APPENDIX C Configuration Change Management Verification and Validation Procedures

Size: px
Start display at page:

Download "APPENDIX C Configuration Change Management Verification and Validation Procedures"

Transcription

1 DCMA-INST 217 APPENDIX C Configuration Change Management Verification and Validation Procedures

2 Table of Contents C1. Introduction... C-1 C2. Implementation... C-1 C3. Pre-Inspection: Verification... C-1 C3.1. Pre-Inspection: Implementation.... C-1 C3.2. Pre-Inspection: Completeness Requirements.... C-2 C3.3. Pre-Inspection: Coordination Requirements.... C-3 C3.4. Pre-Inspection: Content Requirements.... C-4 C4. Post-Inspection: ECP Validation... C-5 C4.1. Post-Inspection: ECP Implementation.... C-5 C4.2. Post-Inspection: ECP Document Status (Class I).... C-6 C4.3. Post-Inspection: ECP Configuration Validation.... C-7 A

3 Record of Changes Table Version Date Description 00 11/30/2012 Initial Release 01 03/01/2013 Accomplished minor changes to text for clarity. Added Paragraph C3.4.4., Paragraph C2.2: revised paragraph in its entirety to comply with DCMA-INST 1201, Corrective Action Process. 02 2/15/16 Accomplished minor changes to text for clarity. Adds references to: SAE EIA 649-1, Configuration Management Requirements For Defense Contracts, Nov Adds terminology from SAE EIA B

4 C1. Introduction C1.1. This Appendix provides Configuration Change Management (CCM) document verification and validation procedures for CCM documents. This Appendix supplements the DCMA-INST 217, Configuration Change Management Instruction by adding verification and validation procedures. Verification and validation confirm that the CCM document is a valid configuration control document (verification) and that changes described in the document are incorporated properly into the product Configuration Item (CI) and the Configuration Document (CD) (validation). MIL-HDK-61A, Section 8, Configuration Verification and Audit, Reference (e), and SAE EIA-649-B, Section 5.5, Configuration Verification and Audit, Reference (f), discuss the overall verification and validation of systems. C1.2. Configuration Approval Authority (CAA) introduced by SAE EIA is a synonym for CCM Instruction, Chapter 2, Table 1, Configuration Change Authority (CCA). SAE EIA CAA is used within and should serve as a replacement for CCA. C2. Implementation C2.1. Use of Appendix C, CCM verification and validation procedures, is required by the CCM Instruction, Chapter 3, Procedures, and Appendix B, the Configuration Change Management Documentation Checklist. Appendix A, Configuration Change Management Concepts, Principles, and Guidance, defines principles, guidelines and best practices for each specific CCM document type. C2.2. A Corrective Action Request (CAR) is issued to address contract noncompliance discovered during Pre-Inspection: Verification, Paragraph C3, and Post-Inspection: ECP Validation, Paragraph C4. Refer to CCM Instruction, Chapter 3, Paragraph 3.2.5, for procedures for issuing CARs and for procedures for systemic noncompliance s to the Supplier s Configuration Management (CM) system. (SAE EIA CCM 649B/649-1 Principle CCM-1.) C2.3. DCMA Engineers performing CCM document verification and validation will comply with the Safety and Occupational Health requirements of the CCM Instruction, Chapter 3, Paragraph C3. Pre-Inspection: Verification C3.1. Pre-Inspection: Implementation. (See SAE EIA-649B/649-1 Principle CCM-1.) C A successful pre-inspection verification confirms that the document to be evaluated is a valid Configuration control document and is ready for CAA evaluation. MIL- HDBK-61A, Paragraph 9.2.5, Digital Data Transmittal, discusses the expected format of transmitted CM type documents. C-1

5 C Insufficient, incomplete or systemic CM issues pertaining to this preinspection verification should be discussed with the Supplier, and the CCM document should be returned to the Supplier for correction, clarification or cancellation. The DCMA Engineer should prepare a CAR, as appropriate, in accordance with Paragraph C2.2, to correct any contract noncompliance. (See SAE EIA-649B/649-1 Principle CCM-1.) C3.2. Pre-Inspection: Completeness Requirements. (See SAE EIA-649B/649-1 Principles CCM-2, CCM-3, CCM-4 and CCM-5.) C Upon CCM document receipt, the DCMA Engineer will: C Confirm that the format, structure, form number, and document title are in accordance with approved contract CM provisions, such as the Supplier s Configuration Management Plan (CMP), Contract Data Requirements List, or Statement of Work. MIL-HDBK-61A, Paragraph , ECP Preparation and Submittal, provides information on Acquirer CMPs. C Suppliers may have company or site level process instructions, others will have program specific instructions, and some will have a combination of both. Suppliers may also have CI instructions for a particular program design or acquisition production phase. Obtaining a complete set of all these applicable documents will be required to perform appropriate verification and validation. C Review the classification, justification codes, appropriate identifiers, and other field information attributes for missing or incomplete data. The Supplier s CCM classification rules should match or be synonymous to the Government s classification and guidelines identified in MIL-HDBK-61A, Paragraph 6.2.2, ECP Activity Guides. Appropriate or synonymous identifiers should be identified in related contractual CM documents, such as a CMP or similar document (Paragraph C ). (See MIL-HDBK-61A, Table 6-6, Activity Guide: ECP Content, Subsection: ECP Identification and Administrative Attributes. ). C Review the document for overall completeness. This includes reviewing to confirm that required sections are complete, and that previous corrections or markups are incorporated. A CCM best practice is verifying that empty form CCM document text blocks are acknowledged and recognized with editing marks, such as a hyphen, Not Applicable (NA), being grayed-out, etc., to confirm the document originator intends the text block to be empty. C Confirm that dates are sequential and not dated in the future, that they appear where required, and that their appearance, format and detail are satisfactory for a contractual technical document. C-2

