Central Park Water Operational Audit

Size: px
Start display at page:

Download "Central Park Water Operational Audit"

Transcription

1 Central Water Operational Audit Independent Pricing and Regulatory Tribunal Water Industry Competition Act 2006 Network Operator's Licence Audit Report (Operational Audit) Licence No. 12_022: Central Water Factory Pty Ltd (also known as Central Water) Licence Holder: Central Water Factory Company Pty Ltd (ACN ) Final Report 31st July 2015 Water Futures. ABN Merrivale Rd, Pymble Cobbitty Consulting PO box 561, Bayswater, Vic 3153.

2 Table of Contents 1. EXECUTIVE SUMMARY INTRODUCTION OBJECTIVE LICENSEE S INFRASTRUCTURE, SYSTEMS AND PROCEDURES AUDIT METHOD... 5 Audit scope... 5 Audit standard... 5 Audit steps... 5 Audit team... 6 Acknowledgements... 6 Audit grades REGULATORY REGIME QUALITY ASSURANCE PROCESS AUDIT FINDINGS SITE AUDIT AGENDA FOR TUESDAY 9 TH JUNE AUDIT IF TRIGGERED OBLIGATIONS SUMMARY OF FINDINGS REVIEW OF ACTIONS OPPORTUNITIES FOR IMPROVEMENT GENERAL OBLIGATIONS SUMMARY OF FINDINGS REVIEW OF ACTIONS OPPORTUNITIES FOR IMPROVEMENT WATER SUPPLY INFRASTRUCTURE SUMMARY OF FINDINGS REVIEW OF ACTIONS OPPORTUNITIES FOR IMPROVEMENT NON- POTABLE WATER SUPPLY INFRASTRUCTURE SUMMARY OF FINDINGS REVIEW OF ACTIONS OPPORTUNITIES FOR IMPROVEMENT SEWERAGE INFRASTRUCTURE SUMMARY OF FINDINGS REVIEW OF ACTIONS OPPORTUNITIES FOR IMPROVEMENT SCHEDULE B TO THE NETWORK OPERATOR S LICENCE SUMMARY OF FINDINGS REVIEW OF ACTIONS OPPORTUNITIES FOR IMPROVEMENT APPENDICES Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 2 of 63

3 1. Executive Summary This report sets out the findings of an Operational Audit completed in respect of the Network Operator s Licence (Licence No. 12_022) for Central Water, NSW for the period 23 January 2014 to 30 April A Follow- up Licence Plan Audit, which is reported separately, was undertaken in conjunction with this audit. The auditors were provided with sufficient and appropriate evidence, as described in the IPART Audit Guideline for Greenfield Schemes, Water Industry Competition Act 2006 (NSW), July 2013 (the Audit Guideline), on which to base the conclusions reached during the audit. The auditors have observed the requirements of the Audit Guideline and the Audit Deed in conducting the audit, determining audit findings and preparing this report. The reported audit findings accurately reflect the professional opinion of the auditors. The findings have not been unduly influenced either by the Licensee or any of its associates and express the auditors opinions as to whether the Licensee has met the Licence conditions and regulatory requirements as specified in the scope. A summary of the audit findings is given in the following chapters and a detailed breakdown of the full audit findings against the audited criteria is given in the detailed Audit Tables in Appendices A to D. The audited infrastructure complied with the audited requirements of the Regulation and Licence conditions and was found to be operating safely. The Licensee, Central Water Pty Ltd (ACN ) (CPW) was found to be constructing, repairing, maintaining and operating the infrastructure without any Significant Non- compliances with the audited criteria. An additional five (5) clauses were reported as No requirement under the scope of the current audit. Those five (5) No requirement clauses need to be audited as part of the next audit. Three Insignificant non- compliances were identified and these are summarised as follows: WIC Reg Sched 1 cl.6(2)(a) Non- compliant Insignificant [relating to water supply infrastructure]: CPW demonstrated that it is fully implementing, and that its activities are being carried out in accordance with, the Infrastructure Operating Plan. Furthermore, it demonstrated that personnel involved in the overall management, operation and maintenance of the network are appropriately trained to do so. The Follow- up Licence Plan Audit undertaken in conjunction with this audit has, however, identified that some aspects of the Infrastructure Operating Plan requires update. Furthermore, whilst CPW was able to demonstrate that it has procedures in place to ensure that the Infrastructure Operating Plan is kept under regular review, the auditor is of the opinion that a 5 yearly review interval is insufficient to ensure that the Infrastructure Operating Plan remains fully appropriate to its purpose. WIC Reg Sched 1 cl.11 Non- compliant Insignificant A potable to recycled water cross connection integral to the network is still in place, albeit shut off by not one but two closed valves, but it is not physically broken by removal of a pipe section as recommended in good practice. WIC Reg Sched 1 cl.13(2)(a) Non- compliant Insignificant [relating to sewerage infrastructure]: CPW demonstrated that it is fully implementing, and that its activities are being carried out in accordance with, the Infrastructure Operating Plan. Furthermore, it demonstrated that personnel involved in the overall management, operation and maintenance of the network are appropriately trained to do so. The Follow- up Licence Plan Audit undertaken in conjunction with this audit has, however, identified that some aspects of the Infrastructure Operating Plan requires update. Furthermore, whilst CPW was able to demonstrate that it has procedures in place to ensure that the Infrastructure Operating Plan is kept under regular review, the auditor is of the opinion that a 5 yearly review interval is insufficient to ensure that the Infrastructure Operating Plan remains fully appropriate to its purpose. 7 opportunities for improvement were identified that may assist CPW in maintaining full compliance in the future and these are noted in the body of this report. In summary, the audited recycled water infrastructure complied with the audited requirements of the Regulation and Licence conditions, and was found to be capable of operating safely and in accordance with the Central Water Infrastructure Operating Plan, Water Quality Plan (drinking water), Water Quality Plan Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 3 of 63

4 (non potable water) and Sewage Management Plan. Furthermore, the Licence Holder audited (Central Water) was found to have the technical and organisational capacity to carry out the activities authorised by the Licence. In the opinion of the auditors, the Licence Holder can continue commercial operation for the safe and reliable supply of recycled water. The auditors support IPART in continuing approval of the commercial operation of the assets operated under this WICA licence. Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 4 of 63

5 2. Introduction 2.1 Objective This report presents the findings of an audit undertaken for the Independent Pricing and Regulatory Tribunal (IPART) under the Water Industry Competition Act The audit comprised of an Operational Audit as required in respect of the Network Operator's Licence (Licence No. 09_002) for Central Water. The Licensee is Central Water Pty Ltd (ACN ) (CPW). A Follow- up Licence Plan Audit was undertaken in conjunction with this audit and is reported separately. 2.2 Licensee s infrastructure, systems and procedures The Licence Holder s infrastructure, systems and procedures audited were those related to Central Water (the Scheme) (refer The Licence Holder, CPW, is responsible for the operation and maintenance of parts of the Central sewerage network, drinking water network, a water recycling plant that treats raw sewage and produces recycled (non- potable) water and pipelines for the distribution/reticulation of non- potable water back into parts of Central. Flow Systems Pty Limited [Water Factory Company Pty Limited] (ACN ) and Permeate Partners Pty Ltd (ACN ) are Authorised Persons named under this Licence. 2.3 Audit method Audit scope This audit covers the operation and maintenance of the licenced infrastructure and addresses the scope specified by IPART relating to an Operational Audit in respect of the audit period 23 January 2014 to 30 April Audit standard The audit broadly followed the generic principles of auditing given in ISO 19011: Guidelines for auditing management systems. The principal document used to guide the audit was the IPART Audit Guideline for Greenfield Schemes, Water Industry Competition Act 2006 (NSW), July 2013 (the Audit Guideline). Audits are by necessity limited to sampling processes. It is not practicable, nor necessary, to inspect 100 percent of items within an audit scope. Auditing forms part of the broader risk management process, providing an independent check on the veracity of the processes and procedures in place to manage risk. Finding a balance between audit effort and practicality requires the exercise of experienced professional judgement. The amount of effort allocated to this audit has been kept to a reasonable minimum level. The audit was undertaken and reported in accordance with the Audit Guideline and its associated Appendices. The audit templates given in the Guideline provided the reporting format for the audit as well as the detailed audit criteria. Audit steps An Audit Plan was submitted to both IPART and the Licensee prior to the audit taking place. Documentation was supplied by the Licensee to both the auditor and IPART. Desktop auditing took place both prior and subsequent to the site audit. A site audit took place on Thursday, 9 th July 2015; this comprised of on- site asset inspections during the morning followed by an office based desktop audit during the remainder of the day. Some evidence was followed up after the audit with the report being prepared and submitted to the Licensee as draft, then a final, before submission to IPART. Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 5 of 63

