IEOR 130 Methods of Manufacturing Improvement Practice Examination Problems Part II of Course Prof. Leachman Fall, 2017

Size: px
Start display at page:

Download "IEOR 130 Methods of Manufacturing Improvement Practice Examination Problems Part II of Course Prof. Leachman Fall, 2017"

Transcription

1 IEOR 130 Methods of Manufacturing Improvement Practice Examination Problems Part II of Course Prof. Leachman Fall, For a particular semiconductor product, the customer orders received to date are as follows, sorted by date due to ship to customer: Delivery date Total orders due The current finished goods inventory of the product is 80 units. The production plan for the product is as follows: Output date Output quantity (a) A new customer calls and asks for delivery of 10 units per period beginning in period 4 and ending in period 6. Can the company provide delivery as requested? (b) Calculate the best delivery schedule the company can offer the customer. (c) Assuming the customer accepts the quote you calculated in part (b), calculate the new available-to-promise (ATP) quantities by period. Indicate whether you use cumulative ATP or incremental ATP. 2. For a particular semiconductor product, the customer orders received are as follows, sorted by date due to ship to customer: Delivery date Total orders due The current finished goods inventory of the product is 120 units. The production plan for the product is as follows: Output date Output quantity (a) A new customer calls and asks for delivery of 30 units per period beginning in period 3 and ending in period 6. Can the company provide delivery as requested? (b) Calculate the best delivery schedule the company can offer the customer. 1

2 (c) Assuming the customer accepts the quote you calculated in part (b), calculate the new available-to-promise (ATP) quantities by period. Indicate whether you use cumulative ATP or incremental ATP. 3. The finished goods inventory of a particular device is 100 units. The projected output over the next 6 weeks is 50, 50, 40, 40, 50, 50, respectively. The on-hand orders due for delivery over the next 6 weeks are 100, 60, 60, 40, 40, 20, respectively. (a) Calculate the availability of the device. (b) A prospective customer calls and asks for a delivery quote. The customer requests a delivery of 15 units per week in weeks 3, 4, 5, 6. If these quantities can not be met, the customer would like a quote of deliveries catching up to this schedule as quickly as possible. Calculate the best delivery quote that can be offered to the customer. (c) The same company sells a different device type that has bin splits into high-speed, mediumspeed and low-speed versions. These bin splits are 25%, 25% and 50%, respectively. Customers for the low speed version will accept shipment of either the medium-speed or the high-speed version in lieu of a low-speed version; customers for the medium-speed version will accept shipment of the high-speed version in lieu of the medium-speed version; and customers for the high-speed version will not accept any version substitution. Currently the company has 50 units in inventory of the low-speed version, but no inventory of the other versions. There are orders for 25 units of the high-speed version, 50 units of the medium-speed version, and 100 units of the low-speed version that need to be filled as soon as possible. Given the bin splits, the orders and the initial inventory, determine the minimum number of units of the device type that should be manufactured. 4. For a particular semiconductor product, the customer orders received are as follows, sorted by date due to ship to customer: Delivery date Total orders due The current finished goods inventory of the product is 200 units. The production plan for the product is as follows: Output date Output quantity (a) A new customer calls and asks for delivery of 10 units in period 2, 10 units in period 3 and 10 units in period 5. Can the company provide delivery as requested? 2

3 (b) Calculate the best delivery schedule the company can offer the customer. (c) Assuming the customer accepts the quote you calculated in part (b), calculate the new available-to-promise (ATP) quantities by period. (d) Now suppose that because of yield problems, the output quantity in period 5 is reduced to 60 (instead of 70). How does the quote to the new customer change? 5. A semiconductor company sells a device type that has bin splits into high-speed and lowspeed versions. These bin splits are 25% and 75%, respectively. Customers for the low speed version will accept shipment of the high-speed version in lieu of a low-speed version. Customers for the high-speed version will not accept version substitution. Currently the company has 100 units in inventory of the low-speed version, but no inventory of the high-speed version. The production plan for the product is as follows: Output date Output quantity before bin split The total customer orders received are as follows, sorted by date due to ship to customer: Delivery date Total orders due for high-speed Total orders due for low-speed (a) Calculate the available-to-promise (ATP) quantities for both versions by period. Indicate whether you use cumulative ATP or incremental ATP. (b) A new customer calls and asks for a delivery quote. The customer requests a delivery of 10 units of high-speed version and 20 units of low-speed version per day on day 2 and day 3. If these quantities cannot be met, the customer would like a quote of deliveries catching up to this schedule as quickly as possible. Calculate the best delivery quote that can be offered to the customer. (c) Suppose the fab experienced unexpected machine down when the new customer calls. The fab management is forced to adjust the production plan so that the actual output will be as follows: Output date Output quantity before bin split Can the company still ship as planned? How should it respond to the new customer in this case? 3

4 6. Formulate linear programs to accomplish requirements planning of binning products for the simplified case below. The goal is to efficiently translate demands for final products into demands for starts of assembly products. The notation and parameters are as follows. Indices t time period, t = 1,, T. i assembly product, i = 1,, I. j quality bin of assembly product, j = 1,., J. k final product, k = 1,, K. r demand class, r = 1,2. Class 1 consists of customer commitments that must be fulfilled as ontime as possible. Class 2 includes class 1 commitments plus all other forecasted demand. Demands d = demand in class r for final product k during period t. r kt Product structure i j denotes that assembly product i generates bin j. j k denotes that bin j is suitable for fulfilling demands for final product k. k j denotes that final product k is an allowed usage of bin j. aij = fraction of output of assembly product i that falls into bin j. L = cycle time for assembly products (assumed to be integer). Economic parameters cit = discounted cost of output of one unit of assembly product i in period t. skt = discounted revenue for one unit of final product k in period t. bkt = discounted backorder cost for one unit of final product k committed in period t. Initial conditions Ij0 = initial inventory of bin j. wit = projected WIP-out of assembly product i in period t, t = 1,, L. BOk0 = initial shortage to customer commitments of final product k. 7. The process flow for making an advanced DRAM device requires the use of a 193nm scanner photolithography machine at the photo steps in layers 1, 5 and 9. The cycle times from fab start to the photo steps in layers 1, 5 and 9 are 0.2 weeks, 0.8 weeks and 1.8 weeks, respectively. The fab line yield is 100%. The UPH (units per hour) factors at the photo steps in layers 1, 5 and 9 are 50, 48 and 45, respectively. There are 3 193nm scanners in service. The CEE of the 193nm scanners is 72%. The fab operates 24 hours a day, 7 days per week. The 193nm scanner is believed to be the fab bottleneck equipment type. It is desired to develop a capacity constraint on weekly fab starts for the purposes of production planning. 4

5 (a) Let xt denote the fab starts in week t. Express the 193nm scanner capacity constraint on xt, xt-1 and xt-2. You may assume the fab will operate every day of every week. You do not need to simplify your expression. (b) (6 points) In steady state, how many wafers may be started per week? (c) Suppose 4,000 wafer starts were made last week, and 6,000 wafer starts were made the week before that. What is the maximum number of wafers that may be started this week without extending 193nm scanner cycle time? 8. A small fabrication line operates two process flows, flow A and flow B. The important steps in each flow are as follows: Flow A Flow B Qualified CT up Qualified CT up Step UPH Machine_types to Step Step UPH Machine_types to Step 1 50 M M1 or M M1 or M M1 or M2 or M M1 or M M1 or M2 or M3 2 Note: UPH = units per hour, the speed of the machine when it performs that step. CT up to step is the average cycle time from fab start to arrival at the process step, expressed in weeks. Data on the photo machines is as follows: Machine_type Quantity CEE M M M The factory operates 168 hours per week and line yield losses are negligible. (a) Let xt denote the constant rate of starts of flow A in week t, and let yt denote the constant rate of starts of flow B in week t. Express capacity constraints on xt and yt in an arbitrary week t. You do not need to simplify numerical expressions. (b) Suppose no starts of flow B are allowed. What is the maximum steady-state starts rate for flow A? In that case, which machine type(s) is (are) the bottleneck(s)? (c) Suppose no starts of flow A are allowed. What is the maximum steady-state starts rate for flow B? In that case, which machine type(s) is (are) the bottleneck(s)? (d) The starts rates in the last two weeks for each flow were as follows: 5