6 C Confirm that the document addresses the appropriate contract number, that it is not confused with another contract or program, and that the document is configured and dedicated to the contract number(s) to which the Engineering Change Proposal (ECP) applies. (See MIL-HDBK-61A, Table 6-6, Activity Guide: ECP Content, Subsection: Contract Information. ) C Verify that the CCM document contains all the information needed to accomplish the engineering changes to the CD. Confirm that the CCM ECP document Technical Data Package (TDP) references valid documents. Review the document package enclosures or attachments for their existence, completeness, quality and clarity. A Notice of Revision document from the Supplier may help. (See MIL-HDBK-61A, Paragraph 6.4, Notice of Revision. ) C3.3. Pre-Inspection: Coordination Requirements. (See SAE EIA-649B/649-1 Principles CCM-6 and CCM-7.) C Upon CCM document receipt, the DCMA Engineer will: C Scan the Supplier department functions and signature blocks appearing in the document. C Verify that all Supplier signatures are complete and dated. Dated signatures should be organized in a normal workflow sequence and start at the lower functional Supplier program tiers or departments. The Government CAA should be the last blank (empty) signatory block in the document. C Verify that the CCM document has been properly coordinated and integrated across all impacted Supplier departments by verifying entries in the appropriate signatory blocks (engineering, quality, manufacturing, assembly, logistics, packaging, etc.). C The verification of appropriate Supplier signatory blocks (departments) is accomplished by reviewing contractual related CM documents, such as the CMP, and comparing them to the CCM document properties (form fields, text blocks). All the appropriate Supplier departments should be identified and listed. C Verification is also accomplished by confirming that all the signatory blocks required are identified and listed. Confirm with the Supplier or CCM document originator that all the required signatory blocks appear in the document. A CCM document TDP requiring packaging, quality review, or another Supplier s department handling, should have packaging, quality, or other listed as one of the signatory blocks. Confirmation can also be accomplished by evaluating the CCM document, making note of the actions required in the document, and noting whether that action had a signatory block listed. C-3

7 C Confirm that the document is being addressed in the normal or regular workflow process. Confirm that the format, document workflow, and sign-offs are equal to previous Supplier CCM documents of the same type. This type of verification helps to prevent unauthorized changes. C3.4. Pre-Inspection: Content Requirements. (See SAE EIA-649B/649-1 Principles CCM-2, CCM-3, CCM-4 and CCM-5.) following: C Upon CCM document receipt, the DCMA Engineer will perform the C Verify that the CCM document TDP contains all the technical information details required to justify disposition (views, figures, drawings, test data, technical analyses, performance data, or white paper). (See MIL-STD-31000, Standard Practice Technical Data Package, MIL-HDBK-61A, Paragraph , ECP Supporting Data, and Table 6-6, Activity Guide: ECP Content, Subsection: Description of Proposed Change. ) C Confirm that an adequate configuration control audit trail exists in the CCM document by verifying before and after conditions are provided in the CCM document or associated TDP. This verification process can be accomplished by capturing the specific before ( was ) condition. This procedure captures the previous configuration before any proposed revision to the CD or CI is accomplished. This practice will also assist in the validation process (Paragraph C4). C Verify that the CCM document description is sufficient in quantity and detail. Poor, unclear, ambiguous, or incomplete technical writing should be cause for rejection. Draft pen-and-ink mark-up or redlines to CDs in the TDP that accompanies the CCM document is acceptable, if the content is clear and provides definition. It is a best practice that TDPs of CCM documents include screen shots of CD or CI areas being changed, with the proposed changes identified. This practice will also assist in the validation process. C Confirm, as applicable, the document s effectivity as follows: C Verify that the effectivity is identified by quantity or range (retrofit/spares/future production) and the manner in which the effectivity will be incorporated (attrition or forced schedule). (See MIL-HDBK-61A, Paragraph , Effectivity, and Table 6-6, Activity Guide: ECP Content. ) C Verify that the same effectivity is addressed throughout the enclosed document TDP, as applicable. C Confirm that the appropriate acquisition or manufacturing production sequence is used and is being established, as applicable (design followed by C-4

8 production). A hardware CCM document would usually be in place before the software is developed. Product testing requires a product to be produced, and human engineering may need product integration to be done first. CI Process One is required to be accomplished and finished before beginning Process Two. C Confirm that the latest TDP CDs or CIs are being utilized to justify the proposed CCM document position. C Assess the product CI design producibility described in the CCM document, as applicable. Producibility is a measure of relative ease of manufacturing a product. The proposed product should be easily and economically fabricated, assembled, inspected, and tested with high quality on the first design or change. Producibility is often difficult to achieve because it may require performance or functionality sacrifices. A new manufacturing process for a design has increased producibility risk. C It is a best practice that the Supplier (CCM document originator) acknowledge and assess the CCM document classification, informing the DCMA Engineer by including a statement in the CCM document similar or equal to, This Class II ECP is in accordance with the CMP, contains no defined Configuration baseline changes and does not alter contract requirements or Government cost or property owned. C CCM documents should include a matrix of Reliability, Availability, and Maintainability assessment that provides an evaluation of cost, schedule, performance, risk, and life cycle metrics impact. (Search Acquisition Community Connection for the DoD Guide For Achieving Reliability, Availability, And Maintainability. ) C Verify that the Supplier has approved the proposed ECP. The ECP should include the Supplier s recommendation. The recommendation should be supported by the Supplier signatures recommending that particular condition. C Confirm the Notice of Revisions (NOR) (DD Form 1695, or similar form), if used, identifies the correct number of drawings scheduled for revisions. A NOR is used to document and define revisions to CDs which require revisions after ECP approval. Consult with the contract or Acquirer regarding the handling and submitting of NORs. C4. Post-Inspection: ECP Validation C4.1. Post-Inspection: ECP Implementation. C Post-Inspection ECP Validation can only be accomplished to approved, revised, and produced CDs and CIs resulting from an approved CCM document. These procedures confirm that the CCM document engineering changes are properly incorporated into the associated CDs for CI production. It is recommended that Post-Inspections ECP Validations C-5

9 precede any product CI signoff or approval by the Government. (See MIL-HDBK-61A, Paragraph 5.7, Engineering Release. ) C The DCMA Engineer will plan all CCM document Post-Inspection ECP Validation procedures in accordance with the DCMA-INST 207, Engineering Surveillance Instruction. C Insufficient, incomplete, or systemic CM issues pertaining to this Post- Inspection: ECP Validation should be discussed with the Supplier, and the previously approved CCM document identified for correction, clarification or cancellation. The DCMA Engineer should prepare a CAR, as appropriate, in accordance with Paragraph C2.2, to correct any contract noncompliance. C The DCMA Engineer will determine if risk resulting from validation testing indicates required or additional regression testing is needed to correct an issue. Regression testing is performed to validate that the modified CDs or CIs do not introduce additional issues or faults that did not exist prior to incorporating ECP change. If risk, cost, or lack of insight dictates that further regression testing may be required, the DCMA Engineer may refer this decision to the Government Program Office (Acquirer) where the risks and risk mitigation techniques are better understood or justified. C4.2. Post-Inspection: ECP Document Status (Class I). C These procedures apply to Class I ECPs. A similar procedure is accomplished to Class II ECPs in Procedure C The DCMA Engineer will: C Periodically, and as required, conduct an assessment of all open Class I ECPs not dispositioned. The Acquirer, Supplier, or DCMA Engineering Change Proposal (ECP)/Request for Variance (RFV) Tracking Log may help identify open Class I ECPs. Class I ECP. C Inquire with the Acquirer and request the status of each open C Offer assistance to satisfy the disposition requirements to closeout open ECPs. Note: Value Engineering Change Proposals (VECPs) have a 45-day Acquirer evaluation period. C The Acquirer should be informed of Class I ECPs not being dispositioned in a timely fashion. Timely disposition of CCM documents allow CDs and Configuration baselines to be updated quickly. Prompt updates are a best practice of appropriate CCM and CM configuration control. (See MIL-HDBK-61A, Paragraph 6.1, Configuration Control Activity, and Appendix D, Paragraph D.1, Scope. ) C-6