6 The audit process involved seeking objective evidence that the Licensee met the Licence obligations identified for audit by IPART. The auditors collected evidence through interview, document review and site inspection. The auditors randomly sampled examples sufficient to verify claims made by the Licensee. Audit team The audit was conducted in an integrated manner by two auditors who collectively addressed the various components of the audit scope; this report sets out the audit criteria that were applied. The two- member team that conducted the audit consisted of Dr Dan Deere and Mr Jim Sly, both of whom hold Lead Auditor Accreditation in respect of Licence Regulations and Compliance under IPART s Technical Services and Water Licensing Audit Panel. Acknowledgements The audit team notes, and greatly appreciates, the presence of IPART staff members Alfredo Careaga and Jamie Luke as a valuable observers and commentators during the audit. The audit team notes, and greatly appreciates, the work and effort put in by those audited, including: Andrew Horton, Executive Manager Utility Operations; and Laura Dixon, Rick and Compliance Manager. Audit grades Audit grades were awarded in accordance with the definitions given in the Audit Guideline. Compliance of operation of the infrastructure with the relevant legal and formal requirements was assessed. More generally the infrastructure was assessed for its capability to operate safely. Grades were allocated as follows: No Requirement (NR) Compliant (C) Non- compliant Insignificant (NCI) Non- compliant Significant (NCS) 2.4 Regulatory regime The scheme operates under the Water Industry Competition Act 2006 (WICA) which in turn references the following requirements: Water Industry Competition (General) Regulation (2008) (WIC Regulation). Conditions of Network Operator's Licence No. 09_002. IPART Audit Guideline for Greenfield Schemes, Water Industry Competition Act 2006 (NSW), July Relevant aspects of the national Australian Guidelines for Water Recycling: Managing Health and Environmental Risks (Phase 1) Relevant water industry and environmental NSW and national codes of practice and regulations, as applicable. 2.5 Quality assurance process Quality was assured using a professional review process. Each auditor s work was reviewed and approved by the other auditor. Both auditors are longstanding members of the IPART audit panel. Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 6 of 63

7 2.6 Audit findings Audit findings are summarised in the above Executive Summary; they are presented in more detail in the next section of this report and in full detail in the Appendices that follow. 2.7 Site audit agenda for Tuesday 9 th June 2015 Time Item and audit questions Location Lead 9:00 Opening meeting and site induction Central Dan Deere 9:10 Asset inspection Which infrastructure is currently in commercial operation? Has any new infrastructure been introduced into commercial operation? If so has it been appropriately approved [WIC Reg Sched 1 cl. 2(1),(2(a,b))]? Is there evidence that the system is being operated in a safe and reliable manner and maintained in a proper condition [WIC Reg Sched 1 cl. 3(c)]? Is there alignment between the IOP, SMP, WQP (npw) and WQP (dw) on the one hand and the observed assets on the other [WIC Reg Sched 1 cl. 6(2)(a), 7(4)(a), WIC Reg Sch 1 cl. 13(2)(a) and WIC Reg Sched 1 cl. 14(3)(a)]? What evidence is present on site relating to the management of risk from cross- connections from network assets [WIC Reg Sched 1 cl. 7(4)(a) and WIC Reg Sch 1 cl. 10(a)]? Is there alignment between the critical limits and requirements between the WQP, daily operator's recording worksheet and SCADA system [WIC Reg Sched 1 cl. 7(4)(a)]? Is there evidence on site that the customer s installations comply with the Plumbing and Drainage Act 2011(NSW) [WIC Reg Sched 1 cl. 8(1) and cl. 11]? What evidence is present on site relating to the management of risk from cross- connections from customer assets [WIC Reg Sched 1 cl. 11 and WIC Reg Sch 1 cl. 10(a)]? Central Dan Deere Audit if triggered obligations General conditions 11:00 Significant change to IOP WIC Reg Sch 1 cl. 6(3)(a) If any significant change is made to its infrastructure operating plan (or the Minister or IPART demands it), the network operator must provide a copy of the amended plan to IPART and an approved auditor, and provide the Minister or IPART with a report, prepared by the approved auditor, regarding the adequacy of the plan and the condition of its infrastructure having regard to the purposes for which it was licensed. Audit question: Has this clause been triggered and if so what evidence can CPW provide of compliance? 11:10 Significant change to WQP WIC Reg Sch 1 cl. 7(5)(a) If any significant change is made to its water quality plan (or the Minister or IPART demands it), the network operator must provide IPART with an amended copy of the plan and provide the Minister or IPART with a report, prepared by an approved auditor, regarding the adequacy of the plan Audit question: Has this clause been triggered and if so what evidence can CPW provide of compliance? Central Central Jim Sly Dan Deere Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 7 of 63

8 Time Item and audit questions Location Lead Drinking water 11:20 Compliance with PHA WIC Reg Sch 1 cl. 9(c) A network operator of water infrastructure to supply drinking water must ensure the water supplied complies with any requirements under the Public Health Act 2010 (NSW) and the Public Health Regulation 2012 (NSW) in relation to the supply of safe drinking water. Audit question: Has this clause been triggered and if so what evidence can CPW provide of compliance? Central Dan Deere Sewerage infrastructure 11:25 Significant change to IOP WIC Reg Sch 1 cl. 13(3)(a) If any significant change is made to its infrastructure operating plan (or the Minister or IPART demands it), the network operator must provide a copy of the amended plan to IPART and an approved auditor, and provide the Minister or IPART with a report, prepared by the approved auditor, regarding the adequacy of the plan and the condition of its infrastructure having regard to the purposes for which it was licensed. Audit question: Has this clause been triggered and if so what evidence can CPW provide of compliance? Central Jim Sly Operating Licence 11:30 Refined water Network Operator Licence cl. B4 The Licensee must carry out the activities authorised by this Licence in compliance with any requirements of NSW Health that: (i) IPART has agreed to; and (ii) are notified from time to time to the Licensee by IPART in writing. IPART: Licensee is required to refrain from the use of the term "refined water" in IPART's letter dated 7 April References to "refined water" in licensee's website should be removed from its website asap. The term "refined water" should also be removed from any marketing materials and signage by 30 June Auditor to assess progress. As part of this audit, please review the Incident and Emergency Management Plans. Audit question: What evidence can CPW provide of compliance? Central Dan Deere General obligations for a network operator Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 8 of 63

9 Time Item and audit questions Location Lead 11:35 Incidents WIC Reg Sched 1 cl. 1(2)(a,b,c,d,e) a) A network operator must immediately notify IPART of any incident in the conduct of its activities that threatens, or could threaten, water quality, public health or safety. b) A network operator must immediately notify the Minister administering the Public Health Act 2010 (NSW) and the Public Health Regulation 2012 (NSW) of any incident in the conduct of its activities that threatens, or could threaten, water quality, public health or safety. c) A network operator must immediately notify the Minister administering Part 2 of the Water Industry Competition Act 2006 (NSW) of any incident in the conduct of its activities that threatens, or could threaten, water quality, public health or safety. d) A network operator must immediately notify any licensed retail supplier that supplies water or provides sewerage services by means of the licensed network operator's infrastructure of any incident in the conduct of its activities that threatens, or could threaten, water quality, public health or safety. e) A network operator must immediately notify any licensed network operator or public water utility whose infrastructure is connected to the licensed network operator s infrastructure of any incident in the conduct of its activities that threatens, or could threaten, water quality, public health or safety. IPART: The auditor should review whether this clause was triggered or not. A sample of incident records and/or water monitoring data should be reviewed. lf no notification was required in the audit period, no further audit is necessary. A NR audit grade should be awarded to the clause. Audit question: What evidence can CPW provide (e.g. incident records, water quality monitoring and SCADA results) to show whether or not any incidents occurred during the audit period that threatened water quality, public health or safety? Central Dan Deere 11:45 New infrastructure WIC Reg Sched 1 cl. 2(1),(2(a,b)) A network operator must not bring any new water or sewerage infrastructure into commercial operation without the written approval of the Minister. a) The network operator must provide to the Minister a report, prepared by an approved auditor that indicates that the infrastructure complies with the requirements of the Regulation and any licence conditions. b) The network operator must provide to the Minister a report, prepared by an approved auditor that indicates that the infrastructure is capable of operating safely and in accordance with its infrastructure operating plan and its water quality or sewage management plan, as the case requires. IPART: Check infrastructure against licence. Yes/No Check. Currently a technical breach arising as a result of a 'regulatory gap' where the pipes downstream of a customer connection point are not included in water industry infrastructure and therefore not regulated under WICA. Only audit [clauses a and b] if new infrastructure brought into commercial operation. If no new infrastructure an 'NR' audit grade should be awarded to the clause. Triggered by WIC Reg Sch 1 d. 2(1). Audit question: Which infrastructure is currently in commercial operation? What evidence can CPW provide to demonstrate that no new infrastructure has been introduced into commercial operation and, if so, that the new infrastructure has been appropriately approved? Central Jim Sly Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 9 of 63

10 Time Item and audit questions Location Lead 11:50 Codes and standards. 12:00 Lunch WIC Reg Sched 1 cl. 3(c) The water or sewerage infrastructure is properly designed and constructed, operated in a safe and reliable manner and maintained in a proper condition, having regard to any publicly available standards or codes relating to its design, construction, operation and maintenance. IPART: As part of this audit, please review any procedures in place for identifying changes to publicly available standards or codes, and ensuring it remains up to date with such standards and codes. Licensee have acknowledged the need and have an Implementation Plan. Full compliance requires the following: Documentation of procedures for identifying changes to publicly available standards or codes, and ensuring that Central Water remains up to date with such standards and codes. Audit question: What evidence can CPW provide to demonstrate its use of publicly available standards or codes relating to the operation and maintenance of the infrastructure? Central - Jim Sly - Water supply infrastructure 1:00 IOP implementation and currency WIC Reg Sched 1 cl.6(2)(a) The network operator must ensure that the infrastructure operating plan is fully implemented and kept under regular review and all of the network operator s activities are carried out in accordance with that plan. IPART: As part of this audit, please review whether there is a procedure in place to ensure that the Plan is kept under regular review. Audit question: What evidence can CPW provide to demonstrate that the infrastructure operating plan is fully implemented, that the network operator s activities are carried out in accordance with that plan and that the plan is it kept under regular review? 1:05 WQP implementation and currency WIC Reg Sched 1 cl.7(4)(a) The network operator must ensure that its water quality plan is fully implemented and kept under regular review and the network operator s activities are carried out in accordance with that plan. IPART: As part of this audit, please review any potential cross- connections between drinking and recycled water pipes, and recommendations of Auditor's reports in 2014 are included in updated plans. Audit question: What evidence can CPW provide to demonstrate that the water quality plan is fully implemented, that the network operator s activities are carried out in accordance with that plan and that the plan is it kept under regular review? Central Central Jim Sly Dan Deere Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 10 of 63

