DESIGN AUTHORITY ADVICE NOTE

Size: px
Start display at page:

Download "DESIGN AUTHORITY ADVICE NOTE"

Transcription

1 DESIGN AUTHORITY ADVICE NOTE Title: Implications for Sizewell B from the Flamanville 3 Reactor Pressure Vessel Manufacturing Issues EAN No: Revision: 000 Author: Author s Organisation/Section/ Group: EDF Energy / Design Authority / Sizewell B Safety Case QA Grade: Task File Number: 2 E/TSK/SZB/13567 Attachments: None Station: Sizewell B Date: April 2016 Verifier(s): Verifier s Organisation/Section/Group: EDF Energy / Design Authority / Sizewell B Safety Case Verification Statement: This EAN has been verified by appropriate EDF Energy SQEPs in accordance with BEG/SPEC/DAO/010. I am satisfied that the conclusions are reasonable and are supported by the evidence presented. Approver: Section/Group: Design Authority / Sizewell B Safety Case Head Tech. Reviewer(s): N/A SQEP status/evidence of competence of the reviewer(s): N/A Commissioning of Technical Review Commissioned by: N/A 2016 Published in the United Kingdom by EDF Energy Nuclear Generation Ltd. All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means, including photocopying and recording, without the written permission of the copyright holder, EDF Energy Nuclear Generation Ltd., application for which should be addressed to the publisher. Such written permission must also be obtained before any part of this publication is stored in a retrieval system of any nature. Requests for copies of this document should be referred to Barnwood Document Centre, Location 12, EDF Energy Nuclear Generation Ltd, Barnett Way, Barnwood, Gloucester GL4 3RS (Tel: ). The electronic copy is the current issue and printing renders this document uncontrolled. Controlled copy-holders will continue to receive updates as usual. LIMITATION OF LIABILITY Whilst EDF Energy Nuclear Generation Ltd believes that the information given in this document is correct at the date of publication it does not guarantee that this is so, nor that the information is suitable for any particular purpose. Users must therefore satisfy themselves as to the suitability of the information for the purpose for which they require it and must make all checks they deem necessary to verify the accuracy thereof. EDF Energy Nuclear Generation Ltd shall not be liable for any loss or damage (except for death or personal injury caused by negligence) arising from any use to which the information is put.

2 Page 2 of 12 Outline of, or reference to, the nuclear safety related application in which the work is to be used: N/A Technical review outcome N/A Details of aspects of the work reviewed: N/A 1 INTRODUCTION Flamanville 3 (FA3) is a Pressurised Water Reactor of EPR design currently under construction in France. Much of the plant has been completed and the large forgings have been installed. As part of the technical qualification of the manufacturing operations on the FA3 Reactor Pressure Vessel (RPV) domes, mechanical tests were performed on samples intended to be representative of the dome material. Such tests have not previously been standard practice because the nuclear pressure equipment order (known as ESPN) which required this evidence had only come into force in It became public in April 2015 that these tests had found variations in the mechanical properties and that subsequent investigation had identified variations in carbon content of the FA3 RPV upper and lower domes. This meant that some regions of the tested domes did not meet the manufacturing specification requirements. Areva, the company responsible for the FA3 dome manufacture, are currently assessing the full implications for the FA3 safety case. Given that the upper and lower domes for Sizewell B (SZB) and FA3 were both manufactured at the same site in Le Creusot, France, the Office for Nuclear Regulation (ONR) have asked if there is any risk that Sizewell B could have suffered a similar problem. A brief was provided to ONR in April 2015 (see Appendix A) which gave an initial view that there was no evidence for such an anomaly also existing at Sizewell B. Further work was identified as necessary to support this judgement. As part of this further work EDF Energy Materials group have reviewed the manufacturing processes [1] and Structural Analysis Group have performed sensitivity analysis on the RPV fracture analysis [6]. The remaining input has been provided by Design Authority and is summarised in this EAN. This Advice Note brings together all the work done in order to provide an overall judgement on the significance of the FA3 event to the Sizewell B RPV structural integrity. 2 SIGNIFICANCE TO SIZEWELL B The EDF Energy assessment of this event indicates that there is not a significant threat to the integrity of the Sizewell B RPV domes and that the Sizewell B safety case continues to be robust. Because of the low risk this event poses to Sizewell B it is not considered ALARP to perform any further analysis. There are a number of factors that give confidence in this position; Design & Specification The Sizewell B vessel domes were designed to have robust material properties. This included a low carbon content specification of 0.20% or less. Manufacturing Process There is confidence that Sizewell B would not have suffered from significant positive carbon segregation because Sizewell B used a much smaller ingot (approx 60 tonnes compared to 160 tonnes) and used a different ingot production process to the FA3 EPR process. The techniques used to produce the Sizewell B ingots have been proven to have suitably uniform solidification and acceptable positive segregation of carbon. In addition, material taken from the edge of the Sizewell B forging (the test ring) was tested and shown to have acceptable properties. Operational Experience There have been a large number of RPV domes produced which are similar to the Sizewell B dome, including many at the same forge using the same techniques. There have not been any recorded failures of such domes or any issues with carbon segregation despite a large number of reactor operating years having now been accumulated.

3 Page 3 of 12 Margins in the Fracture Analysis Even if there was some reduction in fracture toughness for the Sizewell B RPV domes, there are large safety margins in the Sizewell B fracture analysis so the demonstration of integrity safety case would not be undermined. Analysis has indicated that there would not be a cliff edge effect associated with reduced fracture toughness. The size of a crack which could be reasonably expected to occur would still be small compared to a crack which could lead to RPV failure. Consequences for the RPV Integrity The most likely locations of reduced fracture toughness are on the outer surface of the domes which are of less concern. Even if crack growth were to be worse than expected, it would most likely propagate to the nearest stress reliever, namely, the penetrations, rather than through wall. 2.1 Design & Specification The Sizewell B safety case for the Reactor Pressure Vessel includes a discussion regarding how the integrity was achieved such that the possibility of disruptive failure of the RPV shell without forewarning is sufficiently remote as to be deemed incredible [7]. Claimed as integral to this approach are a robust design and appropriate materials specification. The Sizewell B RPV was constructed in accordance with an established code of practice, the American Society of Mechanical Engineers (ASME) Code Section III (as adapted for UK use). The ASME Section II low alloy steel specification of SA-508 Class 3 was chosen in order to achieve robust mechanical properties. Sizewell B then specified an enhancement by reducing the maximum carbon content to 0.20% (Section 3.1 of Reference [1]). This was less than the carbon content of 0.22% specified for the FA3 forgings (Section 2.2 of [1]). Ensuring a low carbon content allows less opportunity for carbon to concentrate although it is recognised that the EPR forging has seen levels of carbon segregation of 0.30% despite a specification of 0.22%. The processes used at Sizewell B to prevent these levels of positive segregation are addressed in Section Manufacturing Process EDF Energy Materials Group have examined the manufacturing processes for both the Sizewell B and Flamanville 3 domes [1]. This included review of the Sizewell B manufacturing specifications and records. This review concluded that there is no clear evidence for a similar anomaly existing in the Sizewell B RPV domes as that found during the technical qualification for FA3. The primary evidence given to support this statement is that the different ingot production method used for Sizewell B is proven to have a lower propensity for developing areas of positive carbon segregation (Section 3.2 of Reference [1]). Supplementary to this is that SZB used much smaller ingots (approx 60 tonnes compared to 160 tonnes for FA3 domes) (Section 3.2 of Reference [1]). The smaller SZB ingots would have taken less time to solidify which would have made them less susceptible to carbon segregation and would have facilitated controls on segregation (Section 4 of Reference [1]). The ingot production method used for the Sizewell B ingot is a bottom pouring technique known by its French abbreviation LSD (Section 3.1 of Reference [1]). Such a technique was not considered possible for the very large EPR forgings and hence they utilised a conventional top pouring ingot technique. Figure 1 illustrates what is meant by top and bottom pouring. The LSD technique was developed with reducing positive carbon segregation as a specific consideration (Section 3.2 of Reference [1]). The exact mechanisms by which the LSD process reduces areas of positive segregation are complex but in general it results in a more even solidification which reduces the opportunity for carbon to concentrate in particular areas [1]. Special features of the LSD process include the fact that it involves bottom pouring of the ingot and also a thick iron plate at the base of the ingot mould to take away heat [1]. For the LSD process there are requirements to achieve a specific low height to diameter ratio to assist in the even solidification. The cooling process

