UHV Cleanliness Requirements: Cleaning/Baking and Contamination Control
|
|
- Melina Maxwell
- 6 years ago
- Views:
Transcription
1 UHV Cleanliness Requirements: Cleaning/Baking and Contamination Control Dennis Coyne HAM-SAS Bidder s LIGO Laboratory, Caltech 25 October 2005 Livingston, LA Hanford, WA LIGO R&D 1
2 Basic UHV Compatibility Requirements Cleanliness Requirements:» Achieve a Non-Volatile Residue (NVR) level of A/50 or better (per MIL-STD- 1246C or IEST-STD-CC1246D) on piece parts before clean assembly» Achieve a Particulate Cleanliness Level of 50 or better (per MIL-STD C or IEST-STD-CC1246D) on piece parts before clean assembly» Perform clean assembly and all steps through UHV Packaging in a Class 100 Clean Room (per FED-STD-209)» Comply with Contamination Control Protocols defined in E (M is also a good guide)» Package the Clean Parts per E No Virtual Leaks» Full Penetration Welds No Cold Welding» Stainless fasteners into Aluminum» Silver coated Stainless Fasteners into Stainless» Oversized pilot and tap for tapped holes LIGO R&D 2
3 Ultra-High Vacuum (UHV) Cleanliness Requirements Related to Manufacturing Processes RECEIVE/ INSPECT MATERIALS/ PARTS GROSS CLEANING PER MIL-STD-1246 OR E UHV COMPATIBLE WELDING RESTRICTIONS & FULL PENETRATION WELD CERTIFICATION Notes: (1) The process sequence depicted here is suggestive, and not meant to be prescriptive. (2) Loaded GAS Filter, Spring Blades to be Creep Relaxed in Air Bake REASONABLY CLEAN ENVIRONMENT & HANDLING MACHINE INSPECT PRE-CLEAN INSPECT DIRTY ASSEMBLY - FIT CHECK TUNE UHV COMPATIBLE MACHINING RESTRICTIONS HANDLING/ CONTAMINATION CONTROL PROTOCOL FOR WINDINGS WELD WIND MARAGING HEAT TREAT STRESS RELIEF POTTING WELDMENT MACHINING LIGO LAB QUALIFIES CONTRACTOR CLEANING/BAKING/ CONTAMINATION CONTROL WITH TEST PIECES AND RGA PER E SHIP PACK PARTIAL DISASSEMBLY CLEAN ASSEMBLY (GAS TUNE) FTIR TEST AIR BAKE PRECISION CLEAN DIS- ASSEMBLE UHV PACKAGING PER E (REFERENCE M990034, E960022) CONTAMINATION CONTROL PER E (REFERENCE M990034) CLASS 100 (PER FED-STD-209) FTIR TEST PER MIL- STD-1246 OR IEST-STD-CC1246D TO NVR LEVEL A/50 & PARTICULATE AIR BAKE PER section 5.5 of E (SIMILAR TO E990452) PRECISION CLEANING PER MIL-STD-1246 OR E OR E LIGO R&D LEVEL 100 3
4 Practical UHV Requirements Must pre-clean parts before welding and winding Must clean parts multiple times during fabrication Must thoroughly clean parts!» gross clean with solvents and acids» Mechanical clean (scrub) parts especially tapped holes multiple times, with powered rotary tool during gross and precision clean steps» precision clean with hot, water soluble detergents (steam or hot water spray) multiple times» Never let parts dry with detergent» Multiple rinses with Deionized water Must bake parts (air or vacuum) after precision cleaning Must maintain parts in a class 100 clean room» or keep wrapped in UHV Foil and keep in at least a class 10,000 clean area)» limit exposure, keep wrapped /covered when possible Must Control Contamination with Good Clean Room Practice» All tools must be cleaned, air baked, wrapped & kept in Class 100 areas» All personnel must wear full clean room garb, including hair net, face mask and gloves LIGO R&D 4
5 UHV Requirement References Particulate Level 50 and NVR Level A/50 per MIL-STD-1246C or IEST-STD- CC1246D Cleaning for UHV Service:» Contractor is to certify the cleaning and baking process with representative parts to demonstrate 1246 Level 50-A/50 NVR Level to be confirmed via FTIR (Fourier Transform Infrared analysis) Particulate level to be confirmed by particle sizing and counting or equivalent particle area coverage» LIGO Lab will independently assess the contractor s cleaning/baking process with representative parts by RGA (mass spectrometer outgassing analysis) per E960022» Guidance: E048227, Process Specification for