11 Time Item and audit questions Location Lead 1:10 Water metering WIC Reg Sched 1 cl 8(1,2(a,b,c)) Any water meter that is connected to a network operator's water main must comply with the requirements of the Plumbing Code of Australia. While water is being supplied to premises in respect of which a water meter has been installed, a network operator must ensure that the water meter is properly maintained and periodically tested. While water is being supplied to premises in respect of which a water meter has been installed, a network operator must ensure that the water meter is read at intervals of no more than 4 months. While water is being supplied to premises in respect of which a water meter has been installed, a network operator must ensure that written notice of each meter reading is sent to the relevant licensed retail supplier. IPART: Central Water has demonstrated that water meters connected to its water mains comply with the Plumbing Code of Australia. Whilst residential customer meters are not typically maintained or tested other than in response to a customer complaint, it is appropriate that the approach to water meter maintenance, testing and renewal is documented in an Asset Management Plan; this is yet to be developed by Central Water. As part of this audit, please review that Central Water has an Implementation Plan to further develop its documentation. Audit question: What evidence can CPW provide to demonstrate that its meters comply with the Plumbing Code of Australia, that the meters are maintained, periodically tested, read at least every four months and written notice of each meter reading is issued to the relevant retail supplier? 1:20 Customer plumbing WIC Reg Sched 1 cl. 11 The licensee must not allow a customer's installation to be connected to a licensee's water main unless the installation complies with the Plumbing and Drainage Act 2011 (NSW). IPART: Check for cross- connections. Audit question: What evidence can CPW provide to demonstrate that customer s installations comply with the Plumbing and Drainage Act 2011(NSW)? Central Central Jim Sly Dan Deere Non- potable water supply infrastructure 1:30 Fitness for purpose WIC Reg Sched 1 cl, 10(a) The network operator under a licence for water infrastructure to supply non- potable water for a particular purpose must ensure that the water supplied is fit for that purpose. IPART: Specifically to address cross- connections between drinking and recycled water pipes. Audit question: What evidence can CPW provide (e.g. water quality monitoring and SCADA results as well as controls on water usage including cross- connection controls) to demonstrate that the water supplied is fit for purpose? Central Dan Deere Sewerage infrastructure Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 11 of 63

12 Time Item and audit questions Location Lead 1:40 IOP implementation and currency WIC Reg Sch 1 cl. 13(2)(a) The infrastructure operating plan is fully implemented and kept under regular review and all of the network operator's activities are carried out in accordance with that plan. IPART: As part of this audit, please review whether there is a procedure in place to ensure that the Plan is kept under regular review. Audit question: What evidence can CPW provide to demonstrate that the infrastructure operating plan is fully implemented, that the network operator s activities are carried out in accordance with that plan and that the plan is it kept under regular review? 1:50 SMP implementation and currency WIC Reg Sched 1 cl. 14(3)(a) The network operator must ensure that its sewage management plan is fully implemented and kept under regular review and all of the network operator s activities are carried out in accordance with that plan. Audit question: What evidence can CPW provide to demonstrate that the sewage management plan is fully implemented, that the network operator s activities are carried out in accordance with that plan and that the plan is it kept under regular review? Central Central Jim Sly Dan Deere Schedule B to the network operator's licence 2:00 Technical, financial and organisational capacity. Network Operators Licence cl. B1 The Licensee must have the technical, capacity to carry out the activities authorised by this Licence. If the Licence Holder ceases to have this capacity, it must report this to IPART immediately. The Licensee must have the organisational capacity to carry out the activities authorised by this Licence. If the Licence Holder ceases to have this capacity, it must report this to IPART immediately. IPART Auditors to review position descriptions, CV's, training programs (including training needs analysis and proposed delivery program). Central Water does not have in place procedures for identifying, and reporting to IPART, if it ceases to have the technical, financial and organisational capacity required to carry out the activities authorised by the Licence. Central Water does not have procedures in place for identifying, and reporting to IPART, if it ceases to have the technical, financial and organisational capacity required to carry out the activities authorised by the Licence. Full compliance requires documentation of procedures for identifying, and reporting to IPART if Central Water ceases to have the technical, financial and organisational capacity to carry out the activities authorised by the Licence. Auditors to review licensee's procedures or contractual arrangements to carry out the licenced activity by staff, contractors or third parties. Review resource plans and levels of staffing. Demonstrate the risk of business continuity is under control and risk managed satisfactorily. Audit question: What evidence can CPW provide that it has the technical and organisational capacity to carry out the activities authorised by this Licence? Central Jim Sly Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 12 of 63

13 Time Item and audit questions Location Lead 2:05 Insurance Network Operators Licence cl. B3.(1,2,3) The Licensee must maintain appropriate insurance sufficient for the size and nature of the activities authorised under this Iicence. The Licensee must provide a copy of each certificate of currency of the insurance maintained by the Licensee to IPART in accordance with the Reporting Manual. Whenever there is a change in the type, or Ievel of insurance held by the Licensee in relation to the activities authorised under this Licence the Licensee must provide a copy of the certificate of currency to IPART within 10 days of the change being made. Audit question: What evidence can CPW provide that it has appropriate insurance and that IPART has been kept suitably informed? 2:10 Reporting Network Operator Licence cl. B5 The Licence Holder must prepare and submit reports in accordance with the Reporting Manual. Audit question: What evidence can CPW provide that it has submitted reports in accordance with the Reporting Manual? 2:15 Verification Network Operator Licence cl. B8.(1,2,3) The Licensee must undertake any monitoring that is required for the purposes of this Licence, any Plan, the Act or the Regulation in accordance with this clause. The Licensee must keep the following records of any samples taken for monitoring purposes specified in the Water Quality Plan: (a) the date on which the sample was taken, (b) the time at which the sample was collected, (c) the point or location at which the sample was taken, and (d) the chain of custody of the sample (if applicable. The Licensee must ensure that analyses of all samples taken for the purposes of Verification Monitoring are carried out by a laboratory accredited for the specified tests by an independent body that is acceptable to NSW Health, such as the National Association of Testing Authorities or an equivalent body. Audit question: What evidence can CPW provide that the appropriate water quality verification monitoring has been undertaken in compliance with the WQP? What evidence can CPW provide of date, time, location, name of sampler (e.g. chain of custody) and NATA accreditation for that monitoring? Central Central Central Dan Deere Dan Deere Dan Deere Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 13 of 63

14 Time Item and audit questions Location Lead 2:45 Code of Conduct Network Operator Licence cl. B10.(1,2,3,4,5) 1. If a code of conduct has not been established under reg 25 of the Regulation, the Licensee must (by a date specified by IPART) establish a code of conduct (Licensee's Code of Conduct) in accordance with this clause B The Licensee's Code of Conduct must set out the respective responsibilities of a) the Licensee; and b) each licensed network operator, licensed retail supplier and/or public water utility that supplies water, provides sewerage services or constructs, maintains or operates any other water industry infrastructure in the Specified Area of Operations, by, at a minimum, providing for: a) if the Specified Water Industry Infrastructure is connected to any other water industry infrastructure, who is responsible for repairing, replacing or maintaining any pipes, pumps, valves, storages or other infrastructure connecting the Specified Water Industry Infrastructure to the other water industry infrastructure; b) who is responsible for water quality; c) who is liable in the event of the unavailability of water; d) who is liable in the event of failure of the Specified Water Industry Infrastructure; e) the fees and charges payable in respect of the use of the Specified Water Industry Infrastructure; and f) who is responsible for handling customer complaints 3. (a) Before the Licensee brings the Specified Water lndustry Infrastructure into commercial operation or by a later date specified by IPART (if any), the Licensee's Code of Conduct must be agreed in writing between the Licensee and the other licensed network operators, licensed retail suppliers and/or public water utilities referred to in clause The Licensee must not contravene the Licensee's Code of Conduct to the extent that it makes the Licensee responsible or liable for the matters set out in it. IPART: As part of this audit, please review the Utility Services agreement. It was incomplete and should be completed and finalised addressing all of the relevant criteria identified in the Licence. (May not have a Code of Conduct in place) Audit question: What evidence can CPW provide that the code of conduct has been agreed with all other connected water industry infrastructure network operators or public utilities and supplied to IPART and that the relevant document is current? Central Jim Sly Licence Plan Follow up audit items Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 14 of 63