4 Page 4 of 12 for the LSD ingot is illustrated in Figure 7 of reference [1]. In addition to the techniques which prevent positive segregation, the research conducted has confirmed that material is discarded from the ingot in areas where positive carbon segregation is most likely to occur (Section 3.1 of Reference [1]). The LSD ingots were subject to forging operations to allow discarding to be carried out on a specific region of the ingot. This facilitated a smaller discard region and hence smaller ingot compared to the process used for the FA3 domes although the intent to discard the region of highest segregation is the same in both processes. The LSD process is discussed in more detail in Section 3.2 of Reference [1], it is clear that the theory behind this technique suggests it is much less likely to result in positive segregation than the conventional ingot production technique used for the EPR domes. In addition to the theoretical analysis, there is also strong practical evidence that the LSD process does not result in significant positive segregation. In order to demonstrate the effectiveness of the process, Le Creusot produced a test LSD forging which went through destructive testing. The results of this testing were presented in a 1985 paper to the 10 th International Forging Conference [2] which has been reviewed by EDF Energy in Section 3.2 of Reference [1]. The mechanical properties and chemical composition of the test dome forging were measured across a range of locations of the dome. This included the locations in the centre of the dome which were found to have positive segregation in the EPR forging. It was confirmed that there was an absence of significant positive segregation and that a forging manufactured through the LSD route would demonstrate a greater consistency in mechanical properties [1]. Importantly it also confirmed the test ring (excess material taken from the edge of every dome in order to test the properties of the dome) will provide adequate indication of material properties across a dome forging if it is produced using the same manufacturing route. Sizewell B test ring results have been reviewed [1] and confirmed to be within specification for carbon content, hence it can be inferred that the properties across the dome are also highly likely to be acceptable. The LSD prototype is considered to have been manufactured from an equivalent steel to the Sizewell B domes ensuring the results of the prototype testing are applicable to Sizewell [1]. In summary, there is a high degree of confidence that the Sizewell B domes would have avoided significant positive segregation as found in the EPR forgings. 2.3 Operational Experience There are a large number of reactor operating years which have now been accumulated by PWRs using domes similar to that at Sizewell B, with 30 LSD domes produced at the time of the 1985 assessment [2] and further domes produced since then. In addition there is a vast amount of experience with domes made with other techniques and with other large forgings at nuclear plants. Operational Experience (OPEX) searches have been conducted with major industry bodies (recorded in the task file) and it is reassuring that no failures or cracking attributed to carbon segregation have been found. In fact no failures of the dome base material have been discovered in the searches performed. Failures have occurred in the material used at some power stations for penetrations through the domes but that is not part of the forging (the risk of such failure is considered relatively low for Sizewell B [9]). Because of the dissimilar metal welds, OPEX suggests that failure of the penetrations is much more likely and the dome parent material is relatively very low risk. It may be considered that defects could have been attributed to other mechanisms incorrectly, however there are few significant defects recorded by any mechanism. From OPEX searches, no defects were found to be associated with dome parent material so a search was done more widely, looking at cracking in other major forgings. The only real incident of note has been the large number of defects found in Doel 3 and Tihange 2 Reactor Pressure Vessels in Belgium. The analysis of this event has suggested this was caused by hydrogen flaking, the risk of which has already been judged as insignificant for Sizewell B [3]. The lack of significant defects being discovered worldwide gives a great deal of confidence given the huge number of non-destructive examinations which have been done on Reactor Pressure Vessels worldwide. Most plants will follow a 10 yearly inspection interval similar to that at Sizewell B. If

5 Page 5 of 12 carbon segregation had lead to significant reduction in fracture toughness some cracking is likely to have been revealed. Hence it can be inferred that significant carbon segregation remains rare. Research in the area of positive carbon segregation in reactor pressure vessels and other large forgings has previously been carried out. Such research has recognised that there will be a tendency towards areas of positive segregation [8]. Thus, efforts have gone into minimising this positive segregation such as using the LSD approach or discarding large areas, as done for the EPR domes. Thus the remaining question is whether there is any research to indicate if significant carbon segregation is common in large nuclear forgings even with measures in place to reduce it. Unfortunately, given the large capital cost such components are rarely destructively tested. In any case no other destructive testing could be more relevant to Sizewell B than the destructive testing of the prototype LSD forging (section 2.2) given it went through the same production process and was made from an equivalent steel. Previously, carbon segregation has not been seen as high risk compared to other factors which may affect fracture toughness (e.g. irradiation embrittlement). Extensive research has been done by the Materials Ageing Institute on material ageing in Light Water Reactors and carbon segregation does not feature in their main publication [4]. It may be that carbon segregation becomes higher priority and further research is done in this area in light of the Flamanville issue. In this case EDF Energy will be aware as part of normal business OPEX reviews and involvement with industry bodies. 2.4 Margins in the Fracture Analysis The demonstration of integrity for the Reactor Pressure Vessel [5] includes assessment of defect sizes which could cause the RPV to fail against sizes of defects that could credibly occur in the vessel. The margin between these two defect sizes is known as the Validation Factor and a value approaching 2 (or greater) is targeted in order to give confidence in the integrity. Structural Analysis Group have revisited this assessment [6] to ensure that there are no cliff edge effects associated with a reduced fracture toughness in the RPV domes which could occur if there was carbon segregation such as that seen at FA3. The Structural Analysis Group sensitivity calculations (Section 3 of Reference [6]) have applied factors of 0.8 and 0.7 to the original assessments to emulate the effects of different amounts of fracture toughness reduction. These values are considered reasonably conservative in light of the carbon measurements for the EPR domes. Acceptable validation factors (>2) are obtained even with a factor of 0.7 on the generic lower bound toughness. The sensitivity analysis demonstrates that if more realistic data is used for these locations then much larger margins would be expected. This would more than off-set a postulated reduction in fracture toughness. The Structural Analysis assessment [6] concludes that the Sizewell B integrity case for the upper and lower heads is not challenged by the findings related to the Flamanville 3 RPV head forgings. Even in the unlikely situation that the fracture toughness values used in the safety case are reduced in some areas there remains significant safety margin. The work performed by Structural Analysis Group indicates that there are no cliff edge effects associated with a hypothetical reduced fracture toughness (Section 5 of Reference [6]). 2.5 Consequences for the RPV Integrity For Sizewell B, the concave region/bottom of LSD forgings were used as the inside surface for the RPV [1]. This was to provide further assurance that should any positive segregation remain, it would be located on the outer surface rather than the inner surface of the RPV. Even if crack growth were to be worse than expected, it would most likely propagate to the nearest stress reliever, namely, the penetrations, rather than through wall. Hence, even in the very unlikely situation that there is reduced fracture toughness and a crack does occur, the location of the reduced toughness would limit the consequences compared to other locations of the RPV. The irradiation of the RPV domes is relatively low compared to other parts of the RPV, hence, even if it were to have some reduced fracture toughness it is still not likely to be the region most at risk of

