Inspection Results by Plant 2017

Size: px
Start display at page:

Download "Inspection Results by Plant 2017"

Transcription

1 Fall 2017 EQ Technical Conference November 8-10, 2017 Clearwater, Florida William Horin, Winston & Strawn, LLP (Counsel to NUGEQ Ron Wise, NEQ Consulting (NUGEQ Technical Consultant

2 High Level Overview Currently, 13 of the 17 EQ DBA Inspections scheduled for 2017 have been completed Inspections have occurred across all 4 NRC regions 3 in NRC Region I 4 in NRC Region II 3 in NRC Region III 3 in NRC Region IV 2

3 Inspection Results for Region I Region I Station Date Results Remarks Hope Creek Week 1: May 8, 2017 Week 2: May 22, Green NCV (Violation of TS ) for failure to maintain secondary containment IR / Millstone Week 1: July 31, 2017 Week 2: Aug 14, 2017 Ginna Week 1: Aug 7, 2017 Week 2: Aug 21, 2017 integrity 1 Green NCV (Violation of TS a) for not implementing procedures as required by RG 1.33 No NRC identified or self revealing findings were identified IR / & IR / IR /

4 Inspection Results for Region II Region I Station Date Results Remarks McGuire Week 1: Jan 23, 2017 Week 2: Feb 6, Green NCV (App B, Criterion III) for failure to translate requirements necessary to maintain qualification of Namco LS 1 st EQ DBAI IR / & IR / Watts Bar Week 1: June 5, 2017 Week 2: June 19, Green NCV (App B Criterion V) for failure to implement instructions necessary maintain qualification of Namco LS 1 Green NCV (50.49(j)) for failure to maintain a complete record of qualification for Brand-Rex Cables 3 Unresolved Items IR / & IR /

5 Inspection Results for Region II (continued) Region I Station Date Results Remarks Hatch Week 1: Aug 14, 2017 Week 2: Aug 28, 2017 No NRC identified or self revealing findings were identified 2 Unresolved Items IR / & IR / Robinson Week 1: Oct 2, 2017 Week 2: Oct 16, Green NCVs 2 NOVs (Significance TBD) 5 Unresolved Items Exited on 10/31/17 5

6 Inspection Results for Region III Region III Station Date Results Remarks Fermi Week 1: May 8, 2017 Week 2: May 22, Green NCV (App B, Criterion III) involving protective devices in MCCs 1 Green NCV (50.49 (e)(1)) involving two examples related to post accident op-time calculations 1 Green NCV (App B, Criterion III) on failure to translate requirement into maintenance procedures 1 Licensee Identified violation for 10 CFR 50.49(k) IR /

7 Inspection Results for Region III (continued) Region III Station Date Results Remarks LaSalle Week 1: June 26, 2017 Week 2: July 10, Green NCV (50.49 (f)(4)) for failure to provide adequate analysis in combination with partial type testing 1 Green NCV (50.49 (j)) for failure to have adequate justification for extending service life of grease IR / & IR /

8 Inspection Results for Region III (continued) Region III Station Date Results Remarks Monticello Week 1: Sept 18, 2017 No NRC identified or self revealing Exited on 10/6/2017 Week 2: Oct 2, 2017 findings were identified 8

9 Inspection Results for Region IV Region IV Station Date Results Remarks Wolf Creek Week 1: May 8, 2017 Week 2: May 22, Green NCV (50.54 (q)(2)) for failure to maintain the effectiveness of the E-Plan upon loss of CHRRM IR / ANO Week 1: July 24, 2017 Week 2: Aug 7, Green NCV (App B, Criterion XVI) for failure to promptly identify and correct an inadequate design basis calculation IR / & IR / Cooper Week 1: Aug 24, 2017 Week 2: Aug 28, 2017 No findings were identified. IR /

10 10 So what were the two NOVs at Robinson? #1 Failure to perform adequate similarity analysis between Westinghouse prototype and installed Crouse-Hinds EPA #2 Qualified Life of ASCO NP-1 coils based on activation energy from a different material (MW35 vs. MW16). Related to use of NUGEQ memo. Both categorized as Significance TBD at (final) exit

11 Unresolved Items Region I: None Region II: 10 3 at Watts Bar 2 at Hatch 5 at Robinson Region III: None Region IV: None 11

12 So what is the significance of these URIs? Several of these URI s have generic implications To other licensees To vendors To other equipment types Some have the potential to change/challenge the CLB for the affected plants URI s in BOLD are related to NUGEQ comments 12

13 Unresolved Items at Watts Bar URI #1 Potential Failure to Address Environmental Qualification of Brand-Rex Cables Centered around the derivation of the activation energy for the cable insulation NRC challenged method that eliminated one data point (highest temperature) since it reflected the presences of a 2 nd order reaction 13

