thomas J. Wood Agenda Why pavement maintenance / preservation is important Dealing with cracks When to apply a surface treatment Fog Sealing Micro Milling UTBWC Thin
More informationCITY OF FARGO SPECIFICATIONS SEAL COATS
SEAL COATS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of furnishing all labor, material, accessories, and plant necessary
More informationSection 508. CHIP SEALS Description. Prepare the surface and apply the specified single chip seal, double chip seal or shoulder chip seal.
508.01 Section 508. CHIP SEALS 508.01 Description. Prepare the surface and apply the specified single chip seal, double chip seal or shoulder chip seal. 508.02 Materials. Use materials meeting the following.
More informationCOLD-IN-PLACE PAVEMENT RECYCLING
COLD-IN-PLACE PAVEMENT RECYCLING PART 1 - GENERAL 1.01 SECTION INCLUDES Cold-in-place recycling (CIR) of asphalt roadways 1.02 DESCRIPTION OF WORK Includes milling and mixing of existing asphalt materials,
More informationAsphalt Pavement Construction: Best Practices
Percent Service Life 12/13/2016 Asphalt Pavement Construction: Best Practices 57th Annual Illinois Bituminous Paving Conference December 12-13, 2016 Effect of In-Place Voids on Life 100 Washington State
More informationSPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 17 ASPHALT CONCRETE PAVEMENT General Materials
SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 17 ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS 17.1 General...17-1 17.2 Materials...17-1 17.3 Asphalt Mix Design...17-1 17.4 Sampling and Testing...17-2 17.5
More informationRelease 10 11/7/
1-1 1-2 We want to build quality roadways but what is quality? Who is the customer? If you are an aggregate or binder supplier your customer is the asphalt producer. If you produce asphalt mix and sell
More informationPavement Preservation Checklist Series. 14 Fabric. Interlayer Application
Pavement Preservation Checklist Series 14 Fabric Interlayer Application Fabric Interlayer Application Checklist This checklist is one of a series created to guide State and local highway maintenance and
More informationSPECIAL SPECIFICATION 3280 Paver-Laid Surface Treatment
1993 Specifications CSJ 0617-01-157, etc. SPECIAL SPECIFICATION 3280 Paver-Laid Surface Treatment 1. Description. This Item shall govern for the construction of a surface treatment composed of a polymer-modified
More information1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.
SECTION 1300 - ASPHALTIC CONCRETE PAVEMENT 1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas. 1302 GENERAL. Pavement shall be constructed to the lines, grades,
More information1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.
SECTION 1300 - ASPHALTIC CONCRETE PAVEMENT 1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas. 1302 GENERAL. Pavement shall be constructed to the lines, grades,
More informationSPECIFICATIONS FOR ASPHALT-RUBBER SURFACE TREATMENT WITH AGGREGATE COVER
SPECIFICATIONS FOR ASPHALT-RUBBER SURFACE TREATMENT WITH AGGREGATE COVER STRESS ABSORBING MEMBRANE - SAM STRESS ABSORBING MEMBRANE INTERLAYER - SAMI 0395 This specification covers requirements for materials,
More informationJanuary 2008 No. 700
January 2008 No. 700 INDEX FOR SPECIFICATIONS FOR GRANULAR BASE COURSE Page 700. 1 SCOPE...1 1.1 Pre-Construction Meeting...1 1.2 Mobilization of Equipment...1 700. 3 MATERIALS 3.1 Granular Base Course
More informationCOLD IN PLACE RECYCLING
Sponsored by of New York COLD IN PLACE RECYCLING OVERVIEW What is Cold Recycling? Why Recycle? Types & Processes Candidate Selection Core Sampling Mix Design Economics WHAT IS COLD RECYCLING? Effective
More informationPAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE
PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE Quality Assurance is not Quality Control Quality control is Contractors responsibility during construction. Quality Assurance
More informationEnd of Load Segregation identification, causes, cures Part 2