6 Page 6 of 12 failure, the effects of irradiation and temperature in the core shell region over the reactor lifetime are still likely to be bounding. It is also noted that the Boric Acid corrosion programme involves regular walk downs to check for any leaks from the RPV. This would be expected to detect a leak from the upper or lower domes. There are also visual inspections performed in line with ASME requirements. These inspections are designed to detect any cracks which may be visible on the surface. The next visual inspection of the upper dome is scheduled for RO ALARP Review of the Safety Case With the evidence presented it is considered that there is very low risk of the Sizewell B domes having experienced significant positive carbon segregation. An advanced manufacturing process was used and OPEX does not suggest such positive segregation is common. Even if segregation has occurred it is unlikely to significantly change the risk to the RPV integrity. The dome is still unlikely to fail as there is significant margin in the fracture analysis and the affected regions are bounded by other higher risk regions of the RPV. Even in the very unlikely situation of a crack developing, a crack in the outer surface of the dome presents relatively low consequences. The Sizewell B achievement of integrity safety case [7] claims there is low risk of RPV failure due to high quality manufacturing processes. The review of the manufacturing processes supports this claim [1] and more specifically, it has been shown that reasonably practicable measures were used to reduce positive segregation. The safety case also demonstrates the integrity of the RPV domes via fracture analysis [5]. It has been shown that this analysis would not be undermined by a reduction in fracture toughness similar to that found for the EPR domes [6]. Hence, the current safety case is considered to remain adequate for demonstrating that the risk at Sizewell B is ALARP. Further work has been considered, such as destructive testing of the old Sizewell B vessel head removed in RFO7. However, given that the current position is considered low risk, further work would provide minimal risk benefit and resources would be better committed elsewhere. This position is subject to Sizewell B Structural Integrity Panel (SIP) agreement and this EAN will be circulated to the SIP members upon completion. 3 CONCLUSION This Advice Note claims that there is no challenge to the Sizewell B Reactor Pressure Vessel domes integrity from the findings of positive carbon segregation during the qualification of the Flamanville 3 EPR domes. Given that there is no challenge to the Sizewell B dome integrity, the safety case remains an adequate justification that the risks for Sizewell B are ALARP. Given that the risks are ALARP, no further work is considered necessary. 4 REFERENCES 1. E/EAN/BBHB/0373/SZB/16; Review of Sizewell B RPV Dome Forging Components Following Flamanville 3 EPR OPEX; ; March 2016; 2. Application of Directional Solidification Ingot (LSD) in Forging of PWR Reactor Vessel Heads; and 10th International Forging Conference, Sheffield (UK); September EC ; Review Of Doel-3 Issues And Relevance To Sizewell B Safety Case; ; November 2014; 4. Materials Ageing in Light Water Reactors; Materials Ageing Institute; ; SXB-IP ; IR 5.3(2) Demonstration of Reactor Pressure Vessel Integrity; April 2014; Issue E/EAN/BBJB/0379/SZB/16; Sizewell B Consideration of Reduced Toughness in the Upper and Lower Closure Heads; March 2016;

7 Page 7 of SXB-IP ; IR 5.3(1) Achievement of Reactor Pressure Vessel Integrity; October 2015; Issue UKAEA report AERE-R9581; Investigation of the homogeneity of chemical composition and mechanical properties in a large A508 class 3 steel pressure vessel forging; September E/EAN/BAEB/0016/SXB/05; Management of the Degradation due to Primary Water Stress Corrosion Cracking (PWSCC) of Alloy 600 Components and Alloy 82 and 182 Welds; ; March 2006, 5 FIGURES Figure 1: Pouring of metal through (a) top-pouring and (b) bottom-pouring processes; (1) ladle with metal, (2) mold, (3) stool, and (4) fountain 6 DISTRIBUTION LIST Barnwood - Design Authority Barnwood - Design Authority Barnwood - Design Authority Barnwood - Engineering Barnwood - Engineering Barnwood - Engineering Barnwood Independent Nuclear Assurance Sizewell B - Components & Programmes ED00037 ED00863 ED03047 EDWPB01 ED03075 EDCJG01 ED00348 BBBAJ24

8 Page 8 of 12 APPENDIX A APRIL 2015 BRIEF TO THE ONR Brief to ONR on the Implications to Sizewell B of EPR Reactor Pressure Vessel (RPV) Domes Reduced Material Properties Due to Carbon Segregation Prepared by Structural Integrity Lead Design Authority Summary The recent public statements regarding an anomaly in the material properties of the FA-3 RPV domes has prompted ONR to ask EDF Energy to consider the potential implications to Sizewell B, given the components were all made at Le Creusot forge. The ONR is aware of the variations in carbon and the potential effects on fracture toughness based on the destructive testing of an EPR (USA) RPV Head by AREVA. This brief is in response to that request and has been prepared by the Sizewell B Design Authority with support from Structural Integrity Branch. It represents an initial review of the manufacturing process coupled with indicative fracture assessment calculations to gauge potential implications to Sizewell B. Our conclusion from this initial review is that there is no clear evidence for such an anomaly being present at Sizewell B and the judgements presented provide assurance of RPV integrity. In the unlikely event these are incorrect; the initial fracture assessment for postulated defects provides additional reassurance. The brief also outlines further work required to back up the judgements. Assessments to Date Consideration has focused on two main areas. Firstly the manufacturing processes adopted for the making of the RPV domes at Sizewell B. This included the steel making process and material specification. Secondly, a fracture assessment in the affected areas, taking account of a potential reduction in fracture toughness values.

9 Page 9 of 12 Manufacturing Processes Both the original RPV Head domes 1 and the bottom RPV dome for Sizewell B were made around the same time using similar manufacturing techniques. The specification for the low alloy ferritic steel stipulated a maximum carbon content of 0.2%. It is noted that there is a difference in the ingot weight between FA-3 (approx 160 tonnes) and Sizewell B (approx 60 tonnes). Significantly, for Sizewell B domes a bottom pouring (ladle to ingot) process was adopted. This process had been designed to produce ingots with a more uniform solidification and to reduce macrosegregation. This potential benefit is being investigated further. An initial view of the forging process also suggests that positive segregation (a region of higher carbon content and associated inclusions) is removed during the process through discards taken from the top of the forging. This also requires confirmation. Testing of RPV domes prolongations gave consistent, acceptable values, which are compliant with both the design code (ASME) and the RPV equipment specification. No specific testing for carbon was done on the region of concern; however, product analysis (both head domes and lower dome) gave carbon values in the range %, all below the specified maximum carbon content. Fracture Assessments Structural Analysis Group has reviewed the fracture assessments for both RPV domes. The perforated regions of both domes is not considered in any detail in the safety case due to the lower stress levels in the region and the bounding approach adopted by the safety case. The review has determined that both Locations (19 upper dome & 20 lower dome) are bounded by Location 1. (see below diagram from SSR for locations). However Location 1 is a weld and the analyses therefore assumed the presence of a uniform 55MPa residual stress. Location 18 was not considered to bound the locations. Structural Analysis group has undertaken indicative calculations to establish potential effects of reduced fracture toughness. The original limiting (initiating) defect size for Location 1 is 57.7 mm for a 0.1 aspect ratio. The previous calculations have been reworked to take account of the absence of residual stresses and recent updates to the R6 Defect Assessment Procedure. This results in an increased defect size of 96 mm. A reduction of 20% in fracture toughness has then been applied reducing the limiting defect size back to 79.4 mm. This reduction is an estimate of a likely reduction in fracture toughness. Further sensitivities will be required. The value was chosen to get a feel for how sensitive it would be on safety margins. Crack growth for Location 1 has been determined as 2.8 mm over 40 years. This results in a validation factor of 79.4/27.8 = 2.85 (s-o-l crack is 25mm). This is for Condition I & II. Note this crack growth has not been factored and still represents the crack growth in a weld. 1 The original Sizewell B RPV head dome was replaced in 2007 by another, originally planned for Hinkley Point C. Both domes were made around the same time to the same specification at Le Creusot Forge.