14 Unresolved Items at Watts Bar (continued) URI #2 Potential Failure to Justify Qualification of O-rings by Commercial Grade Dedication Centered around a dedication of O-rings for Barton Transmitters by a 3 rd party approved App B vendor Dedication confirmed material to be same as the baseline EQ certified O-ring NRC challenged why dedication did not include verification Ea or EQ testing for the O-rings 14

15 Unresolved Items at Watts Bar (continued) URI #3 Potential Failure to Address Environmental Qualification of Barton Transmitters Centers around the qualified life of Barton 764 transmitters and justification for deviating from the original 0.5eV activation. 0.92eV values was used by WEC (as well as Barton) for the O-rings 15

16 16 Unresolved Items at Watts Bar (continued) URI #3 Potential Failure to Address Environmental Qualification of Barton Transmitters Due to an anomaly, replacement O-rings were aged using 0.92eV for 14 hours during the test program NRC challenged the justification for deviating from the original 0.5eV value including synergistic effects and uncertainties.

17 Unresolved Items at Hatch URI #1 Potential Failure to Adequately Justify the Activation Energies by Licensee Related to the justification for selecting activation energies for 600V MCC fuses and Zytel 103 used in Scram Solenoid Pilot Valves NRC considered the activation energies being used as non-conservative 17

18 Unresolved Items at Hatch (continued) URI #2 Potential Failure to Adequately Justify the Activation Energies by 10 CFR 50 Appendix B vendors Centers around the adequacy of the licensee s acceptance of vendor s justification for the activation energies for the 600V MCC fuses and the Zytel 103 subcomponent in the SSPV 18

19 Unresolved Items at Robinson URI #1 Qualification of Penetrations Failure to consider UFSAR reference to proposed IEEE standard. Discrepancy regarding ampacity during shortcircuit conditions between RNP calculation and specification 19

20 Unresolved Items at Robinson (continued) URI #2 EQDP-0900 (Crouse-Hinds Penetration) Did not adequately extend the QL to 60 years due to inappropriate application of Arrhenius to determine activation energy and uncertainties. 20

21 Unresolved Items at Robinson (continued) URI #3 EQDP-0401 (Rosemount Transmitters) Unjustified use of single activation energy (0.78eV). NRC believes RNP should have considered multiple ev values over temperature range RNP provided insight from RNII describing the appropriateness of Ea used in QL Calculation 21

22 Unresolved Items at Robinson (continued) URI #4 Chemical Spray Qualification Maximum ph stated in TS Bases and UFSAR is The EQ Zone map and supporting WCAP calculation indicate max ph of A GSI-191 calculation shows a max ph of

23 Unresolved Items at Robinson (continued) URI #5 Penetration Submergence Qualification Submergence qualification of electrical penetration F-01 not proven. Issue previously identified by NRC in 1980s and drove modification. Closed by NRC in

24 Questions or Comments? 24

EQ-Related Enforcement Activity

EQ-Related Enforcement Activity EQ-Related Enforcement Activity Fall 2014 EQ Technical Conference Nuclear Utility Group on Equipment Qualification November 10-14, 2014 Clearwater, Florida William Horin, Winston & Strawn, LLP (Counsel

More information

Qualified Life - Challenge or Challenger Rick Weinacht October 31, October 31, Curtiss-Wright

Qualified Life - Challenge or Challenger Rick Weinacht October 31, October 31, Curtiss-Wright Qualified Life - Challenge or Challenger Rick Weinacht October 31, 2018 2 October 31, 2018 2018 Curtiss-Wright Challenge vs. Challenger CHALLENGE CHALLENGER Presented at the IEEE Symposium on Nuclear Power

More information

NRC Activities. Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation

NRC Activities. Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation NRC Activities Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation Agenda Nuclear Power Plant Reviews Inspection News Regulatory Guide News Research Activities IEC/IEEE Joint

More information

2014 Equipment Qualification Technical Meeting Agenda

2014 Equipment Qualification Technical Meeting Agenda 2014 Equipment Qualification Technical Meeting Agenda Dates Monday - Tuesday, November 10-11, 2014, EQ Advanced Training Wednesday Thursday & half day Friday, November 12-14, 2014, EQ Technical Meeting

More information

Challenges in The Environmental Qualification of First of A Kind Components

Challenges in The Environmental Qualification of First of A Kind Components Challenges in The Environmental Qualification of First of A Kind Components Jeffrey Jacobson Office of New Reactors November 9, 2017 1 Problem Statement Many environmental qualification activities are

More information

NUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S.

NUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S. NUPIC General Membership and Vendor Meetings June 2014 Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S. NRC 1 Insights from the Fukushima Event 2014 NRC Vendor Inspections Recent

More information

Re-Defining the Harsh / Mild Environmental Threshold for EQ

Re-Defining the Harsh / Mild Environmental Threshold for EQ Re-Defining the Harsh / Mild Environmental Threshold for EQ Iepson Consulting Enterprises, Inc. (ICE) IEEE Meeting, October 4, 2005 What is the Harsh / Mild Threshold for EQ? The values for a set of environmental

More information

INPO Health Report Initiative

INPO Health Report Initiative Fall 2014 Joint EQ Technical Conference November 4-6, 2014 Sand Key, Florida William Horin, Winston & Strawn, LLP (whorin@winston.com) Ronald Wise, NEQ Consulting (ronwise@aol.com) Today s topic is intended

More information

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications

More information

July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC

July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 SUBJECT: Petition Pursuant to 10 CFR 2.206 Demand For Information Regarding

More information

Environmental Qualification of

Environmental Qualification of Environmental Qualification of Safety Related Electrical Equipment for Nuclear Power Plants Gary W Castleberry PE PMP Gary W. Castleberry 1 of 63 Learning Modules 1. What is Environmental Qualification

More information

Greg Galletti & Richard McIntyre Quality Electrical Vendor Branch Quality Mechanical Vendor Branch Office of New Reactors U.S. NRC

Greg Galletti & Richard McIntyre Quality Electrical Vendor Branch Quality Mechanical Vendor Branch Office of New Reactors U.S. NRC NUPIC General Membership Meeting and Vendor Conference June 2015 Greg Galletti & Richard McIntyre Quality Electrical Vendor Branch Quality Mechanical Vendor Branch Office of New Reactors U.S. NRC 1 Update

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL INSPECTION PROCEDURE CQV/EQV INSPECTION OF COMMERCIAL-GRADE DEDICATION PROGRAMS PROGRAM APPLICABILITY: 2504, 2507, 2700-01 INSPECTION OBJECTIVES 01.01 To verify that the dedicating

More information

Environmental Qualification Program for Krsko NPP

Environmental Qualification Program for Krsko NPP HR9800119 Environmental Qualification Program for Krsko NPP Janko Cerjak, Peter Klenovsek Nuclear Power Plant Krsko, Vrbina 12, Krsko, SLOVENIA Janez Pavsek Elektroinstitut Milan Vidmar, Hajdrihova 2,

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL NMSS/RII INSPECTION PROCEDURE MECHANICAL COMPONENTS PROGRAM APPLICABILITY: 2630-01 INSPECTION OBJECTIVES 01.01 To determine whether the technical requirements detailed or referenced

More information

US REGULATORY OVERSIGHT OF COMMERCIAL-GRADE DEDICATION

US REGULATORY OVERSIGHT OF COMMERCIAL-GRADE DEDICATION US REGULATORY OVERSIGHT OF COMMERCIAL-GRADE DEDICATION KERRI KAVANAGH CHIEF OF THE QUALITY ASSURANCE VENDOR INSPECTION BRANCH- 2, OFFICE OF NEW REACTORS, US NUCLEAR REGULATORY COMMISSION Agenda Background

More information

REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH. REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006)

REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH. REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006) U.S. NUCLEAR REGULATORY COMMISSION March 2007 Revision 1 REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006) DAMPING VALUES FOR

More information

Maintaining Seismic Qualification

Maintaining Seismic Qualification Nuclear Division Maintaining Seismic Qualification 1 May 17, 2016 2014 Curtiss-Wright A white paper is being developed in IEEE 344 to identify changes that may impact seismic qualification Working group

More information

Accepting Supplier ISO 9000 Quality Programs

Accepting Supplier ISO 9000 Quality Programs Accepting Supplier ISO 9000 Quality Programs IEEE Subcommittee on Qualification October 7-8, 2004 Leigh A. Aparicio PSE Technical Leader aparicio@epri.com Project Overview ISO 9000 Phase I Initiated in

More information

APPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS

APPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS APPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS This Page Intentionally Left Blank E-ii E.1 INTRODUCTION The NRC Advisory

More information

Lifetime Extension of Nuclear I&C I & C Obsolescence and PLEX October 27, 2016 Curtiss-Wright Nuclear Division

Lifetime Extension of Nuclear I&C I & C Obsolescence and PLEX October 27, 2016 Curtiss-Wright Nuclear Division Lifetime Extension of Nuclear I&C I & C Obsolescence and PLEX October 27, 2016 Curtiss-Wright Nuclear Division 1 November 3, 2016 Proprietary 2014 Curtiss-Wright It all started on the sands of Kitty Hawk

More information

ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1

ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 Karte: Wikipedia CIS GmbH Experts in ASME Code Consulting CIS GmbH Consulting Inspection Services 3 rd Party Inspection Training

More information

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,

More information

REQUIREMENTS FOR SAFETY RELATED (ASME AND NON-ASME) ITEMS OR SERVICES

REQUIREMENTS FOR SAFETY RELATED (ASME AND NON-ASME) ITEMS OR SERVICES Special Quality Assurance Documents (SQAD) (Continued) SQAD-1 REQUIREMENTS FOR SAFETY RELATED (ASME AND NON-ASME) ITEMS OR SERVICES 1.1 QA PROGRAM: Items or services supplied under the PO/ Contract shall