15 Time Item and audit questions Location Lead 3:00 IOP adequacy potable water and sewerage WIC Reg Sch 1 cl. 6(1)(a) and d. 13(1)(a) 6 and 13. Infrastructure operating plans. (1) Before commencing to operate water infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, an infrastructure operating plan that indicates the arrangements that the licensee has made, or proposes to make, in relation to: a) the design, construction, operation and maintenance of the infrastructure, including particulars as to the life- span of the infrastructure, the system redundancy built into the infrastructure and the arrangements for the renewal of the infrastructure. Previous non- compliance: Whilst the Infrastructure Operating Plan addresses most of the aspects required, it requires further development; outstanding activities are identified in the Implementation Plan (included in the Infrastructure Operating Plan). Furthermore, the fully developed Plan is dependent upon development of an Asset Management Plan. Accordingly, Central Water is not considered to have demonstrated full compliance with this requirement. However, given the state of development of the Plan, the non- compliance is not deemed to be significant. IPART: Full compliance requires the following: finalise development of the IOP; development of an Asset Management Plan and supporting procedural documentation; finalisation of (i.e. fully populate) the Asset Register; demonstrated implementation of the documented infrastructure management practices; and demonstration that activities identified in the Implementation Plan are completed as scheduled. Audit question: What evidence can CPW provide that it was progressed to full development and implementation of the IOP and has addressed this inadequacy? 3:15 IOP adequacy potable water and sewerage WIC Reg Sch 1 cl. 6(1)(b) and d. 13(1)(b) 6 and 13. Infrastructure operating plans. (1) Before commencing to operate water infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, an infrastructure operating plan that indicates the arrangements that the licensee has made, or proposes to make, in relation to: b) the continued safe and reliable performance of the infrastructure. Previous non- compliance: Although Central Water has demonstrated that it is able effectively manage the continued safe and reliable performance of the infrastructure, full compliance with this requirement requires preparation of the Asset Management Plan and supporting procedural documentation. The non- compliance is not, however, deemed to be significant given that activities are currently in hand to ensure that operational monitoring and maintenance activities are effectively managed and the demonstrated knowledge of Central Water operational personnel. IPART: Full compliance requires the following: development of an Asset Management Plan and supporting procedural documentation; demonstrated implementation of the documented infrastructure management practices; and demonstrate that maintenance activities are being effectively implemented and records maintained. Audit question: What evidence can CPW provide that it was progressed to full development and implementation of the IOP and has addressed this inadequacy? Central Central Jim Sly Jim Sly Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 15 of 63

16 Time Item and audit questions Location Lead 3:30 WQP (dw) adequacy ADWG Element One WIC Reg Sched 1 cl. 7(1)(a) 7. Water quality plans (dw). (1) Before commencing to operate water infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, a water quality plan, in relation to the water supplied from the infrastructure, that specifies: b) if the water so supplied is drinking, how the 12 elements of the framework for the management of drinking water quality, as detailed in the Australian Drinking Water Guidelines, have been addressed and will be implemented. Previous non- compliance: Whilst the WQP addresses most of the aspects required, the stakeholder contact information is some years out of date. Accordingly, Central Water is not considered to have demonstrated full compliance with this requirement. However, given the state of development of the WQP and the minimal extent of passive infrastructure currently in service, the non- compliance is not deemed to be significant. IPART: Update the stakeholder contact list. Audit question: What evidence can CPW provide that its WQP complies with the ADWG and has addressed this inadequacy? 3:35 WQP (dw) adequacy ADWG Element Two WIC Reg Sched 1 cl. 7(1)(a) (as above) Previous non- compliance: Whilst the WQP addresses most of the aspects required, the risk assessment did not include an uncertainty analysis. Accordingly, Central Water is not considered to have demonstrated full compliance with this requirement. However, given the state of development of the WQP and the minimal extent of passive infrastructure currently in service, the non- compliance is not deemed to be significant IPART: Augment the risk assessment to include the major sources of uncertainty associated with each hazard and hazardous event and outline the actions considered to reduce uncertainty. Audit question: What evidence can CPW provide that its WQP complies with the ADWG and has addressed this inadequacy? 3:40 WQP (dw) adequacy ADWG Element Six WIC Reg Sched 1 cl. 7(1)(a) (as above) Previous non- compliance: Central Water has yet to complete a coherent incident and emergency management plan for this scheme and has out dated contact details for key stakeholders. However, given the demonstrated competence of Flow Systems in managing incidents and emergencies under a WICA regime along with the fact that Flow Systems are currently remedying this gap, and noting the minimal and passive nature of this infrastructure, this non- compliance is considered insignificant. IPART: Complete the incident and emergency management plan and update the stakeholder contact list. Audit question: What evidence can CPW provide that its WQP complies with the ADWG and has addressed this inadequacy? Central Central Central Dan Deere Dan Deere Dan Deere Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 16 of 63

17 Time Item and audit questions Location Lead 3:45 SMP adequacy WIC Reg Sched 1 cl. 14(1)(a) and (b) 14. Sewage management plans. (1) Before commencing to operate sewerage infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, a sewage management plan, in relation to the conveyance, treatment and disposal of sewage by means of the infrastructure, that indicates: a) the manner in which health and ecological assessments will be undertaken and any concerns arising from any such assessment addressed, and b) the arrangements for the disposal of waste from the infrastructure. Previous non- compliance: Central Water has yet to complete a coherent incident and emergency management plan for this scheme and has out dated contact details for key stakeholders. However, given the demonstrated competence of Flow Systems in managing incidents and emergencies under a WICA regime along with the fact that Flow Systems are currently remedying this gap, and noting the minimal and passive nature of this infrastructure, this non- compliance is considered insignificant. IPART: Complete the incident and emergency management plan and update the stakeholder contact list. Audit question: What evidence can CPW provide that it was progressed to full development and implementation of the SMP and has addressed this inadequacy? 3:50 IOP adequacy recycled water WIC Reg Sch 1 cl. 6(1)(a) 6. Infrastructure operating plans. (1) Before commencing to operate water infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, an infrastructure operating plan that indicates the arrangements that the licensee has made, or proposes to make, in relation to: a) the design, construction, operation and maintenance of the infrastructure, including particulars as to the life- span of the infrastructure, the system redundancy built into the infrastructure and the arrangements for the renewal of the infrastructure. Previous non- compliance: Whilst the Infrastructure Operating Plan addresses most of the aspects required, it requires further development; outstanding activities are identified in the Implementation Plan (included in the Infrastructure Operating Plan). Furthermore, the fully developed Plan is dependent upon development of an Asset Management Plan. Accordingly, Central Water is not considered to have demonstrated full compliance with this requirement. However, given the state of development of the Plan, the non- compliance is not deemed to be significant. IPART: Full development of the Infrastructure Operating Plan, including development of an Asset Management Plan and demonstrated implementation of the infrastructure management practices documented therein. Audit question: What evidence can CPW provide that it was progressed to full development and implementation of the IOP and has addressed this inadequacy? Central Central Dan Deere Jim Sly Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 17 of 63

18 Time Item and audit questions Location Lead 4:00 IOP adequacy recycled water WIC Reg Sch 1 cl. 6(1)(b) 6. Infrastructure operating plans. (1) Before commencing to operate water infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, an infrastructure operating plan that indicates the arrangements that the licensee has made, or proposes to make, in relation to: b) the continued safe and reliable performance of the infrastructure. Previous non- compliance: Although Central Water has demonstrated that it is able effectively manage the continued safe and reliable performance of the infrastructure, full compliance with this requirement requires preparation of the Asset Management Plan and supporting procedural documentation. The non- compliance is not, however, deemed to be significant given that activities are currently in hand to ensure that operational monitoring and maintenance activities are effectively managed and the demonstrated knowledge of Central Water operational personnel. IPART: Preparation of an Asset Management Plan and supporting procedural documentation and demonstrated implementation of appropriate infrastructure management practices. Audit question: What evidence can CPW provide that it was progressed to full development and implementation of the IOP and has addressed this inadequacy? 4:15 WQP (npw) adequacy AGWR Element One WIC Reg Sched 1 cl. 7(1)(b) 7. Water quality plans (npw). (1) Before commencing to operate water infrastructure commercially, the licensed network operator for the infrastructure must prepare, and forward to IPART, a water quality plan, in relation to the water supplied from the infrastructure, that specifies: b) if the water so supplied is non- potable water, how the 12 elements of the framework for the management of recycled water quality and use, as detailed in the Australian Guidelines for Water Recycling, have been addressed and will be implemented and, having regard to those guidelines, the purposes for which the water may be used and the purposes for which the water may not be used. Previous non- compliance: Central Water has demonstrated that it currently holds the technical and organisational capacity to carry out the activities authorised by the Licence. Central Water does not, however, have in place procedures for identifying, and reporting to IP ART, if it ceases to have the technical and organisational capacity required to carry out the activities authorised by the Licence. Central Water is still making reference to out- dated documents. This represents a systematic failure somewhere in the processes that Flow Systems uses to keep up to date with codes and standards that are directly relevant to water quality management and needs to be resolved by the licence holder to mitigate the low risk of out- dated standards being used. The lack of up to date and explicit contact details for Central Water stakeholders presents a small operational risk for this scheme and is something that is currently being. IPART: To be fully compliant, the following needs to be demonstrated: Documentation of procedures for identifying, and reporting to IP ART, if Central Water ceases to have the technical and organisational capacity to carry out the activities authorised by the Licence. Documentation of procedures for identifying changes to publicly available standards or codes to ensure that Central Water remains up to date with such standards and codes; and Documentation of updated Business Contacts List and associated contact details (this recommendation is also relevant to Element Six). Audit question: What evidence can CPW provide that its WQP complies with the AGWR and has addressed this inadequacy? Central Central Jim Sly Dan Deere Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 18 of 63