Ad-LIGO Seismic Isolation System In- Vacuum Mechanical Elements: Fabrication (includes cleaning) Contamination Control:» Per E048228, Process Specification for Ad-LIGO Seismic Isolation System In-Vacuum Mechanical Elements: Contamination Control» Additional Guidance: M990034, LIGO Contamination Control Plan FED-STD-209, Airborne Particulate Cleanliness Classes in Cleanrooms and Clean Zones ISO-14644, Cleanrooms and controlled environments [ISO superceeds FED-STD-209] Packaging:» Per E048227, Process Specification for Ad-LIGO Seismic Isolation System In-Vacuum Mechanical Elements: UHV Packaging LIGO R&D 5
6 Clean Room & Gowning Room Class 10,000 Room Class 100 Clean Room HEPA Filter Gowning Room Sticky Mat LIGO R&D 6
7 HAM Chamber Clean Rooms Full Clean Room Dress Concrete Floor Cleaned Routinely, not ideal, but serviceable LIGO R&D 7
8 UHV Foil Annealed (baked) UHV Aluminum Foil for Wrapping Parts LIGO R&D 8
LASER INTERFEROMETER GRAVITATIONAL WAVE OBSERVATORY SPECIFICATION. Sheet 1 of 6 Manufacturing Process for Cantilever Spring Blades for Advanced LIGO
Sheet 1 of 6 APPROVALS DATE AUTHORS: Calum I. Torrie, Ken Mason, Dennis Coyne, Janeen Romie, Doug Cook, Mike 12 July 2010 Meyer, Mick Flanigan. Updated by Norna Robertson 2 nd Oct 2013 CHECKED: Dennis
More informationREQUIREMENTS. Metal Components for use in the Advanced LIGO Vacuum System
Sheet 1 of 5 APPROVALS DATE Document Change Notice AUTHOR(S): Calum Torrie, Dennis Coyne, Ken Mailand 27-Oct-2010 see DCC record Status: 1 Introduction All metal components intended for vacuum service
More informationEE-527: MicroFabrication
EE-527: MicroFabrication Clean Rooms How Big of a Particle is Tolerable? Example: 0.5 µm CMOS technology Lateral Features: pattern size = 0.5 µm pattern tolerance = 0.15 µm level-level registration = 0.15
More informationCompounding Aseptic Isolators (CAI) James T Wagner
Compounding Aseptic Isolators (CAI) James T Wagner jimwagner@cenvironment.com Disclaimer "Although I am a member of the USP Sterile Compounding Expert Committee, I am speaking today in my individual capacity
More informationMedical Device Reprocessing Assessment - General (Cleaning, Disinfection, and/or Sterilization)
Medical Device Reprocessing Assessment - General (Cleaning, Disinfection, and/or Sterilization) Date: Office Name: Office Number: Responsible Physician: Assessor: M.1. General Yes No N/A If No Please Comment
More informationTechnical Specification
Technical Specification No.: Vacuum 005/2008 Version 1.6 / 22.09.2010 Guidelines for UHV-Components at DESY U. Hahn (FS-BT), K. Zapfe (MVS) Contents 1 General Information... 3 1.1 Introduction... 3 1.2
More informationControlling the molecular & particle contamination for the Sentinel-5 Spectrometer
Controlling the molecular & particle contamination for the Sentinel-5 Spectrometer ing. L van der Laan, ir. D.J. Naron (TNO) VCCN symposium, May 31, 2017 TNO & contamination control Design & development
More informationFM Collection & Identification Services. Taywin Channo Asst. QA & Lab Manager
FM Collection & Identification Services Taywin Channo Asst. QA & Lab Manager Agenda 01 Microelectronic Laboratory Overview 02 How We Can Help You? 03 Contamination Analysis 04 Source of Contamination Main
More informationMICROCHIP MANUFACTURING by S. Wolf
MICROCHIP MANUFACTURING by S. Wolf Chapter 8: CONTAMINATION- CONTROL & CLEANING TECHNOLOGY for ULSI APPLICATIONS 2004 by LATTICE PRESS CHAPTER CONTENTS Contamination-Types in IC Fabrication Sources of
More informationNAVSEA STANDARD ITEM. 1.1 Title: Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish
NAVSEA STANDARD ITEM ITEM NO: 009-06 DATE: 06 MAR 2018 CATEGORY: I 1. SCOPE: 1.1 Title: Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish 2. REFERENCES: 2.1 Standard Items
More informationK. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.