10 C4.3. Post-Inspection: ECP Configuration Validation. (See SAE EIA-649B/649-1 Principles CCM-8, CVA-1 and CVA-2.) C Audit the amount of time the Supplier takes to update CDs and product CIs based on CCM document approval. Updates to CDs and product CIs should occur in a timely fashion. Timely updates allow Configuration baselines to be updated quickly. Prompt updates is a CM best practice for appropriate CD Configuration control and prevents later engineering changes from being made to documentation pending an earlier revision. (Refer to the references in Paragraph C for the importance of timely updates.) C A CCM audit will be accomplished to CDs modified by CCM documents. The audit purpose is to verify the traceability (flow down) of approved CCM document TDP requirements into the referenced CDs for appropriate CI production. The CCM audit serves to validate that the CCM document TDP changes are incorporated into the CDs. The DCMA Engineer will perform or support the DCMA Quality Assurance (QA) Personnel in performing the following CCM audit tasks: C Participate in pre-production product examinations as necessary to confirm that the traceability of approved requirements addressed in the CCM document TDP are incorporated into the production CDs. C Select a CCM document and associated TDP for the CCM audit and obtain the associated CCM document CDs. The CCM audit should be performed on production CDs addressed by the CCM document TDP. C Verify the appropriate CD Data Version Control, and that the CCM document changes are incorporated correctly into the CD(s) by: (See MIL-HDBK-61A, Table 5-8, Activity Guide: Engineering Drawing and Associated Lists, and Paragraph 9.2.4, Data Version Control. ) indicator has incremented. is the CCM document. C Verifying that the applicable CD revision C Verifying that the CD revision indicator authority C Confirm that an adequate Configuration control audit trail exists by verifying that the CD revision has before conditions identified or cited. (See Paragraph C ) C Confirm verification of the CD revision by the appearance of Supplier signatures that approve or check the updated CD(s). These CD checkers verify that the individual who incorporated or revised the CD did it correctly. C-7

11 C Spot-check or review the revision to the CD for engineering change depiction accuracy. C Verify that the CCM document is accurately incorporated into the CI. The DCMA Engineer, in coordination with DCMA QA personnel, should reconcile the CCM document by performing a product CI examination after production or assembly, by inspection, and by observing or witnessing appropriate regression testing for adequacy and compliance. (See DCMA-INST 324, Product Evaluation - QA Instruction.) Confirm that the CCM document changes have been incorporated into the deliverable CI properly. The first item of production should be inspected for CCM document requirement incorporation similar to First Article Testing, depending on the change complexity. C Confirm compliance by reviewing the list of approved CDs for use in production. Verify that product CI configuration information and related support assets are updated with the CCM document and requirements. Documents such as the (1) CI production list of CDs, (2) Supplier process manufacturing instructions, (3) test equipment, (4) requirements for spares, (5) retrofit kits, (6) CI operating instructions (logistics), and (7) existing CI orders should be reviewed to verify that the changes identified in the CCM document and TDP are incorporated or addressed in the final product. C The DCMA Engineer will periodically audit the Supplier s Configuration Status Accounting (CSA) identifying effectivity and the installation status of approved CCM engineering changes impacting the CI product. The Supplier s CSA and release program should identify both engineering changes made to the current CIs and those engineering change configuration requirements that were superseded for the product CI being delivered. The Supplier s CSA should detail and log design, production, modification, retrofit, or maintenance changes occurring to the product CIs. The DCMA Engineer will periodically audit the Supplier s CSA for accurate Supplier process information for approved CCM documentation. (See MIL-HDBK-61A Paragraph 5.7, Engineering Release, and Table 7-1, Typical CSA Information Over The Acquisition Program Life Cycle. ) C Each approved CCM document change should be incorporated into all associated and affected CDs within its program CI set (lots, units, mission, design, series, type, model, or series). Released CDs for each CI, at the time of its formal acceptance, should be retained in the associated Supplier release records. This information is of particular importance in the case of warranties associated with the CI or its components. C-8

APPENDIX A Configuration Change Management Concepts, Principles, and Guidance

APPENDIX A Configuration Change Management Concepts, Principles, and Guidance DCMA-INST 217 APPENDIX A Configuration Change Management Concepts, Principles, and Guidance Table Of Contents A1. Introduction... A-1 A2. Configuration Change Management Document Guidance... A-2 A3. Class

More information

AS9003A QUALITY MANUAL

AS9003A QUALITY MANUAL Your Logo AS9003A QUALITY MANUAL Origination Date: (month/year) Document Identifier: Date: Document Status: Document Link: AS9003A Quality Manual Latest Revision Date Draft, Redline, Released, Obsolete

More information

CODE: FD10 Rev: A Date: 9/24/2008 CONFIGURATION MANAGEMENT

CODE: FD10 Rev: A Date: 9/24/2008 CONFIGURATION MANAGEMENT 1.0 Definition of terms: CONFIGURATION MANAGEMENT 1.01 The term shall, will and may are used with specific intent thought-out these documents and will observe the following rules: 1.1 Requirements defined

More information

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017 Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program

More information

DEPARTMENT OF DEFENSE STANDARD PRACTICE FOR CALIBRATION AND MEASUREMENT REQUIREMENTS

DEPARTMENT OF DEFENSE STANDARD PRACTICE FOR CALIBRATION AND MEASUREMENT REQUIREMENTS NOT MEASUREMENT SENSITIVE MIL-STD-1839C 27 November 2000 SUPERSEDING MIL-STD-1839B 20 AUGUST 1995 DEPARTMENT OF DEFENSE STANDARD PRACTICE FOR CALIBRATION AND MEASUREMENT REQUIREMENTS AMSC F4562 AREA QCIC

More information

AEROSPACE STANDARD. (R) Inspection and Test Quality Systems Requirements for Aviation, Space, and Defense Organizations RATIONALE