More information

Environmental Qualification of Safety Related Electrical Equipment

Environmental Qualification of Safety Related Electrical Equipment PDHonline Course E185 (1 PDH) Environmental Qualification of Safety Related Electrical Equipment Instructor: Gary W Castleberry, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C April 28, 1993

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C April 28, 1993 http://www.nrc.gov/reading-rm/doc-collections/gen-comm/info-notices/1993/in93033.html UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C. 20555 NRC INFORMATION

More information

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-SI-05

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-SI-05 Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Compliance of AP1000 Main Structural Components with ASME III Design Rules MAIN ASSESSMENT AREA RELATED ASSESSMENT AREA(S) RESOLUTION PLAN REVISION GDA

More information

Historical Data Summary of the Systematic Assessment of Licensee Performance

Historical Data Summary of the Systematic Assessment of Licensee Performance NUREG-4 Revision 4 Historical Data Summary of the Systematic Assessment of Licensee Performance Manuscript Completed: October 996 Date Published: October 996 D. Gamberoni Division of Inspection and Support

More information

DRAFT REGULATORY GUIDE

DRAFT REGULATORY GUIDE U.S. NUCLEAR REGULATORY COMMISSION June 2007 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE Contact: Satish Aggarwal (301) 415-6005 DRAFT REGULATORY GUIDE DG-1132 QUALIFICATION

More information

Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009

Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009 Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009 1 Agenda Welcome - Carl Fricker Introductions - Carl Fricker Purpose of the Meeting - Carl Fricker Overview of Salem & Hope Creek

More information

Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants

Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants NUREG-1800 Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Inside Front Cover (NRC to supply)

More information

NEI Draft White Paper. Use of the Generic Letter Process and Alternative Source Terms in the Context of Control Room Habitability

NEI Draft White Paper. Use of the Generic Letter Process and Alternative Source Terms in the Context of Control Room Habitability I. Current Situation A number of plants either have conducted, or plan to conduct in the near term, tracer gas testing of the control room envelope to determine if design and licensing basis inleakage

More information

2010 RadBench Liquid Data Update

2010 RadBench Liquid Data Update 2010 RadBench Liquid Data Update Lisa Edwards LLW & RM Program Manager EPRI 1 What is RadBench??? Tool developed through EPRI based funding for the collection of LLW benchmark data Only Comprehensive Industry

More information

Notice of Intent to Sue for Violations of the Clean Water Act

Notice of Intent to Sue for Violations of the Clean Water Act December 8, 2009 BY CERTIFIED MAIL - RETURN RECEIPT REQUESTED Bill Richter, Manager Thomas A. Korman, Illinois Agent Freeman Coal Industry Mine Freeman United Coal Mining Co., LLC 1480 E. 1200 th St. 222

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly

More information

Managing I&C Obsolescence for Plant Life Extension

Managing I&C Obsolescence for Plant Life Extension Managing I&C Obsolescence for Plant Life Extension IAEA-CN-155/075 Larry Chi Consulting Engineer Bin Zhang Senior Engineer GE-Hitachi Nuclear Energy October 2007 1 Managing I&C Obsolescence for Plant Life

More information

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as

More information

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION COMMISSIONERS: Allison M. Macfarlane, Chairman Kristine L. Svinicki George Apostolakis William D. Magwood, IV William C. Ostendorff In the Matter

More information

AOO \ RS July 23, U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC

AOO \ RS July 23, U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC Exelon. Exelon Generation www.exeloncorp. co Nuclear 4300 Winfield Road WaTrenvi]le, IL 60555 RS-01-143 July 23, 2001 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

More information

Commissioning and Retro Commissioning Programs Title Slide for Energy Efficiency

Commissioning and Retro Commissioning Programs Title Slide for Energy Efficiency Commissioning and Retro Commissioning Programs Title Slide for Energy Efficiency International Conference for Enhanced Building Operations, New York City Amit Kulkarni, Senior Engineer, National Grid Presentation

More information

SPESS F Document Preparation Profile (DPP) Version 04 dated 16 November 2018

SPESS F Document Preparation Profile (DPP) Version 04 dated 16 November 2018 1 SPESS F Document Preparation Profile (DPP) Version 04 dated 16 November 2018 1. IDENTIFICATION Document Category or set of publications to be revised in a concomitant manner: Safety Guides Working ID:

More information

Page 1 / 11. Version 0 June 2014

Page 1 / 11. Version 0 June 2014 Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning

More information

Appendix B. Aging Management Programs and Activities

Appendix B. Aging Management Programs and Activities Appendix B Aging Management Programs and Activities This page is intentionally blank. TABLE OF CONTENTS Table of Contents...i Appendix B: Aging Management Programs and Activities... B.1-1 B.1 INTRODUCTION...