DIVISION 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING PART 1 GENERAL 1.1 SECTION INCLUDES A. Structural steel framing members, support members. 1.2 RELATED REQUIREMENTS A. Section 05 50 00 - Metal Fabrications:
More informationVALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY
VALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY Oren Levin, Diane Gordon VisionCare Ophthalmic Technologies, POB 3879, Petah Tikva 49130,
More informationCUSTOMER CATALOG ASI: SAGE: ASB:
CUSTOMER CATALOG ASI: 79897 ASI: 79897 Table of Contents Custom Labeled Spring Water.............................. pg 3 Multi-purpose Applicator Squeegee........................ pg 4 3-7/8 Round Sandstone
More informationTHE EXPERTS IN INDUSTRIAL CLEANING
THE EXPERTS IN INDUSTRIAL CLEANING CASTROL OFFERS YOU A COMPREHENSIVE RANGE OF WORLD-CLASS INDUSTRIAL CLEANERS AND PRODUCT SUPPORT SERVICES THAT WILL HELP YOU TO: > Achieve more reliable cleanliness of
More informationTABLE OF CONTENTS. 1.0 INTRODUCTION Page SCOPE Page REFERENCES Page REQUIREMENTS Page QUALITY ASSURANCE Page 8
TABLE OF CONTENTS 1.0 INTRODUCTION Page 3 2.0 SCOPE Page 3 3.0 REFERENCES Page 4 4.0 REQUIREMENTS Page 5 5.0 QUALITY ASSURANCE Page 8 6.0 SUBMITTALS Page 9 7.0 PREPARATION FOR SHIPMENT Page 10 Page 2 of
More informationExecutive Summary. Service can be provided for 5x8 at standard rates, or 7x24 at premium rates. Available for most Wright Line Products
Seismic Bracing Contents Executive Summary...1 Details of Service for Concrete Slab Floor...2 Details of Service for Raised Tile Computer Room Floor..3 Assumptions...4 Scope of Responsibility...5 Other
More informationNAVSEA STANDARD ITEM. 1.1 Title: Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish
NAVSEA STANDARD ITEM ITEM NO: 009-06 DATE: 30 JUL 2015 CATEGORY: I 1. SCOPE: 1.1 Title: Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish 2. REFERENCES: 2.1 Standard Items
More informationSTANDARD OPERATING PROCEDURES SOP: 2040 PAGE: 1 of 10 REV: 0.0 DATE: 05/17/02
PAGE: 1 of 10 1.0 SCOPE AND APPLICATION* 2.0 METHOD SUMMARY* CONTENTS 3.0 SAMPLE PRESERVATION, CONTAINERS, HANDLING, AND STORAGE* 4.0 INTERFERENCES AND POTENTIAL PROBLEMS 5.0 EQUIPMENT/APPARATUS* 5.1 Sampling
More informationTable of Contents. Pipette Tips. Table of Contents
Table of Contents 53 Table of Contents 54 56 Optifit Tips 57 SafetySpace Filter Tips 58 Low Retention Tips 60 Packaging Options 54 Optifit Tips and SafetySpace Filter Tips The Perfect Match for Your Pipette
More information1. Supply, delivery, engineering and installation of new storage equipment.
