Inspection Results by Plant 2017
|
|
- Alexia Johnson
- 6 years ago
- Views:
Transcription
1 Fall 2017 EQ Technical Conference November 8-10, 2017 Clearwater, Florida William Horin, Winston & Strawn, LLP (Counsel to NUGEQ Ron Wise, NEQ Consulting (NUGEQ Technical Consultant
2 High Level Overview Currently, 13 of the 17 EQ DBA Inspections scheduled for 2017 have been completed Inspections have occurred across all 4 NRC regions 3 in NRC Region I 4 in NRC Region II 3 in NRC Region III 3 in NRC Region IV 2
3 Inspection Results for Region I Region I Station Date Results Remarks Hope Creek Week 1: May 8, 2017 Week 2: May 22, Green NCV (Violation of TS ) for failure to maintain secondary containment IR / Millstone Week 1: July 31, 2017 Week 2: Aug 14, 2017 Ginna Week 1: Aug 7, 2017 Week 2: Aug 21, 2017 integrity 1 Green NCV (Violation of TS a) for not implementing procedures as required by RG 1.33 No NRC identified or self revealing findings were identified IR / & IR / IR /
4 Inspection Results for Region II Region I Station Date Results Remarks McGuire Week 1: Jan 23, 2017 Week 2: Feb 6, Green NCV (App B, Criterion III) for failure to translate requirements necessary to maintain qualification of Namco LS 1 st EQ DBAI IR / & IR / Watts Bar Week 1: June 5, 2017 Week 2: June 19, Green NCV (App B Criterion V) for failure to implement instructions necessary maintain qualification of Namco LS 1 Green NCV (50.49(j)) for failure to maintain a complete record of qualification for Brand-Rex Cables 3 Unresolved Items IR / & IR /
5 Inspection Results for Region II (continued) Region I Station Date Results Remarks Hatch Week 1: Aug 14, 2017 Week 2: Aug 28, 2017 No NRC identified or self revealing findings were identified 2 Unresolved Items IR / & IR / Robinson Week 1: Oct 2, 2017 Week 2: Oct 16, Green NCVs 2 NOVs (Significance TBD) 5 Unresolved Items Exited on 10/31/17 5
6 Inspection Results for Region III Region III Station Date Results Remarks Fermi Week 1: May 8, 2017 Week 2: May 22, Green NCV (App B, Criterion III) involving protective devices in MCCs 1 Green NCV (50.49 (e)(1)) involving two examples related to post accident op-time calculations 1 Green NCV (App B, Criterion III) on failure to translate requirement into maintenance procedures 1 Licensee Identified violation for 10 CFR 50.49(k) IR /
7 Inspection Results for Region III (continued) Region III Station Date Results Remarks LaSalle Week 1: June 26, 2017 Week 2: July 10, Green NCV (50.49 (f)(4)) for failure to provide adequate analysis in combination with partial type testing 1 Green NCV (50.49 (j)) for failure to have adequate justification for extending service life of grease IR / & IR /
8 Inspection Results for Region III (continued) Region III Station Date Results Remarks Monticello Week 1: Sept 18, 2017 No NRC identified or self revealing Exited on 10/6/2017 Week 2: Oct 2, 2017 findings were identified 8
9 Inspection Results for Region IV Region IV Station Date Results Remarks Wolf Creek Week 1: May 8, 2017 Week 2: May 22, Green NCV (50.54 (q)(2)) for failure to maintain the effectiveness of the E-Plan upon loss of CHRRM IR / ANO Week 1: July 24, 2017 Week 2: Aug 7, Green NCV (App B, Criterion XVI) for failure to promptly identify and correct an inadequate design basis calculation IR / & IR / Cooper Week 1: Aug 24, 2017 Week 2: Aug 28, 2017 No findings were identified. IR /
10 10 So what were the two NOVs at Robinson? #1 Failure to perform adequate similarity analysis between Westinghouse prototype and installed Crouse-Hinds EPA #2 Qualified Life of ASCO NP-1 coils based on activation energy from a different material (MW35 vs. MW16). Related to use of NUGEQ memo. Both categorized as Significance TBD at (final) exit
11 Unresolved Items Region I: None Region II: 10 3 at Watts Bar 2 at Hatch 5 at Robinson Region III: None Region IV: None 11
12 So what is the significance of these URIs? Several of these URI s have generic implications To other licensees To vendors To other equipment types Some have the potential to change/challenge the CLB for the affected plants URI s in BOLD are related to NUGEQ comments 12
13 Unresolved Items at Watts Bar URI #1 Potential Failure to Address Environmental Qualification of Brand-Rex Cables Centered around the derivation of the activation energy for the cable insulation NRC challenged method that eliminated one data point (highest temperature) since it reflected the presences of a 2 nd order reaction 13