AEROSPACE STANDARD. (R) Inspection and Test Quality Systems Requirements for Aviation, Space, and Defense Organizations RATIONALE AEROSPACE STANDARD AS9003 Issued 2001-10 Revised 2012-07 REV. A Superseding AS9003 (R) Inspection and Test Quality Systems Requirements for Aviation, Space, and Defense Organizations RATIONALE This standard

More information

TECHNICAL REPORT EIA Configuration Management Requirements For Defense Contracts. Issued RATIONALE

TECHNICAL REPORT EIA Configuration Management Requirements For Defense Contracts. Issued RATIONALE TECHNICAL REPORT EIA-649-1 Issued 2014-11 Configuration Management Requirements For Defense Contracts RATIONALE This is a defense unique standard to the non-government standard, ANSI/EIA-649B Configuration

More information

AS9003A QUALITY MANUAL

AS9003A QUALITY MANUAL AS9003A QUALITY MANUAL Origination Date: (month/year) Document Identifier: Date: Document Status: Document Link: AS9003A Latest Revision Date Draft, Redline, Released, Obsolete Location on Server (if used)

More information

DEPARTMENT OF DEFENSE HANDBOOK ACQUISITION OF SOFTWARE ENVIRONMENTS AND SUPPORT SOFTWARE

DEPARTMENT OF DEFENSE HANDBOOK ACQUISITION OF SOFTWARE ENVIRONMENTS AND SUPPORT SOFTWARE NOT MEASUREMENT SENSITIVE MIL-HDBK-1467 10 DECEMBER 1997 SUPERSEDING SEE 6.2 DEPARTMENT OF DEFENSE HANDBOOK ACQUISITION OF SOFTWARE ENVIRONMENTS AND SUPPORT SOFTWARE This handbook is for guidance only.

More information

LM Logistic Services Quality Notes Conversion Chart

LM Logistic Services Quality Notes Conversion Chart Page 1 of 10 LM Logistic Services s Conversion Chart The latest issue to this document is the version that is available on the Lockheed Martin Logistic Services Supplier Management website: http://www.lockheedmartin.com/us/suppliers/bu-info/aeronautics/sustainment-services.html

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Government Contract Quality Assurance (GCQA) Surveillance Planning

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Government Contract Quality Assurance (GCQA) Surveillance Planning DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Government Contract Quality Assurance (GCQA) Surveillance Planning Quality Assurance Directorate DCMA-INST 309 OPR: DCMA-QA Administrative

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Product Acceptance and Release - QA

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Product Acceptance and Release - QA DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Product Acceptance and Release - QA Quality Assurance Directorate DCMA-INST 314 OPR: DCMA-QA Validated Current with Administrative Changes,

More information

National Aeronautics and Space Administration Washington, DC 20546

National Aeronautics and Space Administration Washington, DC 20546 Technical Standards Division Publication NASA-STD-2100-91 NASA Software Documentation Standard Software Engineering Program NASA-STD-2100-91 -91 Approved: July 29, 1991 National Aeronautics and Space Administration

More information

PERFORMANCE SPECIFICATION HYBRID MICROCIRCUITS, GENERAL SPECIFICATION FOR

PERFORMANCE SPECIFICATION HYBRID MICROCIRCUITS, GENERAL SPECIFICATION FOR INCH-POUND This document and process conversion measures necessary to comply with this revision shall be completed by 13 March 2011 MIL-PRF-38534H 13 September 2010 SUPERSEDING MIL-PRF-38534G 9 March 2009

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Process Review - QA

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Process Review - QA DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Process Review - QA Quality Assurance Directorate DCMA-INST 311 OPR: DCMA-QA 1. PURPOSE. This Instruction: a. Reissues and uupdates

More information

Quality Management System

Quality Management System Quality Management System 6.1 Quality Q-Codes () 6.1 Quality Q-Codes Quality Clauses The following quality control clauses apply when specifically noted on the Gear Technology purchase order: Q1- Material

More information

EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL

EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL Revision: 6 Date 05/18/09 EPICOR, INCORPORATED 1414 E. Linden Avenue P.O. Box 1608 Linden, NJ. 07036-0006 Tel. 1-908-925-0800 Fax 1-908-925-7795 Table of Contents:

More information

IMMEDIATE POLICY CHANGE

IMMEDIATE POLICY CHANGE DEPARTMENT OF DEFENSE Defense Contract Management Agency IMMEDIATE POLICY CHANGE Deficiency Reports Quality Assurance Directorate DCMA-INST 305 (IPC-1) OPR: DCMA-QAA July 7, 2015 Administrative Change,

More information

FEC QUALITY MANUAL. Federal Equipment Company River Rd. Cincinnati, Ohio

FEC QUALITY MANUAL. Federal Equipment Company River Rd. Cincinnati, Ohio QMS-20 2016 FEC QUALITY MANUAL Federal Equipment Company 5298 River Rd Cincinnati, Ohio 45233 www.federalequipment.com www.fecheliports.com www.usdrillhead.com www.orionseals.com www.tkf.com REVISION:

More information

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev - February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February

More information

IMMEDIATE POLICY CHANGE

IMMEDIATE POLICY CHANGE DEPARTMENT OF DEFENSE Defense Contract Management Agency IMMEDIATE POLICY CHANGE Data Collection and Analysis Component Name DCMA-INST 323 (IPC-1) OPR: DCMA-QA June 26, 2015 Administrative Change, July

More information

QUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A

QUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production

More information

Supplier Handbook. Partnering for tomorrow. This supplier handbook is a guide for conducting business with Chemring Ordnance

Supplier Handbook. Partnering for tomorrow. This supplier handbook is a guide for conducting business with Chemring Ordnance Supplier Handbook Partnering for tomorrow This supplier handbook is a guide for conducting business with Chemring Ordnance 15 January 2016 Revision: A Supplier Handbook Table of Contents A. Purpose B.

More information

TECHNICAL REVIEWS AND AUDITS

TECHNICAL REVIEWS AND AUDITS Chapter 11 Technical Reviews and Audits CHAPTER 11 TECHNICAL REVIEWS AND AUDITS 11.1 PROGRESS MEASUREMENT The Systems Engineer measures design progress and maturity by assessing its development at key

More information

Supplier Quality Manual

Supplier Quality Manual ALLIANCE ELECTRONICS DISTRIBUTOR Supplier Quality Manual 22412 Gilberto Rd. Rancho Santa Margarita, CA 92688 INTRODUCTION Welcome to Alliance Electronics Distributor (AED) Alliance Electronics Distributor

More information

Objective Evidence Record (OER)

Objective Evidence Record (OER) This material is derived from SAE AS9101D, which is copyrighted intellectual property of SAE international. SAE is not responsible for outcomes resulting from use of this material. APPENDIX A OBJECTIVE

More information

JUL 14 Rev B All Paragraphs Revised

JUL 14 Rev B All Paragraphs Revised Quality Specification 102-32039 22 JUL 14 Rev B All Paragraphs Revised Counterfeit Electronic Parts Detection and Avoidance System 1. PURPOSE 1.1. Content The purpose of this document is to describe the

More information

QUALITY DEPT request to have FORM 1135 for REVIEW/APPROVAL Cycle everytime form will be updated/revised.