10 Page 10 of 12 Further assessment of Conditions III & IV also gave acceptable validation factors taking credit for ductile tearing (1mm), where appropriate. The bounding fault for this region is considered the small LOCA on the basis the RPV is still at pressure. Other transients have not been considered at this stage. Initial Judgements The initial review suggests that there is no clear evidence for a similar anomaly existing in the Sizewell B RPV domes. The following judgements are given to provide assurance of RPV integrity whilst investigations continue. Judgement 1 Significant efforts were made during manufacture of Sizewell B s domes to limit the formation of positive macrosegregation. The different manufacturing processes used and the significantly lower ingot weight for Sizewell B than FA-3 provide evidence that the Sizewell B domes would be expected to have a lower propensity for carbon segregation The way the ingot is formed offers a more uniform solidification than a top-poured ingot. The forging process adopted and the location of discard indicates that areas of positive segregation will have been removed. All these aspects are supportive of reducing the likelihood that large-scale segregation would be present in the finished components, such as those observed on EPR (USA). Judgement 2 Margins of safety remain high for the RPV domes based on indicative calculations for a postulated defect in the regions of concern using a reduction in fracture toughness of 20%. This does not take credit for any potential increase in fracture toughness at the inner surface. The assessment covers both normal and fault conditions. Judgement 3 Any postulated crack will most likely occur on the inner surface, not the outer surface where reductions in fracture toughness have been discovered on the EPR (USA). It is judged that in all probability a crack in the perforated region will propagate to the nearest stress reliever, namely, the CRDM or BMI penetrations at the top and bottom of the domes. Hence, the calculations remain conservative for a postulated through wall orientated crack. These judgements will be further backed by future assessment work to be undertaken in the coming months. The confidence in these judgements is also based on the reliable operating experience of PWRs worldwide and older than Sizewell B. The collective measures taken during design, manufacture, construction and operation and embedded in the twin arms of the structural integrity safety case, namely the demonstration and achievement of integrity provide assurance that RPV integrity can be maintained. Further Work To support the above judgements and to be able to give a definitive answer to Sizewell B s position with respect to carbon segregation, a programme of work is proposed covering three main activities and potentially backed by a fourth work stream.

11 Page 11 of 12 Work Stream 1 Manufacturing Process Materials Group will undertake production of an Engineering Advice Note (EAN) similar to the one produced for the Doel 3 issue. This will involve a detailed understanding of the manufacturing process and comparisons with FA-3 processes. The scope of this work will include: -Compare steelmaking, to include: material specification, understanding the steelmaking route, ladle chemical analysis, sizes of ingots, the location and amount of material discard. -Compare forging processes, to include: understanding the forging route, review of forging ratios. -Compare heat treatment and machining operations, to include: times and temperatures used, component thickness at heat treatment stages, quenching process, extent of machining to achieve component dimensions. -Compare final properties, to include: final product chemical analysis, mechanical properties. Work Stream 2 Fracture Assessment Structural Analysis Group to undertake a detailed fracture assessment of the perforated region for normal and fault conditions and conduct sensitivity on fracture toughness values. A wider number of fault transients should be considered. Potential impact on safety margins to be reported. Work Stream 3 Opex Search Design Authority to conduct an Opex search to determine whether any other PWR operator has experienced failure attributed to carbon segregation. Also to engage research bodies to establish results from destructive testing results from other PWRs e.g. Materials Ageing Institute, EPRI. Work Stream 4 Test work The potential exists to conduct testing of the old Sizewell B RPV Head currently residing in the outage building. The Structural Integrity Panel will advise on the merits of testing taking account of ALARP considerations. It is understood from discussions with Health Physics and Materials Group that filings from drillings at different depths would give a clear indication of carbon content through the RPV Head dome wall thickness. This would give confidence that the extent of any segregation was well defined. Alternatively more comprehensive destructive testing of the RPV Head, including fracture toughness testing could be performed. The current position is that it not ALARP to do this test. However, this is only a preliminary view and this might change with more information forthcoming from AREVA.

12 Page 12 of 12 Programme Work requests will be added to respective work programme and prioritised as appropriate. Recognising the existing work programmes and the reporting of future test work by AREVA it is proposed to adopt the following programme for deliverables: Materials Group to deliver EAN by end of November 2015* Structural Analysis Group to deliver EAN by end of October 2015* Design Authority to deliver EAN by end of November 2015* * Dates to be agreed with respective groups. In the event any anomaly is identified during the work programme it will result in sentencing under normal business processes. This brief is prepared at QA Grade 3 with peer checks from Structural Analysis Group and Materials Group (Structural Integrity Branch)

ENGINEERING ADVICE NOTE

ENGINEERING ADVICE NOTE ENGINEERING ADVICE NOTE Title: Sizewell B. Consideration of Reduced Toughness in the Upper and Lower Closure Heads EAN No: Revision: 000 Author: QA Grade: Task File Number: 2 E/TSK/SZB/13395 Structural

More information

WENRA. Recommendation in. in French reactors.

WENRA. Recommendation in. in French reactors. WENRA Recommendation in connection with macrosegregation anomalies found in French reactors. 1 01 Background 01.1 The findings in France In late 2014, mechanical tests performed on a Reactor Pressure Vessel

More information

Office for Nuclear Regulation

Office for Nuclear Regulation Office for Nuclear Regulation Civil Nuclear Reactors Programme Doel 3 and Tihange 2 Reactor Pressure Vessel Inspection Findings and their implications for Sizewell B and Hinkley Point C Assessment Report:

More information

REPUBLIQUE FRANÇAISE. Having regard to the Environment Code, in particular its articles L to L and R ;

REPUBLIQUE FRANÇAISE. Having regard to the Environment Code, in particular its articles L to L and R ; REPUBLIQUE FRANÇAISE ASN opinion 2017-AV-0298 of 10 October 2017 concerning the anomaly in the composition of the steel used for the Flamanville NPP EPR reactor pressure vessel lower head and closure head

More information

Pressurized Water Reactor Materials Reliability Program (QA)

Pressurized Water Reactor Materials Reliability Program (QA) Pressurized Water Reactor Materials Reliability Program (QA) Program Description Program Overview Stress corrosion cracking and general environmental corrosion of reactor coolant system components have

More information

Summary report for the Advisory Committee of experts for nuclear pressure equipment. CODEP-DEP IRSN Report /

Summary report for the Advisory Committee of experts for nuclear pressure equipment. CODEP-DEP IRSN Report / Summary report for the Advisory Committee of experts for nuclear pressure equipment IRSN Report /2016-00005 English translation Session of 24 th June 2016 Procedure proposed by Areva to prove adequate

More information

The risk of reactor pressure vessel material degradation Doel-3/Tihange-2

The risk of reactor pressure vessel material degradation Doel-3/Tihange-2 The risk of reactor pressure vessel material degradation Doel-3/Tihange-2 Ilse Tweer NURIS 2015, Vienna, 16-17 April 2015 Reactor pressure vessel structural integrity The reactor pressure vessel (RPV)

More information

Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2

Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2 Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2 Progress report 2014 Contents 1. Introduction... 3 2. Historical overview... 3 3. Progress of the mid-term actions in 2014... 6

More information

UK ABWR Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity

UK ABWR Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity Form10/00 Document ID Document Number Revision Number : : : GA91-9101-0101-08000 RE-GD-2043 C Generic Design Assessment Generic PCSR Chapter 8 : Structural Integrity Hitachi-GE Nuclear Energy, Ltd. Form01/03

More information

RPV DESIGN. FABRICATION AND MATERIALS

RPV DESIGN. FABRICATION AND MATERIALS RPV DESIGN. FABRICATION AND MATERIALS Marta Serrano. CIEMAT IAEA Training Workshop on Assessment of Degradation Mechanisms of Primary Components in Water Cooled Nuclear Reactors: Current Issues and Future

More information

ALLOY 600 REACTOR VESSEL HEAD PENETRATION ISSUES. Dudenstrasse 44, Mannheim, Germany. Post Office Box 355 Pittsburgh, PA ABSTRACT

ALLOY 600 REACTOR VESSEL HEAD PENETRATION ISSUES. Dudenstrasse 44, Mannheim, Germany. Post Office Box 355 Pittsburgh, PA ABSTRACT ALLOY 600 REACTOR VESSEL HEAD PENETRATION ISSUES Herbert Lenz 1, Edward Siegel 2 and Donald Seeger 2 1 Westinghouse Reaktor GmbH, Dudenstrasse 44, 68167 Mannheim, Germany 2 Westinghouse Electric Company

More information

Office for Nuclear Regulation (ONR) Site Report for Sizewell B Power Station

Office for Nuclear Regulation (ONR) Site Report for Sizewell B Power Station Title of document Office for Nuclear Regulation (ONR) Site Report for Sizewell B Power Station 1 October 2017 31 December 2017 Foreword This report is issued as part of ONR's commitment to make information

