1 NLC - The Next Linear Collider Project NLC Project Costing Workshop: WBS 1.2 Overview; Sources, Linacs, and BC2s: J. C. Sheppard Damping Ring : M. C. Ross

2 Bottom Line Next Linear Collider What s Been Costed Philosophy and Methodology (Strategy and Tactics) Validation and What s Next Engineering and Administration Damping Rings

3 Bottom Line 1st Cut CD 0.4 Cost is $552M Lehman Cost was $794M Next Linear Collider 1st Cut has several data and arithmetic errors in the RF costs. Anticipate further reductions in cost by $25-$30M or so. Concerns: Errors which bring up costs Missing work (rf R&D, for instance) Cost Validation

4

5

6 What Are the Costs? (by WBS Level 3, M&S and Labor) Area M&S Labor Cost CD 04 Cost (M$) (M$) (M$) Sys. Eng Sources Damping Rings Prelinacs/BC2s Grand Total

7 Where do Savings Come From? (by WBS Level 3) Area CD 04 LEHMAN DIFFERENCE (M$) (M$) (M$) Sys. Eng Sources Damping Rings Prelinacs/BC2s Grand Total

8 Where do Savings Come From? SYSTEM CD 04 LEHMAN DIFFERENCE (M$) (M$) (M$) Magnets RF Sys. Eng Install Vacuum Instruments Sources Grand Total

9 Philosophy and Methodology: Strategy has developed the layout, the technical specifications, and the inventories in conjunction with Accelerator Physics have asked the Engineering Groups for the estimates, parsed by the CD04 categories has developed the costs for Engineering and Administration is responsible for concatenation of the numbers

10 Philosophy and Methodology: Tactics Made Inventory sheets, based on decks and sketches Distributed to Engineering Teams Collected unit costs Multiplied and Added Sorted into WBS template and submitted information to NLC PMCS folks

11 Validation: Largely not done Next Linear Collider Check Inventory: whats in, what s not (cables, racks) Check Entries (counts) Check Arithmetic, Algorithms Check Binning (CD, R&D, Design, Acquisition, Sustaining Engineering, IIT) Hold Engineering Cost Reviews Attend Engineering Cost Reviews

12 What s Next? Next Linear Collider Identify and Plug Holes (aka missing pieces: rf R&D, for example) Identify Cost Drivers and Do More Work Scrutinize Cost Estimate: Why does something costs what it costs? Easy on acquisition; not so easy on design, sustaining engineering, installation Need to develop project schedule; this impacts validity of our ability to actually get the work done Need to understand disparity between DR M&S$ and DR Labor$ in comparison to Sources and Prelinacs M&S/Labor $; in comparison to Project M&S/Labor $

13 Engineering and Administration WBS Element Labor Hrs Labor $ M&S $ Total $ (hours) (k$) (k$) (k$) $44M is 8.7% of Costs Depending on Schedule, a significant portion of this can be moved naturally to Pre-Operations Engineering and Administration is in addition to but not in substitution of Sustaining Engineering which seems to be largely missing in the Sources and Prelinacs Areas but well accounted for in the Damping Ring Area, maybe excessively so. There is certainly a disconnect within the with regards to Sustaining Engineering

14 WBS NLC Engineering and Administration

15 WBS : NLC Engineering and Administration