19 Time Item and audit questions Location Lead 4:20 WQP (npw) adequacy AGWR Element Four WIC Reg Sched 1 cl. 7(1)(b) (as above) Previous non- compliance: There is a low risk that small volumes of non- compliant recycled water might be supplied in the event of factors such as: a critical limit exceedance of unspecified maximum duration for chlorination; inadequate specification of a number of supporting limits (flow rate and measures of biomass integrity) for the MBR; ph drift after chlorine dose; and UV system warm up after UV power up. In addition, the potable to recycled water cross- connection is still in place and there is a risk that it may not be removed. IPART: To be fully compliant, the following needs to be demonstrated: maximum exceedance periods for the chlorine critical limits; supporting limits, such as flow rate and measures of biomass integrity, for the MBR; verification of no significant ph drift after chlorine dose; a process to avoid supply of water whilst the UV system warms up; credible verification of removal of the potable to recycled water cross- connection when the infrastructure is brought into operation; and credible verification of the existence of a differential pressure between the potable and recycled water systems when the infrastructure is brought into operation. These latter two items are relevant to the lop as well, but are only noted here for brevity. Audit question: What evidence can CPW provide that its WQP complies with the AGWR and has addressed this inadequacy? 4:40 WQP (npw) adequacy AGWR Element Five WIC Reg Sched 1 cl. 7(1)(b) (as above) Previous non- compliance: Verification of drinking water quality There is a small risk that Central Water will fail to use a laboratory accredited for the specified tests by an independent body acceptable to NSW Health for verification testing in the longer term. IPART: To be fully compliant, the following needs to be demonstrated: a formalised, documented requirement to use a suitable laboratory for verification testing. Audit question: What evidence can CPW provide that its WQP complies with the AGWR and has addressed this inadequacy? 4:50 WQP (npw) adequacy AGWR Element Ten WIC Reg Sched 1 cl. 7(1)(b) (as above) Previous non- compliance: Documentation and reporting A number of key documents are not explicitly referenced in the Recycled Water Quality Plan. As a result, there is a small but increasing risk that Central Water will lose sight of key detailed documents that are essential for the proper documentation and operation of the scheme. IPART: To be fully compliant, the following needs to be demonstrated: Make detailed and explicit cross- references to the key supporting documents that form an essential component of an adequate WQP (npw) under WICA. Audit question: What evidence can CPW provide that its WQP complies with the AGWR and has addressed this inadequacy? Central Dan Deere 5:00 Audit close Central Dan Deere Report on the Operational Audit of Network Operator s Licence No. 12_022 (Central Water) under WICA. Page 19 of 63

Central Park Water Licence Plan Audit including Follow-up Audit and Review of Adequacy of Amended Licence Plans Audit Report

Central Park Water Licence Plan Audit including Follow-up Audit and Review of Adequacy of Amended Licence Plans Audit Report Central Park Water Licence Plan Audit including Follow-up Audit and Review of Adequacy of Amended Licence Plans Audit Report Independent Pricing and Regulatory Tribunal Water Industry Competition Act 2006

More information

WICA Audit Report to IPART New Infrastructure Audit (Recycled Water) Green Square Water

WICA Audit Report to IPART New Infrastructure Audit (Recycled Water) Green Square Water WICA Audit Report to IPART New Infrastructure Audit (Recycled Water) Green Square Water Independent Pricing and Regulatory Tribunal Water Industry Competition Act 2006 Network Operator's Licence Audit

More information

New Infrastructure Audit (Drinking Water) Audit Report Huntlee Water

New Infrastructure Audit (Drinking Water) Audit Report Huntlee Water New Infrastructure Audit (Drinking Water) Audit Report Huntlee Water Independent Pricing and Regulatory Tribunal Water Industry Competition Act 2006 Network Operator's Licence Audit Report Licence No.

More information

Central Park Water. Independent Pricing and Regulatory Tribunal. Operational Audit. # Version 2.1

Central Park Water. Independent Pricing and Regulatory Tribunal. Operational Audit. # Version 2.1 #14053-10-002 Version 2.1 July 2017 Document History This document has been issued and amended as follows: Version Date Description Created by Checked by Approved by 1.0 3 July 2017 Draft (issued to Licensee

More information

Catherine Hill Bay Water Utility

Catherine Hill Bay Water Utility #14054-10-001 Version 2.0 Independent Pricing and Regulatory Tribunal August 2017 Document History Independent Pricing and Regulatory Tribunal This document has been issued and amended as follows: Version

More information

Catherine Hill Bay Water Utility

Catherine Hill Bay Water Utility #14054-10-002 Version 2.0 Independent Pricing and Regulatory Tribunal August 2017 Document History Independent Pricing and Regulatory Tribunal This document has been issued and amended as follows: Version

More information

Network Operator s Licence Operational Audit

Network Operator s Licence Operational Audit Cooranbong Water Pty Ltd Network Operator s Licence Operational Audit Flow Systems Date: February 2018 Version: 3.00 Final report Document Status: Version: 3.00 Final report Document History: Status Review

More information

Solo Water. Retail Supply Management Plan IMS-OPER-B-8314-SW

Solo Water. Retail Supply Management Plan IMS-OPER-B-8314-SW Retail Supply Management Plan IMS-OPER-B-8314-SW Document Status Revision Date Revision Details Author Review Approved A 4/12/2013 IPART Application Harvest B. Irwin B. Irwin 1 08/9/2017 General Review

More information

Operational Audit Audit Report 1 Bligh Street Recycled Water Scheme

Operational Audit Audit Report 1 Bligh Street Recycled Water Scheme Water Futures t-cam onsulting Operational Audit Audit Report 1 Bligh Street Recycled Water Scheme Independent Pricing and Regulatory Tribunal Water Industry ompetition Act 2006 Network Operator's Licence

More information

Memorandum of Understanding

Memorandum of Understanding Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation July 2016 MoU between Sydney Water and NSW Ministry of Health - July 2016 Page 1 of 11 1. Introduction and purpose

More information

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further

More information

CORPORATE STANDARD ROUTINE MINOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS

CORPORATE STANDARD ROUTINE MINOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS CORPORATE STANDARD ROUTINE MINOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS VERSION: 1.0 2.0 Corporate Standard Routine Minor Works Developers and Accredited Suppliers Contents 1. Introduction... 4 2. Purpose...

More information

CORPORATE STANDARD ROUTINE MAJOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS VERSION: 1.0

CORPORATE STANDARD ROUTINE MAJOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS VERSION: 1.0 CORPORATE STANDARD ROUTINE MAJOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS VERSION: 1.0 Contents 1. Introduction... 5 2. Purpose... 5 3. Scope... 5 3.1 Audience... 6 4. Definitions... 6 5. The delivery

More information

Walkaway Wind Power Pty Ltd

Walkaway Wind Power Pty Ltd Final For 2008 Performance Audit and Asset Management System Review Electricity Generation Licence EGL2 Audit Period 27 th January 2006 to 31 st January 2008 Audit Plan Authorisation Name Position Date

More information

Water NSW Reporting Manual

Water NSW Reporting Manual Water NSW Reporting Manual Operating Licence 2017-2022 Reporting Manual Water July 2017 Independent Pricing and Regulatory Tribunal of New South Wales 2017 This work is copyright. The Copyright Act 1968

More information

Harvey Water Asset Management & Operational Audit

Harvey Water Asset Management & Operational Audit Asset Management & Operational Audit March 2008 Contents Executive summary... 1 Post-Audit Implementation Plan... 7 Follow up of Previous Audit Recommendations... 19 Operational Audit -Observations, Findings

More information

2. Performance Audit Asset Management System Effectiveness Review... 12

2. Performance Audit Asset Management System Effectiveness Review... 12 CONTENTS 1. Executive Summary... 2 1.1 Performance Audit Summary 3 1.1.2 Limitation Of Scope 4 1.2 Asset Management System Review Summary 4 2. Performance Audit... 7 2.1 Performance Audit Scope 7 2.2 Performance

More information

Bluewaters Power 1 Pty Ltd

Bluewaters Power 1 Pty Ltd Bluewaters Power 1 Pty Ltd Electricity Generation Licence (EGL 4) 2014 Performance Audit (Independent Assurance) Report June 2014 Deloitte Touche Tohmatsu ABN 74 490 121 060 Woodside Plaza Level 14 240

More information

PERFORMANCE AUDIT AND ASSET MANAGEMENT SYSTEM REVIEW OF WESFARMERS KLEENHEAT GAS PTY LTD DISTRIBUTION LICENCE GDL 9 REPORT

PERFORMANCE AUDIT AND ASSET MANAGEMENT SYSTEM REVIEW OF WESFARMERS KLEENHEAT GAS PTY LTD DISTRIBUTION LICENCE GDL 9 REPORT PERFORMANCE AUDIT AND ASSET MANAGEMENT SYSTEM REVIEW OF WESFARMERS KLEENHEAT GAS PTY LTD DISTRIBUTION LICENCE GDL 9 REPORT PREPARED BY: GEOFF WOOD DATE: 29 AUGUST 2011 ACHIEVE IT CONSULTING 131 PONTE VECCHIO

More information

Guidelines for preparing Strategic Asset Management Plans. July 2010

Guidelines for preparing Strategic Asset Management Plans. July 2010 Guidelines for preparing Strategic Asset Management Plans July 2010 This publication has been compiled by Queensland Water Supply Regulator, Water Supply Division, Department of Energy and Water Supply.