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Works for the Manufacture of Chain Cable for ships Revision 2, April 2015 Page 1 of 19 Lloyd s Register Group Limited, its subsidiaries and

More information

SI N C E T H E 1990S, stress corrosion

SI N C E T H E 1990S, stress corrosion Deep-hole drilling to measure residual stress BY DICK KOVAN A British company uses a technique known as deep-hole drilling to measure residual stresses in thick-section nuclear components. SI N C E T H

More information

Report of the National Scientific Expert Group on the RPVD3T2

Report of the National Scientific Expert Group on the RPVD3T2 Report of the National Scientific Expert Group on the RPVD3T2 Prepared by: Rudi Denys Ludovic Noels Thomas Pardoen Dirk Vandepitte The National Scientific Expert Group (further termed NSEG) has been installed

More information

Structural Performance of next-generation nuclear components: lessons from the UK's R5 and R6 structural integrity assessment procedures

Structural Performance of next-generation nuclear components: lessons from the UK's R5 and R6 structural integrity assessment procedures Structural Performance of next-generation nuclear components: lessons from the UK's R5 and R6 structural integrity assessment procedures MATISSE Workshop on cross-cutting issues in structural materials

More information

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT DESIGN ASSESSMENT AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT 10/2016 Stephen J Walls, EDF Energy Nuclear New Build 1 Olivier Bard, EDF HINKLEY POINT C (HPC) 2 HPC Financial Investment

More information

REACTOR VESSEL ASSESSMENT

REACTOR VESSEL ASSESSMENT WANO Technical Conference Doel 3-Tihange 2 RPV Issue 1 DOEL 3 TIHANGE 2 REACTOR VESSEL ASSESSMENT TU DELFT 28 JUNE 2013 2 1 GDF SUEZ KEY FIGURES 90.7 billion in 2011 revenues 218,900 employees Capacity:

More information

Office for Nuclear Regulation

Office for Nuclear Regulation ASSESSMENT REPORT Civil Nuclear Reactors Programme NNB GenCo: Hinkley Point C Pre-Construction Safety Report 2012 Assessment Report for Equipment Qualification Work Stream (B3) Assessment Report: ONR-CNRP-AR-13-101

More information

ONR GUIDE INTEGRITY OF METAL STRUCTURES, SYSTEMS AND COMPONENTS. Nuclear Safety Technical Assessment Guide. NS-TAST-GD-016 Revision 5

ONR GUIDE INTEGRITY OF METAL STRUCTURES, SYSTEMS AND COMPONENTS. Nuclear Safety Technical Assessment Guide. NS-TAST-GD-016 Revision 5 ONR GUIDE INTEGRITY OF METAL STRUCTURES, SYSTEMS AND COMPONENTS Document Type: Unique document ID and Revision no: Nuclear Safety Technical Assessment Guide NS-TAST-GD-016 Revision 5 Date issued: March

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Foundry for the Manufacture of Steel Castings Revision 3, January 2015 Lloyd s Register Group Limited, its subsidiaries and affiliates and

More information

OFFICIAL. Magnox Swarf Storage Silo (MSSS) Risk and Hazard Reduction Programme

OFFICIAL. Magnox Swarf Storage Silo (MSSS) Risk and Hazard Reduction Programme Title of document Magnox Swarf Storage Silo (MSSS) Risk and Hazard Reduction Programme Application for Agreement to Commence Installation and Inactive Commissioning of SEP2 and 1 Mobile Caves in MSSS Project

More information

Standard Specification for Centrifugally Cast Ferritic Alloy Steel Pipe for High- Temperature Service 1

Standard Specification for Centrifugally Cast Ferritic Alloy Steel Pipe for High- Temperature Service 1 Designation: Standard Specification for Centrifugally Cast Ferritic Alloy Steel Pipe for High- Temperature Service 1 This standard is issued under the fixed designation A 426/A 426M; the number immediately

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Foundry for the Manufacture of Stainless Steel Castings including Propellers Revision 2, January 2015 Lloyd s Register Group Limited, its

More information

NOT PROTECTIVELY MARKED. REDACTED PUBLIC VERSION HPC PCSR3 Sub-chapter 17.4 Conclusions of the HPC ALARP Assessment NNB GENERATION COMPANY (HPC) LTD

NOT PROTECTIVELY MARKED. REDACTED PUBLIC VERSION HPC PCSR3 Sub-chapter 17.4 Conclusions of the HPC ALARP Assessment NNB GENERATION COMPANY (HPC) LTD Page No.: i / iii NNB GENERATION COMPANY (HPC) LTD HPC PCSR3: CHAPTER 17 COMPLIANCE WITH ALARP SUB-CHAPTER 17.4 CONCLUSIONS OF THE HPC ALARP ASSESSMENT { PI Removed } uncontrolled. 2017 Published in the

More information

ABSTRACT INTRODUCTION

ABSTRACT INTRODUCTION A UK regulatory view on the analysis and design of nuclear structures subjected to dynamic and impact loadings C.M. Pratchett & A.M. Coatsworth EM Nuclear Installations Inspectorate, Health and ABSTRACT

More information

ECNDT Moscow 2010 ADVANCED APPROACH OF REACTOR PRESSURE VESSEL HEAD INSPECTION AND REPAIR of CRDM J-WELD

ECNDT Moscow 2010 ADVANCED APPROACH OF REACTOR PRESSURE VESSEL HEAD INSPECTION AND REPAIR of CRDM J-WELD ECNDT Moscow 2010 ADVANCED APPROACH OF REACTOR PRESSURE VESSEL HEAD INSPECTION AND REPAIR of CRDM J-WELD Mladen Pajnić, Hrvoje Franjić, Gabrijel Smoljkić, Krunoslav Markulin, Fran Jarnjak INETEC Institute

More information

Edward W. Russell and Brian L. Anderson Lawrence Livermore National Laboratory Prepared by LLNL under Contract DE-AC52-07NA27344

Edward W. Russell and Brian L. Anderson Lawrence Livermore National Laboratory Prepared by LLNL under Contract DE-AC52-07NA27344 Comparison of German and American Fabrication Standards for Transportation and Storage Containments of High Level Radioactive Material Type B Packages 15055 ABSTRACT Edward W. Russell and Brian L. Anderson

More information

NDT 2010 Conference Topics

NDT 2010 Conference Topics NDT 2010 Conference Topics Session 3B (2) Inspection Qualification Chairman M Mienczakowski 10.15 Use of simulation in the NDE qualification process. Application to the EPR RPV Inspection Authors - Jack

More information

PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE WELD REPAIRS

PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE WELD REPAIRS Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA PVP2011-57675 PVP2011- PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE

More information

Effective Aging Management of Baffle-to-Former Bolts to Assure Long-Term Reliability of Reactor Vessel Internals

Effective Aging Management of Baffle-to-Former Bolts to Assure Long-Term Reliability of Reactor Vessel Internals Effective Aging Management of Baffle-to-Former Bolts to Assure Long-Term Reliability of Reactor Vessel Internals Tiangan Lian Kyle Amberge Electric Power Research Institute Fourth Nuclear Power Plant Life

More information

Report to the Advisory Committee of Experts for Nuclear Pressure Equipment. ASN Report reference CODEP-DEP IRSN Report /

Report to the Advisory Committee of Experts for Nuclear Pressure Equipment. ASN Report reference CODEP-DEP IRSN Report / Report to the Advisory Committee of Experts for Nuclear Pressure Equipment ASN Report reference CODEP-DEP-2017-019368 IRSN Report /2017-00011 English version Public version Session of 26 and 27 June 2017

More information

Office for Nuclear Regulation

Office for Nuclear Regulation Generic Design Assessment New Civil Reactor Build Step 4 Structural Integrity Assessment of the EDF and AREVA UK EPR TM Reactor Assessment Report: ONR-GDA-AR-11-027 14 November 2011 COPYRIGHT Crown copyright

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Works for the Manufacture of Non-heat treated ERW Steel Pipes Revision 2, Sept 2014 Lloyd s Register Group Limited, its subsidiaries and affiliates