6 Week Flow A Flow B 0 9,000 12, ,000 14,000 If in week 1 the starts for flow A are required to be zero, what is maximum amount of starts of flow B that should be allowed in week 1? Why is this number different from your answer to part (c)? Which machine type(s) will be the bottleneck(s) in week 1? 9. A small fabrication line operates two process flows, 180nm and 250nm. The photo steps are as follows: 180nm 250nm CT up CT up Step UPH Machine_type to Step Step UPH Machine_type to Step 1 50 Scanner DUV stepper DUV stepper I Line stepper DUV stepper I Line stepper DUV stepper I Line stepper Scanner DUV stepper 4 Note: UPH = units per hour, the speed of the machine when it performs that step. CT up to step is the average cycle time from fab start to arrival at the process step, in weeks. Data on the photo machines is as follows: Machine_type Quantity CEE Scanner DUV stepper I Line stepper The factory operates 168 hours per week and line yield losses are negligible. (a) Let xt denote the constant rate of 180nm starts in week t, and let yt denote the constant rate of 250nm starts in week t. Express capacity constraints on xt and yt for each type of photo machine in an arbitrary week t. You do not need to simplify numerical expressions. (b) If in every week t, xt = yt, what is the maximum steady-state starts rate for each process flow? (c) For your answer to (b), which machine type(s) is (are) the bottleneck(s)? (d) Can the starts rate of either the 180nm or 250nm processes be increased from your answer to (b) without exceeding capacities? If so, how much? 6

7 (e) Considering your answer to (d), has (have) the bottleneck(s) changed? If so, what is (are) the bottleneck(s) now? 10. Consider a factory that has two products in production, A and B. Sales of product A are a steady 1,000 wafers per week and its remaining product life is two years. The average selling price per wafer is $5,000 and that price is declining 30% per year. Sales of product B are a steady 5,000 wafers per week and the remaining product life is one year. The average selling price per wafer is $2,000 and that selling price is declining 60% per year. (a) The cycle time to make product A is 30 days. The cycle time to make product B is 45 days. Compute the remaining lifetime revenue for each product. (b) There are 17 photo machines in the factory and they achieve 88% availability operating 168 hours per week. The mean and standard deviation of a down time event on photo machines at the factory are 9 and 6 hours, respectively. There are 17 photo steps to make product A and 20 photo steps to make product B. The process time to perform any photo step is 0.5 hours per 25-wafer lot and the standard cycle time per lot is 0.75 hours. Assume line yields for both products are 100%. Assuming utilization is balanced across all 10 photo machines, compute the utilization of availability of the photo machines. (c) Let m denote the number of photo machines qualified to perform a given photo step. Management is considering engineering work to qualify more photo machines at various photo steps to make Product A as follows: Step m # of Required Type steps engineering hours in flow to add 1 more to m for all steps of that type Management also is considering engineering work to qualify more photo machines at various photo steps to make Product B as follows: Step m # of Required Type steps engineering hours in flow to add 1 more to m for all steps of that type Estimate the current total cycle time for each type of photo step on each product. You may assume ca 2 =1, and c0 2 = 1 for all step types. 7

8 (d) If all of the proposed work for Product A is undertaken, what additional revenue will the company obtain over the life of Product A? If all of the proposed work for Product B is undertaken, what additional revenue will the company obtain over the life of Product B? (e) Because of other engineering tasks and limited engineering staff, the company might not be able to undertake all of the photo qualification work above. Order the product-step-type projects listed above in the order of decreasing economic return per engineering hour expended. 11. The photolithography department is considering doing the engineering work to qualify one more photo machine at various photo steps. There are different possible steps where this work could be done. Information is as follows: Step m MTTR cr 2 PT (per A U/A # of Required Type step) steps engineering hours in flow to add 1 more to m to each step of that type (a) Estimate the cycle time per step for each machine type. You may assume fab line yield is 100%, ca 2 =1, c0 2 = 1 and SCT = 1.5 per step for all step types. (b) Considering the number of steps in the overall process flow within each step type, estimate the total cycle time of each step type. (c) For each step type, estimate the total cycle time reduction if one more machine is qualified for every step of that type. Assume no more machines are installed and the fab starts rate is kept constant. (d) Considering the cycle time reduction per engineering hour expended, which step type qualification effort has the highest return on investment? 12. The management of a wafer fab with one process flow is considering the purchase of an additional process machine in order to reduce cycle time. At present, there is room in the fab for one more machine of either Type 1 or Type 2. Statistics about these machines are as follows: Type m MTTR cr 2 PT (per A U/A SCT (per No. of steps step) step) in process flow (a) Estimate the cycle time per step for each machine type. You may assume fab line yield is 100%, ca 2 =1, and c0 2 = 1. 8

9 For type 1, the queue time per step is 9.4 hours and the cycle time per step is 10.9 hours. For type 2, the queue time per step is 5.0 hours and the cycle time per step is 6.6 hours. (b) Considering the number of steps in the process flow performed by each machine type, estimate the total cycle time in the process flow contributed by each machine type. (c) Estimate the total cycle time reduction if one more machine of type 1 is installed, while keeping the fab starts rate constant. (d) Repeat (c) for one more machine of type 2. (e) The cost to install one more machine of type 1 is 1.0 million dollars. The cost to install one more machine of type 2 is 1.5 million dollars. Which installation would offer the greatest cycle time reduction per capital dollar expended? 13. The photolithography department in a semiconductor fabrication plant has 10 identical photo machines. Manufacturing lots move through a series of 100 steps in the plant, including five photolithography steps. At present, any of the ten machines can be used to perform any of the five photo steps. To improve the die yield, the photo process engineer proposes a lot-to-lens dedication policy, whereby each manufacturing lot would be required to visit the same photo machine for processing of photo steps 2, 3, 4 and 5 that the lot visited for photo step 1. It still would be the case that a lot could be processed by any of the ten machines at photo step 1. Suppose the photo machines average 90% availability, the factory works 168 hours per week, and the total hours of processing work that the ten photolithography machines perform is 1250 hours per week. a. Assuming utilization of the ten machines is balanced, what is the utilization of availability for the photo machines? b. Assume all lots at all photo steps have the same process time. Assume the proposed change in policy would not have any effect on the lot inter-arrival times at each step nor any effect on equipment down times or process times. Estimate the RATIO of lot queue time at photo step 2 if lot-to-lens dedication is implemented to lot queue time at photo step 2 at present. c. Estimate the percentage increase in total lot queue time for all five photo steps if lot-to-lens dedication is implemented. You may assume there is no line yield loss, i.e., each step has an equal production volume. 14. The processing cycle for a diffusion furnace consists of three phases: load, run, and unload. During the load portion of the cycle, an operator transfers wafers from incoming lots into a boat accommodating 150 wafers. If the incoming lots include less than 150 wafers, the operator inserts dummy wafers to raise the total wafers in the boat up to 150. During the run portion of the cycle, the boat is mechanically inserted into the furnace, the wafers are cooked for a specified length of time, and then the boat is mechanically withdrawn from the furnace. During the unload portion of the cycle, the operator unloads the product wafers from the boat into lots 9

10 to be sent to follow-on operations, and he/she unloads the dummy wafers for re-use in subsequent furnace runs as may be required. For a particular furnace, the run portion of the cycle takes exactly 6 hours every cycle. The theoretical times to perform the load and unload portions of the cycle are 0.5 hours each, but sometimes the operators take longer to complete these tasks. The average load time is estimated to be 0.6 hours (and the average unload time also is 0.6 hours). Last week this furnace completed 20 process cycles and experienced 4.5 hours of down time. The average batch size was 5.7 lots (i.e., product wafers). (a) Estimate the utilization of total time, utilization of availability, and OEE of this furnace last week. Assume the factory is operated 24 hours per day, seven days per week. (b) Identify the two reasons that rate efficiency was less than 100% for this furnace. (c) The equipment vendor offers a modification to the furnace whereby the furnace would be equipped with dual boats instead of a single boat. If equipped with dual boats, the operator could load boat B while the furnace was running boat A. After the run on boat A was completed, the furnace could immediately start the run on boat B. In parallel with the run on boat B, the operator could unload boat A. When loading and unloading are conducted in parallel with processing, the furnace is said to be backloaded. If equipped with dual boats, what is the reduction in theoretical process time per cycle? (d) Assuming the same number of process cycles were run with the same average batch size, estimate the OEE and utilization of availability last week if the furnace had been equipped with dual boats and all batches could be backloaded. (e) Assuming the same number of process cycles were run with the same average batch size, estimate the reduction in cycle time last week if the furnace had been equipped with dual boats and all batches could be backloaded. Assume there are no alternative furnaces, i.e., this is the only one that can be used, and assume down time statistics and process time variability would be unchanged if dual boats are installed. Other data: c0 = 1, MTTR = 4.5, cr = 1.0, ca = 1, lot arrival rate = lots per hour. (f) Suppose the current revenue from one lot is $25,000 and is declining 25% per year. The current fab cycle time is 40 days. The remaining product lifetime is 3 years. Assuming last week s processing rate is maintained, estimate the revenue gain from installation of dual boats in the furnace. 15. A wet bench consists of a series of tanks served by a robot arm. Two production lots (50 wafers total) form one batch that travels down the bench. The batch is dunked in each tank by the robot arm. One of the tanks contains sulfuric acid that strips an undesired film off the wafers. With repeated use, the acid bath contains more and more residue from previously stripped wafers, and there is increasing probability that the film on the wafers in the next batch may be inadequately stripped. An inspection step carried out after the wet bench step would detect this, 10