More information

Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants

Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants Wayne Marquino Chairman, ISA S67.04 Committee Team Leader, ESBWR System

More information

APPLICATION OF THE COMMERCIAL GRADE ITEM (CGI) DEDICATION PROCESS FOR PROCUREMENT OF NUCLEAR SAFETY RELATED ITEMS AT NUCLEAR POWER PLANT KRSKO (NEK)

APPLICATION OF THE COMMERCIAL GRADE ITEM (CGI) DEDICATION PROCESS FOR PROCUREMENT OF NUCLEAR SAFETY RELATED ITEMS AT NUCLEAR POWER PLANT KRSKO (NEK) HR9800124 APPLICATION OF THE COMMERCIAL GRADE ITEM (CGI) DEDICATION PROCESS FOR PROCUREMENT OF NUCLEAR SAFETY RELATED ITEMS AT NUCLEAR POWER PLANT KRSKO (NEK) Zoran Heruc, dipl.ing. - NEK Janez Pozar,

More information

NRC Licensing Process for Review of SMRs

NRC Licensing Process for Review of SMRs NRC Licensing Process for Review of SMRs Small Modular Reactors for Nuclear Power LAS/ANS Symposium On Behalf of Commissioner William D. Magwood, IV Commissioner of the U.S. Nuclear Regulatory Commission

More information

APPLICATION OF THE GIP METHODOLOGY TO DEMONSTRATE SEISMIC ADEQUACY OF NEW AND REPLACEMENT EQUIPMENT AND PARTS IN USI A 46 PLANTS

APPLICATION OF THE GIP METHODOLOGY TO DEMONSTRATE SEISMIC ADEQUACY OF NEW AND REPLACEMENT EQUIPMENT AND PARTS IN USI A 46 PLANTS ~ r----------------------------------------------, This material may be protected by Copyright law (Title 17 U.S. Code) PVP-Vol. 275-2. Seismic Engineering - Volume 2 ASME 1994 APPLICATION OF THE GIP METHODOLOGY

More information

Configuration Control during Maintenance of Safety Related Equipment

Configuration Control during Maintenance of Safety Related Equipment International Conference Nuclear Energy for New Europe 2003 Portorož, Slovenia, September 8-11, 2003 http://www.drustvo-js.si/port2003 Configuration Control during Maintenance of Safety Related Equipment

More information

Reverse Engineering Guidance Update

Reverse Engineering Guidance Update Reverse Engineering Guidance Update Marc Tannenbaum Technical Leader RAPID Conference May 15, 2017 What does reverse engineering mean to you? Photo courtesy of NextEra Energy Different tiers exist Items

More information

EPRI Update Procurement Engineering and Supply Chain

EPRI Update Procurement Engineering and Supply Chain EPRI Update Procurement Engineering and Supply Chain Marc H. Tannenbaum Technical Executive Readily Accessible Parts Information Directory Conference and Technical Exhibit May 21, 2018 Recently Completed

More information

Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS

Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS 1.0 INTRODUCTION The significance determination process (SDP) provides a method to place inspection findings in context

More information

Proposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman

Proposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman Proposed Work Plan for Seventh Plan Development October 2, 2014 GRAC Tom Eckman Council s Analytical Process Flow Load Forecast Model Load Forecast Range (without efficiency) Regional Portfolio Model Data

More information

Conversion of NEK Standard Technical Specifications into Improved Technical Specifications

Conversion of NEK Standard Technical Specifications into Improved Technical Specifications International Conference Nuclear Energy for New Europe 2003 Portorož, Slovenia, September 8-11, 2003 http://www.drustvo-js.si/port2003 Conversion of NEK Standard Technical Specifications into Improved

More information

CONTENTS. Section Title Page 1.0 SUMMARY TEST SPECIMENS TEST PROGRAM Pretest Inspection Thermal Aging 3

CONTENTS. Section Title Page 1.0 SUMMARY TEST SPECIMENS TEST PROGRAM Pretest Inspection Thermal Aging 3 CONTENTS Section Title Page 1.0 SUMMARY 1 2.0 TEST SPECIMENS 1 3.0 TEST PROGRAM 3 3.1 Pretest Inspection 3 3.2 Thermal Aging 3 3.3 Radiation Exposure 6 3.4 Loss of Coolant Accident and 6 Main Steamline

More information

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Resolution Plan for GI-AP1000-RC-01 Accident Source Terms. Protection, PSA and Fault Studies

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Resolution Plan for GI-AP1000-RC-01 Accident Source Terms. Protection, PSA and Fault Studies Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Accident Source Terms MAIN ASSESSMENT AREA Reactor Chemistry RELATED ASSESSMENT AREA(S) Radiation Protection, PSA and Fault Studies RESOLUTION PLAN REVISION

More information

Equipment Qualification of Accident Monitoring Equipment for Severe Accidents

Equipment Qualification of Accident Monitoring Equipment for Severe Accidents Equipment Qualification of Accident Monitoring Equipment for Severe Accidents James F. Gleason, P.E. November 2018 Fukushima Lessons Learned SA License Requirements IEEE 497-2016 / RG 1.97 SAMG Qualification