QUALITY DEPT request to have FORM 1135 for REVIEW/APPROVAL Cycle everytime form will be updated/revised. REF ONLY-DATA MANAGEMENT: 1 ST (2) PAGES IS NOT PART OF FORM 1135. QUALITY DEPT request to have FORM 1135 for REVIEW/APPROVAL Cycle everytime form will be updated/revised. FORM 1135 QUALITY ASSURANCE CLAUSES

More information

QUALITY ASSURANCE REQUIREMENTS

QUALITY ASSURANCE REQUIREMENTS SPACE AT MUCKLENEUK CAMPUS PRETORIA QUALITY ASSURANCE REQUIREMENTS SPACE AT MUCKLENEUK CAMPUS, PRETORIA Page 1 1.1 QUALITY ASSURANCE REQUIREMENTS In undertaking the works (including all incidental services

More information

QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES

QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Your Company Name QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 QMS Policies and Procedures Latest Revision Date Abstract:

More information

SHELTON INDUSTRIAL PATTERN INC.

SHELTON INDUSTRIAL PATTERN INC. Defintions: Seller : Supplier of materials, parts and or services that support production Supplies : materials, parts that support production FOD : Foreign Object Debri / Damage 1. Quality Management System

More information

Definitions contained in the above mentioned document and industry regulations are applicable herein.

Definitions contained in the above mentioned document and industry regulations are applicable herein. Quality Specification TEC-1021 21May12 Rev E Global Quality Management System Supplement for Various International Nuclear Quality Assurance Criteria, Regulations, and Requirements 1. SCOPE 1.1. Content

More information

Orbital ATK Alliant Techsystems Defense Electronic Systems Special Mission Aircraft Fort Worth

Orbital ATK Alliant Techsystems Defense Electronic Systems Special Mission Aircraft Fort Worth QUALITY ASSURANCE PROVISIONS FOR PURCHASE ORDER This document includes all Quality Assurance Provisions and definition available for inclusion on purchase orders and subcontracts issued by, Inc.,,, referenced

More information

REFERENCES Overview Quality Assurance Engineering Program...5

REFERENCES Overview Quality Assurance Engineering Program...5 TABLE OF CONTENTS REFERENCES... 4 CHAPTER 1 QAE GUIDANCE OVERVIEW 1.1. Overview... 5 1.2. Quality Assurance Engineering Program...5 CHAPTER 2 QAE MANAGEMENT STRUCTURE 2.1. Heads of DCMA QA-HQ and Operations...6

More information

STANDARD QUALITY ASSURANCE PROVISIONS FOR PURCHASED MATERIALS

STANDARD QUALITY ASSURANCE PROVISIONS FOR PURCHASED MATERIALS 1. GOVERNMENT/CUSTOMER SOURCE INSPECTION: a. Government/Customer inspection is required prior to shipment from your plant. Upon receipt of this order, promptly notify the Government/Customer representative

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

QM-1 QUALITY MANAGEMENT SYSTEMS MANUAL. Revision 10

QM-1 QUALITY MANAGEMENT SYSTEMS MANUAL. Revision 10 QM-1 QUALITY MANAGEMENT SYSTEMS MANUAL Revision 10 Page: 1 of 54 TABLE OF CONTENTS 1. DOCUMENT REVISION HISTORY... 5 2. INTRODUCTION... 6 2.1 Purpose... 6 2.2 Scope... 7 Figure 1: Sequence and Interaction

More information

DCMA INSTRUCTION 2501 CONTRACT MAINTENANCE

DCMA INSTRUCTION 2501 CONTRACT MAINTENANCE DCMA INSTRUCTION 2501 CONTRACT MAINTENANCE Office of Primary Responsibility: Contract Maintenance Capability Effective: August 14, 2017 Releasability: Cleared for public release New Issuance Incorporates:

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Effective Control of Nonconforming Material

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Effective Control of Nonconforming Material DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Effective Control of Nonconforming Material Multifunctional Instruction DCMA-INST 1207 Lead Component: Quality Assurance 1. PURPOSE.

More information

Procurement Standard Text Codes Revision I - Dated 20 April, 2005

Procurement Standard Text Codes Revision I - Dated 20 April, 2005 THE CODES LISTED HEREIN ARE ADDITIONAL REQUIREMENTS THAT MAY BE REFERENCED IN ORBITAL S PURCHASE DOCUMENTS. THE FIRST PORTION OF THIS FORM LISTS THE CODES AND THEIR TITLES SORTED BY THEIR CODE GROUPS.

More information

INSPECTION SYSTEM REQUIREMENTS

INSPECTION SYSTEM REQUIREMENTS MILITARY SPECIFICATIONS MIL-I-45208A INSPECTION SYSTEM REQUIREMENTS This specification has been approved by the Department of Defense and is mandatory for use by all Agencies. 1. SCOPE 1.1 Scope. This

More information

0. 0 TABLE OF CONTENTS

0. 0 TABLE OF CONTENTS QUALITY MANUAL Conforming to ISO 9001:2008 0. 0 TABLE OF CONTENTS Section Description ISO 9001 Clause Page 0 TABLE OF CONTENTS n/a 2 1 PIMA VALVE, INC. DESCRIPTION n/a 3 2 QUALITY MANUAL DESCRIPTION 4.2.2

More information

ISO /TS 29001:2010 SYSTEMKARAN ADVISER & INFORMATION CENTER SYSTEM KARAN ADVISER & INFORMATION CENTER

ISO /TS 29001:2010 SYSTEMKARAN ADVISER & INFORMATION CENTER SYSTEM KARAN ADVISER & INFORMATION CENTER SYSTEM KARAN ADVISER & INFORMATION CENTER PETROLEUM, PETROCHEMICAL AND NATURAL GAS INDUSTRIES -- SECTOR-SPECIFIC QUALITY MANAGEMENT SYSTEMS -- REQUIREMENTS FOR PRODUCT AND SERVICE SUPPLY ORGANIZATIONS

More information

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date:

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: 20130524 AMSC Number: N9379 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of the ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

Parts Management Implementation Spring LMI. PSMC Spring

Parts Management Implementation Spring LMI. PSMC Spring Parts Management Implementation Spring 2016 - LMI 1 PM Implementation Goal Develop and define processes and training for the implementation of the Parts Management requirements in MIL-STD-3018 Initial

More information

Production Part Approval Process (PPAP)

Production Part Approval Process (PPAP) Document ID: QN-M04 Page 1 of 13 Aerojet Rocketdyne Quality Note M04 Date: 03/16/2016 Table of Contents 1. PURPOSE... 2 2. APPLICATION... 2 2.1. Resubmissions... 2 2.2. Applicable Documents... 3 3. CONVENTIONS...