11 in which case the batch must be re-worked. At some point the acid bath must be dumped and repoured with fresh acid; this involves one hour of down time to the wet bench as well as the expenses for new sulfuric acid and disposing of the old acid. The process time in the sulfuric acid tank is 30 minutes per batch, whether for a first-time batch or a re-worked batch. Each batch is dunked for a lesser amount of time in the other tanks on the bench (pre-cleaning, rinsing and drying); the total time for a batch to traverse the bench is 90 minutes. The wet etch engineer estimates the probability that rework is required is a linear function of bath usage: P(n) = 0.05*n, where n is the number of first-time batches processed since the acid bath was re-poured and P(n) is the probability that the n th batch must be re-worked. You may assume that with probability one a batch that is reworked will be successfully stripped of the undesired film on the second pass through the tank, and that reworking does not cause the acid bath to deteriorate. (a) Suppose our objective is maximum wet-bench capacity. What frequency of re-pour is best? (By frequency, we mean how many batches between re-pours of the sulfuric acid bath.) (b) Now suppose our objective is minimum cycle time. Assume the following data for the wet bench: m=1, ca = 1, ce = 1, the wet bench receives 250 lots per week (i.e., 125 batches per week, excluding rework), and the only down time is for re-pouring the acid bath. Now what frequency of re-pour is best? (Hint: You can calculate the availability and average rework rate as functions of the re-pour frequency. And be sure to include rework in utilization.) (c) Now suppose our objective is maximum profit. What factors should be taken into account to decide the best frequency of re-pour? What other data would you request in order to make this determination? 16. A wafer fab operates a single process flow that has a photo step at the end of layers one through five. Layer six includes the remaining process steps after the last photo step. A detailed simulation of the fab has been run and stable steady-state statistics were collected as follows: Layer Avg. Wait time Std. Dev. Of Wait time Avg. No. of Lots in the layer (days) in the layer (days) in the layer The average output rate in the steady-state statistics of the simulation is 20 lots per day. (a) What was the steady-state average total cycle time in the simulation? 11

12 (b) Suppose management sets the target cycle time for the process flow to be equal to the simulated average total cycle time. For an output rate of 20 lots per day, recommend target WIP levels in each layer. (c) Suppose fab outs to date are on time, and suppose the target output rate of 20 lots per day will be maintained for many weeks. The fab operates two 12-hour shifts per day. Suppose it is the start of a shift and the current WIP levels in each layer are as follows: Layer WIP (no. of lots) Calculate IPQs and Schedule Scores for each photo step. What is the priority order for scheduling the photo steps? (d) In the etch area of the fab, the process time is 0.5 hours for all etch steps. There are two etch machines, M1 and M2. Each machine can perform any etch step. At the start of the shift, the etch area has the following data: Step IPQ (lots) Available WIP (lots) A 6 4 B 2 4 C D 2 8 The following shift schedule has been prepared by the etch area supervisor: Machine M1: Run 4 lots of A, then run 2 lots of B, then run 6 lots of C Machine M2: Run 8 lots of C, then run 4 lots of D Can this schedule be improved upon? If so, suggest the best schedule you can, and briefly note the reasons why your schedule should be preferred over the schedule above. 17. A fabrication process includes 4 visits to the photo bottleneck, one each at the end of layers 1, 2, 3 and 4. Recent statistics about the fabrication process are as follows: Layer Avg. total WIP Avg. active WIP (no. of lots) (no. of lots)

13 The average production rate during the period of data collection was 10 lots per shift. No line yield losses were experienced. (a) Recommend target cycle times by layer assuming line yields are 100% and the overall target cycle time is 50 shifts. (b) Current WIP status is as follows. Data concerning the photo steps also is displayed. Layer Actual WIP WIP at Photo Photo process Qualified (lots) (lots) time (hours/lot) Machines A, B, C B, C A, B C 5 15 Assume it is now the start of a shift and that fab-outs to date are on time. The target production rate continues to be 10 lots per shift. Calculate the ideal production quantity (IPQ) and the schedule score (SS) for each photo step for this shift. (c) Assume one shift lasts 8 hours. Using the data in part (b), determine an efficient shift schedule for the steppers. Assume only the WIP at photo may be scheduled and assume all 3 steppers will be available for all 8 hours. (An efficient schedule has the following properties: as much of the IPQs are completed as possible, steppers are utilized as much as possible, and changeovers of the steppers are minimized.) 18. A fabrication process includes 4 visits to the photo bottleneck, one each at the end of layers 1, 2, 3 and 4. Recent statistics about the process are as follows: Layer Avg. cycle time Standard Avg. number of (shifts) cycle time (shifts) active lots (a) Assuming the current production rate is the same as the rate during the period the above statistics were tabulated, recommend target WIP levels by layer, assuming line yields are 100% and the target cycle time is 40 shifts. (b) The current WIP status is as follows. Data concerning the photo steps at the end of each layer also are displayed. 13

14 Layer Actual WIP WIP at Photo Photo process Qualified (lots) (lots) time (hours/lot) Machines A, B, C B, C A, B C 5 15 Assume it is currently the start of a shift. Calculate the ideal production quantity (IPQ) and the schedule score (SS) for each photo step for the upcoming shift. (c) Assume one shift lasts 8 hours. Using the data in part (b), determine an efficient shift schedule for the steppers. Assume only the WIP at photo may be scheduled and assume all 3 steppers will be available for all 8 hours. (An efficient schedule has the following properties: as much of the IPQs are completed as possible, steppers are utilized as much as possible, and changeovers of the steppers are minimized.) 19. A fabrication process includes 4 visits to the photo bottleneck, one each at the end of layers 1, 2, 3 and 4. A simulation of the fabrication process produced the following statistics: Layer Avg. cycle time Standard deviation Avg. number of (shifts) of cycle time (shifts) active lots (Note: Active lots are lots that are not waiting, i.e., they are experiencing processing or transport between steps.) The simulated average production rate was 10 lots per shift. No line yield losses were simulated. (a) Recommend target cycle times by layer assuming line yields are 100% and the target cycle time is 40 shifts. (b) The fab outs at the end of the simulation had achieved the target output. The WIP status at the end of the simulation was as follows. Data concerning the photo steps also is displayed. Layer Actual WIP WIP at Photo Photo process Qualified (lots) (lots) time (hours/lot) Machines A, B, C B, C A, B C