14 Unresolved Items at Watts Bar (continued) URI #2 Potential Failure to Justify Qualification of O-rings by Commercial Grade Dedication Centered around a dedication of O-rings for Barton Transmitters by a 3 rd party approved App B vendor Dedication confirmed material to be same as the baseline EQ certified O-ring NRC challenged why dedication did not include verification Ea or EQ testing for the O-rings 14
15 Unresolved Items at Watts Bar (continued) URI #3 Potential Failure to Address Environmental Qualification of Barton Transmitters Centers around the qualified life of Barton 764 transmitters and justification for deviating from the original 0.5eV activation. 0.92eV values was used by WEC (as well as Barton) for the O-rings 15
16 16 Unresolved Items at Watts Bar (continued) URI #3 Potential Failure to Address Environmental Qualification of Barton Transmitters Due to an anomaly, replacement O-rings were aged using 0.92eV for 14 hours during the test program NRC challenged the justification for deviating from the original 0.5eV value including synergistic effects and uncertainties.
17 Unresolved Items at Hatch URI #1 Potential Failure to Adequately Justify the Activation Energies by Licensee Related to the justification for selecting activation energies for 600V MCC fuses and Zytel 103 used in Scram Solenoid Pilot Valves NRC considered the activation energies being used as non-conservative 17
18 Unresolved Items at Hatch (continued) URI #2 Potential Failure to Adequately Justify the Activation Energies by 10 CFR 50 Appendix B vendors Centers around the adequacy of the licensee s acceptance of vendor s justification for the activation energies for the 600V MCC fuses and the Zytel 103 subcomponent in the SSPV 18
19 Unresolved Items at Robinson URI #1 Qualification of Penetrations Failure to consider UFSAR reference to proposed IEEE standard. Discrepancy regarding ampacity during shortcircuit conditions between RNP calculation and specification 19
20 Unresolved Items at Robinson (continued) URI #2 EQDP-0900 (Crouse-Hinds Penetration) Did not adequately extend the QL to 60 years due to inappropriate application of Arrhenius to determine activation energy and uncertainties. 20
21 Unresolved Items at Robinson (continued) URI #3 EQDP-0401 (Rosemount Transmitters) Unjustified use of single activation energy (0.78eV). NRC believes RNP should have considered multiple ev values over temperature range RNP provided insight from RNII describing the appropriateness of Ea used in QL Calculation 21
22 Unresolved Items at Robinson (continued) URI #4 Chemical Spray Qualification Maximum ph stated in TS Bases and UFSAR is The EQ Zone map and supporting WCAP calculation indicate max ph of A GSI-191 calculation shows a max ph of
23 Unresolved Items at Robinson (continued) URI #5 Penetration Submergence Qualification Submergence qualification of electrical penetration F-01 not proven. Issue previously identified by NRC in 1980s and drove modification. Closed by NRC in
24 Questions or Comments? 24
EQ-Related Enforcement Activity
EQ-Related Enforcement Activity Fall 2014 EQ Technical Conference Nuclear Utility Group on Equipment Qualification November 10-14, 2014 Clearwater, Florida William Horin, Winston & Strawn, LLP (Counsel
More informationQualified Life - Challenge or Challenger Rick Weinacht October 31, October 31, Curtiss-Wright
Qualified Life - Challenge or Challenger Rick Weinacht October 31, 2018 2 October 31, 2018 2018 Curtiss-Wright Challenge vs. Challenger CHALLENGE CHALLENGER Presented at the IEEE Symposium on Nuclear Power
More informationNRC Activities. Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation
NRC Activities Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation Agenda Nuclear Power Plant Reviews Inspection News Regulatory Guide News Research Activities IEC/IEEE Joint
More information2014 Equipment Qualification Technical Meeting Agenda
2014 Equipment Qualification Technical Meeting Agenda Dates Monday - Tuesday, November 10-11, 2014, EQ Advanced Training Wednesday Thursday & half day Friday, November 12-14, 2014, EQ Technical Meeting
More informationChallenges in The Environmental Qualification of First of A Kind Components
Challenges in The Environmental Qualification of First of A Kind Components Jeffrey Jacobson Office of New Reactors November 9, 2017 1 Problem Statement Many environmental qualification activities are
More informationNUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S.