More information

Conditions of Award. Royal Society Newton International Fellowships funded under the Newton Fund

Conditions of Award. Royal Society Newton International Fellowships funded under the Newton Fund Conditions of Award Royal Society Newton International Fellowships funded under the Newton Fund These Conditions of Award set out the standard terms and conditions for all Royal Society Newton International

More information

Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts

Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts April 2016 Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity

More information

How to set up a sewer mining scheme

How to set up a sewer mining scheme Sewer Mining How to set up a sewer mining scheme With a growing population and highly variable rainfall over the catchments, water recycling is making an increasingly important contribution to our water

More information

WESTERN WATER DESIGN AND CONSTRUCTION GUIDELINES FOR SUBDIVISIONAL WORKS

WESTERN WATER DESIGN AND CONSTRUCTION GUIDELINES FOR SUBDIVISIONAL WORKS WESTERN WATER DESIGN AND CONSTRUCTION GUIDELINES FOR SUBDIVISIONAL WORKS December 2014 Page 1 Table of contents 1 ROLES AND RESPONSIBILITES... 3 2 GENERAL DESIGN STANDARDS... 8 2.1 Design presentation...

More information

Conditions of Award. Royal Society Funding Schemes

Conditions of Award. Royal Society Funding Schemes Conditions of Award Royal Society Funding Schemes These Conditions of Award set out the standard terms and conditions for all Royal Society Awards. The Conditions of Award should be read in conjunction

More information

MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE. (Effective 1 December 2017)

MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE. (Effective 1 December 2017) MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE Contents 1 THE PARTIES...3 2 PURPOSE OF THIS DOCUMENT...3 3 INTERPRETATION...3 4 CONTRACT TERM...4 4.1 Commencement of contract...4 4.2 Termination

More information

APPLICATION PACK FOR THE ECOLABEL

APPLICATION PACK FOR THE ECOLABEL APPLICATION PACK FOR THE ECOLABEL PART 1: Guidance notes ISSUED BY: Insert name of Competent Body and contact details (address, telephone and fax numbers, Email address) Date of issue: Page 1 of 12 Introduction

More information

South Australian Public Health (Wastewater) Regulations 2013

South Australian Public Health (Wastewater) Regulations 2013 Version: 1.7.2017 South Australia South Australian Public Health (Wastewater) Regulations 2013 under the South Australian Public Health Act 2011 Contents Part 1 Preliminary 1 Short title 3 Interpretation

More information

TRANSMISSION COMPLIANCE MONITORING FRAMEWORK FOR THE SOUTH AFRICAN ELECTRICITY INDUSTRY

TRANSMISSION COMPLIANCE MONITORING FRAMEWORK FOR THE SOUTH AFRICAN ELECTRICITY INDUSTRY TRANSMISSION COMPLIANCE MONITORING FRAMEWORK FOR THE SOUTH AFRICAN ELECTRICITY INDUSTRY TABLE OF CONTENTS 1. PURPOSE...2 2. OBJECTIVE...2 3. BACKGROUND...2 3.1 REGULATORY INTERFACE AND COMMUNICATION CHANNELS...2

More information

Rules for Ship Recycling Management System Certification

Rules for Ship Recycling Management System Certification Rules for Ship Recycling Management System Certification Effective from July 1 st 2009 RINA Società per azioni Via Corsica, 12-16128 Genova - Italy Tel.: +39 01053851 - Fax: +39 0105351000 www.rina.org

More information

Orica Australia Pty Ltd A.C.N MATRAVILLE NSW 2036

Orica Australia Pty Ltd A.C.N MATRAVILLE NSW 2036 ENVIRONMENTALLY HAZARDOUS CHEMICALS ACT 1985 Licence No: 26 EPA File No: EF13/2466 Name of licensee: Address of licensee: Commencement Date: 20 July 2018 In force until: 20 July 2021 Orica Australia Pty

More information

QP 02 Audit and Certification Procedure

QP 02 Audit and Certification Procedure 1. AUDIT PROGRAMME [9.1.1] The audit programme shall be conducted in stages within a 3-year certification cycle as follows; Initial audit: Two stage process Surveillance audit: Conducted in the first and

More information

Microgeneration Installation Standard: MCS 001. MCS Contractor certification scheme requirements Issue 2.5

Microgeneration Installation Standard: MCS 001. MCS Contractor certification scheme requirements Issue 2.5 Microgeneration Installation Standard: MCS 001 MCS Contractor certification scheme requirements Issue 2.5 This Microgeneration Installation Standard is the property of Department of Energy and Climate

More information

James Cottrill Member of Russell Bedford International

James Cottrill   Member of Russell Bedford International Review of Network Quality and Reliability of Supply Performance Reporting James Cottrill Email: jcottrill@stantons.com.au Liability limited by a scheme approved under Professional Standards Legislation

More information

POST LICENSING OVERSIGHT AND INSPECTION OF MAJOR HAZARD FACILITIES AN AUSTRALIAN REGULATOR S EXPERIENCE

POST LICENSING OVERSIGHT AND INSPECTION OF MAJOR HAZARD FACILITIES AN AUSTRALIAN REGULATOR S EXPERIENCE POST LICENSING OVERSIGHT AND INSPECTION OF MAJOR HAZARD FACILITIES AN AUSTRALIAN REGULATOR S EXPERIENCE Geoff Cooke, Sarah Sinclair and Rob Sheers Hazard Management Division, WorkSafe Victoria The Occupational

More information

Electricity Networks Corporation (t/a Western Power)

Electricity Networks Corporation (t/a Western Power) Networks Corporation (t/a Western Power) Transmission Licence (ETL 2) Performance Audit Report January 2013 Grant Thornton Australia Ltd. All rights reserved. Contents Acronym List 2 1. Introduction 5

More information

Microgeneration Installation Standard: MCS 001. MCS Contractor certification Scheme requirements Issue 3.0

Microgeneration Installation Standard: MCS 001. MCS Contractor certification Scheme requirements Issue 3.0 Microgeneration Installation Standard: MCS 001 MCS Contractor certification Scheme requirements Issue 3.0 This Microgeneration Installation Standard is the property of Department of Energy and Climate

More information

1. Executive Summary Performance Audit Summary Limitation of Scope Asset Management System Review Summary 7

1. Executive Summary Performance Audit Summary Limitation of Scope Asset Management System Review Summary 7 Contents 1. Executive Summary 4 1.1 Performance Audit Summary 5 1.1.2 Limitation of Scope 7 1.2 Asset Management System Review Summary 7 2. Performance Audit 10 2.1 Performance Audit Scope 10 2.2 Performance

More information

DRINKING WATER INCIDENTS: THE REGULATOR S PERSPECTIVE. Nigel Garson. Office of the Water Supply Regulator, DERM Qld

DRINKING WATER INCIDENTS: THE REGULATOR S PERSPECTIVE. Nigel Garson. Office of the Water Supply Regulator, DERM Qld DRINKING WATER INCIDENTS: THE REGULATOR S PERSPECTIVE Paper Presented by: Nigel Garson Authors: Nigel Garson, Senior Project Officer, Claire Tallis, Senior Project Officer, Office of the Water Supply Regulator,

More information

Occupational Health and Safety. Improvement Standard

Occupational Health and Safety. Improvement Standard Premier s Department New South Wales Occupational Health and Safety Improvement Standard A tool for measuring OHS performance within NSW Government Agencies OHS IMPROVEMENT STANDARD NSW GOVERNMENT - REVIEW

More information

Electricity Networks Corporation (Western Power) Electricity Transmission Licence (ETL 2) Performance Audit Report

Electricity Networks Corporation (Western Power) Electricity Transmission Licence (ETL 2) Performance Audit Report Networks Corporation (Western Power) Transmission Licence (ETL 2) Performance Audit Report September 2011 Grant Thornton Australia Ltd. All rights reserved. Contents Acronym List 1 1. Introduction 4 2.

More information

Document 2007 Rev 0 December 2005 Page 1 of 8

Document 2007 Rev 0 December 2005 Page 1 of 8 Document 2007 Rev 0 December 2005 Page 1 of 8 1. Scope... 2 2. Definitions... 2 a. LabTest...2 b. Factory Location/ Manufacturer's Premises...2 c. Manufacturer...2 d. Subcontractor...2 e. f. Out-Worker...2

More information

RULES FOR THE CONCESSION AND MAINTENANCE OF CHAIN OF CUSTODY CERTIFICATION OF FOREST BASED PRODUCTS (PEFC - CHAIN OF CUSTODY)

RULES FOR THE CONCESSION AND MAINTENANCE OF CHAIN OF CUSTODY CERTIFICATION OF FOREST BASED PRODUCTS (PEFC - CHAIN OF CUSTODY) RULES FOR THE CONCESSION AND MAINTENANCE OF CHAIN OF CUSTODY CERTIFICATION OF FOREST BASED PRODUCTS (PEFC - CHAIN OF CUSTODY) In force from 10/10/2016 RINA Via Corsica 12 16128 Genova - Italy tel +39 010

More information

<Full Name> Quality Manual. Conforms to ISO 9001:2015. Revision Date Record of Changes Approved By

<Full Name> Quality Manual. Conforms to ISO 9001:2015. Revision Date Record of Changes Approved By Conforms to ISO 9001:2015 Revision history Revision Date Record of Changes Approved By 0.0 [Date of Issue] Initial Issue Control of hardcopy versions The digital version of this document is

More information

SAI Global Full Service Team

SAI Global Full Service Team General information regarding elements of the certification process is described below. A degree of flexibility and options in the certification process are available so please feel free to contact us

More information

Case Study on Water Safety Plan Implementation and Lessons Learned. Auditing WSPs in Victoria, Australia

Case Study on Water Safety Plan Implementation and Lessons Learned. Auditing WSPs in Victoria, Australia Case Study on Water Safety Plan Implementation and Lessons Learned Auditing WSPs in Victoria, Australia 2011 Case Study on WSP Implementation and Lessons Learned Auditing WSPs in Victoria, Australia 1)