15 Assume the simulation ended at the start of a shift. Calculate the ideal production quantity (IPQ) and the schedule score (SS) for each photo step for that shift. (c) Assume one shift lasts 8 hours. Using the data in part (b), determine an efficient shift schedule for the steppers. Assume only the WIP at photo may be scheduled and assume all 3 steppers will be available for all 8 hours. (An efficient schedule has the following properties: as much of the IPQs are completed as possible, steppers are utilized as much as possible, and changeovers of the steppers are minimized.) 20. A fabrication process includes three steps performed on the bottleneck equipment type. Layer 1 of the process ends at the first bottleneck step; layer 2 ends at the second bottleneck step; layer 3 ends at the third bottleneck step; and layer four includes all steps of the process after the third bottleneck step. The machines performing the bottleneck steps are inflexible whereby each bottleneck step must be performed by a different machine. Data on cycle times is as follows: Layer Actual Avg. Standard Theoretical i Cycle Time Deviation of Cycle Time (ACTi) ACTi ( i) (SCTi) Management of the factory operating the process has decided to set the target cycle time for the process to be 90% of the actual average cycle time (ACT). The total WIP level in the process in the most recent week was 400. (a) According to management s target cycle time for the process, what is the target for the total WIP in the process? (b) Compute efficient target WIP levels for each layer. (c) Instead of your answer to (b), suppose management decides to set the target WIP level in each layer to be 90% of the actual WIP level in that layer. If management implements their target WIP levels, which of the three bottleneck steps will have the greatest idle time over the long run? And in this layer, will the amount of idle time be higher or lower than it would be using the target WIP levels in your answer in (b)? Explain. 21. A simulation of a factory with a single process flow achieves steady-state. Various machines are used to perform the steps of the process flow; each machine performs one step on one production lot at a time. The steady-state statistics show that, on average, 63.5 out of 80 machines are busy processing lots. Summing across all steps in the process flow, the average total waiting time for each lot is 8.5 days, and the average total number of lots in queues is (a) What is the production rate of the factory? 15

16 (b) What is the level of active WIP in the factory? (c) What is the standard cycle time of the process flow? (d) What is the actual cycle time of the process flow? 22. A wafer fab has a single process flow with five masking layers. The standard deviation of the WIP level at each photo exposure operation has been computed as follows: Layer 1-11 lots Layer 2-19 lots Layer 3-25 lots Layer 4-25 lots Layer 5-20 lots The sum of standard cycle times for the process steps in each layer has been computed as follows: Layer 1-2 days Layer 2-4 days Layer 3-4 days Layer 4-4 days Layer 5-4 days Layer 6-2 days (a) The target cycle time for the entire fab process is 60 days. The target production rate is 10 lots per day. Determine the target WIP level for each layer. (b) Currently, layer 5 has a WIP level of 150 lots. The photo stepper machines can process two lots per hour when they are up; average availability of these machines is 90% and the average utilization (of total time) is 75%. If two steppers are qualified to perform the layer 5 exposure, how long will it take to reduce the WIP in layer 5 to the target level? (c) How many steppers need to be qualified for layer 5 if the recovery time is to be within one shift, i.e., less than 8 hours? 16

17 23. A wafer fab has a single process flow with five masking layers. The standard deviation of the cycle time between photo exposure operations has been computed as follows: Fab-in to Layer 1 exposure shifts (where one shift equals 8 hours) Layer 1 exposure to Layer 2 exposure shifts Layer 2 exposure to Layer 3 exposure shifts Layer 3 exposure to Layer 4 exposure shifts Layer 4 exposure to Layer 5 exposure shifts Layer 5 exposure to fab-out shifts The sum of standard cycle times for the process steps in each layer has been computed as follows: Layer 1-2 shifts Layer 2-4 shifts Layer 3-4 shifts Layer 4-4 shifts Layer 5-4 shifts Layer 6-2 shifts (a) The target cycle time for the entire fab process is 40 shifts. The target production rate is 10 lots per shift. Determine the target WIP level for each layer. (b) Currently, layer 5 has a WIP level of 110 lots. The photo stepper machines each can process two lots per hour when they are up; average availability of these machines is 90% and the average utilization (of total time) is 65%. If two steppers are qualified to perform the layer 5 exposure, estimate how long it will take to reduce the WIP in layer 5 to the target level. (c) How many steppers would need to be qualified for layer 5 if the recovery time is to be within four hours, i.e., less than 0.5 shifts? (d) Now suppose at the start of a shift the actual WIP levels (expressed in lots) are as follows: Layer Total WIP WIP On-Hand Qualified in Layer at Photo step Steppers A,B,C,D 17

18 C,D A,B,C,D D B Assuming fab-outs up until the start of the shift are exactly on time, determine the ideal production quantity (IPQ) and schedule score (SS) for each photo operation. (Each photo operation is the last operation in its layer.) (e) The fab has four total steppers (A,B,C,D). Each stepper is qualified to perform only certain photo operations, as specified in the table above. Assume that all four steppers will be available all 8 hours during the shift, and that the process time per lot is 0.5 hours for all photo operations. Suggest an efficient shift schedule for the four steppers. Assume that only WIP on-hand at photo may be scheduled for processing by the steppers. 24. A wafer fab has a single process flow with five masking layers. The standard deviation of the WIP level at each photo exposure operation has been computed as follows: Layer 1-5 lots Layer 2-8 lots Layer 3-10 lots Layer 4-10 lots Layer 5-7 lots The sum of standard cycle times for the process steps in each layer has been computed as follows: Layer 1-1 day Layer 2-2 days Layer 3-2 days Layer 4-2 days Layer 5-2 days Layer 6-1 day 18

19 (a) The target cycle time for the entire fab process is 20 days. The target production rate is 8 lots per day. Determine the target WIP level for each layer. Identify the active WIP and buffer WIP levels for each layer. (b) Currently, the total WIP in each layer and the WIP at the photo operation in each layer are as follows. Layer Total WIP WIP at photo Compute the schedule score for the photo operation in each layer. Assume there is no shortage or surplus in fab outs to date. Assume there are two 12-hour shifts per day. (c) Suppose one of the steppers is about to run out of lots for its current operation. According to the schedule scores, which photo operation has the highest priority for next setup? (d) Suppose downstream WIP continues to move from layer to layer according to the target production rate, and suppose one stepper is set up to process the photo operation you identified in part (c). Estimate how long it will take to raise the schedule score for this operation to zero. Assume steppers have 90% availability, and assume the standard process time for photo operations is 2 hours per lot. 25. In a wafer fab with a single process flow and five masking layers, the following information on standard deviation of the cycle time between photo steps is available: Fab start to Layer 1 photo step shifts Layer 1 photo step to Layer 2 photo step shifts Layer 2 photo step to Layer 3 photo step shifts Layer 3 photo step to Layer 4 photo step shifts Layer 4 photo step to Layer 5 photo step shifts Layer 5 photo step to Fab out shifts The sum of the standard cycle times for the process steps in each layer has been computed as follows: Layer 1-1 shift 19

20 Layer 2-1 shift Layer 3-2 shifts Layer 4-3 shifts Layer 5-2 shifts Layer 6-1 shift (Note: "Layer 6" is just the portion of the fab process after the Layer 5 photo step until fab out.) (a) The target cycle time for the entire fab process is 25 shifts. The target production rate is 10 lots per shift. The photo machines are the bottleneck. Determine the target WIP level for each layer. (b) Currently, the total WIP in each layer, the WIP at the photo operation in each layer, and the qualified steppers in each layer are as follows: Layer Total WIP WIP at Photo Qualified Steppers A,C,D,E B,C C,D,E B,E D Assuming fab-outs up until the start of the shift are exactly on time, determine the ideal production quantity (IPQ) and schedule score (SS) for each photo operation. (c) The fab has five total steppers (A,B,C,D,E). Each stepper is qualified to perform only certain operations, as specified in the table above. Assume all five steppers are available for all 8 hours during the shift and that the process time per lot is 0.5 hours for all photo operations. Suggest an efficient schedule for the five steppers. Assume that only WIP on hand at the photo may be scheduled for processing by the steppers. 20

IEOR 130 Methods of Manufacturing Improvement Practice Examination Problems Part I of Course Prof. Leachman Fall, 2017

IEOR 130 Methods of Manufacturing Improvement Practice Examination Problems Part I of Course Prof. Leachman Fall, 2017 IEOR 130 Methods of Manufacturing Improvement Practice Examination Problems Part I of Course Prof. Leachman Fall, 2017 1. The thickness of a film deposited on wafers at a particular process step is subject

More information

Closed-Loop Measurement of Equipment Efficiency and Equipment Capacity. Prof. Rob Leachman University of California at Berkeley

Closed-Loop Measurement of Equipment Efficiency and Equipment Capacity. Prof. Rob Leachman University of California at Berkeley Closed-Loop Measurement of Equipment Efficiency and Equipment Capacity Prof. Rob Leachman University of California at Berkeley Introduction Important concept from "TPM" paradigm: Overall Equipment Efficiency

More information

IEOR 130 Methods of Manufacturing Improvement Fall, 2016, Prof. Leachman Homework Assignment #5, Due Thursday, Oct. 6, 2016