NUPIC General Membership and Vendor Meetings June 2014 Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S. NRC 1 Insights from the Fukushima Event 2014 NRC Vendor Inspections Recent
More informationRe-Defining the Harsh / Mild Environmental Threshold for EQ
Re-Defining the Harsh / Mild Environmental Threshold for EQ Iepson Consulting Enterprises, Inc. (ICE) IEEE Meeting, October 4, 2005 What is the Harsh / Mild Threshold for EQ? The values for a set of environmental
More informationINPO Health Report Initiative
Fall 2014 Joint EQ Technical Conference November 4-6, 2014 Sand Key, Florida William Horin, Winston & Strawn, LLP (whorin@winston.com) Ronald Wise, NEQ Consulting (ronwise@aol.com) Today s topic is intended
More informationNRC INSPECTION MANUAL INSPECTION PROCEDURE 35065
NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications
More informationJuly 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC
July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 SUBJECT: Petition Pursuant to 10 CFR 2.206 Demand For Information Regarding
More informationEnvironmental Qualification of
Environmental Qualification of Safety Related Electrical Equipment for Nuclear Power Plants Gary W Castleberry PE PMP Gary W. Castleberry 1 of 63 Learning Modules 1. What is Environmental Qualification
More informationGreg Galletti & Richard McIntyre Quality Electrical Vendor Branch Quality Mechanical Vendor Branch Office of New Reactors U.S. NRC
NUPIC General Membership Meeting and Vendor Conference June 2015 Greg Galletti & Richard McIntyre Quality Electrical Vendor Branch Quality Mechanical Vendor Branch Office of New Reactors U.S. NRC 1 Update
More informationNRC INSPECTION MANUAL
NRC INSPECTION MANUAL INSPECTION PROCEDURE CQV/EQV INSPECTION OF COMMERCIAL-GRADE DEDICATION PROGRAMS PROGRAM APPLICABILITY: 2504, 2507, 2700-01 INSPECTION OBJECTIVES 01.01 To verify that the dedicating
More informationEnvironmental Qualification Program for Krsko NPP
HR9800119 Environmental Qualification Program for Krsko NPP Janko Cerjak, Peter Klenovsek Nuclear Power Plant Krsko, Vrbina 12, Krsko, SLOVENIA Janez Pavsek Elektroinstitut Milan Vidmar, Hajdrihova 2,
More informationNRC INSPECTION MANUAL
NRC INSPECTION MANUAL NMSS/RII INSPECTION PROCEDURE MECHANICAL COMPONENTS PROGRAM APPLICABILITY: 2630-01 INSPECTION OBJECTIVES 01.01 To determine whether the technical requirements detailed or referenced
More informationUS REGULATORY OVERSIGHT OF COMMERCIAL-GRADE DEDICATION
US REGULATORY OVERSIGHT OF COMMERCIAL-GRADE DEDICATION KERRI KAVANAGH CHIEF OF THE QUALITY ASSURANCE VENDOR INSPECTION BRANCH- 2, OFFICE OF NEW REACTORS, US NUCLEAR REGULATORY COMMISSION Agenda Background
More informationREGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH. REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006)
U.S. NUCLEAR REGULATORY COMMISSION March 2007 Revision 1 REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006) DAMPING VALUES FOR
More informationMaintaining Seismic Qualification
Nuclear Division Maintaining Seismic Qualification 1 May 17, 2016 2014 Curtiss-Wright A white paper is being developed in IEEE 344 to identify changes that may impact seismic qualification Working group
More informationAccepting Supplier ISO 9000 Quality Programs
Accepting Supplier ISO 9000 Quality Programs IEEE Subcommittee on Qualification October 7-8, 2004 Leigh A. Aparicio PSE Technical Leader aparicio@epri.com Project Overview ISO 9000 Phase I Initiated in
More informationAPPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS
APPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS This Page Intentionally Left Blank E-ii E.1 INTRODUCTION The NRC Advisory
More informationLifetime Extension of Nuclear I&C I & C Obsolescence and PLEX October 27, 2016 Curtiss-Wright Nuclear Division
Lifetime Extension of Nuclear I&C I & C Obsolescence and PLEX October 27, 2016 Curtiss-Wright Nuclear Division 1 November 3, 2016 Proprietary 2014 Curtiss-Wright It all started on the sands of Kitty Hawk
More informationASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1
ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 Karte: Wikipedia CIS GmbH Experts in ASME Code Consulting CIS GmbH Consulting Inspection Services 3 rd Party Inspection Training
More informationMarch 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC
ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,
More informationREQUIREMENTS FOR SAFETY RELATED (ASME AND NON-ASME) ITEMS OR SERVICES
Special Quality Assurance Documents (SQAD) (Continued) SQAD-1 REQUIREMENTS FOR SAFETY RELATED (ASME AND NON-ASME) ITEMS OR SERVICES 1.1 QA PROGRAM: Items or services supplied under the PO/ Contract shall