End of Load Segregation identification, causes, cures Part 2 Definition End-of-Load segregation is a recurring pattern of segregation created during paving operations. Typically, it is the result from
More informationSection 3 Specification 3.24 Chip Seal Coat TABLE OF CONTENTS
TABLE OF CONTENTS 3.24 CHIP SEAL COAT... 1 3.24.1 GENERAL... 1 3.24.2 MATERIALS... 1 3.24.2.1 Aggregate... 1 3.24.2.2 Temporary Markers... 1 3.24.2.3 Asphalt... 1 3.24.2.4 Water... 1 3.24.2.5 Line Painting
More informationMix Design & Construction -1-
Mix Design & Construction -1- AGENDA RCC Mix Design RCC Mix Production RCC Construction Process -2- THE FINAL SURFACE TYPE WILL DICTATE THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL Natural
More informationconstruction checklist
construction checklist for asphalt parking lots Checklist for Parking Lots To achieve the longest life, lowest maintenance costs, and best performance from an asphalt parking lot, the entire construction
More informationBest Practices for Constructing and Specifying HMA Longitudinal Joints A Cooperative Effort between Asphalt Institute & FHWA
Best Practices for Constructing and Specifying HMA Longitudinal Joints A Cooperative Effort between Asphalt Institute & FHWA Mark D. Blow, P.E. Sr. Regional Engineer Asphalt Institute Don t We Already
More informationSECTION 503 TEMPORARY PAVEMENT RESTORATION
SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with
More informationPaver Operations for Quality
Information Series 125 Paver Operations for Quality www.hotmix.org This publication is provided by the Members of the National Asphalt Pavement Association (NAPA), who are the nation s leading Hot Mix
More informationOKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR PLANT MIX BITUMINOUS BASES AND SURFACES
418-1(a-f)99 OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR PLANT MIX BITUMINOUS BASES AND SURFACES These Special Provisions revise, amend and where in conflict, supersede applicable sections
More informationThe Cardiac Arrest of Hot Mix Asphalt Pavements. Timothy R. Murphy, P.E., M. ASCE President
The Cardiac Arrest of Hot Mix Asphalt Pavements Timothy R. Murphy, P.E., M. ASCE President Our Job is to Evaluate Risk LCCA Durability Process Control Rugged review of practices with numerous agencies
More informationASPHALTIC CONCRETE FRICTION COURSE (ASPHALT-RUBBER):
SECTION 414 ASPHALTIC CONCRETE FRICTION COURSE (ASPHALT-RUBBER): 414-1 Description: Asphaltic Concrete Friction Course (Asphalt-Rubber), hereinafter asphaltic concrete, shall consist of furnishing all
More information2011 Regional Asphalt Meetings. Frequently Asked Questions
2011 Regional Asphalt Meetings Frequently Asked Questions Quiet Pavement Questions 1. Based on the data from the SR 234 site, the decibel difference between the dense graded and PFC was only 1 dba. Is
More information2004 Specifications CSJ SPECIAL SPECIFICATION 3250 Emulsified Asphalt Slurry Seal Surface Treatment
2004 Specifications CSJ 6240-39-001 SPECIAL SPECIFICATION 3250 Emulsified Asphalt Slurry Seal Surface Treatment 1. Description. Furnish and place an emulsified asphalt slurry seal surface treatment consisting
More informationSPECIAL SPECIFICATION 3347 Ultra Thin Hot Mix Bonded Wearing Course
1993 Specifications CSJ s 0114-12-005 and 1685-01-083 SPECIAL SPECIFICATION 3347 Ultra Thin Hot Mix Bonded Wearing Course 1. Description. This Item shall govern for the construction of a surface treatment
More informationTrenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association
Trenton M. Clark, P.E. Director of Engineering Virginia Asphalt Association Representatives of VDOT (consultant or inspector) must be familiar with the VDOT Road and Bridge Specifications as well as Special
More informationSECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING
SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING 402.1 Description. This work shall consist of placing, spreading and compacting a bituminous mixture as shown on the plans or as directed by the engineer.