IEOR 130 Methods of Manufacturing Improvement Fall, 2016, Prof. Leachman Homework Assignment #5, Due Thursday, Oct. 6, 2016 IEOR 130 Methods of Manufacturing Improvement Fall, 2016, Prof. Leachman Homework Assignment #5, Due Thursday, Oct. 6, 2016 1. The management of a wafer fabrication facility is trying to sort out how much

More information

Prof. Rob Leachman University of California at Berkeley Leachman & Associates LLC

Prof. Rob Leachman University of California at Berkeley Leachman & Associates LLC Cycle Time Management Prof. Rob Leachman University of California at Berkeley Leachman & Associates LLC October 25, 2016 Oct. 26, 2016 Leachman - Cycle Time 1 Agenda Definitions of cycle time Measures

More information

IEOR 130 Factory Floor Scheduling Prof. Robert C. Leachman May, 2017

IEOR 130 Factory Floor Scheduling Prof. Robert C. Leachman May, 2017 IEOR 130 Factory Floor Scheduling Prof. Robert C. Leachman May, 2017 1. Introduction The primary purpose of factory floor scheduling is to ensure the factory production plan is fulfilled. As described

More information

Flow and Pull Systems

Flow and Pull Systems Online Student Guide Flow and Pull Systems OpusWorks 2016, All Rights Reserved 1 Table of Contents LEARNING OBJECTIVES... 4 INTRODUCTION... 4 BENEFITS OF FLOW AND PULL... 5 CLEARING ROADBLOCKS... 5 APPROACH

More information

REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION

REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION Computer Integrated Manufacturing. J. Winsor, AI Sivakumar and R Gay, eds. World Scientific, (July 1995), pp 889-896. REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION Giam Kim Toh, Ui Wei

More information

PRACTICE PROBLEM SET Topic 1: Basic Process Analysis

PRACTICE PROBLEM SET Topic 1: Basic Process Analysis The Wharton School Quarter II The University of Pennsylvania Fall 1999 PRACTICE PROBLEM SET Topic 1: Basic Process Analysis Problem 1: Consider the following three-step production process: Raw Material

More information

Aggregate modeling in semiconductor manufacturing using effective process times

Aggregate modeling in semiconductor manufacturing using effective process times Aggregate modeling in semiconductor manufacturing using effective process times C.P.L. Veeger 1, L.F.P. Etman 1, A.A.J. Lefeber 1, I.J.B.F. Adan 2, J. van Herk 3, and J.E. Rooda 1 1 Systems Engineering

More information

Customer Support: Leveraging Value of Ownership

Customer Support: Leveraging Value of Ownership Customer Support: Leveraging Value of Ownership Bernard Carayon SVP Customer Support WW Analyst Day, 30 September 2004 / Slide 1 Agenda! Customer Support main activities! Worldwide Organization and installed

More information

Modeling, Analysis, Simulation and Control of Semiconductor Manufacturing Systems: A Generalized Stochastic Colored Timed Petri Net Approach

Modeling, Analysis, Simulation and Control of Semiconductor Manufacturing Systems: A Generalized Stochastic Colored Timed Petri Net Approach Modeling, Analysis, Simulation and Control of Semiconductor Manufacturing Systems: A Generalized Stochastic Colored Timed Petri Net Approach Ming-Hung Lin and Li-Chen F u Dept. of Computer Science and

More information

Report 1. B. Starting Wafer Specs Number: 10 Total, 6 Device and 4 Test wafers

Report 1. B. Starting Wafer Specs Number: 10 Total, 6 Device and 4 Test wafers Aaron Pederson EE 432 Lab Dr. Meng Lu netid: abp250 Lab instructor: Yunfei Zhao Report 1 A. Overview The goal of this lab is to go through the semiconductor fabrication process from start to finish. This

More information

Getting the Best 300mm Fab Using the Right Design and Build Process. Presented on SEMI ITRS

Getting the Best 300mm Fab Using the Right Design and Build Process. Presented on SEMI ITRS Getting the Best 300mm Fab Using the Right Design and Build Process Presented on SEMI ITRS Agenda Introduction Objectives of Fab Design Design Process Overview From process flow to toolset Resource Modeling

More information

There are three options available for coping with variations in demand:

There are three options available for coping with variations in demand: Module 3E10 Operations management for Engineers - Crib 1 (a) Define the theoretical capacity of a manufacturing line. Explain why the actual capacity of a manufacturing line is often different from its

More information

Stop Planning Semiconductor Chips Like Potato Chips!

Stop Planning Semiconductor Chips Like Potato Chips! epaper Series Version A.1.0 Stop Planning Semiconductor Chips Like Potato Chips! Overview It s no surprise that the Semiconductor industry is very asset-intensive, with long leadtimes and expensive capital

More information

Applying LP to Plan Production at Jos A Bank

Applying LP to Plan Production at Jos A Bank Applying LP to Plan Production at Jos A Bank Learning objectives today Understand Jos A Bank production Issues in production planning Formulating an LP to plan production Issues in formulation Solving

More information

The Tri-Star Simulation Model

The Tri-Star Simulation Model The Tri-Star Simulation Model After Mark Redmond and his former colleague, Hal Brookings, finished a nice dinner at Mark s country club and a lengthy discussion of Hal s experiences with lean manufacturing,

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION 1 CHAPTER 1 INTRODUCTION 1.1 MANUFACTURING SYSTEM Manufacturing, a branch of industry, is the application of tools and processes for the transformation of raw materials into finished products. The manufacturing

More information

EUV Products and Business Opportunity

EUV Products and Business Opportunity EUV Products and Business Opportunity Christophe Fouquet Executive Vice President Business Line EUV ASML EUV Lithography product and business opportunity Key Messages ASML EUV lithography extends our Logic

More information

EUV Products and Business Opportunity

EUV Products and Business Opportunity EUV Products and Business Opportunity Christophe Fouquet Executive Vice President Business Line EUV ASML EUV Lithography product and business opportunity Key Messages ASML EUV lithography extends our Logic

More information

Production Management and Scheduling

Production Management and Scheduling Production Management and Scheduling Meet Your Due Dates Your production process can be simple or complex, time consuming or quick, but one thing remains constant the drive to meet your customer s delivery

More information

MIT Manufacturing Systems Analysis Lecture 1: Overview

MIT Manufacturing Systems Analysis Lecture 1: Overview 2.852 Manufacturing Systems Analysis 1/44 Copyright 2010 c Stanley B. Gershwin. MIT 2.852 Manufacturing Systems Analysis Lecture 1: Overview Stanley B. Gershwin http://web.mit.edu/manuf-sys Massachusetts

More information

PRINCIPLES OF LEAN MANUFACTURING. Purdue Manufacturing Extension Partnership (800)

PRINCIPLES OF LEAN MANUFACTURING. Purdue Manufacturing Extension Partnership (800) PRINCIPLES OF LEAN MANUFACTURING Purdue Manufacturing Extension Partnership (800) 877-5182 www.mep.purdue.edu What Is Lean? 2 Defining Lean Manufacturing Lean manufacturing is a systematic approach to

More information

Chapter 17. Synchronizing and Balancing Processes. Level the master production schedule. Production. Time

Chapter 17. Synchronizing and Balancing Processes. Level the master production schedule. Production. Time Chapter 17 Synchronizing and Balancing Processes 1 Goal Achieve uniform flow Level the master production schedule Production Time Avg. Reduce the size of batches produced for final assembly Production

More information

Inventory and Variability

Inventory and Variability Inventory and Variability 1/29 Copyright c 21 Stanley B. Gershwin. All rights reserved. Inventory and Variability Stanley B. Gershwin gershwin@mit.edu http://web.mit.edu/manuf-sys Massachusetts Institute

More information

Factory Operations Research Center (FORCe II)

Factory Operations Research Center (FORCe II) Factory Operations Research Center (FORCe II) SRC/ISMT 2004-OJ-1214 Configuration, monitoring and control of semiconductor supply chains Jan. 7, 2005 Shi-Chung Chang (task 1) Argon Chen (task 2) Yon Chou

More information

Quick Manufacturing Stencil

Quick Manufacturing Stencil Quick Manufacturing Stencil Quick Manufacturing is one of evsm s Quick Stencils and supports plant level mapping of discrete parts and assemblies in industries like automotive, electro-mechanical, and