More information

Quality, Health Safety & Environment Code: 2013

Quality, Health Safety & Environment Code: 2013 Price: AUD 35 Quality, Health Safety & Environment Code Quality, Health Safety & Environment Code: 2013 Published by: TQCS International Pty Ltd Head Office: 117A Tapleys Hill Road HENDON SA 5014 AUSTRALIA

More information

Alinta DEWAP Pty Ltd. Electricity Integrated Regional Licence (EIRL7) 2016 Asset Management System Review November 2016 report

Alinta DEWAP Pty Ltd. Electricity Integrated Regional Licence (EIRL7) 2016 Asset Management System Review November 2016 report Alinta DEWAP Pty Ltd Electricity Integrated Regional Licence (EIRL7) 2016 Asset Management System Review November 2016 report Deloitte Touche Tohmatsu ABN 74 490 121 060 Tower 2 Brookfield Place 123 St

More information

Affinity Water Limited New Supplies

Affinity Water Limited New Supplies 1 of 13 Affinity Water Limited New Supplies Policy and Company Specific Requirements for Water Mains and Service Pipes Constructed by Self-Lay Organisations 2 of 13 CONTENTS 1 Introduction 3 1.1 General

More information

TruckSafe Operator Business Rules and Code of Conduct

TruckSafe Operator Business Rules and Code of Conduct Operator Business Rules and Code of Conduct Contents 1.0 Business Rules and Code of Conduct 3 2.0 Decision Making Bodies 4-6 3.0 Purpose 6 4.0 How the Rules will be amended 6 5.0 Introduction 6 6.0 Entry

More information

Green Product Mark Certification Scheme

Green Product Mark Certification Scheme Green Product Mark Certification Scheme www.tuv.com FOREWORD Product environmental labels are claims regarding the environmental impact of a product. They provide information about the product s overall

More information

Responsible Wood Certification Scheme

Responsible Wood Certification Scheme Responsible Wood Certification Scheme RESPONSIBLE WOOD 30 Boothby Street Kedron, QLD 4031 www.responsiblewood.org.au RESPONSIBLE WOOD LOGO USE RULES MANUAL November 2017 Responsible Wood Labelling Rules

More information

Alinta Sales Pty Ltd

Alinta Sales Pty Ltd Alinta Sales Pty Ltd Gas Trading Licence (GTL9) 2010 Performance Audit (Independent Assurance) Report October 2010 Limitations of use This report is made solely to the management of Alinta Sales Pty Ltd

More information

Water Quality and Public Health. Water Suppliers

Water Quality and Public Health. Water Suppliers Water Quality and Public Health Water Suppliers Water Unit Supporting the Public Health Network Aboriginal Communities Water and Sewerage Program Public Health Act 2010 drinking water quality assurance

More information

MANUAL FUNDING AND DELIVERY OF GROWTH INFRASTRUCTURE VERSION:

MANUAL FUNDING AND DELIVERY OF GROWTH INFRASTRUCTURE VERSION: MANUAL FUNDING AND DELIVERY OF GROWTH INFRASTRUCTURE VERSION: VERSION: 1.0 1.0 Contents 1. Introduction... 3 2. Purpose... 3 3. Scope... 3 3.1 Audience... 4 4. Definitions... 4 5. Roles and responsibilities...

More information

Licence Details Number: 6830 Anniversary Date: 15-February. Licensee ABLE LIQUID WASTE PTY LTD PO BOX 307 LANE COVE NSW 1595

Licence Details Number: 6830 Anniversary Date: 15-February. Licensee ABLE LIQUID WASTE PTY LTD PO BOX 307 LANE COVE NSW 1595 Licence Details Number: 6830 Anniversary Date: 15-February Licensee ABLE LIQUID WASTE PTY LTD PO BOX 307 LANE COVE NSW 1595 Licence Type Transporter of Waste Scheduled Activity Transport of trackable waste

More information

Audit and Review Guidelines: Electricity and Gas Licences

Audit and Review Guidelines: Electricity and Gas Licences Audit and Review Guidelines: Electricity and Gas Licences April 2014 This document is available from the Economic Regulation Authority s website at www.erawa.com.au. For further information, contact: Economic

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN 2018-2020 DOCUMENT CONTROL Document Controller: Manager Adopted: 22 February 2018 Document number: EP0128 Rev Date Description Prepared Approved 1.0 Feb 2018 Initial issue

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,

More information

Asbestos Management. Final Internal Audit Report 2018/19. Powys Teaching Health Board. NHS Wales Shared Services Partnership

Asbestos Management. Final Internal Audit Report 2018/19. Powys Teaching Health Board. NHS Wales Shared Services Partnership Final Internal Audit Report 2018/19 NHS Wales Shared Services Partnership Audit and Assurance Services Reasonable Assurance - + Previous rating: 2012/13 Limited Assurance Report Contents CONTENTS Page

More information

We consider that NPPL has adequate controls in place that are appropriate to the nature and scale of its activities.

We consider that NPPL has adequate controls in place that are appropriate to the nature and scale of its activities. Performance Audit and Asset Management Review Executive Summary General Newmont Power Pty Ltd (NPPL) holds an electricity retail licence (ERL9) and an electricity distribution licence (EDL4). NPPL s assets

More information

SOIL ASSOCIATION CERTIFICATION INTERNATIONAL GROUP FOREST MANAGEMENT CERTIFICATION PROCEDURES

SOIL ASSOCIATION CERTIFICATION INTERNATIONAL GROUP FOREST MANAGEMENT CERTIFICATION PROCEDURES FSC A000525 PEFC/16-44-917 SOIL ASSOCIATION CERTIFICATION INTERNATIONAL GROUP FOREST MANAGEMENT CERTIFICATION PROCEDURES Procedures for International Group Forest Management Certification 1. Enquiry When

More information

National self-insurer OHS management system audit tool. Version 3

National self-insurer OHS management system audit tool. Version 3 National self-insurer OHS management system audit tool Version 3 Release Date: 4 August 2014 Next Review Date: 2016 Approval Status: Prepared by: Approved by Heads of Workers Compensation Authorities WorkCover

More information

Scheme of Delegation

Scheme of Delegation Scheme of Delegation Terms of Reference Part 1 Reviewed by Trustees April 2017 Part 1 should be read in conjunction with the Part 2 and the Committee Information sheets. 1 Contents Subject Page Number

More information

2016/17 Report to the Minister for Energy on the Economic Regulation Authority s compliance

2016/17 Report to the Minister for Energy on the Economic Regulation Authority s compliance Economic Regulation Authority 2016/17 Report to the Minister for Energy on the Economic Regulation Authority s compliance Wholesale Electricity Market Rules 2016/17 Report to the Minister for Energy on

More information

Alinta Energy Transmission (Roy Hill) Pty Ltd

Alinta Energy Transmission (Roy Hill) Pty Ltd Alinta Energy Transmission (Roy Hill) Pty Ltd Electricity Integrated Regional Licence (EIRL6) 2016 Asset Management System Review December 2016 report Deloitte Risk Advisory Pty Ltd ACN 611 748 184 Tower

More information

ANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance

ANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance ANNEX THREE Regime for Monitoring of Separation of Batelco and NBN Compliance Compliance Monitoring Regime Draft for Discussion Purpose: To establish a regime for monitoring Batelco s compliance with the

More information

SERVICE LEVEL PROCEDURE

SERVICE LEVEL PROCEDURE SERVICE LEVEL PROCEDURE METERING PROVIDER SERVICES PREPARED BY: AEMO MARKETS VERSION: 1.3 EFFECTIVE DATE: 01 DECEMBER 2017 STATUS: FINAL Approved for distribution and use by: APPROVED BY: PETER GEERS TITLE:

More information

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS INSTRUCTIONS TO DESIGNERS CONTENTS 1. INTRODUCTION 3 2. ROLE OF THE WATER SERVICING COORDINATOR 3 3. ROLE OF THE DESIGNER 3 4. DESIGN

More information

Trade Waste Management Policy Supporting Document

Trade Waste Management Policy Supporting Document Trade Waste Management Policy Supporting Document 1. Purpose The Trade Waste Management Policy Supporting Document is written to provide information and advice on trade waste matters. 2. Scope This document

More information

Health and Safety Policy Standard

Health and Safety Policy Standard Health and Safety Policy Standard Issue Date: 1 st July 2010 Authority: Directors, AES Group Applicability: AES Group covering all business divisions, operating companies and business units throughout

More information

ONRSR Guideline. Asset Management

ONRSR Guideline. Asset Management Document control Objective Document ID: A389849 Version number: 2.0 Approved by: Chief Executive Date approved: 26 February 2019 Policy changes to 2.0 Periodic Review Office of the National Rail Safety

More information

QUALITY MANUAL 1.0 INTRODUCTION POLICY AND OBJECTIVES DEFINITIONS SCOPE QUALITY SYSTEM... 3

QUALITY MANUAL 1.0 INTRODUCTION POLICY AND OBJECTIVES DEFINITIONS SCOPE QUALITY SYSTEM... 3 CONTENTS QUALITY MANUAL 1.0 INTRODUCTION... 2 2.0 POLICY AND OBJECTIVES... 2 3.0 DEFINITIONS... 3 4.0 SCOPE... 3 5.0 QUALITY SYSTEM... 3 6.0 ORGANISATIONAL CHARTS... 4 6.0 BRISBANE HEAD OFFICE... 4 7.0