More informationSURFACINGS AND PAVEMENTS SECTION 37: BITUMINOUS SEALS 37-1 SEAL COATS
SURFACINGS AND PAVEMENTS SECTION 37: BITUMINOUS SEALS 37-1 SEAL COATS 37-1.01 DESCRIPTION This work shall consist of an application or applications of asphaltic emulsion and screenings or an application
More informationASPHALTIC CONCRETE FRICTION COURSE (ASPHALT-RUBBER):
SECTION 414 ASPHALTIC CONCRETE FRICTION COURSE (ASPHALT-RUBBER): 414-1 Description: Asphaltic Concrete Friction Course (Asphalt-Rubber), hereinafter asphaltic concrete, shall consist of furnishing all
More informationHMA Base Repair RPR Spring Meeting February 23, 2017 Ken Walschlager
HMA Base Repair RPR Spring Meeting February 23, 2017 Ken Walschlager TS HOT MIX ASPHALT (HMA) BASE 25.0 MM FOR BASE REPAIRS Base repair will be required... Possibly consisting of removal and replacement
More informationAsphalt Materials: Basics of RAP, Usage and Specifications
Asphalt 103 - Materials: Basics of RAP, Usage and Specifications 36 th Annual Rocky Mountain Asphalt Conference and Equipment Show February 19, 2009 Denver, Colorado By Tom Blair Director of Product Engineering
More informationFTBA CONSTRUCTION CONFERENCE
A WIRTGEN GROUP COMPANY FTBA CONSTRUCTION CONFERENCE 01 17 19 NEW PAVING TECHNOLOGIES L., Manager Commercial Support & Development Paver Controls Past & Present Present: Intelligent Machine Control Past:
More informationTABLE ASPHALTIC CONCRETE MIX DESIGN CRITERIA
SECTION 413 ASPHALTIC CONCRETE (ASPHALT-RUBBER): 413-1 Description: Asphaltic Concrete (Asphalt-Rubber), hereinafter asphaltic concrete, shall consist of furnishing all materials, mixing at a plant, hauling,
More informationCONSTRUCTION SPECIFICATION FOR COLD MIXED, COLD LAID, OPEN AND DENSE GRADED BITUMINOUS MIX TABLE OF CONTENTS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 309 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR COLD MIXED, COLD LAID, OPEN AND DENSE GRADED BITUMINOUS MIX TABLE OF CONTENTS 309.01 SCOPE 309.02
More informationIntelligent compaction is a concept gaining increasing attention from
N EW G ENERATIONS by Arnie Consdorf, Contributing Editor Taking the Guesswork Out of Compaction How do you justify the extra cost of Bomag s intelligent compaction technology? We ask early users what they
More informationCONSTRUCTION SPECIFICATION FOR SINGLE AND DOUBLE SURFACE TREATMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 304 NOVEMBER 2016 CONSTRUCTION SPECIFICATION FOR SINGLE AND DOUBLE SURFACE TREATMENT TABLE OF CONTENTS 304.01 SCOPE 304.02 REFERENCES 304.03 DEFINITIONS
More informationPrepaving Conferences
Prepaving Conferences Presenters ODOT: Bob Townsend Assistant Project Manager The Dalles Construction Office Knife River: Tyrone Belgarde Project Superintendent Knife River Corporation-Northwest Prepaving
More informationPaving Equipment - Manufactures Perspective
Agenda: 1. Differences in equipment - Road paving VS Airport Paving Principles of Screed Compaction Vibratory, Compaction & High Compaction Screeds Surface Texture and Density Wide Paving Eliminate Joints
More informationWhat s Known and What s New. Timothy R. Murphy, P.E. President
What s Known and What s New Timothy R. Murphy, P.E. President Transportation Research Board s Report 202 (1984) Mr. Allan Wood US Army, 82 nd Airborne Parachuted into Holland 9/17/1944 Operation Market
More informationSPECIAL SPECIFICATION 3419 Ultra Thin Hot Mix Bonded Wearing Course
1993 Specifications CSJ 0196-03-236 SPECIAL SPECIFICATION 3419 Ultra Thin Hot Mix Bonded Wearing Course 1. Description. This Item will govern for the construction of a surface treatment composed of the
More informationChecklist Series. 2 Chip. !Pavement Preservation. Seal Application
!Pavement Preservation Checklist Series 2 Chip Seal Application Chip Seal Application Checklist This checklist is one of a series created to guide State and local highway maintenance and inspection staff
More informationSection 409 of the Standard Specifications is hereby deleted and replaced with the following: DESCRIPTION
Sample Project Special Provision: 409cas 08-11-2016 (Re-issued 07-03-17 with City of Montrose Edits) 1 Section 409 of the Standard Specifications is hereby deleted and replaced with the following: DESCRIPTION
More informationSUPPLEMENTAL SPECIFICATION HIGH PERFORMANCE CHIP SEAL
May 21, 2008 HIGH PERFORMANCE CHIP SEAL 411 High Performance Chip Seal 411.1 Description High Performance Chip Seal is a high macro-texture surface treatment that is applied in a continuous operation.