More information

ThermoFab and DBR: Manufacturing At Warp Speed. A White Paper Report

ThermoFab and DBR: Manufacturing At Warp Speed. A White Paper Report ThermoFab and DBR: Manufacturing At Warp Speed A White Paper Report June 2004 You probably know ThermoFab as a leading custom thermoforming provider of high-quality plastic enclosures for a wide range

More information

MASTER PRODUCTION SCHEDULE (MPS)

MASTER PRODUCTION SCHEDULE (MPS) MASTER PRODUCTION SCHEDULE (MPS) Anticipated build schedule for manufacturing end products (or product options) A statement of production, not a statement of market demand MPS takes into account capacity

More information

A WIP Balance Study from Viewpoint of Tool Group in a Wafer Fab

A WIP Balance Study from Viewpoint of Tool Group in a Wafer Fab Integrationsaspekte der Simulation: Technik, Organisation und Personal Gert Zülch & Patricia Stock (Hrsg.) Karlsruhe, KIT Scientific Publishing 2010 A WIP Balance Study from Viewpoint of Tool Group in

More information

A Machine Setup Model for TFT-LCD Cell Back-End Process

A Machine Setup Model for TFT-LCD Cell Back-End Process A Machine Setup Model for TFT-LCD Cell Back-End Process Y.-C. Chang 1, P.-S. Chen 2, P.-C. Chen 1 1 Department of Industrial Engineering and Management, National Chiao Tung University, Hsinchu, Taiwan

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 23 Safety Stock Reduction Delayed Product Differentiation, Substitution

More information

CHAPTER 3.0 JUST-IN-TIME (JIT) MANUFACTURING SYSTEMS

CHAPTER 3.0 JUST-IN-TIME (JIT) MANUFACTURING SYSTEMS CHAPTER 3.0 JUST-IN-TIME (JIT) MANUFACTURING SYSTEMS 3.1 Abstract The Just-In-Time technique based manufacturing system, developed and implemented in the Toyota Motor Company may be defined as manufacturing

More information

Family-Based Scheduling Rules of a Sequence-Dependent Wafer Fabrication System

Family-Based Scheduling Rules of a Sequence-Dependent Wafer Fabrication System IEEE TRANSACTIONS ON SEMICONDUCTOR MANUFACTURING, VOL. 16, NO. 1, FEBRUARY 2003 15 Family-Based Scheduling Rules of a Sequence-Dependent Wafer Fabrication System Ching-Chin Chern and Yu-Lien Liu Abstract

More information

Inventory Management 101 Basic Principles SmartOps Corporation. All rights reserved Copyright 2005 TeknOkret Services. All Rights Reserved.

Inventory Management 101 Basic Principles SmartOps Corporation. All rights reserved Copyright 2005 TeknOkret Services. All Rights Reserved. Inventory Management 101 Basic Principles 1 Agenda Basic Concepts Simple Inventory Models Batch Size 2 Supply Chain Building Blocks SKU: Stocking keeping unit Stocking Point: Inventory storage Item A Loc

More information

RESOURCE-DRIVEN AND JOB-DRIVEN SIMULATIONS

RESOURCE-DRIVEN AND JOB-DRIVEN SIMULATIONS RESOURCE-DRIVEN AND JOB-DRIVEN SIMULATIONS Theresa M. Roeder*, Seth A. Fischbein, Mani Janakiram, and Lee W. Schruben* *Department of Industrial Engineering and Operations Research University of California,

More information

Lecture 12. Introductory Production Control

Lecture 12. Introductory Production Control Lecture 12 Introductory Production Control 167 Where we ve come from: Models of Manufacturing Systems: Deterministic, Queuing, Simulation Key ideas: Some WIP useful for buffering stations, but More WIP

More information

Operation and supply chain management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras

Operation and supply chain management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras Operation and supply chain management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras Lecture - 37 Transportation and Distribution Models In this lecture, we

More information

Particulars P Q (a) Production / Sales Quantity (units) 1,00,000 50,000. (b) Batch Size (units) 1, (c) No. of Batches (a b)

Particulars P Q (a) Production / Sales Quantity (units) 1,00,000 50,000. (b) Batch Size (units) 1, (c) No. of Batches (a b) FINAL CA NOV 2018 SUB: COSTING Topics: Simulation, CPM & PERT, Activity Based Costing, Budgetary Control, Life Cycle Costing, Standard Costing, Integral & Non- Integral Accounts. Test Code CF7 Branch (MULTIPLE)

More information

MIT 2.853/2.854 Introduction to Manufacturing Systems. Multi-Stage Control and Scheduling. Lecturer: Stanley B. Gershwin

MIT 2.853/2.854 Introduction to Manufacturing Systems. Multi-Stage Control and Scheduling. Lecturer: Stanley B. Gershwin MIT 2.853/2.854 Introduction to Manufacturing Systems Multi-Stage Control and Scheduling Lecturer: Stanley B. Gershwin Copyright c 2002-2016 Stanley B. Gershwin. Definitions Events may be controllable

More information

JUST IN TIME. Manuel Rincón, M.Sc. October 22nd, 2004

JUST IN TIME. Manuel Rincón, M.Sc. October 22nd, 2004 JUST IN TIME Manuel Rincón, M.Sc. October 22nd, 2004 Lecture Outline 1. Just-in-Time Philosophy 2. Suppliers Goals of JIT Partnerships Concerns of Suppliers 3. JIT Layout Distance Reduction Increased Flexibility

More information

Analyzing Controllable Factors Influencing Cycle Time Distribution in. Semiconductor Industries. Tanushree Salvi

Analyzing Controllable Factors Influencing Cycle Time Distribution in. Semiconductor Industries. Tanushree Salvi Analyzing Controllable Factors Influencing Cycle Time Distribution in Semiconductor Industries by Tanushree Salvi A Thesis Presented in Partial Fulfillment of the Requirements for the Degree Master of

More information

OM (Fall 2016) Outline

OM (Fall 2016) Outline Lean Operations Outline Global Company Profile: Toyota Motor Corporation Lean Operations Lean and Just-in-Time Lean and the Toyota Production System Lean Organizations Lean in Services 2 Toyota Motor Corporation

More information

Simulation and Queing Theory

Simulation and Queing Theory Simulation and Queing Theory BUS 735: Business Decision Making and Research Goals and Agenda Learning Objective Active Learning Activity Learn how to simulate probability distribution Example problem in

More information

Examination. Telephone: Please make your calculations on Graph paper. Max points: 100

Examination. Telephone: Please make your calculations on Graph paper. Max points: 100 KPP227 TEN1 Production and Logistics Planning Examination Course: Production and Logistics Planning Date: 2014-01-14 Number of hours: 5 hours Group: Freestanding course Course code: KPP227 Examination

More information

Optimizing Reverse Logistics with SAP

Optimizing Reverse Logistics with SAP Srivathsan Narayanan Optimizing Reverse Logistics with SAP ERP Bonn Boston Contents Preface... 11 Introduction... 15 1 Reverse Logistics... 17 1.1 Definition of Reverse Logistics... 17 1.2 Business Processes

More information

A Hit-Rate Based Dispatching Rule For Semiconductor Manufacturing

A Hit-Rate Based Dispatching Rule For Semiconductor Manufacturing International Journal of Industrial Engineering, 15(1), 73-82, 2008. A Hit-Rate Based Dispatching Rule For Semiconductor Manufacturing Muh-Cherng Wu and Ting-Uao Hung Department of Industrial Engineering

More information

Ch 26 Just-In-Time and Lean Production. What is Lean Production? Structure of Lean Production System. Activities in Manufacturing.

Ch 26 Just-In-Time and Lean Production. What is Lean Production? Structure of Lean Production System. Activities in Manufacturing. Ch 26 Just-In-Time and Lean Production Sections: 1. Lean Production and Waste in Manufacturing 2. Just-in-time Production Systems 3. Autonomation 4. Worker Involvement What is Lean Production? Lean production

More information

IT 470a Six Sigma Chapter X

IT 470a Six Sigma Chapter X Chapter X Lean Enterprise IT 470a Six Sigma Chapter X Definitions Raw Materials component items purchased and received from suppliers WIP work in process, items that are in production on the factory floor

More information

ENGR 1181 Lab 2: Quality and Productivity Lab

ENGR 1181 Lab 2: Quality and Productivity Lab ENGR 1181 Lab 2: Quality and Productivity Lab - Preparation Material - Lab Procedure - Report Guidelines ENGR 1181 Lab 2: Quality and Productivity Lab Preparation Material Preparation Material ENGR 1181

More information

MFS605/EE605 Systems for Factory Information and Control

MFS605/EE605 Systems for Factory Information and Control MFS605/EE605 Systems for Factory Information and Control Fall 2004 Larry Holloway Dept. of Electrical Engineering and Center for Robotics and Manufacturing Systems 1 Collect info on name, major, MS/PhD,

More information

The Value of Strategically Sourced Sub-Assembly. Outsourced sub-assembly creates measurable savings and fulfillment flexibility.