More information

Business Plan Guidance for Retail Licence Applicants

Business Plan Guidance for Retail Licence Applicants SEPTEMBER 2005 Business Plan Guidance For Retail Licence Applicants Contents Business Plan Guidance Page 1 General Guidance and Introduction 1 2 Corporate Structure and Management Team 4 3 Market and Operating

More information

Railway Interface Planning Scheme Rules (RIPS Rules)

Railway Interface Planning Scheme Rules (RIPS Rules) Contents 1. Purpose.. 1 2. Scope... 2 3. Scheme Rules.... 3 4. Roles and Responsibilities... 4 5. Management System Requirements... 7 6. Investigating Breaches of the Railway Interface Planning Scheme

More information

Wesfarmers Kleenheat Gas Pty Ltd. Gas Trading Licence (GTL10) 2016 Performance Audit (Independent Assurance) January 2017 report

Wesfarmers Kleenheat Gas Pty Ltd. Gas Trading Licence (GTL10) 2016 Performance Audit (Independent Assurance) January 2017 report Wesfarmers Kleenheat Gas Pty Ltd Gas Trading Licence (GTL10) 2016 Performance Audit (Independent Assurance) January 2017 report Deloitte Risk Advisory Pty Ltd ACN 611 748 184 Mr Colin York General Manager,

More information

Chemical Inhibitor Approval Scheme (CIAS) Audit Procedure

Chemical Inhibitor Approval Scheme (CIAS) Audit Procedure Page 1 of 5 Chemical Inhibitor Approval Scheme (CIAS) Audit Procedure 1. Introduction This audit procedure defines the ongoing requirements for NSF Licence holders of CIAS approved products during their

More information

UNIT 10 CLAUSE-WISE INTERPRETATION OF ISO 22000: 2005

UNIT 10 CLAUSE-WISE INTERPRETATION OF ISO 22000: 2005 ISO 22000:2005 UNIT 10 CLAUSE-WISE INTERPRETATION OF ISO 22000: 2005 Structure 10.0 Objectives 10.1 Introduction 10.2 Clause-wise Explanation of the Standard 10.2.1 Clause 1: Scope 10.2.2 Clause 2: Normative

More information

Corporate Governance Statement

Corporate Governance Statement 58 PROGRAMMED 2015 ANNUAL REPORT Corporate Governance Statement Programmed is committed to ensuring that its obligations and responsibilities to its various stakeholders are fulfilled through appropriate

More information

Code of Practice for a Waterworks System Consisting Solely of a Water Distribution System

Code of Practice for a Waterworks System Consisting Solely of a Water Distribution System Code of Practice for a Waterworks System Consisting Solely of a Water Distribution System Effective June 1, 2012 Made under the Environmental Protection and Enhancement Act, RSA 2000, ce-12 Published by

More information

QSS 0 Products and Services without Bespoke Contracts.

QSS 0 Products and Services without Bespoke Contracts. QSS 0 Products and Services without Bespoke Contracts. Use: Typically Sub 50k processes without a bespoke contract. Amendment History Version Date Status V3 June 2018 Updated for 2018 deployment Contents

More information

Building Standards Customer Journey

Building Standards Customer Journey Building Standards Customer Journey Are you doing building work or home improvements? If so, this guide is for you. Building Standards Customer Journey Contents 2 Contents Building Standards Customer Journey

More information

CEN Keymark Scheme Rules for Thermostatic Radiator Valves. 2 nd Edition

CEN Keymark Scheme Rules for Thermostatic Radiator Valves. 2 nd Edition CEN Keymark Scheme Rules for Thermostatic Radiator Valves 2 nd Edition Content Foreword... 3 Introduction... 3 1 Scope... 4 2 References... 4 3 Terms and Definitions... 4 4 Application... 5 4.1 Product

More information

1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General

1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General 1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General The organization s management with executive The commitment and involvement of the responsibility shall define, document

More information

June Auditor regulation and oversight plan This report is for:

June Auditor regulation and oversight plan This report is for: June 2018 Auditor regulation and oversight plan 2018-2021 This report is for: Auditors People who prepare financial statements Directors of FMC reporting entities. This copyright work is licensed under

More information

Application for a New Approval And/or Modification Guide for Completing the Form S-0001

Application for a New Approval And/or Modification Guide for Completing the Form S-0001 Page: 1 of 6 How to Complete the Form- S-0001 is a certification body and are not approvals consultants. We specialise in providing fast efficient electrical product safety certification with guaranteed

More information

Annex II - Category B evidence. User Manual. for providing and evaluating Category B evidence

Annex II - Category B evidence. User Manual. for providing and evaluating Category B evidence Annex II - Category B evidence User Manual for providing and evaluating Category B evidence August 2014 Content 1. Introduction... 2 1.1 Scope... 2 1.2 Challenging task... 2 1.3 Framework for Category

More information

Review of Victoria s Electricity and Gas Network Safety Framework- Supplementary Issues Paper APA VTS Operations (Australia) Pty Ltd Submission

Review of Victoria s Electricity and Gas Network Safety Framework- Supplementary Issues Paper APA VTS Operations (Australia) Pty Ltd Submission 16 June 2017 Review of Victoria s Electricity and Gas Network Safety Framework- APA VTS Operations (Australia) Pty Ltd Submission Background: APA VTS Australia (Operations) Pty Ltd (APA VTS Operations)

More information

Regulatory Compliance and Enforcement Framework

Regulatory Compliance and Enforcement Framework Contents 1. About us... 3 1.1 Our Mission and Values... 3 2. Relevant Legislation and Obligations... 4 3. Approach to Regulatory Compliance and Enforcement... 4 3.1 Our Approach... 4 3.2 Working with Stakeholders...

More information

MANUAL DELIVERY OF DEVELOPER WORKS VERSION:

MANUAL DELIVERY OF DEVELOPER WORKS VERSION: MANUAL DELIVERY OF DEVELOPER WORKS VERSION: VERSION: 1.0 1.0 Contents 1. Introduction... 4 2. Purpose... 4 3. Scope... 4 3.1 Audience... 5 4. Definitions... 5 5. The delivery of Developer Works model...

More information

Privacy Policy 1. Introduction 2. What personal information does Paperless Warehousing collect and why?

Privacy Policy 1. Introduction 2. What personal information does Paperless Warehousing collect and why? 1. Introduction 1.1. Paperless Warehousing respects people's privacy. Paperless Warehousing is bound by the Australian Privacy Principles in the Privacy Act, as well as other applicable laws protecting

More information

Asset Management System Review

Asset Management System Review Asset Management System Review 3606-24 Prepared for Economic Regulation Authority of Western Australia 8 September 2017 8 September 2017 Cardno i Contact Information Cardno (QLD) Pty Ltd ABN 57 051 074

More information

PEFC contribution to the review. of the EU Timber Regulation

PEFC contribution to the review. of the EU Timber Regulation PEFC contribution to the review of the EU Timber Regulation 12.08.2015 Introduction PEFC, the Programme for the Endorsement of Forest Certification, is the world s leading forest certification system.

More information

Practical Systems Review. A Self-Review Tool for Local Government to Evaluate the Capability and Performance of Compliance Systems

Practical Systems Review. A Self-Review Tool for Local Government to Evaluate the Capability and Performance of Compliance Systems Practical Systems Review A Self-Review Tool for Local Government to Evaluate the Capability and Performance of Compliance Systems October 2012 Prepared for the Hunter & Central Coast Regional Environmental

More information

Marketing Code of Conduct

Marketing Code of Conduct Marketing Code of Conduct Approved for the purposes of the Electricity Supply Act 1995 (NSW) and the Gas Supply Act 1996 (NSW) by the NSW Minister for Energy 1 January 2011 CONTENTS 1. FOREWORD... 1 1.1

More information

Phoenix Energy Holdings Gas Ltd Health & Safety Policy

Phoenix Energy Holdings Gas Ltd Health & Safety Policy Phoenix Energy Holdings Gas Ltd Health & Safety Policy July 2017 Phoenix Energy Holdings Ltd Health & Safety Policy July 2017 Contents 1.0 Introduction 2.0 Purpose 3.0 Scope 4.0 References 5.0 Definitions

More information

Environment Plan Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities.

Environment Plan Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities. Environment Plan 18 Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities. Environment Plan 18 Introduction Sydney Water s vision is to

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

MoU2017v1. Memorandum of Understanding between the Department of Health and Water Corporation for Drinking Water

MoU2017v1. Memorandum of Understanding between the Department of Health and Water Corporation for Drinking Water MoU2017v1 Memorandum of Understanding between the Department of Health and Water Corporation for Drinking Water Contents 1.0 Foreword 1 1.1 Design of the MoU 2 2.0 Interpretation 3 3.0 Role of the Department

More information

THE ROLE OF A WATER TREATMENT PLANT OPERATOR IN THE SUCCESSFUL IMPLEMENTATION OF A DRINKING WATER MANAGEMENT SYSTEM. Sallyanne Bartlett

THE ROLE OF A WATER TREATMENT PLANT OPERATOR IN THE SUCCESSFUL IMPLEMENTATION OF A DRINKING WATER MANAGEMENT SYSTEM. Sallyanne Bartlett THE ROLE OF A WATER TREATMENT PLANT OPERATOR IN THE SUCCESSFUL IMPLEMENTATION OF A DRINKING WATER MANAGEMENT SYSTEM Paper Presented by: Sallyanne Bartlett Author: Sallyanne Bartlett, Scientist, WaterQPlus

More information