More information

Revision. Quality Manual. Multilayer Prototypes. Compliant to ISO / AS9100 Rev C

Revision. Quality Manual. Multilayer Prototypes. Compliant to ISO / AS9100 Rev C 1 of 29 Quality Manual Multilayer Prototypes Compliant to ISO 9001-2008 / AS9100 Rev C This Quality Manual sets forth the quality system policies and Defines compliance with the ISO 9001-2008 SAE AS 9100

More information

ORDER FOR SUPPLIES OR SERVICES

ORDER FOR SUPPLIES OR SERVICES ORDER FOR SUPPLIES OR SERVICES PAGE 1 OF 6 1. CONTRACT/PURCH ORDER/AGREEMENT NO. 2. DELIVERY ORDER/CALL NO. 3. DATE OF ORDER/CALL 4. REQUISITION/PURCH REQUEST NO. 2015 APR 20 0057970092 9. CONTRACTOR CODE

More information

Procurement Quality Assurance Requirements

Procurement Quality Assurance Requirements 1. REQUIREMENTS 1.1 Quality System This document provides the minimum Quality System Requirements to externally provided processes, products and services to Superior Thread Rolling (STR). Suppliers must

More information

EVANS CAPACITOR COMPANY

EVANS CAPACITOR COMPANY DISTRIBUTION LIST: Location Book # Quality Manager 0001 President 0002 CEO 0003 Engineering Manager 0004 Production Manager 0005 Office Manager 0006 Page 1 of 33 REV A 11/18/03 TABLE OF CONTENTS Page Distribution

More information

IUID Education and Training Series. IUID Contracting. IUID Center Representative NSWC Corona, IUID Center 2 August 2016

IUID Education and Training Series. IUID Contracting. IUID Center Representative NSWC Corona, IUID Center 2 August 2016 IUID Education and Training Series IUID Contracting IUID Center Representative NSWC Corona, IUID Center 2 August 2016 1 Housekeeping Please mute your telephone Please use the chat box for questions which

More information

Association of American Railroads Mechanical Division MANUAL OF STANDARDS AND RECOMMENDED PRACTICES

Association of American Railroads Mechanical Division MANUAL OF STANDARDS AND RECOMMENDED PRACTICES Association of American Railroads MANUAL OF STANDARDS AND RECOMMENDED PRACTICES EQUIPMENT IDENTIFICATION AND WARRANTY ADMINISTRATION Specification M-xxx-xxx Adopted: (date) DRAFT #18 Compiled by the ISM-RIF-WWG

More information

HP Standard Supplier Requirements for Safe and Legal Products

HP Standard Supplier Requirements for Safe and Legal Products HP Standard 014-2 Supplier Requirements for Safe and Legal Products Document Identifier Revision and Date Last Revalidation Date Abstract Applicability Status HX-00014-02 G, This standard describes HP

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Title: Test Plans/Test Procedures Number: DI-SESS-81704 Approval Date: 20061122 AMSC Number: F7658 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Preparing Activity: 10

More information

Project Management Institute (PMI) Practice Standard for Configuration Management

Project Management Institute (PMI) Practice Standard for Configuration Management Project Configuration Management Project Management Institute (PMI) Practice Standard for Configuration Management Project Configuration Management What we will cover: Introduction Relationship with other

More information

PERFORMANCE SPECIFICATION PRINTED CIRCUIT BOARD/PRINTED WIRING BOARD, GENERAL SPECIFICATION FOR

PERFORMANCE SPECIFICATION PRINTED CIRCUIT BOARD/PRINTED WIRING BOARD, GENERAL SPECIFICATION FOR NOT MEASUREMENT SENSITIVE MIL-PRF-31032 1 November 1995 PERFORMANCE SPECIFICATION PRINTED CIRCUIT BOARD/PRINTED WIRING BOARD, GENERAL SPECIFICATION FOR This specification is approved for use by all Departments

More information

Independent Verification and Validation (IV&V)

Independent Verification and Validation (IV&V) Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification

More information

TASK REQUIREMENTS. Supplier Quality Requirements

TASK REQUIREMENTS. Supplier Quality Requirements This document is applicable only to suppliers of Production Items as defined below and their subtier suppliers. Non-Production Item suppliers are not subject to this document. This document specifies the

More information

DEPARTMENT OF DEFENSE HANDBOOK PARTS MANAGEMENT

DEPARTMENT OF DEFENSE HANDBOOK PARTS MANAGEMENT NOT MEASUREMENT SENSITIVE MIL-HDBK-512A 31 October 2001 SUPERSEDING MIL-HDBK-512 04 October 2000 DEPARTMENT OF DEFENSE HANDBOOK PARTS MANAGEMENT This handbook is for guidance only. Do not cite this document

More information

THE COMMANDER NAVY REGION, SOUTHWEST (CNRSW) HAZARDOUS MATERIALS (HAZMAT) OPERATIONS QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) 20 June 2000

THE COMMANDER NAVY REGION, SOUTHWEST (CNRSW) HAZARDOUS MATERIALS (HAZMAT) OPERATIONS QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) 20 June 2000 THE COMMANDER NAVY REGION, SOUTHWEST (CNRSW) HAZARDOUS MATERIALS (HAZMAT) OPERATIONS QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) 20 June 2000 TABLE OF CONTENTS 1.0 INTRODUCTION 1 1.1 PURPOSE... 1 2.0 OVERVIEW.2

More information

NATO MUTUAL GOVERNMENT QUALITY ASSURANCE (GQA) PROCESS

NATO MUTUAL GOVERNMENT QUALITY ASSURANCE (GQA) PROCESS AQAP 2070 NATO MUTUAL GOVERNMENT QUALITY ASSURANCE (GQA) PROCESS AQAP 2070 (January 2004) I ORIGINAL Page blank II ORIGINAL AQAP 2070 NORTH ATLANTIC TREATY ORGANIZATION NATO STANDARDISATION AGENCY (NSA)

More information

Quality Supplier Requirements for Beckwith Electric Co., Inc.