More information

Farm Energy IQ. Future. Tom Manning, New Jersey Agricultural Experiment Station

Farm Energy IQ. Future. Tom Manning, New Jersey Agricultural Experiment Station Farm Energy IQ Farms Farm Today Energy Securing Audits Our Energy Future Tom Manning, New Jersey Agricultural Experiment Station An energy audit is the process of determining energy consumption of a building

More information

EXTRABUDGETARY PROGRAMME ON SAFETY ASPECTS OF LONG TERM OPERATION OF WATER MODERATED REACTORS

EXTRABUDGETARY PROGRAMME ON SAFETY ASPECTS OF LONG TERM OPERATION OF WATER MODERATED REACTORS IAEA-EBP-LTO-03 21-05-04 EXTRABUDGETARY PROGRAMME ON SAFETY ASPECTS OF LONG TERM OPERATION OF WATER MODERATED REACTORS STANDARD REVIEW PROCESS INTERNATIONAL ATOMIC ENERGY AGENCY 1. INTRODUCTION The number

More information

NUCLEAR QUALITY ASSURANCE MANUAL

NUCLEAR QUALITY ASSURANCE MANUAL NUCLEAR QUALITY ASSURANCE MANUAL COLUMBIANA HI TECH 1621 Old Greensboro Road, Kernersville, NC 27284 INTRODUCTION The Columbiana Hi Tech. Nuclear Quality Assurance Manual for 10 CFR Part 71, Subpart H,

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION ADVISORY COMMITTEE ON REACTOR SAFEGUARDS WASHINGTON, DC January 24, 2011

UNITED STATES NUCLEAR REGULATORY COMMISSION ADVISORY COMMITTEE ON REACTOR SAFEGUARDS WASHINGTON, DC January 24, 2011 UNITED STATES NUCLEAR REGULATORY COMMISSION ADVISORY COMMITTEE ON REACTOR SAFEGUARDS WASHINGTON, DC 20555-0001 January 24, 2011 The Honorable Gregory B. Jaczko Chairman U.S. Nuclear Regulatory Commission

More information

May 10, 2012 DUANE ARNOLD ENERGY CENTER NRC INTEGRATED INSPECTION REPORT /

May 10, 2012 DUANE ARNOLD ENERGY CENTER NRC INTEGRATED INSPECTION REPORT / UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 10, 2012 Mr. Peter Wells Vice President NextEra Energy Duane Arnold, LLC 3277 DAEC Road

More information

EMERGENCY VEHICLE TRAFFIC SIGNAL PRE-EMPTION AND ENTRANCE SIGNALS

EMERGENCY VEHICLE TRAFFIC SIGNAL PRE-EMPTION AND ENTRANCE SIGNALS Page 1 of 3 RECOMMENDED PRACTICES PART SECTION SUB-SECTION TRAFFIC SIGNALS General Emergency vehicle pre-emption may be considered if emergency vehicles are consistently having difficulty responding to

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

Part 192 Corrosion Enforcement Guidance

Part 192 Corrosion Enforcement Guidance Part 192 Corrosion Enforcement Introduction The materials contained in this document consist of guidance, techniques, procedures and other information for internal use by the PHMSA pipeline safety enforcement

More information

DRAFT REGULATORY GUIDE

DRAFT REGULATORY GUIDE U.S. NUCLEAR REGULATORY COMMISSION April 2015 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE DRAFT REGULATORY GUIDE DG-1322 (Proposed New Regulatory Guide) Technical Lead Steven

More information

Implementation of the Rules for the Continued Operation in Korea

Implementation of the Rules for the Continued Operation in Korea Implementation of the Rules for the Continued Operation in Korea Presented by Jong-Jooh Jooh Kwon Contents I. Dynamic and Innovative Nuclear Energy Activities in Korea II. Process Implementing requirements

More information

Proposed - For Interim Use and Comment

Proposed - For Interim Use and Comment Proposed - For Interim Use and Comment U.S. NUCLEAR REGULATORY COMMISSION DESIGN-SPECIFIC REVIEW STANDARD FOR mpower TM ipwr DESIGN 14.2 INITIAL PLANT TEST PROGRAM - DESIGN CERTIFICATION AND NEW LICENSE

More information

SOLANO COUNTY WATER AGENCY

SOLANO COUNTY WATER AGENCY SOLANO COUNTY WATER AGENCY Grant E-67020 Evapotranspiration Controller System Project P.O. Box 349 6040 Vaca Station Road, Building 84 Elmira, California 95625-0349 Phone (707) 451-6090 FAX (707) 451-6099

More information

BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS]

BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS] BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS] 13 th Annual RETS-REMP Meeting Dr. Jason C. Jang US Nuclear Regulatory Commission June 23-25, 2003 Pittsburgh, Pennsylvania Capturing

More information

Overview of SQUG generic implementation procedure (GIP)

Overview of SQUG generic implementation procedure (GIP) Nuclear Engineering and Design 123 (1990) 225-231 North-Holland 225 Overview of SQUG generic implementation procedure (GIP) Richard G. Starck II MPR Associates, Inc., 1050 Connecticut Avenue, N. w.. Washington,