SECTION 10 51 13 - METAL LOCKERS * ALL FIELDS IN [ ] MUST BE EDITED PART 1 - GENERAL 1.1. RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationLoading Arm Installation, Maintenance & Safety Manual
Loading Arm Installation, Maintenance & Safety Manual Version Loading Arm Hot Line: 1-800-547-9393 Dear OPW Customer: Thank you for selecting OPW Engineered Systems, Inc. ("OPW"), and giving us the opportunity
More informationWork Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts
1) Introduction Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts Triumvirate Environmental Inc. (TEI) shall perform
More informationVERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f:
VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA 02189 www.vertexeng.com p: 781.952.6000 f: 781.335.3543 EZRA BAKER ELEMENTARY SCHOOL/GYMNASIUM ASBESTOS ABATEMENT WORK PLAN ASBESTOS CONTAINING
More informationBack TO Basics: Sample Collection & Handling
Back TO Basics: Sample Collection & Handling What is QA/QC? QA stands for Quality Assurance QC stands for Quality Control Both are very important to the integrity of the sample data. Both start at the
More informationSampling Instructions for Active Sampling
Sampling Instructions for Active Sampling Please read carefully before sampling CASSEN CASSEN Testing Laboratories Telephone: 416 679 9663 Toll Free: 1 866 423 3001 www.cassen.ca CASSEN Testing Laboratories
More informationSECTION AIR DUCT CLEANING
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationArchitectural Details. Walls. Including PVC cove, UL Listed Raceway, & Integration to Flooring. AES Pharma Wall & Walk-On Ceiling Cleanroom System
Architectural Details Section One Walls Including PVC cove, UL Listed Raceway, & Integration to Flooring AES Pharma Wall & Walk-On Ceiling Cleanroom System Architectural Components AES PHARMA SYSTEM AES
More informationPhEn-602 Notes # 4 J. Manfredi
PhEn-602 Notes # 4 J. Manfredi Spring 2009 1 Basic definitions Clean Room: A room in which the concentration of airborne particles is controlled and contains one or more clean zones Clean Zone: A defined
More informationa solution for reducing the
Outsourcing the precision cleaning, a solution for reducing the environmental impact Trade fair Hanover 2015 Heiko ZSCHIEDRICH Hanover April 15, 2015 Summary 1. Introduction and presentation of ECP 2.
More informationDivision 8 Section "Flush Wood Doors" for louvers in wood doors. Division 15 Sections for louvers that are a part of mechanical equipment.
0 0 0 0 0 SECTION 000 - LOUVERS AND VENTS PART GENERAL RELATED DOCUMENTS EASTLAKE FIRE STATION REPLACEMENT HILLSBOROUGH COUNTY CIP # Drawings and general provisions of the Contract, including General and
More informationSection 716. SHOP CLEANING AND COATING STRUCTURAL STEEL
716.01 Section 716. SHOP CLEANING AND COATING STRUCTURAL STEEL 716.01. Description. This work consists of shop cleaning and applying a complete coating system on new structural steel as a part of fabricating
More informationGuide for Cleaning, Sterilization and Storage of Reusable Introducers
Guide for Cleaning, Sterilization and Storage of Reusable Introducers M Manufactured by: Caldera Medical, Inc. 5171 Clareton Drive Agoura Hills, CA 91301 U.S. Toll Free: 866-4-CALDERA Telephone: 818-879-6555
More informationAsbestos cement products in your home
Asbestos cement products in your home What is asbestos? Asbestos is a naturally occurring fibrous crystalline mineral, found in rock formations. Three main types of asbestos have been mined in Australia,
More informationGuide for Cleaning, Sterilization and Storage of Introducers for Caldera Medical Implants
Guide for Cleaning, Sterilization and Storage of Introducers for Caldera Medical Implants M Manufactured by: Caldera Medical, Inc. 5171 Clareton Drive Agoura Hills, CA 91301 U.S. Toll Free: 866-4-CALDERA
More informationCorrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries
Corrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries API SPECIFICATION 20F FIRST EDITION, XXX 201X 1 1. Scope 1.1 Purpose This API specification specifies requirements for the
More informationDIVISION 5 METALS SECTION STRUCTURAL STEEL
DIVISION 5 METALS SECTION 05 12 00 PART 1 GENERAL 1.01 SUMMARY A. Section Includes: All labor and materials required to furnish and install the structural steel shown on the Drawings and required by these
More informationGirth Weld Coating With Fusion Bond Epoxy
fact sheets Girth Weld Coating With Fusion Bond Epoxy Processing guidelines The guidelines below describe surface preparation and application requirements and procedures, inspection and safety recommendations
More informationWork Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos
University of Washington Facilities Services Maintenance & Alterations 9.5.02 Work Practice for Penetrating or Removing Wallboard Systems with
More information1.02 RELATED SECTIONS: Water supply piping, water use piping, electrical, irrigation, foundations, site plans.