More information

GN01 DEAERATOR CRACKING

GN01 DEAERATOR CRACKING GN01 DEAERATOR CRACKING 1 SCOPE 1.1 This note summarises the results of surveys and investigations of Australian and overseas incidents with deaerators and associated water storage vessels, and makes recommendations

More information

Boiling Water Reactor Vessel and Internals

Boiling Water Reactor Vessel and Internals Boiling Water Reactor Vessel and Internals Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared, first in

More information

Activities of OECD/NEA in the Regulatory Aspects of Plant Life Management

Activities of OECD/NEA in the Regulatory Aspects of Plant Life Management Activities of OECD/NEA in the Regulatory Aspects of Plant Life Management Andrei Blahoianu NEA / CSNI / IAGE Chairman Andrei.Blahoianu@cnsc-ccsn.gc.ca ccsn.gc.ca Alejandro Huerta OECD/NEA Nuclear Safety

More information

Maintaining Nuclear Reactor Components Performance and Integrity for Plant Safety

Maintaining Nuclear Reactor Components Performance and Integrity for Plant Safety Boosting your Excellence through Knowledge and Training Maintaining Nuclear Reactor Components Performance and Integrity for Plant Safety Academy Academy Academy Seminar objective Academy Generally, well-run

More information

ONR-HYA-PAR Revision 0. LI 594 Consent

ONR-HYA-PAR Revision 0. LI 594 Consent Title of document PROJECT ASSESSMENT REPORT Unique Document ID and Revision No: Project: ONR-HYA-PAR-15-017 Revision 0 Boiler spine recovery project Site: Heysham 1 Title: Licence Instrument No: (if applicable)

More information

Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station

Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station November 26, 2015 The Kansai Electric Power Co., Inc. Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station

More information

ONR-HYB-PAR Revision 1. LI 582 Approval

ONR-HYB-PAR Revision 1. LI 582 Approval Title of document PROJECT ASSESSMENT REPORT Unique Document ID and Revision No: Project: Site: Title: Licence Instrument No: (if applicable) ONR-HYB-PAR-14-012 Revision 1 Heysham 2 Power Station Request

More information

Standard Specification for Carbon and Alloy Steel Forgings for Thin-Walled Pressure Vessels 1

Standard Specification for Carbon and Alloy Steel Forgings for Thin-Walled Pressure Vessels 1 Designation: A 372/A 372M 03 An American National Standard Standard Specification for Carbon and Alloy Steel Forgings for Thin-Walled Pressure Vessels 1 This standard is issued under the fixed designation

More information

When a Refractory Failure Isn t!- Some Anchor Issues

When a Refractory Failure Isn t!- Some Anchor Issues When a Refractory Failure Isn t!- Some Anchor Issues Michael C Walton and Paul A Plater Co-Principals RefMet P. O. Box 126 PRAHRAN, Victoria 3181 Keywords: Steel Anchors, Failures, Refractories, Embrittlement.

More information

HEAVY PLATE FOR PETROCHEMICAL REACTORS SOPHISTICATION IN CHROMIUM-MOLYBDENUM STEEL DILLINGER HÜTTE GTS

HEAVY PLATE FOR PETROCHEMICAL REACTORS SOPHISTICATION IN CHROMIUM-MOLYBDENUM STEEL DILLINGER HÜTTE GTS HEAVY PLATE FOR PETROCHEMICAL REACTORS SOPHISTICATION IN CHROMIUM-MOLYBDENUM STEEL DILLINGER HÜTTE GTS EXPERIENCE THAT MASTERS EVEN THE GREATEST DEMANDS Construction of reactors and vessels for the petrochemicals

More information

Boiling Water Reactor Vessel and Internals (QA)

Boiling Water Reactor Vessel and Internals (QA) Boiling Water Reactor Vessel and Internals (QA) Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared, first

More information

Pressurized Water Reactor Materials Reliability Program

Pressurized Water Reactor Materials Reliability Program Pressurized Water Reactor Materials Reliability Program Program Description Program Overview Stress corrosion cracking and general environmental corrosion of reactor coolant system components have cost

More information

SPECIFICATION FOR TITANIUM AND TITANIUM ALLOY CASTINGS

SPECIFICATION FOR TITANIUM AND TITANIUM ALLOY CASTINGS TECHNICAL LITERATURE: ASME SB-367 [ASTM B367] Company Website: www.metalspiping.com Your Reliable Supplier of Titanium & Nickel Alloys SB-367 SPECIFICATION FOR TITANIUM AND TITANIUM ALLOY CASTINGS SB-367

More information

STEP 3 STRUCTURAL INTEGRITY ASSESSMENT OF THE EDF and AREVA UK EPR DIVISION 6 ASSESSMENT REPORT NO. AR 09/012-P

STEP 3 STRUCTURAL INTEGRITY ASSESSMENT OF THE EDF and AREVA UK EPR DIVISION 6 ASSESSMENT REPORT NO. AR 09/012-P Health and Safety Executive NUCLEAR DIRECTORATE GENERIC DESIGN ASSESSMENT NEW CIVIL REACTOR BUILD STEP 3 STRUCTURAL INTEGRITY ASSESSMENT OF THE EDF and AREVA UK EPR DIVISION 6 ASSESSMENT REPORT NO. AR

More information

Reactor Internals Overview

Reactor Internals Overview 1 Reactor Internals Overview Mechanisms: Cracking due to Irradiation Assisted Stress Corrosion (IASCC) and Stress Corrosion (SCC) Reduction of Fracture Toughness due to Irradiation Embrittlement (IE) and

More information

Doel 3 and Tihange 2 issue International Review Board Final Report

Doel 3 and Tihange 2 issue International Review Board Final Report 2015 Doel 3 and Tihange 2 issue International Review Board Final Report FANC-AFCN 14-8-2015 28-8-2015 Content Executive Summary... 3 Preface by Belgian Federal Agency for Nuclear Control... 6 Analysis

More information

Boiling Water Reactor Vessel and Internals Project (QA)

Boiling Water Reactor Vessel and Internals Project (QA) Boiling Water Reactor Vessel and Internals Project (QA) Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared,

More information

OFFICIAL. ONR-CNRP-PAR Revision 0. Assessment of Sizewell B Periodic Safety Review. Role Name Position Signature Date

OFFICIAL. ONR-CNRP-PAR Revision 0. Assessment of Sizewell B Periodic Safety Review. Role Name Position Signature Date Title of document PROJECT ASSESSMENT REPORT Unique Document ID and Revision No: Project: Site: ONR-CNRP-PAR-14-020 Revision 0 Periodic Safety Review Sizewell B TRIM Ref: 2015/21872 Title: Licence Instrument

More information

FATIGUE MONITORING FOR DEMONSTRATING FATIGUE DESIGN BASIS COMPLIANCE

FATIGUE MONITORING FOR DEMONSTRATING FATIGUE DESIGN BASIS COMPLIANCE FATIGUE MONITORING FOR DEMONSTRATING FATIGUE DESIGN BASIS COMPLIANCE D. Gerber, G. Stevens, T. Gilman, J. Zhang Structural Integrity Associates,San Jose,USA Structural Integrity Associates,San Jose,USA

More information

PRESSURE-TEMPERATURE LIMIT CURVES

PRESSURE-TEMPERATURE LIMIT CURVES Training School, 3-7 September 2018 Polytechnic University of Valencia (Spain) PRESSURE-TEMPERATURE LIMIT CURVES Carlos Cueto-Felgueroso This project received funding under the Euratom research and training

More information

Overview of NRC-EPRI PWSCC Initiation Testing - Status Update

Overview of NRC-EPRI PWSCC Initiation Testing - Status Update Overview of NRC-EPRI PWSCC Initiation Testing - Status Update Materials Reliability Program Industry-NRC Materials R&D Meeting June 2-4, 2015 Rockville, MD Presentation Outline Background on PWSCC Initiation