More informationCompaction Principles
Compaction Principles The A, B, Cs Asphaltic concrete mix is like eggs, meat and milk it has a shelf life and must be compacted before it cools (spoils) Binder content makes it either more difficult to
More informationFlexible Pavement Preservation Treatment Construction Patching and Edge Repair AT-TC3PP T1-JA01. Suggested Field Considerations
Suggested Field Considerations The following field considerations are a guide to the important aspects of patching or edge repair. These issues should be determined as required before, during, and after
More informationSECTION ASPHALT PAVING AND SURFACING
SECTION 02500 ASPHALT PAVING AND SURFACING PART 1 - GENERAL 1.01 WORK INCLUDED A. Traffic control as required to divert vehicular and pedestrian traffic around construction. B. Spreading and compacting
More informationThe Cardiac Arrest of Hot Mix Asphalt Pavements
The Cardiac Arrest of Hot Mix Asphalt Pavements Timothy R. Murphy, P.E. President What Are You Really Going To Remember from this Convention? What will you really remember most about today? 70% of what
More informationVDOT S PREVENTIVE MAINTENANCE TECHNIQUES & EXPECTATIONS
VDOT S PREVENTIVE MAINTENANCE TECHNIQUES & EXPECTATIONS Todd Rorrer Regional Field Engineer CO Asphalt Programs 2017 Asphalt Regional Seminars 1 VDOT S PREVENTIVE MAINTENANCE TECHNIQUES & EXPECTATIONS
More informationProduct PJ September 2005
Department of Civil Engineering Texas Tech University Center for Multidisciplinary Research in Transportation Submitted to Texas Department of Transportation Product 0-4362-PJ September 2005 Tex-YYY-Y:
More informationReclamation Guidelines
Reclamation Guidelines MAAPT 63 rd Asphalt Conference December 7, 2016 Terry Beaudry MnDOT Grading Base, Recycling, and Aggregate Engineer Outline 2 Design and Preliminary Work Construction Production
More informationFlexible Pavement Preservation Industry Perspective Rod Birdsall, P.E. PRDOT PP Conference
F Flexible Pavement Preservation Industry Perspective Rod Birdsall, P.E. PRDOT PP Conference 11.15.2011 ASMG Family of Companies ASMG Locations Outline of Presentation What is Pavement Preservation Why
More informationSECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS...
SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK... 20-2 2. MATERIAL REQUIREMENTS... 20-2 3. CONSTRUCTION AND INSTALLATION REQUIREMENTS... 20-2 4. METHOD OF MEASUREMENT... 20-5 20-1 SECTION 20 PAVING FABRIC
More informationSPECIFICATION FOR QUALITY ASSURANCE FOR HOT MIX ASPHALT
TNZ Q/2:1995 SPECIFICATION FOR QUALITY ASSURANCE FOR HOT MIX ASPHALT 1. SCOPE This specification covers the quality assurance requirements for contracts which include surfacings work incorporating hot
More informationTUFF-TAC TM BRIDGE MEMBRANE INSTALLATION GUIDE
5 pages TUFF-TAC TM BRIDGE MEMBRANE INSTALLATION GUIDE The following will describe the proper procedure to use when installing Tuff-Tac TM bridge deck membrane. The guide will cover recommended tools to
More information1. Evolution of Screeds in the USA A. Fixed Screeds with Hydraulic Strike-off, Becoming Obsolete B. Rear Mount Screeds with & without strikeoff C. Fro
1. Evolution of Screeds In the US 2. Inline Pave (Hot on Hot) 3. Spray Paver Technology 4. RCC, CTB & Applications 5. Foam Mix and Recycling 6. Narrow & Medium Width High Quality Pavement 7. Navitronic
More informationNO-TACK INLAY ON MILED SURFACE: PROJECT REPORT
NCAT Report 99-02 NO-TACK INLAY ON MILED SURFACE: PROJECT REPORT By L. Allen Cooley Jr. February 1999 277 Technology Parkway Auburn, AL 36830 NO-TACK INLAY ON MILLED SURFACE: PROJECT REPORT By L. Allen
More informationConstruction of Polish PERS test section
PoroElastic Road SUrface: an innovation to Avoid Damages to the Environment EUROPEAN COMMISSION - DG RESEARCH Directorate 1 - Environment Seventh Framework Programme - Contract No. 226313 Document type
More informationExtraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method
3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed
More informationSpecial Provision No. 335S03 April 2015
COLD IN-PLACE RECYCLED EXPANDED ASPHALT MIX Item No. Special Provision No. 335S03 April 2015 Amendment to OPSS 335, November 2009 OPSS 335, November 2009, Construction Specification for Cold In-Place Recycling
More informationCity of Estevan. Construction Specifications
City of Estevan Construction Specifications 1.0 GENERAL This section governs the requirements for the supply and placement of Asphaltic Concrete pavement. 2.0 MATERIALS 2.1 Aggregate Shall consist of hard,
More informationMaterials 206: Handling RAP (Advanced) Contractor QC and Specifications
Materials 206: Handling RAP (Advanced) Contractor QC and Specifications 38 th Annual Rocky Mountain Asphalt Conference and Equipment Show February 25, 2011 Denver, Colorado By Tom Blair Director of Product
More information610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT
SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT 610.1 DESCRIPTION Construct a wearing surface composed of an asphalt prime coat followed by the applications of 2 asphalt seal coats and cover material as specified
More informationASTEC encourages its engineers and executives to author articles that will be of value to members of the hot mix asphalt (HMA) industry.