INC. ENGINEERING/CONSTRUCTION/MANUFACTURING /WWW.CONTAINWATER.COM SPRINGS, TEXAS. 78620 MODEL SPECIFICATION FOR CONTAIN WATER INC. 30 DEGREE ROOF CORRUGATED STEEL WATER STORAGE Part 1 GENERAL 1.01 SECTION
More information1.02 RELATED SECTIONS: Water supply piping, water use piping, electrical, irrigation, foundations, site plans.
INC. ENGINEERING/CONSTRUCTION/MANUFACTURING /WWW.CONTAINWATER.COM SPRINGS, TEXAS. 78620 MODEL SPECIFICATION FOR CONTAIN WATER INC. DOME ROOF CORRUGATED STEEL WATER STORAGE TANKS. Part 1 GENERAL 1.01 SECTION
More informationSECTION MECHANICAL EQUIPMENT - GENERAL REQUIREMENTS
SECTION 11000 MECHANICAL EQUIPMENT - GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 DESCRIPTION A. This section contains general information required to install mechanical equipment as shown on the plans and
More informationUNITED INDUSTRIES GROUP INC.
SECTION 13205 AWWA D100-05 WELDED STEEL RESERVOIR SPECIFICATIONS REFERENCE SPECIFICATIONS, CODES AND STANDARDS. Commercial Standards: AWWA/ANSI D100-05 Welded Steel Tanks for Water Storage ASTM A36-01
More informationADHESIVES CERAMICS CHEMICALS COATINGS COSMETICS FINE CHEMICALS FOODS INKS PHARMACEUTICALS PLASTICS. Performance-Proven Processing Equipment
ADHESIVES CERAMICS CHEMICALS COATINGS COSMETICS FINE CHEMICALS FOODS INKS PHARMACEUTICALS PLASTICS Performance-Proven Processing Equipment A World Leader in Process Equipment... Years of experience coupled
More informationSupplementary Training Modules on Good Manufacturing Practice. Validation. WHO Technical Report Series, No. 937, Annex 4.
Supplementary Training Modules on Good Manufacturing Practice Validation WHO Technical Report Series, No. 937, 2006. Annex 4. Validation Slide 1 of 48 August 2006 Validation! Part 1. General overview on
More informationWHAT IS A CLEAN ROOM?
WHAT IS A CLEAN ROOM? A clean room is an extremely sophisticated work environment, designed and built with the express purpose of providing a high level of cleanliness for a production or research facility.
More informationRAMAPO COLLEGE OF NEW JERSEY PHASE II HOUSING REHABILITATION C 2012
SECTION 10200 - LOUVERS AND VENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More information450 and 550 Series Pressure/Vacuum Relief Valve (ATEX Approved)
Instruction Manual 450 and 550 Series March 2015 450 and 550 Series Pressure/Vacuum Relief Valve (ATEX Approved) Table of Contents Introduction...1 Specifications...2 Principle of Operation...4 Installation...4
More informationDeveloped and Presented by: Wisconsin Healthcare Engineering Association
Infection Control Risk Assessment (ICRA) Developed and Presented by: Wisconsin Healthcare Engineering Association What is an ICRA? An Infection Control Risk Assessment is a tool devised to protect patients
More informationResidue removal in Cleanroom Environments
Residue removal in Cleanroom Environments PDA Midwest Indianapolis Event 06 Oct 2016 Contamination Control Solutions 1/ BIO Beth Kroeger Technical Service Manager STERIS Life Sciences 4 years 24 years
More informationSECTION METAL WELDING
SECTION 05222 - METAL WELDING PART 1 - GENERAL 1.01 SECTION INCLUDES A. Welding Rod/Electrodes B. Stud Shear Connectors C. Shop Welding D. Inspections and Tests by the Contractor E. Inspections and Test
More informationTable of Contents. Pipette Tips. Table of Contents
Table of Contents 57 57 Table of Contents 58 60 Optifit Tips 62 SafetySpace Filter Tips 63 Low Retention Tips 64 Packaging Options 66 Ordering Information 58 58 Optifit Tips and SafetySpace Filter Tips
More information1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.