More information

MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr

MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 50 kbtu/sf/yr 45.1 PROJECT INFORMATION 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 13.0 kbtu/ft2/yr Baseline 10.8 kbtu/ft2/yr

More information

Russian Federal Nuclear and Radiation Safety Inspectorate (Gosatomnadzor) FEDERAL RULES AND REGULATIONS ON THE USE OF NUCLEAR ENERGY

Russian Federal Nuclear and Radiation Safety Inspectorate (Gosatomnadzor) FEDERAL RULES AND REGULATIONS ON THE USE OF NUCLEAR ENERGY Translated from Russian Russian Federal Nuclear and Radiation Safety Inspectorate (Gosatomnadzor) FEDERAL RULES AND REGULATIONS ON THE USE OF NUCLEAR ENERGY APPROVED BY Gosatomnadzor Resolution No. 4 of

More information

COMMERCIAL GRADE DEDICATION OF RELAP5-3D

COMMERCIAL GRADE DEDICATION OF RELAP5-3D COMMERCIAL GRADE DEDICATION OF RELAP5-3D D. Prelewicz Information Systems Laboratories, Inc. 11140 Rockville Pike, Suite 650 Rockville, MD 20850, USA danp@islinc.com B. Wolf, C. Delfino NuScale Power,

More information

Quality Assurance Requirements for Nuclear Facility Applications. March 2019 Draft Revisions

Quality Assurance Requirements for Nuclear Facility Applications. March 2019 Draft Revisions ASME NQA 1 20XX (Proposed revision of ASME NQA 1 2017) Quality Assurance Requirements for Nuclear Facility Applications March 2019 Draft Revisions TENTATIVE SUBJECT TO REVISION OR WITHDRAWAL Specific Authorization

More information

Draft Regulatory Guide DG-1080 (Proposed Revision 3 of Regulatory Guide 1.149)

Draft Regulatory Guide DG-1080 (Proposed Revision 3 of Regulatory Guide 1.149) Draft Regulatory Guide DG-1080(Proposed Revi... Page 1 of 6 U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REGULATORY RESEARCH August 1999 Division 1 Draft DG-1080 DRAFT REGULATORY GUIDE Contact:

More information

Motor Ratings and Qualified Life Issues

Motor Ratings and Qualified Life Issues Motor Ratings and Qualified Life Issues Presented By: Bill Newell Schulz Electric Company Motor Ratings Motor Ratings Include: Voltage Speed KVA Code Full Load Current Frame Design Allowable Ambient Temperature

More information

DAVID J. HOLLER DETAILED EXPERIENCE

DAVID J. HOLLER DETAILED EXPERIENCE DAVID J. HOLLER EXPERIENCE SUMMARY QA Professional and Technical Specialist with 33 years of nuclear power-related experience. Experience and capabilities include quality program assessment, management

More information

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin APRIL 23, 2014 Capacity Value of Wind Assumptions and Planning Reserve Margin Executive Summary Effective Load Carrying Capacity (ELCC), or capacity value, of variable generation and required planning

More information

Regulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants

Regulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants Regulatory Guide 1.173Developing Software Lif... Page 1 of 10 September 1997 Regulatory Guide 1.173 Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear

More information

RECOMMENDATION 2.3: SEISMIC. The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes:

RECOMMENDATION 2.3: SEISMIC. The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes: RECOMMENDATION 2.3: SEISMIC PURPOSE The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes: To gather information with respect to Near Term Task Force

More information

The Seventh Power Plan The Proposed Mix of Generation Resources and Strategies for the Region

The Seventh Power Plan The Proposed Mix of Generation Resources and Strategies for the Region The Seventh Power Plan The Proposed Mix of Generation Resources and Strategies for the Region Northwest Hydroelectric Association 2015 Fall Regional Workshop Eugene, Oregon October 15, 2015 Outline 1.

More information

Corporation of the City of Pembroke

Corporation of the City of Pembroke Corporation of the City of Pembroke 2015 D.W.Q.M.S. Management Review Report February 2016 D. Burton, Supervisor, Drinking Water Treatment/Compliance 1 City of Pembroke Report M. LeMay Mayor L. Scott D.

More information

REGULATION REGARDING EQUIPMENT PROCUREMENT PROCESS AND APPROVAL OF MANUFACTURERS FOR NUCLEAR FACILITIES

REGULATION REGARDING EQUIPMENT PROCUREMENT PROCESS AND APPROVAL OF MANUFACTURERS FOR NUCLEAR FACILITIES REGULATION REGARDING EQUIPMENT PROCUREMENT PROCESS AND APPROVAL OF MANUFACTURERS FOR NUCLEAR FACILITIES SECTION ONE Purpose, Scope, Basis, Definitions and General Considerations Purpose and scope ARTICLE