More information

SAFETY CASE REPORT ADDENDUM. Tihange 2. Reactor Pressure Vessel Assessment. 15 April 2013 e.r. Electrabel sa, av. Simón Bolívar, 1000 Bruxelles

SAFETY CASE REPORT ADDENDUM. Tihange 2. Reactor Pressure Vessel Assessment. 15 April 2013 e.r. Electrabel sa, av. Simón Bolívar, 1000 Bruxelles SAFETY CASE REPORT ADDENDUM Tihange 2 Reactor Pressure Vessel Assessment 15 April 2013 e.r. Electrabel sa, av. Simón Bolívar, 1000 Bruxelles 2 Contents Contents... 2 1 Executive Summary... 3 1.1 Context

More information

CRACK GROWTH AT STRUCTURAL DISCONTINUITIES AND WELDS

CRACK GROWTH AT STRUCTURAL DISCONTINUITIES AND WELDS CREEP AND CREEP-FATIGUE CRACK GROWTH AT STRUCTURAL DISCONTINUITIES AND WELDS Prepared by: F. W. Brust G. M. Wilkowski P. Krishnaswamy K. Wichman Engineering Mechanics Corporation of Columbus (Emc 2 ) Creep

More information

Workshop Information IAEA Workshop

Workshop Information IAEA Workshop IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Overview of Deterministic Safety Analysis: Input Data, Verification & Validation, Conservative/BE Approaches (Part. 2) Lecturer

More information

Knowledge Gaps in Toughness and Irradiation: Lessons of the Past, Prospects for the Future

Knowledge Gaps in Toughness and Irradiation: Lessons of the Past, Prospects for the Future Knowledge Gaps in Toughness and Irradiation: Lessons of the Past, Prospects for the Future Tim Williams, UK IAEA Technical Meeting, 5-8 November 2013, Vienna Themes What can we learn from the past? What

More information

HEALTH AND SAFETY EXECUTIVE HM NUCLEAR INSTALLATIONS INSPECTORATE

HEALTH AND SAFETY EXECUTIVE HM NUCLEAR INSTALLATIONS INSPECTORATE HEALTH AND SAFETY EXECUTIVE HM NUCLEAR INSTALLATIONS INSPECTORATE New Reactor Generic Design Assessment (GDA) - Step 2 Preliminary Review Assessment of: Structural Integrity Aspects of Westinghouse AP1000

More information

ASTM Standards for Pipe & Fittings

ASTM Standards for Pipe & Fittings for Pipe & Fittings There are many International Standards for stainless and carbon steel pipes and fittings. The list below is a basic overview of some of these. For more in-depth details of these Standards

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Works for the Manufacture of Steel Forgings for Semi- Built and Continuous Grain Flow Crankshafts Revision 3, January 2015 Page 1 of 14 Lloyd

More information

New Reactors Programme. GDA close-out for the AP1000 reactor. GDA Issue GI-AP1000-SI-02 - Fatigue Analysis of ASME III Class 1 Piping

New Reactors Programme. GDA close-out for the AP1000 reactor. GDA Issue GI-AP1000-SI-02 - Fatigue Analysis of ASME III Class 1 Piping New Reactors Programme GDA close-out for the AP1000 reactor GDA Issue GI-AP1000-SI-02 - Fatigue Analysis of ASME III Class 1 Piping Assessment Report: ONR-NR-AR-16-010 Revision 0 March 2017 , 2017 If you

More information

Flamanville 3 EPR, safety assessment and on-site inspections

Flamanville 3 EPR, safety assessment and on-site inspections Flamanville 3 EPR, safety assessment and on-site inspections Corinne. PIEDAGNEL, François TARALLO, Bernard MONNOT Institut de Radioprotection et de Sûreté Nucléaire, DSR/SAMS 92262 Fontenay-aux-Roses Cedex,

More information

Latest SCC Issues of Core Shroud and Recirculation Piping in Japanese BWRs

Latest SCC Issues of Core Shroud and Recirculation Piping in Japanese BWRs Transactions of the 7 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 7) Prague, Czech Republic, August 7, 3 Paper # WG- Latest SCC Issues of Core Shroud and Recirculation

More information

Quality Prediction of Cast Ingots

Quality Prediction of Cast Ingots Quality Prediction of Cast Ingots I. Hahn, M. Schneider* J. Terhaar, J. Jarolimeck, R. Sauermann** *MAGMA Giessereitechnologie GmbH, Aachen, Germany **Saarschmiede GmbH Freiformschmiede, Völklingen, Germany

More information

Assessment of the Safety Case for the Reactor Pressure Vessel of the Beznau Unit 1 Nuclear Power Plant

Assessment of the Safety Case for the Reactor Pressure Vessel of the Beznau Unit 1 Nuclear Power Plant Assessment of the Safety Case for the Reactor Pressure Vessel of the Beznau Unit 1 Nuclear Power Plant February 2018 International Review Panel Revision 0 Revision 0 Page 1 of 42 This page is intentionally

More information

Dry storage systems and aging management

Dry storage systems and aging management Dry storage systems and aging management H.Issard, AREVA TN, France IAEA TM 47934 LESSONS LEARNED IN SPENT FUEL MANAGEMENT Vienna, 8-10 July 2014 AREVA TN Summary Dry storage systems and AREVA Experience

More information

Inspection Qualification II

Inspection Qualification II Inspection Qualification II Qualification According to ENIQ of Complete EPR RPV Inspection Using Phased Array F. Mohr, G. Guse, intelligendt System & Services, Germany INTRODUCTION On each new reactor

More information

Structural Integrity and NDE Reliability I

Structural Integrity and NDE Reliability I Structural Integrity and NDE Reliability I Assessment of Failure Occurrence Probability as an Input for RI-ISI at Paks NPP R. Fótos, University of Miskolc, Hungary L. Tóth, P. Trampus, University of Debrecen,

More information

REPORT ON INDEPENDENT ANALYSIS AND ADVICE REGARDING THE SAFETY CASE. Reactor Pressure Vessel Assessment

REPORT ON INDEPENDENT ANALYSIS AND ADVICE REGARDING THE SAFETY CASE. Reactor Pressure Vessel Assessment REPORT ON INDEPENDENT ANALYSIS AND ADVICE REGARDING THE SAFETY CASE Tihange 2 Reactor Pressure Vessel Assessment 19 Décembre 2012 e.r. Electrabel sa, Boulevard Simón Bolívar 34, 1000 Bruxelles Executive

More information

Quarterly report on NPP events

Quarterly report on NPP events Quarterly report on NPP events July September 2018 Peinador Veira M. 2018 This publication is a Technical report by the Joint Research Centre (JRC), the European Commission s science and knowledge service.

More information

Benchmark Exercise on Risk-Informed In-Service Inspection Methodologies

Benchmark Exercise on Risk-Informed In-Service Inspection Methodologies 20th International Conference on Structural Mechanics in Reactor Technology (SMiRT 20) Espoo, Finland, August 9-14, 2009 SMiRT 20-Division 7, Paper 1841 Benchmark Exercise on Risk-Informed In-Service Inspection

More information

Extension to 60 years lifetime

Extension to 60 years lifetime SFEN Conference Atoms for the future October 22 nd -25 th 2012 Extension to 60 years lifetime J.M.Moroni EDF Nuclear Engineering Division PLIM 2012-14-18 May 2012 - Salt Lake City, USA. Summary Elements

More information

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED Rick Rishel WesDyne International LLC I-70 Madison Exit Gate D P.O. Box 409 Madison, PA 15663 USA rishelrd@westinghouse.com

More information

BUREAU OF INDIAN STANDARDS Draft Indian Standard

BUREAU OF INDIAN STANDARDS Draft Indian Standard For Comments Only BUREAU OF INDIAN STANDARDS Draft Indian Standard STEEL PLATES FOR PRESSURE VESSEL FOR INTERMEDIATE AND HIGH TEMPERATURE SERVICE INCLUDING BOILERS (Third Revision of IS 2002) ICS 77.140.30

More information

Gas Transmission and Distribution Piping Systems

Gas Transmission and Distribution Piping Systems ASME B31.8-2014 (Revision of ASME B31.8-2012) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN INTERNATIONAL PIPING CODE ASME B31.8-2014 (Revision of ASME B31.8-2012)