SECTION 05500- METAL FABRICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSealed Enclosure Luminaires Designed and sealed for critical environments
Sealed Enclosure Luminaires Designed and sealed for critical environments Sealed Enclosure LED Luminaires SE Designed and manufactured in the USA SimpleSeal Overlapping and Inset Door Series LED Supporting
More informationSanitation Standard Operating Procedures. New Juice Co
Sanitation Standard Operating Procedures New Juice Co 123 Petunia Drive Anywhere, CA 98765 1. SAFETY OF THE WATER THAT COMES INTO CONTACT WITH FOOD OR FOOD-CONTACT SURFACES, OR IS USED IN THE MANUFACTURE
More informationENVIRONMENTAL HEALTH & SAFETY
ENVIRONMENTAL HEALTH & SAFETY Standard Operating Procedures for Safe Autoclave Operations The purpose of this document is to provide standard operating procedures for the safe use of autoclaves. Autoclaving
More informationLIQUID PENETRANTS USER S MANUAL in accordance to specifications: EN 571, ASTME 1417, AMS 2644, MIL, ASME, DIN, UNI, BS, AFNOR, etc..
LIQUID PENETRANTS USER S MANUAL in accordance to specifications: EN 571, ASTME 1417, AMS 2644, MIL, ASME, DIN, UNI, BS, AFNOR, etc.. The liquid penetrant examination method is an effective means for detecting
More informationATRONA Test Labs, Inc Zenith Parkway, Loves Park, IL Atif Ott Odeh Phone:
SCOPE OF ACCREDITATION TO ISO/IEC 17025:2005 ATRONA Test Labs, Inc. 5271 Zenith Parkway, Loves Park, IL 61111 Atif Ott Odeh Phone: 815-229-8620 TESTING Valid to: March 29, 2017 Certificate Number: AT-1119
More informationASBESTOS SCIENCE TECHNOLOGIES, INC.
ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - astinc17@yahoo.com Report for Trinity Valley Elem. School Willow Creek, Ca. Mold Report - Rooms 12 through
More informationSECTION HVAC GRAVITY VENTILATORS
SECTION 23 37 23 HVAC GRAVITY VENTILATORS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationNTS Contamination Control during Product Creation Process (PCP)
NTS Contamination Control during Product Creation Process (PCP) 1. Introduction 2. NTS Group 3. Cleanliness Outline Marcel Kouters NTS Group, Systems Development 4. Product Challenges 5. Future challenges
More informationBaxa Corporation. Technical Paper. Environmental Controls for Sterile Compounding
Baxa Corporation Environmental Controls for Sterile Compounding Technical Paper A guidance document on developing sterile preparation areas to meet the USP requirements for low and medium risk compounded
More informationSECTION INDOOR AIR QUALITY MANAGEMENT PLAN. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 018119 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationDISTRIBUTOR CATALOG
DISTRIBUTOR CATALOG 763-576-9090 Table of Contents Custom Labeled Spring Water.............................. pg 3 Multi-purpose Applicator Squeegee........................ pg 4 3-7/8 Round Sandstone Coaster..........................
More informationANSI-ASQ National Accreditation Board/ACLASS
ANSI-ASQ National Accreditation Board/ACLASS SCOPE OF ACCREDITATION TO ISO/IEC 17025:2005 ATRONA Test Labs, Inc. 5271 Zenith Parkway, Loves Park, IL 61111 Atif Ott Odeh Phone: 815-229-8620 TESTING Valid
More informationMaterial and Process. Specification
s 146-67- 1 of 7 Document By: Title Name 1. Purpose 1.1 This document defines approved revision levels of Material and Process specifications used by Onboard Systems. This list is for supplier reference
More informationARCHITECTURAL WALL PANELS APPLIED OVER A SHEATHED STUDWALL BY MEANS OF A FIELD ASSEMBLED RAINSCREEN SYSTEM
RAINSCREEN (H&J) SYSTEM INSTALLATION DATA & DETAILS Omnis Panels, Inc. Architectural Building Panels 22 East Chicago Avenue Suite 210 Naperville, Illinois 60540 (800) 450-6099 (630) 355-4040 Fax: (630)