Quality Supplier Requirements for Beckwith Electric Co., Inc. Quality Supplier Requirements for Beckwith Electric Co., Inc. This Page Left Intentionally Blank To Our Valued Suppliers: One of the primary goals of Beckwith Electric is to provide the highest Quality

More information

Correspondence Between ISO 13485:2016 and 21 CFR Part 820 QMS Requirements

Correspondence Between ISO 13485:2016 and 21 CFR Part 820 QMS Requirements Correspondence Between and 21 CFR Part 820 QMS Requirements 10411 Corporate Drive, Suite 102, Pleasant Prairie, WI 53158 262.842.1250 262.842.1240 info@rcainc.com rcainc.com 2 4 Quality Management System

More information

DEFENSE CONTRACT MANAGEMENT AGENCY Department of Defense INSTRUCTION. Strategic Planning

DEFENSE CONTRACT MANAGEMENT AGENCY Department of Defense INSTRUCTION. Strategic Planning DEFENSE CONTRACT MANAGEMENT AGENCY Department of Defense INSTRUCTION Strategic Planning Office of Strategic Effects OPR: DCMA-DE 1. PURPOSE. This Instruction: a. Replaces DCMA Instruction (DCMA-INST),

More information

20 September 2017 Document No. QM-ISO revision T ASTRONAUTICS CORPORATION OF AMERICA S. AS 9100 and FAA QUALITY MANUAL. Proprietary Notice

20 September 2017 Document No. QM-ISO revision T ASTRONAUTICS CORPORATION OF AMERICA S. AS 9100 and FAA QUALITY MANUAL. Proprietary Notice 20 September 2017 Document No. QM-ISO revision T ASTRONAUTICS CORPORATION OF AMERICA S AS 9100 and FAA QUALITY MANUAL Proprietary Notice Information disclosed herein is the property of Astronautics Corporation

More information

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26 Company Name/Certificate Number: Page 1 of 26 a. Organization a.1. Has the Organizational Structure of the program identified the levels of management responsible for the Quality System Program, including

More information

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices Appendix 1 Formulate Programs with a RAM Growth Program II-1 1.1 Reliability Improvement Policy II-3 1.2 Sample Reliability

More information

ASA-100 QUALITY MANUAL

ASA-100 QUALITY MANUAL Your Company Name ASA-100 QUALITY MANUAL Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 Quality Manual Latest Revision Date Abstract: This quality manual describes (your Company's)

More information

D. All distributors shall be reviewed and approved as per company procedure.

D. All distributors shall be reviewed and approved as per company procedure. PROCEDURE Number: QM-251 Purchase Order (QAP) Quality Assurance Provisions Department: Quality Assurance Revision: 5 Publish Date: 2015-11-18 Prepared by: Quality Manager Authorised by: Director of Operations

More information

Quality Assurance Procedure Issued: 15NOV2017 Page 1 of 11

Quality Assurance Procedure Issued: 15NOV2017 Page 1 of 11 Quality Assurance Procedure Issued: 15NOV2017 Page 1 of 11 1.0 Purpose To ensure that Fleet Canada states applicable requirements for purchased products on purchase orders and applicable documents. Requirements

More information

Regulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants

Regulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants Regulatory Guide 1.173Developing Software Lif... Page 1 of 10 September 1997 Regulatory Guide 1.173 Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear

More information

Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70

Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70 Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70 RUSSTECH PURCHASE ORDER CLAUSES RPOC 1000 EARLY DELIVERY OK "Time is of the essence for performance under this Purchase Order. Seller

More information

EB 2678K Compliance Checklist

EB 2678K Compliance Checklist A. GENERAL 1. Is the supplier aware that materials and workmanship forming part of this or any order, may be inspected and tested at any time and place before, during and after manufacture by Purchaser

More information

9100 revision Changes presentation clause-by-clause. IAQG 9100 Team November 2016

9100 revision Changes presentation clause-by-clause. IAQG 9100 Team November 2016 Changes presentation clause-by-clause IAQG 9100 Team November 2016 INTRODUCTION In September 2016, a revision of the 9100 standard has been published by the IAQG (International Aerospace Quality Group)

More information

Appendix QI. Intra-Lockheed Martin Work Transfer Agreement (IWTA) Quality Requirements for Deliverable Items

Appendix QI. Intra-Lockheed Martin Work Transfer Agreement (IWTA) Quality Requirements for Deliverable Items Intra-Lockheed Martin Work Transfer Agreement (IWTA) Quality Requirements for Deliverable Items REVISION RECORD The latest issue to this document is the version that is available on the Lockheed Martin

More information

QUALITY SYSTEM MANUAL

QUALITY SYSTEM MANUAL TITLE: QUALITY SYSTEM MANUAL Page 1 of 15 QUALITY SYSTEM MANUAL TITLE: QUALITY SYSTEM MANUAL Page 2 of 15 Index PARAGRAPH TITLE... PAGE 1.0 GENERAL INFORMATION... 3 2.0 DEFINITIONS... 5 3.0 RELATED DOCUMENTS...

More information

ISO 9001 QUALITY MANUAL

ISO 9001 QUALITY MANUAL ISO 9001 QUALITY MANUAL Origination Date: 10/01/14 Document Identifier: AIF quality control manual Date: 10/01/14 Project: Customer review Document Status: Released Document Link: www.aeroindfast.com Abstract:

More information

Supplier Deviation Disposition Request (SDDR)

Supplier Deviation Disposition Request (SDDR) Waste Treatment Plant Project Supplier Deviation Disposition Request (SDDR) Tracy Hawkins WTP Responsible Engineering Specialist 07-August-2015 Purpose - To define the actions taken when a supplier discovers

More information

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard.