The Value of Strategically Sourced Sub-Assembly. Outsourced sub-assembly creates measurable savings and fulfillment flexibility. The Value of Strategically Sourced Sub-Assembly. Outsourced sub-assembly creates measurable savings and fulfillment flexibility. Introduction Strategic Sourcing of Value-Added Assembly provides benefits

More information

PRODUCTION SCHEDULING PART-A

PRODUCTION SCHEDULING PART-A PRODUCTION SCHEDULING PART-A 1. List out any five priority sequencing rules. (Nov-2017) First come, first served (FCFS) Last come, first served (LCFS) Earliest due date (EDD) Shortest processing time (SPT)

More information

Infor CloudSuite Industrial Whatever It Takes - Advanced Planning & Scheduling for Today s Manufacturer

Infor CloudSuite Industrial Whatever It Takes - Advanced Planning & Scheduling for Today s Manufacturer Infor CloudSuite Industrial Whatever It Takes - Advanced Planning & Scheduling for Today s Manufacturer May 2017 CloudSuite Industrial Where Did APS Come From? APS grew out of the convergence of two movements.

More information

Code No: RR Set No. 1

Code No: RR Set No. 1 Code No: RR410301 Set No. 1 IV B.Tech I Semester Regular Examinations, November 2007 OPERATIONS RESEARCH ( Common to Mechanical Engineering, Mechatronics and Production Engineering) Time: 3 hours Max Marks:

More information

Manufacturing Systems Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Manufacturing Systems Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Manufacturing Systems Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 28 Basic elements of JIT, Kanban systems In this lecture we see some

More information

1. Inventory management

1. Inventory management 1. Inventory management 10.1 Introduction The importance of proper inventory management is evident when one considers that inventories have lead to the demise of many a business. The downfall of some companies

More information

Inventory/ Material Management

Inventory/ Material Management 11-1 Inventory Management HAPTER 7 Inventory/ Material Management Prepared by Şevkinaz Gümüşoğlu using different references about POM McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Proceedings of the 2012 Winter Simulation Conference C. Laroque, J. Himmelspach, R. Pasupathy, O. Rose, and A.M. Uhrmacher, eds

Proceedings of the 2012 Winter Simulation Conference C. Laroque, J. Himmelspach, R. Pasupathy, O. Rose, and A.M. Uhrmacher, eds Proceedings of the 0 Winter Simulation Conference C. Laroque, J. Himmelspach, R. Pasupathy, O. Rose, and A.M. Uhrmacher, eds OPTIMAL BATCH PROCESS ADMISSION CONTROL IN TANDEM QUEUEING SYSTEMS WITH QUEUE

More information

Lecture: Operations Management 1 (t.oma1-en), bodr

Lecture: Operations Management 1 (t.oma1-en), bodr Points: Grade: The duration of the exam is 90 minutes. Allowed resources are any printed documents, manuscripts and books (open book policy), and a pocket calculator. The use of a computer, tablet or smartphone

More information

MODULE 7: ORDER PROMISING. Module Overview

MODULE 7: ORDER PROMISING. Module Overview MODULE 7: ORDER PROMISING Module Overview A company must give customers accurate delivery information for sales orders and it must correctly estimate the receipt date of purchase and transfer orders. In

More information

"Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success " Presented by Larry Akre May 17, 2007

Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success  Presented by Larry Akre May 17, 2007 "Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success " Presented by Larry Akre May 17, 2007 LAKRE 2007 1 Lean Manufacturing What is Lean Manufacturing? A philosophy

More information

COMPUTER INTAGRATED MANUFACTURING

COMPUTER INTAGRATED MANUFACTURING COMPUTER INTAGRATED MANUFACTURING 1 2 Production System A collection of people, equipment, and procedures organized to accomplish the manufacturing operations of a company Two categories: Facilities the

More information

Connecting S&OP to the Shop Floor: Here s How!

Connecting S&OP to the Shop Floor: Here s How! Connecting S&OP to the Shop Floor: Here s How! J. E. Boyer Company, Inc. John E. Boyer, President Copyright 2004 by J. E. Boyer Company, Inc. No portion of this article may be reproduced in whole or in

More information

Ch 19 Flexible Manufacturing Systems

Ch 19 Flexible Manufacturing Systems Ch 19 Flexible Manufacturing Systems Sections: 1. What is a Flexible Manufacturing System? 2. FMS Components 3. FMS Applications and Benefits 4. FMS Planning and Implementation Issues 5. Quantitative Analysis

More information

Just-In-Time (JIT) Manufacturing. Overview

Just-In-Time (JIT) Manufacturing. Overview Just-In-Time (JIT) Manufacturing Overview The Just-in-Time (JIT) Manufacturing Philosophy Prerequisites for JIT Manufacturing Elements of JIT Manufacturing Benefits of JIT Manufacturing Success and JIT

More information

and Control approaches, key issues Professor Dr. Frank Herrmann Innovation and Competence Centre for

and Control approaches, key issues Professor Dr. Frank Herrmann Innovation and Competence Centre for Production Planning and Control State-of-the-art the art approaches, key issues Professor Dr. Frank Herrmann Innovation and Competence Centre for Production Logistics and Factory Planning (IPF) University

More information

Justifying Simulation. Why use simulation? Accurate Depiction of Reality. Insightful system evaluations

Justifying Simulation. Why use simulation? Accurate Depiction of Reality. Insightful system evaluations Why use simulation? Accurate Depiction of Reality Anyone can perform a simple analysis manually. However, as the complexity of the analysis increases, so does the need to employ computer-based tools. While

More information

How much money can you add to the bottom line with good inventory management?

How much money can you add to the bottom line with good inventory management? Inventory Management Key Concepts: Inventory are those stocks or items used to support production (raw materials and work-in-process items), supporting activities (maintenance, repair, and operating supplies),

More information

9.7 Summary. 9.8 Training Cases. 394 Business Process Modeling, Simulation and Design

9.7 Summary. 9.8 Training Cases. 394 Business Process Modeling, Simulation and Design 394 Business Process Modeling, Simulation and Design experience more than 14 min of cycle time under the new design, which more than satisfies the goal of at most 30 min. Furthermore, no type 3 patient

More information

Chapter 11. Decision Making and Relevant Information Linear Programming as a Decision Facilitating Tool

Chapter 11. Decision Making and Relevant Information Linear Programming as a Decision Facilitating Tool Chapter 11 Decision Making and Relevant Information Linear Programming as a Decision Facilitating Tool 1 Introduction This chapter explores cost accounting for decision facilitating purposes It focuses

More information

Finished goods available to meet Takt time when variations in customer demand exist.

Finished goods available to meet Takt time when variations in customer demand exist. Delaware Valley Industrial Resource Center 2905 Southampton Road Philadelphia, PA 19154 Tel: (215) 464-8550 Fax: (215) 464-8570 www.dvirc.org Term Batch-and-Queue Processing Buffer Stock Catchball Cell

More information

Mixed Integer Programming Approaches to Planning and Scheduling in Electronics Supply Chains. Tadeusz Sawik

Mixed Integer Programming Approaches to Planning and Scheduling in Electronics Supply Chains. Tadeusz Sawik Decision Making in Manufacturing and Services Vol. 11 2017 No. 1 2 pp. 5 17 Mixed Integer Programming Approaches to Planning and Scheduling in Electronics Supply Chains Tadeusz Sawik Abstract. This paper

More information

Inventory Segmentation and Production Planning for Chemical Manufacturing

Inventory Segmentation and Production Planning for Chemical Manufacturing Inventory Segmentation and Production Planning for Chemical Manufacturing Introduction: In today s competitive marketplace, manufacturers are compelled to offer a wide range of products to satisfy customers,

More information

Lean Operations. PowerPoint slides by Jeff Heyl. Copyright 2017 Pearson Education, Inc.