More information

EPRI Update Procurement and Supply Chain

EPRI Update Procurement and Supply Chain EPRI Update Procurement and Supply Chain Marc Tannenbaum Technical Leader RAPID Conferences May 5, 2017 Recently Completed EPRI Products (www.epri.com) Prevention and Detection of Undeclared Digital Content

More information

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA)

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA) Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Success Criteria for the Probabilistic Risk Assessment (PSA) MAIN ASSESSMENT AREA RELATED ASSESSMENT AREA(S) RESOLUTION PLAN REVISION GDA ISSUE REVISION

More information

OVERVIEW US EPR EQ Program

OVERVIEW US EPR EQ Program OVERVIEW US EPR EQ Program by Nissen M. Burstein Advisory Engineer, Electrical Systems, New Plants Deployment Presented at NPEC/SC-2 Meeting 07-01 April 17/18, 2007, Myrtle Beach, SC 2 EQ Program > Presentation

More information

Radioactive Materials Released from Nuclear Power Plants

Radioactive Materials Released from Nuclear Power Plants NUREG/CR-2907 BNL-NUREG-51581 Vol. 14 Radioactive Materials Released from Nuclear Power Plants Annual Report 1993 Manuscript Completed: December 1995 Date Published: December 1995 Prepared by J. Tichler,

More information

February 7, 2012 BYRON STATION, UNITS 1 AND 2, NRC INTEGRATED INSPECTION REPORT / ; /

February 7, 2012 BYRON STATION, UNITS 1 AND 2, NRC INTEGRATED INSPECTION REPORT / ; / UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 February 7, 2012 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC

More information

NUCLEAR Untitled /7/11 12:29 PM

NUCLEAR Untitled /7/11 12:29 PM NUCLEAR Untitled-16 1 IMI NUCLEAR - A POWERFUL COMBINATION TRUST IMI Nuclear brings together a powerful combination of brands you know and trust. In fact, over half of the nuclear power plants worldwide

More information

Managing the supply chain: Challenges and Overcoming in Korean nuclear industry

Managing the supply chain: Challenges and Overcoming in Korean nuclear industry Managing the supply chain: Challenges and Overcoming in Korean nuclear industry TM on Topical Issues in the Development of Nuclear Power Infrastructure 4-7 February 2014, Vienna, Austria International

More information

August 1, 2014 SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 NRC INTEGRATED INSPECTION REPORT / ; /

August 1, 2014 SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 NRC INTEGRATED INSPECTION REPORT / ; / UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 August 1, 2014 Mr. Michael J. Pacilio Senior VP, Exelon Generation Co., LLC President and CNO,

More information

Environmental qualification and maintenance of the qualified state of equipment in operating nuclear power plant

Environmental qualification and maintenance of the qualified state of equipment in operating nuclear power plant Hungarian Atomic Energy Authority Guideline 4.13 Environmental qualification and maintenance of the qualified state of equipment in operating nuclear power plant Version number: 2. 2007 March Issued by:

More information

Essential Mathematics 2019 v1.1

Essential Mathematics 2019 v1.1 Problem-solving and modelling task This sample has been compiled by the QCAA to assist and support teachers to match evidence in student responses to the characteristics described in the instrument-specific

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA May 1, 2012

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA May 1, 2012 UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 May 1, 2012 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC

More information

The Use of a Graded Approach in the Application of Safety Requirements for Research Reactors

The Use of a Graded Approach in the Application of Safety Requirements for Research Reactors The Use of a Graded Approach in the Application of Safety Requirements for Research Reactors H. Abou Yehia Research Reactor Safety Section Division of Nuclear Installation Safety International Atomic Energy

More information

Tools available to Station Operators

Tools available to Station Operators Tools available to Station Operators 5 th O&M Workshop, Vienna, 5-9 October 2015 Presented by: Marina Malakhova, Klas Elmgren IDC/OPS/MFO Contributors: S. Nikolova, K. Aktas, M. Lee, S. Mickevicius, E.

More information

An Overview of IEC Activities on Instrument Condition Monitoring for NPPs Pave The Road Towards Condition Based Qualification

An Overview of IEC Activities on Instrument Condition Monitoring for NPPs Pave The Road Towards Condition Based Qualification An Overview of IEC Activities on Instrument Condition Monitoring for NPPs Pave The Road Towards Condition Based Qualification Daowei Bi Representing Sub-Committee 45A (SC45A) International Electrotechnical

More information

LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr

LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 40 kbtu/sf/yr 35 kbtu/sf/yr 30 kbtu/sf/yr 25 kbtu/sf/yr 20 kbtu/sf/yr 15 kbtu/sf/yr 10 kbtu/sf/yr 5 kbtu/sf/yr 0 kbtu/sf/yr 11.9 kbtu/ft2/yr 36.0

More information

Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope

Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope Sandra Julià Technical Project Officer April 18th 2018 Introduction ITER Diagnostics

More information

DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06

DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06 DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06 Kenneth J. Schrader, MSNE Pacific Gas & Electric Co. PO Box 56 Avila Beach, CA 93424 kjse@pge.com

More information