More informationEnvironmental Qualification of Safety Related Electrical Equipment
PDHonline Course E185 (1 PDH) Environmental Qualification of Safety Related Electrical Equipment Instructor: Gary W Castleberry, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C April 28, 1993
http://www.nrc.gov/reading-rm/doc-collections/gen-comm/info-notices/1993/in93033.html UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C. 20555 NRC INFORMATION
More informationWestinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-SI-05
Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Compliance of AP1000 Main Structural Components with ASME III Design Rules MAIN ASSESSMENT AREA RELATED ASSESSMENT AREA(S) RESOLUTION PLAN REVISION GDA
More informationHistorical Data Summary of the Systematic Assessment of Licensee Performance
NUREG-4 Revision 4 Historical Data Summary of the Systematic Assessment of Licensee Performance Manuscript Completed: October 996 Date Published: October 996 D. Gamberoni Division of Inspection and Support
More informationDRAFT REGULATORY GUIDE
U.S. NUCLEAR REGULATORY COMMISSION June 2007 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE Contact: Satish Aggarwal (301) 415-6005 DRAFT REGULATORY GUIDE DG-1132 QUALIFICATION
More informationSalem/Hope Creek License Renewal Presentation to the NRC March 16, 2009
Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009 1 Agenda Welcome - Carl Fricker Introductions - Carl Fricker Purpose of the Meeting - Carl Fricker Overview of Salem & Hope Creek
More informationStandard Review Plan for Review of License Renewal Applications for Nuclear Power Plants
NUREG-1800 Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Inside Front Cover (NRC to supply)
More informationNEI Draft White Paper. Use of the Generic Letter Process and Alternative Source Terms in the Context of Control Room Habitability
I. Current Situation A number of plants either have conducted, or plan to conduct in the near term, tracer gas testing of the control room envelope to determine if design and licensing basis inleakage
More information2010 RadBench Liquid Data Update
2010 RadBench Liquid Data Update Lisa Edwards LLW & RM Program Manager EPRI 1 What is RadBench??? Tool developed through EPRI based funding for the collection of LLW benchmark data Only Comprehensive Industry
More informationNotice of Intent to Sue for Violations of the Clean Water Act
December 8, 2009 BY CERTIFIED MAIL - RETURN RECEIPT REQUESTED Bill Richter, Manager Thomas A. Korman, Illinois Agent Freeman Coal Industry Mine Freeman United Coal Mining Co., LLC 1480 E. 1200 th St. 222
More informationWatts Bar Nuclear Plant Unit 2 Completion Project
Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly
More informationManaging I&C Obsolescence for Plant Life Extension
Managing I&C Obsolescence for Plant Life Extension IAEA-CN-155/075 Larry Chi Consulting Engineer Bin Zhang Senior Engineer GE-Hitachi Nuclear Energy October 2007 1 Managing I&C Obsolescence for Plant Life
More informationRegulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants
Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as
More informationUNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION COMMISSIONERS: Allison M. Macfarlane, Chairman Kristine L. Svinicki George Apostolakis William D. Magwood, IV William C. Ostendorff In the Matter
More informationAOO \ RS July 23, U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC
Exelon. Exelon Generation www.exeloncorp. co Nuclear 4300 Winfield Road WaTrenvi]le, IL 60555 RS-01-143 July 23, 2001 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
More informationCommissioning and Retro Commissioning Programs Title Slide for Energy Efficiency
Commissioning and Retro Commissioning Programs Title Slide for Energy Efficiency International Conference for Enhanced Building Operations, New York City Amit Kulkarni, Senior Engineer, National Grid Presentation
More informationSPESS F Document Preparation Profile (DPP) Version 04 dated 16 November 2018
1 SPESS F Document Preparation Profile (DPP) Version 04 dated 16 November 2018 1. IDENTIFICATION Document Category or set of publications to be revised in a concomitant manner: Safety Guides Working ID:
More informationPage 1 / 11. Version 0 June 2014
Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning
More informationAppendix B. Aging Management Programs and Activities
Appendix B Aging Management Programs and Activities This page is intentionally blank. TABLE OF CONTENTS Table of Contents...i Appendix B: Aging Management Programs and Activities... B.1-1 B.1 INTRODUCTION...