Lean Operations. PowerPoint slides by Jeff Heyl. Copyright 2017 Pearson Education, Inc. Lean Operations 16 PowerPoint presentation to accompany Heizer, Render, Munson Operations Management, Twelfth Edition Principles of Operations Management, Tenth Edition PowerPoint slides by Jeff Heyl 16-1

More information

Inventory Control. Inventory. Inventories in a manufacturing plant. Why inventory? Reasons for holding Raw Materials. Reasons for holding WIP

Inventory Control. Inventory. Inventories in a manufacturing plant. Why inventory? Reasons for holding Raw Materials. Reasons for holding WIP Inventory Control Inventory the oldest result of the scientific management efforts inventory plays a key role in the logistical behavior of virtually all manufacturing systems the classical inventory results

More information

OPTIMIZING DEMAND FULFILLMENT FROM TEST BINS. Brittany M. Bogle Scott J. Mason

OPTIMIZING DEMAND FULFILLMENT FROM TEST BINS. Brittany M. Bogle Scott J. Mason Proceedings of the 2009 Winter Simulation Conference M. D. Rossetti, R. R. Hill, B. Johansson, A. Dunkin and R. G. Ingalls, eds. OPTIMIZING DEMAND FULFILLMENT FROM TEST BINS Brittany M. Bogle Scott J.

More information

Manufacturing Resource Planning

Manufacturing Resource Planning Outline Manufacturing Resource Planning MRP The Strategic Importance of Short- Term Scheduling Scheduling Issues Forward and Backward Scheduling Scheduling Criteria Outline Continued Scheduling Process-Focused

More information

Factory Physics Analytics with applications to Project Production

Factory Physics Analytics with applications to Project Production Factory Physics Analytics with applications to Project Production FACTORY PHYSICS is a registered trademark of Factory Physics Inc. All rights reserved. Why Factory Physics Analytics? Projects are like

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 20 Disaggregation Time Varying Demand, Safety Stock ROL for

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Module - 01 Lecture - 08 Aggregate Planning, Quadratic Model, Demand and

More information

Just In Time (JIT) Quality and Reliability Engg. (171906) H I T. Hit suyo na mono O Iru toki iru dake Tasukuran

Just In Time (JIT) Quality and Reliability Engg. (171906) H I T. Hit suyo na mono O Iru toki iru dake Tasukuran Just In Time (JIT) H I T Hit suyo na mono O Iru toki iru dake Tasukuran (What is needed) (When it is needed and in what quantity) (Make) The crux is, if you cannot use it now do not make it now. Quality

More information

Cork Regional Technical College

Cork Regional Technical College Cork Regional Technical College Bachelor of Engineering in Chemical and Process Engineering - Stage 4 Summer 1996 CE 4.8 - DECISION ANALYSIS AND OPERATIONS RESEARCH (Time: 3 Hours) Answer FOUR Questions.

More information

Ⅰ. Market Introduction _ Wafer Demand by Devices Type and Used Equipment Targets

Ⅰ. Market Introduction _ Wafer Demand by Devices Type and Used Equipment Targets Forecast of Used Equipment Market Based on Demand & Supply 03. 19.2013 Ⅰ. Market Introduction _ Wafer Demand by Devices Type and Used Equipment Targets 300 mm 20 nm to 0.13 μm Computing Microprocessors

More information

Cover-Time Planning, An alternative to Material Requirements Planning; with customer order production abilities and restricted Work-In-Process *

Cover-Time Planning, An alternative to Material Requirements Planning; with customer order production abilities and restricted Work-In-Process * International Conference on Industrial Engineering and Systems Management IESM 2007 May 30 - June 2, 2007 BEIJING - CHINA Cover-Time Planning, An alternative to Material Requirements Planning; with customer

More information

2012 MPS Qualify Exam

2012 MPS Qualify Exam 2012 MPS Qualify Exam The examination will be four hours long. There will be eight questions in all. Students must select 7 out of 8 questions to answer. The exam is open book and open notes. The students

More information

Justifying Advanced Finite Capacity Planning and Scheduling

Justifying Advanced Finite Capacity Planning and Scheduling Justifying Advanced Finite Capacity Planning and Scheduling Charles J. Murgiano, CPIM WATERLOO MANUFACTURING SOFTWARE 1. Introduction How well your manufacturing company manages production on the shop

More information

Multi-Stage Control and Scheduling

Multi-Stage Control and Scheduling SMA 6304 M2 Factory Planning and Scheduling Multi-Stage Control and Scheduling Stanley B. Gershwin November 15 and 20, 2001 Copyright c 2000 Stanley B. Gershwin. All rights reserved. Definitions Events

More information

Modern Logistics & Supply Chain Management

Modern Logistics & Supply Chain Management Modern Logistics & Supply Chain Management As gold which he cannot spend will make no man rich, so knowledge which he cannot apply will make no man wise. Samuel Johnson: The Idler No. 84 Inventory Systems

More information

This is a refereed journal and all articles are professionally screened and reviewed

This is a refereed journal and all articles are professionally screened and reviewed Advances in Environmental Biology, 6(4): 1400-1411, 2012 ISSN 1995-0756 1400 This is a refereed journal and all articles are professionally screened and reviewed ORIGINAL ARTICLE Joint Production and Economic

More information

Change in Overhead Cost Change in Production Units

Change in Overhead Cost Change in Production Units Test Series: October, 2018 MOCK TEST PAPER 2 FINAL (OLD) COURSE: GROUP II PAPER 5: ADVANCED MANAGEMENT ACCOUNTING SUGGESTED ANSWERS/HINTS 1. (a) (*) P Q R I. Contribution per unit 4 3 5 II. Units (Lower

More information

Profit Center Planning & Analysis

Profit Center Planning & Analysis Profit Center Planning & Analysis Theory of constraints, maximizing profitability, and capacity utilization Hierarchy of Resource Consumption Unit-level resources resources consumed on activities proportionally

More information

Tri-Star Manufacturing:

Tri-Star Manufacturing: Tri-Star Manufacturing: A Case Study in Lean Implementation The discussion taking place around the large walnut conference table at Tri-Star s headquarters was heating up to boiling point. In fact, Mark

More information

Operations Management

Operations Management Operations Management Chapter 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer/Render Operations Management, 11ed Some additions and deletions have been made by Ömer Yağız to this

More information

A Case Study of Capacitated Scheduling

A Case Study of Capacitated Scheduling A Case Study of Capacitated Scheduling Rosana Beatriz Baptista Haddad rosana.haddad@cenpra.gov.br; Marcius Fabius Henriques de Carvalho marcius.carvalho@cenpra.gov.br Department of Production Management

More information

Subbu Ramakrishnan. Manufacturing Finance with SAP. ERP Financials. Bonn Boston

Subbu Ramakrishnan. Manufacturing Finance with SAP. ERP Financials. Bonn Boston Subbu Ramakrishnan Manufacturing Finance with SAP ERP Financials Bonn Boston Contents at a Glance 1 Overview of Manufacturing Scenarios Supported by SAP... 25 2 Overview of Finance Activities in a Make-to-Stock

More information

Introduction to Computer Integrated Manufacturing Environment

Introduction to Computer Integrated Manufacturing Environment Introduction to Computer Integrated Manufacturing Environment I. What are the problems facing manufacturing industries today? External pressures: *Technological advancements *Increased cost, quality, and

More information

(4 Marks) (b) Enumerate the industrial applications of linear programming.

(4 Marks) (b) Enumerate the industrial applications of linear programming. 47 PAPER 5 : COST ACCOUNTING & COST SYSTEMS MAY 2003 Question No.1 is compulsory Answer any four questions from the rest. Working notes should form part of the answer. Make assumptions wherever necessary

More information

Supply Chain Design and Alignment

Supply Chain Design and Alignment Supply Chain Design and Alignment A supply chain let s a company move product from its source to its final consumption. Companies now use their supply chain as a competitive weapon to compete. The activities,

More information

DRIVING SEMICONDUCTOR MANUFACTURING BUSINESS PERFORMANCE THROUGH ANALYTICS

DRIVING SEMICONDUCTOR MANUFACTURING BUSINESS PERFORMANCE THROUGH ANALYTICS www.wipro.com DRIVING SEMICONDUCTOR MANUFACTURING BUSINESS PERFORMANCE THROUGH ANALYTICS Manoj Ramanujam Table of Contents 03... Introduction 03... Semiconductor Industry Overview 05... Data Sources and

More information