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard. Quality Manual This manual complies with the requirements of the ISO 9001:2015 International Standard. Northeast Power Systems, Inc. 66 Carey Road Queensbury, New York 12804 Quality Manual Rev 0 Printed

More information

RISK MANAGEMENT SUPPLEMENT TO IEEE

RISK MANAGEMENT SUPPLEMENT TO IEEE SMC Tailoring SMC-T-005 15 May 2015 ------------------------ Supersedes: SMC-T-005 (2014) Air Force Space Command SPACE AND MISSILE SYSTEMS CENTER TAILORING RISK MANAGEMENT SUPPLEMENT TO IEEE-15288.1 APPROVED

More information

Number: DI-IPSC-81427B Approval Date:

Number: DI-IPSC-81427B Approval Date: DATA ITEM DESCRIPTION Title: Software Development Plan (SDP) Number: DI-IPSC-81427B Approval Date: 20170313 AMSC Number: N9775 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Preparing Activity:

More information

Vosky Precision Machining Corp. 70-B Air Park Drive, Ronkonkoma, NY Tel: (631) Fax: (631)

Vosky Precision Machining Corp. 70-B Air Park Drive, Ronkonkoma, NY Tel: (631) Fax: (631) Vosky Precision Machining Corp. 70-B Air Park Drive, Ronkonkoma, NY 11779 Tel: (631) 737-3200 Fax: (631) 737-3240 Quality Control Manual ISSUED: January 21, 2005 Revision. G (12/3/2003) Vosky Precision

More information

METUCHEN CAPACITORS INCORPORATED. Quality Manual P.O. BOX HIGHWAY 35, SUITE 2 HOLMDEL NJ USA

METUCHEN CAPACITORS INCORPORATED. Quality Manual P.O. BOX HIGHWAY 35, SUITE 2 HOLMDEL NJ USA METUCHEN CAPACITORS INCORPORATED Quality Manual P.O. BOX 399 2139 HIGHWAY 35, SUITE 2 HOLMDEL NJ 07733 USA Copy Holder Copy Number : 1 This Quality Manual Covers the activities and functions performed

More information

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy POLICY MANUAL FOR ISO 9001:2008 Document: PM-9001:2008 Date: April 7, 2015 REVIEWED BY: Tim Powers DATE: 4-7-2015 APPROVED BY: C._Bickford Uncontrolled Copy DATE: 4-7-2015 1.0 GENERAL ISS: 1 REV: E Page:

More information

CONFIGURATION MANAGEMENT PLAN TEMPLATE

CONFIGURATION MANAGEMENT PLAN TEMPLATE CONFIGURATION MANAGEMENT PLAN TEMPLATE This template helps you to create a Configuration Management (CM) Plan that allows a formal structure to describe how configuration management will be managed to

More information

9001:2015. Quality Manual 9001:2015. Engineering Value through Quality and Innovation.

9001:2015. Quality Manual 9001:2015. Engineering Value through Quality and Innovation. Quality Manual 9001:2015 9001:2015 Suburban Manufacturing, Inc. encourages comments from customers, suppliers, employees and friends in order to improve our business and its performance. Information contained

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

Report number A0436 PRODUCT REQUIREMENTS FOR SELLERS OF BOEING DESIGNED DETAIL PARTS AND NON-FUNCTIONAL MINOR ASSEMBLIES

Report number A0436 PRODUCT REQUIREMENTS FOR SELLERS OF BOEING DESIGNED DETAIL PARTS AND NON-FUNCTIONAL MINOR ASSEMBLIES Report number A0436 PRODUCT REQUIREMENTS FOR SELLERS OF BOEING DESIGNED DETAIL PARTS AND NON-FUNCTIONAL MINOR ASSEMBLIES Revision date 14 DEC 2007 Revision letter T Issue date 30 APRIL 1970 Contract number

More information

REPORT 2014/162 INTERNAL AUDIT DIVISION

REPORT 2014/162 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2014/162 Audit of the implementation of the Umoja system in the United Nations Support Office for the African Union Mission in Somalia Overall results relating to the effective

More information

SUPPLIER QUALITY PROCUREMENT REQUIREMENTS

SUPPLIER QUALITY PROCUREMENT REQUIREMENTS THIS DOCUMENT ESTABLISHES THE FLOW-DOWN QUALITY ASSURANCE REQUIREMENTS OF PROCUREMENT FROM WINONICS CUSTOMERS TO OUR SUPPLIERS. 1. QUALITY PROGRAM REQUIREMENTS Supplier shall provide and maintain a quality

More information

CHAPTER 5 INFORMATION TECHNOLOGY SERVICES CONTROLS

CHAPTER 5 INFORMATION TECHNOLOGY SERVICES CONTROLS 5-1 CHAPTER 5 INFORMATION TECHNOLOGY SERVICES CONTROLS INTRODUCTION In accordance with Statements on Auditing Standards Numbers 78 and 94, issued by the American Institute of Certified Public Accountants

More information

3). DEFINITIONS. Title: Management Responsibility. Issue Date: June 19, Procedure Number: CP Page: 1 of 5 ACCEPT REJECT COMMENTS

3). DEFINITIONS. Title: Management Responsibility. Issue Date: June 19, Procedure Number: CP Page: 1 of 5 ACCEPT REJECT COMMENTS Page: 1 of 5 1). PURPOSE This Data Configuration Control Procedure governs receipt, usage and distribution of product definition datasets. It defines the determination and identification of authority and

More information

DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION STANDARD PRACTICE FACILITY CONFIGURATION MANAGEMENT

DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION STANDARD PRACTICE FACILITY CONFIGURATION MANAGEMENT FAA-STD-058 November 8, 2002 DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION STANDARD PRACTICE FACILITY CONFIGURATION MANAGEMENT DISTRIBUTION STATEMENT A. Approved for public release; distribution

More information

System Requirements (URS)

System Requirements (URS) System s (URS) System Document Control System Document ID URS000XXX Version 1 DOCUMENT APPROVALS Reason For Signature Name Position Signature Date Prepared by Vic Johnson Project Manager Checked for accuracy

More information

CHECKLIST FOR PART 145 APPROVAL

CHECKLIST FOR PART 145 APPROVAL Section/division AIRWORTHINESS: AIRCRAFT MAINTENANCE ORGANISATION Form Number: CA 145-03 CHECKLIST FOR PART 145 APPROVAL AMO Number Name of organization Physical address Postal address Postal code Telephone

More information

20028 Joint Software Systems Safety Engineering Handbook Implementation Guide

20028 Joint Software Systems Safety Engineering Handbook Implementation Guide 20028 Joint Software Systems Safety Engineering Handbook Implementation Guide Robert E. Smith, CSP Booz Allen Hamilton 20th Annual NDIA Systems Engineering Conference Springfield, VA 25 October 2017 1

More information

How to Lock Down Your Document Recording Processes Focus on compliance and security

How to Lock Down Your Document Recording Processes Focus on compliance and security How to Lock Down Your Document Recording Processes Focus on compliance and security How to Lock Down Your Document Recording Processes 2017 1 How to Lock Down Your Document Recording Processes Focus on

More information

Page 1 / 11. Version 0 June 2014

Page 1 / 11. Version 0 June 2014 Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning

More information

Professional Engineers Using Software-Based Engineering Tools

Professional Engineers Using Software-Based Engineering Tools Professional Engineers Ontario GuidEline Professional Engineers Using Software-Based Engineering Tools Contributors: Eric Brown, P.Eng. / Colin Cantlie, P.Eng., / Norm Fisher, P.Eng., / Jeremy Jackson,

More information