More information

Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Tubing for General Service 1

Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Tubing for General Service 1 Designation: A789/A789M 17 Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Tubing for General Service 1 This standard is issued under the fixed designation A789/A789M;

More information

Licensed Copy: John May, Powertrain Ltd., February 20, 2002, Uncontrolled Copy, (c) BSI

Licensed Copy: John May, Powertrain Ltd., February 20, 2002, Uncontrolled Copy, (c) BSI BRITISH STANDARD BS 70-3: Incorporating Amendment Nos. 1 and 2 Specification for Wrought steel for mechanical and allied engineering purposes Part 3: Bright bars for general engineering purposes BS70-3:

More information

NPP Safety in the aftermath of the Fukushima Accident. UK Response August 2013

NPP Safety in the aftermath of the Fukushima Accident. UK Response August 2013 Health and Safety Executive NPP Safety in the aftermath of the Fukushima Accident Dr. Gary Cook UK Response 26-29 August 2013 Overview ONR response to Fukushima ENSREG stress tests Specification and process

More information

Structural Integrity and NDE Reliability II

Structural Integrity and NDE Reliability II Structural Integrity and NDE Reliability II NDE Experience and Lessons Learnt from Recent EU Projects Focused on Assistance to the Armenian NPP L. Horacek, Nuclear Research Institute, Czech Republic ABSTRACT

More information

Phenomenon of (irradiation assisted) stress corrosion cracking for internals of PWR & BWR systems

Phenomenon of (irradiation assisted) stress corrosion cracking for internals of PWR & BWR systems Phenomenon of (irradiation assisted) stress corrosion cracking for internals of PWR & BWR systems Rdk Radek Novotny & Luigi Lii Db Debarberisb Institute for Energy (IE) Petten, The Netherlands http://www.jrc.ec.europa.eu

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

STRUCTURE AND PROPERTIES OF A508 GR. 4N CLASS 3 GRADE STEEL

STRUCTURE AND PROPERTIES OF A508 GR. 4N CLASS 3 GRADE STEEL STRUCTURE AND PROPERTIES OF A508 GR. 4N CLASS 3 GRADE STEEL Ladislav KANDER a, Šárka STEJSKALOVÁ a, Magdalena ŠMÁTRALOVÁ a, Petr ČÍŽEK a, Petr PUSTĚJOVSKÝ b MATERIAL AND METALLURGICAL RESEARCH Ltd., Ostrava,

More information

Industry and Government working together to deliver Nuclear New Build Programme in UK. Dr Glen Little Industrial Adviser March 2017

Industry and Government working together to deliver Nuclear New Build Programme in UK. Dr Glen Little Industrial Adviser March 2017 Industry and Government working together to deliver Nuclear New Build Programme in UK Dr Glen Little Industrial Adviser March 2017 Contents 1 2 3 4 History of UK Nuclear Power Plant Maintenance of UK Nuclear

More information

Evaluation of Pipe Weld NDE Indications

Evaluation of Pipe Weld NDE Indications Evaluation of Pipe Weld NDE Indications Brasse, Markus Westinghouse Electric Germany Dudenstrasse 44, D-68167 Mannheim, Germany Markus.Brasse@de.westinghouse.com ABSTRACT This paper discusses the evaluation

More information

The prediction of toughness and strength in high integrity forgings

The prediction of toughness and strength in high integrity forgings The prediction of toughness and strength in high integrity forgings H. Pous-Romero 1, J. Talamantes-Silva 2, S. S. Al-Bermani 2, H. K. D. H. Bhadeshia 1 and B. P. Wynne 3 1 University of Cambridge, UK

More information

Office for Nuclear Regulation

Office for Nuclear Regulation An agency of HSE Generic Design Assessment New Civil Reactor Build GDA Close-out for the EDF and AREVA UK EPR Reactor GDA Issue GI-UKEPR-SI-02 Revision 1 Structural Integrity RPV Surveillance Scheme Assessment

More information

Austenitic and Bimetallic Weld Inspection II

Austenitic and Bimetallic Weld Inspection II Austenitic and Bimetallic Weld Inspection II MRP-139 Recommendations: Inspection of Dissimilar Metal Welds in Reactor Pressure Vessels in Spain J.R. Gadea, A. Willke, J.J. Regidor, Tecnatom, Spain ABSTRACT

More information

2. TEST RECORDS: All records of tests and analysis shall be kept in suitable forms approved by the Bureau.

2. TEST RECORDS: All records of tests and analysis shall be kept in suitable forms approved by the Bureau. SCHEME OF TESTING AND INSPECTION FOR CERTIFICATION OF CARBON STEEL BILLETS, BLOOMS, SLABS AND BARS FOR FORGINGS ACCORDING TO IS:1875-1992 (Fifth Revision) 1. LABORATORY: A laboratory shall be maintained

More information

DNVGL-CP-0347 Edition May 2016

DNVGL-CP-0347 Edition May 2016 CLASS PROGRAMME Approval of manufacturers DNVGL-CP-0347 Edition May 2016 The content of this service document is the subject of intellectual property rights reserved by ("DNV GL"). The user accepts that

More information

Office for Nuclear Regulation

Office for Nuclear Regulation Office for Nuclear Regulation Civil Nuclear Reactor Programme NNB GenCo Licence Condition 10 Training Compliance Arrangements Assessment Report: ONR-CNRP-AR-12-095 21 January 2013 Office for Nuclear Regulation

More information

IAEA-TECDOC Reference manual on the IAEA JRQ correlation monitor steel for irradiation damage studies

IAEA-TECDOC Reference manual on the IAEA JRQ correlation monitor steel for irradiation damage studies IAEA-TECDOC-123 Reference manual on the IAEA JRQ correlation monitor steel for irradiation damage studies July 21 The originating Section of this publication in the IAEA was: Nuclear Power Engineering

More information

Licensee Design Authority Capability

Licensee Design Authority Capability Title of document ONR GUIDE Licensee Design Authority Capability Document Type: Unique Document ID and Revision No: Nuclear Safety Technical Assessment Guide NS-TAST-GD-079 Revision 3 Date Issued: April

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of Works for the Manufacture of Fusion Welded Pressure Vessels Revision 4, July 2015 Page 1 of 17 Lloyd s Register Group Limited, its subsidiaries

More information

AEROSPACE MATERIAL SPECIFICATION

AEROSPACE MATERIAL SPECIFICATION AEROSPACE MATERIAL SPECIFICATION AMS 5643Q Issued OCT 1951 Revised JAN 2003 Superseding AMS 5643P Steel, Corrosion-Resistant, Bars, Wire, Forgings, Tubing, and Rings 16Cr - 4.0Ni - 0.30Cb - 4.0Cu Solution

More information

ONR-OFP-PAR Revision 0. Periodic Safety Review. Hinkley Point B 62C Hunterston B Sc.13

ONR-OFP-PAR Revision 0. Periodic Safety Review. Hinkley Point B 62C Hunterston B Sc.13 Title of document PROJECT ASSESSMENT REPORT Unique Document ID and Revision No: Project: ONR-OFP-PAR-16-025 Revision 0 Periodic Safety Review Site: Title: Licence Instrument No: (if applicable) Nuclear

More information

UKEPR Issue 06

UKEPR Issue 06 Title: PCSR Sub-chapter 18.1 Human Factors Total number of pages: 136 Page No.: I / VI Chapter Pilot: A. GODY Name/Initials Date 14-11-2012 Approved for EDF by: A. MARECHAL Approved for AREVA by: G. CRAIG

More information

UK Nuclear New Build. Challenges and Solutions for Chinese Supply Chain Companies. Courtesy of EDF Energy

UK Nuclear New Build. Challenges and Solutions for Chinese Supply Chain Companies. Courtesy of EDF Energy UK Nuclear New Build Challenges and Solutions for Chinese Supply Chain Companies Courtesy of EDF Energy 2 Challenges and Solutions 1. Background CGN has signed agreements with EDF and the UK Government

More information