ASTEC encourages its engineers and executives to author articles that will be of value to members of the hot mix asphalt (HMA) industry. The company also sponsors independent research when appropriate
More informationTack Coat Best Practices
Tack Coat Best Practices FHWA Cooperative Agreement Subtask Longitudinal Joints Intelligent Compaction Far Too Frequent Practices Days later! Courtesy of Road Science Terminology Tack Coat sprayed application
More information610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT
SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT 610.1 DESCRIPTION Construct a wearing surface composed of an asphalt prime coat followed by the applications of 2 asphalt seal coats and cover material as specified
More information1825 W. Adams, Phoenix, AZ Phone (602) / Fax (602)
1825 W. Adams, Phoenix, AZ 85007 Phone (602) 252-3926 / Fax (602) 252-5870 Forward The Arizona AGC Pavement Preservation guides are collections of best practices and recommendations for the state of Arizona.
More informationRecommended Construction Guidelines For Cold Central Plant Recycling (CCPR) Using Bituminous Recycling Agents CR102
Recommended Construction Guidelines For Cold Central Plant Recycling (CCPR) Using Bituminous Recycling Agents CR102 Revised: 4/7/2016 NOTICE It is not intended or recommended that these guidelines be used
More informationSPECIAL SPECIFICATION 3317 Crumb Rubber Modified (CRM) Hot Mix Asphaltic Concrete Pavement
1993 Specifications CSJ 0005-13-041 SPECIAL SPECIFICATION 3317 Crumb Rubber Modified (CRM) Hot Mix Asphaltic Concrete Pavement 1. Description. This Item shall govern for the construction of a level-up
More informationNOTICE TO BIDDERS ADDENDUM NO. 1
NOTICE TO BIDDERS ADDENDUM NO. 1 This Addendum changes the terms of the Bid Proposal and/or plans associated with the Monroe County Road Commission project indicated below. By submitting a bid, any and
More informationADFORS PAVEMENT REINFORCEMENT SYSTEM GlasGrid GG
ADFORS PAVEMENT REINFORCEMENT SYSTEM GlasGrid GG Self-adhesive Crack mitigation Tensile strength Unique protective coating Installation Procedures Your Partner for Innovative Textiles The installation
More informationRoadway Inspection Recertification. Quality Control / Quality Assurance
Roadway Inspection Recertification Quality Control / Quality Assurance **IMPORTANT** Recertification is only for individuals currently certified and actively participating on Asphalt Concrete Projects
More informationLongitudinal Joint Construction
North Central Hot Mix Asphalt Technical Conference Illinois Bituminous Paving Conference January 9, 2008 Springfield, IL Longitudinal Joint Construction William J. Pine, P.E. Heritage Research Group A
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish
More informationTack Coat Best Practices
SEAUPG Nashville, Tennessee Tack Coat Best Practices FHWA Cooperative Agreement Subtask Longitudinal Joints Intelligent Compaction Far too frequent practices. 1 Tack Coat Best Practices Outline Terminology
More informationOutline for Webinar Today. Best Practices for HMA Longitudinal Joints. Don t We Already Know How To Build a Longitudinal Joint? Introduction, Project
Best Practices for HMA Longitudinal Joints Outline for Webinar Today Introduction, Project Density/ Performance/ Permeability A Cooperative Effort between Asphalt Institute & FHWA Construction Best Practices
More information