More informationDevelopment of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants
Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants Wayne Marquino Chairman, ISA S67.04 Committee Team Leader, ESBWR System
More informationAPPLICATION OF THE COMMERCIAL GRADE ITEM (CGI) DEDICATION PROCESS FOR PROCUREMENT OF NUCLEAR SAFETY RELATED ITEMS AT NUCLEAR POWER PLANT KRSKO (NEK)
HR9800124 APPLICATION OF THE COMMERCIAL GRADE ITEM (CGI) DEDICATION PROCESS FOR PROCUREMENT OF NUCLEAR SAFETY RELATED ITEMS AT NUCLEAR POWER PLANT KRSKO (NEK) Zoran Heruc, dipl.ing. - NEK Janez Pozar,
More informationNRC Licensing Process for Review of SMRs
NRC Licensing Process for Review of SMRs Small Modular Reactors for Nuclear Power LAS/ANS Symposium On Behalf of Commissioner William D. Magwood, IV Commissioner of the U.S. Nuclear Regulatory Commission
More informationAPPLICATION OF THE GIP METHODOLOGY TO DEMONSTRATE SEISMIC ADEQUACY OF NEW AND REPLACEMENT EQUIPMENT AND PARTS IN USI A 46 PLANTS
~ r----------------------------------------------, This material may be protected by Copyright law (Title 17 U.S. Code) PVP-Vol. 275-2. Seismic Engineering - Volume 2 ASME 1994 APPLICATION OF THE GIP METHODOLOGY
More informationConfiguration Control during Maintenance of Safety Related Equipment
International Conference Nuclear Energy for New Europe 2003 Portorož, Slovenia, September 8-11, 2003 http://www.drustvo-js.si/port2003 Configuration Control during Maintenance of Safety Related Equipment
More informationReverse Engineering Guidance Update
Reverse Engineering Guidance Update Marc Tannenbaum Technical Leader RAPID Conference May 15, 2017 What does reverse engineering mean to you? Photo courtesy of NextEra Energy Different tiers exist Items
More informationEPRI Update Procurement Engineering and Supply Chain
EPRI Update Procurement Engineering and Supply Chain Marc H. Tannenbaum Technical Executive Readily Accessible Parts Information Directory Conference and Technical Exhibit May 21, 2018 Recently Completed
More informationAppendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS
Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS 1.0 INTRODUCTION The significance determination process (SDP) provides a method to place inspection findings in context
More informationProposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman
Proposed Work Plan for Seventh Plan Development October 2, 2014 GRAC Tom Eckman Council s Analytical Process Flow Load Forecast Model Load Forecast Range (without efficiency) Regional Portfolio Model Data
More informationConversion of NEK Standard Technical Specifications into Improved Technical Specifications
International Conference Nuclear Energy for New Europe 2003 Portorož, Slovenia, September 8-11, 2003 http://www.drustvo-js.si/port2003 Conversion of NEK Standard Technical Specifications into Improved
More informationCONTENTS. Section Title Page 1.0 SUMMARY TEST SPECIMENS TEST PROGRAM Pretest Inspection Thermal Aging 3
CONTENTS Section Title Page 1.0 SUMMARY 1 2.0 TEST SPECIMENS 1 3.0 TEST PROGRAM 3 3.1 Pretest Inspection 3 3.2 Thermal Aging 3 3.3 Radiation Exposure 6 3.4 Loss of Coolant Accident and 6 Main Steamline
More informationWestinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Resolution Plan for GI-AP1000-RC-01 Accident Source Terms. Protection, PSA and Fault Studies
Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Accident Source Terms MAIN ASSESSMENT AREA Reactor Chemistry RELATED ASSESSMENT AREA(S) Radiation Protection, PSA and Fault Studies RESOLUTION PLAN REVISION
More informationEquipment Qualification of Accident Monitoring Equipment for Severe Accidents