More informationARCHITECTURAL WALL PANELS APPLIED OVER A SHEATHED STUDWALL BY MEANS OF A FIELD ASSEMBLED RAINSCREEN SYSTEM
RAINSCREEN (H&J) SYSTEM INSTALLATION DATA & DETAILS Omnis Panels, Inc. Architectural Building Panels 22 East Chicago Avenue Suite 210 Naperville, Illinois 60540 (800) 450-6099 (630) 355-4040 Fax: (630)
More informationMILITARY SPECIFICATION WELDING, ARC AND GAS; FOR FABRICATING GROUND EQUIPMENT FOR ROCKETS AND GUIDED MISSILES
INCH-POUND 30 June 1992 SUPERSEDING MIL-W-47091 (MI) 24 May 1974 MILITARY SPECIFICATION WELDING, ARC AND GAS; FOR FABRICATING GROUND EQUIPMENT FOR ROCKETS AND GUIDED MISSILES This specification is approved
More informationDFE... The Evolution in Filter Element Multi-Pass Development Testing Hy-Pro s Competitive Advantage
... The Evolution in Filter Element Multi-Pass Development Testing Hy-Pro s Competitive Advantage Fluxa Filtri S.p.A. V.le A.De Gasperi, 88/B - 217 Mazzo di Rho (MI) Italy Tel. +39 2.93959.1 (15 linee)
More informationDr. Sheelpriya walde Professor Gurunanak college of pharmacy, Nagpur
Dr. Sheelpriya walde Professor Gurunanak college of pharmacy, Nagpur GMP ( Adopted in 1975 ) In India Good manufacturing practices are the practices required in order to conform to guidelines recommended
More informationEquipment Design Consideration for Cleaning & Cleaning Validation
Equipment Design Consideration for Cleaning & Cleaning Validation Gamal Amer, Ph. D. Principal Premier Compliance Services, Inc. All rights reserved. Do not copy without permission. 1 Cleaning and Cleaning
More informationThe Impact of Spare Parts. Performance
The Impact of Spare Parts Design and Manufacturing on ACQUITY UPLC System Performance High quality spare parts ensure that your ACQUITY UPLC System runs optimally, protecting your investment in state-of-the-art
More informationForm 9: Infection Control Preventive Measures Level 4
Form 9: Infection Control This form is filled out by the construction planning team or designated person(s) to identify the required preventive measures for the activity described in Form 1 Infection Control
More informationSection PANEL SIGNAGE
Section 10 14 23 PANEL SIGNAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including FDOT DIVISION I GENERAL REQUIREMENTS & COVENANTS Specification Sections,
More information1. Cast-in-place concrete is specified in Section
SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record
More informationLaboratory Demonstration of Radiological Decontamination Using Radpro
ABSTRACT Laboratory Demonstration of Radiological Decontamination Using Radpro P. Lear, R. Greene, J. Isham Shaw Environmental and Infrastructure, Inc. 304 Directors Drive, Knoxville, TN 37923 USA R. Martin,
More informationSargent Controls & Aerospace
WELDING 1. Are welders certified as required? Verify spec/code limitations regarding qualification [welding positions, types and thicknesses of base and filler metals, weld process - GTA, MIG, SMA, etc.]
More informationInitial Reliability Requirements
Summary Initial Reliability Requirements Part, Process or Characteristic Major Minor Raw Material 92 90 Machined Parts (General Features) 97 92 Sheet metal fabrication 92 90 Composite Parts 97 90 Fastener
More informationUNISTRUT CORPORATION GENERAL NOTES 1. THIS UNISTRUT SUPPORT SYSTEM IS DESIGNED TO SUPPORT A MAXIMUM UNIFORM LOAD OF PSF.
1. THIS SUPPORT SYSTEM IS DESIGNED TO 4. ALL CHANNEL & FITTINGS TO HAVE STANDARD 1. THIS SUPPORT SYSTEM IS DESIGNED TO 4. ALL CHANNEL & FITTINGS TO HAVE STANDARD 1. THIS SUPPORT SYSTEM IS DESIGNED TO 4.