Equipment Qualification of Accident Monitoring Equipment for Severe Accidents James F. Gleason, P.E. November 2018 Fukushima Lessons Learned SA License Requirements IEEE 497-2016 / RG 1.97 SAMG Qualification
More informationFarm Energy IQ. Future. Tom Manning, New Jersey Agricultural Experiment Station
Farm Energy IQ Farms Farm Today Energy Securing Audits Our Energy Future Tom Manning, New Jersey Agricultural Experiment Station An energy audit is the process of determining energy consumption of a building
More informationEXTRABUDGETARY PROGRAMME ON SAFETY ASPECTS OF LONG TERM OPERATION OF WATER MODERATED REACTORS
IAEA-EBP-LTO-03 21-05-04 EXTRABUDGETARY PROGRAMME ON SAFETY ASPECTS OF LONG TERM OPERATION OF WATER MODERATED REACTORS STANDARD REVIEW PROCESS INTERNATIONAL ATOMIC ENERGY AGENCY 1. INTRODUCTION The number
More informationNUCLEAR QUALITY ASSURANCE MANUAL
NUCLEAR QUALITY ASSURANCE MANUAL COLUMBIANA HI TECH 1621 Old Greensboro Road, Kernersville, NC 27284 INTRODUCTION The Columbiana Hi Tech. Nuclear Quality Assurance Manual for 10 CFR Part 71, Subpart H,
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION ADVISORY COMMITTEE ON REACTOR SAFEGUARDS WASHINGTON, DC January 24, 2011
UNITED STATES NUCLEAR REGULATORY COMMISSION ADVISORY COMMITTEE ON REACTOR SAFEGUARDS WASHINGTON, DC 20555-0001 January 24, 2011 The Honorable Gregory B. Jaczko Chairman U.S. Nuclear Regulatory Commission
More informationMay 10, 2012 DUANE ARNOLD ENERGY CENTER NRC INTEGRATED INSPECTION REPORT /
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 10, 2012 Mr. Peter Wells Vice President NextEra Energy Duane Arnold, LLC 3277 DAEC Road
More informationEMERGENCY VEHICLE TRAFFIC SIGNAL PRE-EMPTION AND ENTRANCE SIGNALS
Page 1 of 3 RECOMMENDED PRACTICES PART SECTION SUB-SECTION TRAFFIC SIGNALS General Emergency vehicle pre-emption may be considered if emergency vehicles are consistently having difficulty responding to
More informationCalifornia Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring
k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends
More informationPart 192 Corrosion Enforcement Guidance
Part 192 Corrosion Enforcement Introduction The materials contained in this document consist of guidance, techniques, procedures and other information for internal use by the PHMSA pipeline safety enforcement
More informationDRAFT REGULATORY GUIDE
U.S. NUCLEAR REGULATORY COMMISSION April 2015 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE DRAFT REGULATORY GUIDE DG-1322 (Proposed New Regulatory Guide) Technical Lead Steven
More informationImplementation of the Rules for the Continued Operation in Korea
Implementation of the Rules for the Continued Operation in Korea Presented by Jong-Jooh Jooh Kwon Contents I. Dynamic and Innovative Nuclear Energy Activities in Korea II. Process Implementing requirements
More informationProposed - For Interim Use and Comment
Proposed - For Interim Use and Comment U.S. NUCLEAR REGULATORY COMMISSION DESIGN-SPECIFIC REVIEW STANDARD FOR mpower TM ipwr DESIGN 14.2 INITIAL PLANT TEST PROGRAM - DESIGN CERTIFICATION AND NEW LICENSE
More informationSOLANO COUNTY WATER AGENCY
SOLANO COUNTY WATER AGENCY Grant E-67020 Evapotranspiration Controller System Project P.O. Box 349 6040 Vaca Station Road, Building 84 Elmira, California 95625-0349 Phone (707) 451-6090 FAX (707) 451-6099
More informationBRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS]
BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS] 13 th Annual RETS-REMP Meeting Dr. Jason C. Jang US Nuclear Regulatory Commission June 23-25, 2003 Pittsburgh, Pennsylvania Capturing
More informationOverview of SQUG generic implementation procedure (GIP)
Nuclear Engineering and Design 123 (1990) 225-231 North-Holland 225 Overview of SQUG generic implementation procedure (GIP) Richard G. Starck II MPR Associates, Inc., 1050 Connecticut Avenue, N. w.. Washington,
More informationMID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 10.8 kbtu/ 2/yr
MID-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 50 kbtu/sf/yr 45.1 PROJECT INFORMATION 40 kbtu/sf/yr 30 kbtu/sf/yr 20 kbtu/sf/yr 10 kbtu/sf/yr 0 kbtu/sf/yr 13.0 kbtu/ft2/yr Baseline 10.8 kbtu/ft2/yr
More informationRussian Federal Nuclear and Radiation Safety Inspectorate (Gosatomnadzor) FEDERAL RULES AND REGULATIONS ON THE USE OF NUCLEAR ENERGY
Translated from Russian Russian Federal Nuclear and Radiation Safety Inspectorate (Gosatomnadzor) FEDERAL RULES AND REGULATIONS ON THE USE OF NUCLEAR ENERGY APPROVED BY Gosatomnadzor Resolution No. 4 of
More informationCOMMERCIAL GRADE DEDICATION OF RELAP5-3D
COMMERCIAL GRADE DEDICATION OF RELAP5-3D D. Prelewicz Information Systems Laboratories, Inc. 11140 Rockville Pike, Suite 650 Rockville, MD 20850, USA danp@islinc.com B. Wolf, C. Delfino NuScale Power,
More informationQuality Assurance Requirements for Nuclear Facility Applications. March 2019 Draft Revisions
ASME NQA 1 20XX (Proposed revision of ASME NQA 1 2017) Quality Assurance Requirements for Nuclear Facility Applications March 2019 Draft Revisions TENTATIVE SUBJECT TO REVISION OR WITHDRAWAL Specific Authorization
More informationDraft Regulatory Guide DG-1080 (Proposed Revision 3 of Regulatory Guide 1.149)
Draft Regulatory Guide DG-1080(Proposed Revi... Page 1 of 6 U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REGULATORY RESEARCH August 1999 Division 1 Draft DG-1080 DRAFT REGULATORY GUIDE Contact:
More informationMotor Ratings and Qualified Life Issues
Motor Ratings and Qualified Life Issues Presented By: Bill Newell Schulz Electric Company Motor Ratings Motor Ratings Include: Voltage Speed KVA Code Full Load Current Frame Design Allowable Ambient Temperature
More informationDAVID J. HOLLER DETAILED EXPERIENCE
DAVID J. HOLLER EXPERIENCE SUMMARY QA Professional and Technical Specialist with 33 years of nuclear power-related experience. Experience and capabilities include quality program assessment, management
More informationAPRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin
APRIL 23, 2014 Capacity Value of Wind Assumptions and Planning Reserve Margin Executive Summary Effective Load Carrying Capacity (ELCC), or capacity value, of variable generation and required planning
More informationRegulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants
Regulatory Guide 1.173Developing Software Lif... Page 1 of 10 September 1997 Regulatory Guide 1.173 Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear
More informationRECOMMENDATION 2.3: SEISMIC. The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes:
RECOMMENDATION 2.3: SEISMIC PURPOSE The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes: To gather information with respect to Near Term Task Force
More informationThe Seventh Power Plan The Proposed Mix of Generation Resources and Strategies for the Region
The Seventh Power Plan The Proposed Mix of Generation Resources and Strategies for the Region Northwest Hydroelectric Association 2015 Fall Regional Workshop Eugene, Oregon October 15, 2015 Outline 1.
More informationCorporation of the City of Pembroke
Corporation of the City of Pembroke 2015 D.W.Q.M.S. Management Review Report February 2016 D. Burton, Supervisor, Drinking Water Treatment/Compliance 1 City of Pembroke Report M. LeMay Mayor L. Scott D.
More informationREGULATION REGARDING EQUIPMENT PROCUREMENT PROCESS AND APPROVAL OF MANUFACTURERS FOR NUCLEAR FACILITIES
REGULATION REGARDING EQUIPMENT PROCUREMENT PROCESS AND APPROVAL OF MANUFACTURERS FOR NUCLEAR FACILITIES SECTION ONE Purpose, Scope, Basis, Definitions and General Considerations Purpose and scope ARTICLE
More informationEPRI Update Procurement and Supply Chain
EPRI Update Procurement and Supply Chain Marc Tannenbaum Technical Leader RAPID Conferences May 5, 2017 Recently Completed EPRI Products (www.epri.com) Prevention and Detection of Undeclared Digital Content
More informationWestinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA)
Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Success Criteria for the Probabilistic Risk Assessment (PSA) MAIN ASSESSMENT AREA RELATED ASSESSMENT AREA(S) RESOLUTION PLAN REVISION GDA ISSUE REVISION
More informationOVERVIEW US EPR EQ Program
OVERVIEW US EPR EQ Program by Nissen M. Burstein Advisory Engineer, Electrical Systems, New Plants Deployment Presented at NPEC/SC-2 Meeting 07-01 April 17/18, 2007, Myrtle Beach, SC 2 EQ Program > Presentation
More informationRadioactive Materials Released from Nuclear Power Plants
NUREG/CR-2907 BNL-NUREG-51581 Vol. 14 Radioactive Materials Released from Nuclear Power Plants Annual Report 1993 Manuscript Completed: December 1995 Date Published: December 1995 Prepared by J. Tichler,
More informationFebruary 7, 2012 BYRON STATION, UNITS 1 AND 2, NRC INTEGRATED INSPECTION REPORT / ; /
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 February 7, 2012 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC
More informationNUCLEAR Untitled /7/11 12:29 PM
NUCLEAR Untitled-16 1 IMI NUCLEAR - A POWERFUL COMBINATION TRUST IMI Nuclear brings together a powerful combination of brands you know and trust. In fact, over half of the nuclear power plants worldwide
More informationManaging the supply chain: Challenges and Overcoming in Korean nuclear industry
Managing the supply chain: Challenges and Overcoming in Korean nuclear industry TM on Topical Issues in the Development of Nuclear Power Infrastructure 4-7 February 2014, Vienna, Austria International
More informationAugust 1, 2014 SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 NRC INTEGRATED INSPECTION REPORT / ; /
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 August 1, 2014 Mr. Michael J. Pacilio Senior VP, Exelon Generation Co., LLC President and CNO,
More informationEnvironmental qualification and maintenance of the qualified state of equipment in operating nuclear power plant
Hungarian Atomic Energy Authority Guideline 4.13 Environmental qualification and maintenance of the qualified state of equipment in operating nuclear power plant Version number: 2. 2007 March Issued by:
More informationEssential Mathematics 2019 v1.1
Problem-solving and modelling task This sample has been compiled by the QCAA to assist and support teachers to match evidence in student responses to the characteristics described in the instrument-specific
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA May 1, 2012
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 May 1, 2012 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC
More informationThe Use of a Graded Approach in the Application of Safety Requirements for Research Reactors
The Use of a Graded Approach in the Application of Safety Requirements for Research Reactors H. Abou Yehia Research Reactor Safety Section Division of Nuclear Installation Safety International Atomic Energy
More informationTools available to Station Operators
Tools available to Station Operators 5 th O&M Workshop, Vienna, 5-9 October 2015 Presented by: Marina Malakhova, Klas Elmgren IDC/OPS/MFO Contributors: S. Nikolova, K. Aktas, M. Lee, S. Mickevicius, E.
More informationAn Overview of IEC Activities on Instrument Condition Monitoring for NPPs Pave The Road Towards Condition Based Qualification
An Overview of IEC Activities on Instrument Condition Monitoring for NPPs Pave The Road Towards Condition Based Qualification Daowei Bi Representing Sub-Committee 45A (SC45A) International Electrotechnical
More informationLOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE PV Genera on Poten al 17.9 kbtu/ 2/yr
LOW-RISE APARTMENT BUILDING PROTOTYPE HIGH PERFORMANCE 40 kbtu/sf/yr 35 kbtu/sf/yr 30 kbtu/sf/yr 25 kbtu/sf/yr 20 kbtu/sf/yr 15 kbtu/sf/yr 10 kbtu/sf/yr 5 kbtu/sf/yr 0 kbtu/sf/yr 11.9 kbtu/ft2/yr 36.0
More informationInformation Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope
Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope Sandra Julià Technical Project Officer April 18th 2018 Introduction ITER Diagnostics
More informationDIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06
DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06 Kenneth J. Schrader, MSNE Pacific Gas & Electric Co. PO Box 56 Avila Beach, CA 93424 kjse@pge.com
More information