More informationSECTION (10705) EXTERIOR SUN CONTROL DEVICES
10 71 13 SECTION (10705) EXTERIOR SUN CONTROL DEVICES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationD1 4426, Approved Process Sources. Purchase Order Flow Down Requirements
D1 4426, Approved Process Sources Purchase Order Flow Down Requirements Common Commodity Requirements Unique Commodity Additional Requirements Chemical Processes Heat Treat Materials Testing Laboratories
More informationHigh Reliability Optoelectronic Devices
High Reliability Optoelectronic Devices Sensors and Specialist Components BI Technologies and OPTEK Technology Hi-Rel products, Hi-Rel service from OPTEK Technology TT Electronics OPTEK Technology solves
More informationHospital Pharmacy Isolator Solutions for USP <797> Compliance from Esco
Hospital Pharmacy Isolator Solutions for USP Compliance from Esco Contents 1. Introduction 2. Clean Air Devices and Isolators 3. Cytotoxic Exposure 4. Esco Pharmacy Isolator (Positive Pressure Model)
More informationTECH 50 SPECIFICATION
for ELECTROPOLISHED TUBING AND FITTINGS FOR USE IN HIGH PURITY PIPING SYSTEMS Current Issue: Pages not including Title Page 3 Mike Pellegrini Division VP Site Manager Jim Bundschuh Engineering and QA Manager
More informationNuclear Service Valves
GE Energy Consolidated* Pressure Relief Valves Nuclear Service Valves Pressure relief solutions for the nuclear industry Safety Relief Valves Safety Valves Advanced Technology and Equipment Manufactured
More informationC. Miscellaneous Metal Fabricators are specified elsewhere in Division 5.
SECTION 05 1200 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.01 SUMMARY A. Extent of structural steel work is shown on drawings, including schedules, notes and details to show size and location of members,
More informationCleanSafe 686 Aqueous Cleaner Precision Cleaning Product Presentation
CleanSafe 686 Aqueous Cleaner Precision Cleaning Product Presentation Petroferm Inc. Manufacturer and global supplier of cleaning products Founded in 1981 Gurnee, Illinois, USA Part of $450M chemical group
More informationSECTION ALUMINUM WINDOWS
SECTION 08520 ALUMINUM WINDOWS 1. PART 1 GENERAL 1.1 WORK INCLUDED: 1. Provide labor, material, equipment and services to furnish and install aluminum windows shown on drawings and specified herein. Window
More informationSPECIFICATIONS Section Gable Walkway Covers
Part 1: General 1.1 Related Documents SPECIFICATIONS Section 107303 Gable Walkway Covers A. The requirements of Division 1 specifications shall apply to work specified in the section. 1.2 Engineering Design
More informationQuality Control and Quality Assurance for Installation of Steel Deck
s American National standards institute/ steel deck institute QA/QC - 2011 Standard for Quality Control and Quality Assurance for Installation of Steel Deck copyright 2012 steel deck institute 1. General
More informationIn general, the management plan development process consisted of:
NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department
More informationCleaning Validation. Olivier Gautier
Cleaning Validation Olivier Gautier Cleaning Validation -" What is it? Clean Establish a documented, effective cleaning protocol Clean using what? How often? What is clean? Validate Prove that you cleaned
More informationCLEANING AND INSPECTION PROCEDURES FOR BALLISTIC MISSILE SYSTEMS
5 S =P 1980 T. 0. 4C-1-1 1 TECHNICAL MANUAL CLEANLINESS STANDARDS CLEANING AND INSPECTION PROCEDURES FOR BALLISTIC MISSILE SYSTEMS F41608-80-D-A00 6 PUSLI$HEO UNOER AUTHORITY OF THE / ECRETARY OF THE AIR
More informationMichigan Small Animal Imaging Resource In Vivo Cellular and Molecular Imaging Center. Department of Radiology. University of Michigan
Date: August 29, 2013 Version: 8 Page: 1 of 6 A. PURPOSE: Many animal use protocols entail the administration or exposure of the research animals to potentially hazardous chemical agents or pathogens.
More informationAsbestos Abatement Standard Procedures Indoor Environment Group, Inc.
The following work procedures are specified on all full containment asbestos abatement projects that we design. A. Preliminary Air Sampling: Many buildings contain background fiber levels prior to, or
More informationSPECIFICATIONS Section Cantilevered Walkway Cover
Part 1: General 1.1 Related Documents SPECIFICATIONS Section 107301 Cantilevered Walkway Cover A. The requirements of Division 1 specifications shall apply to work specified in the section. 1.2 Engineering
More informationMechanical Fabrication Department s Support of B-Factory Operations
Mechanical Fabrication Department s Support of B-Factory Operations Presentation by Karen Fant 4/26/06 1 MFD featured because: Department provides a broad range of services Accelerator Systems Division
More informationPharmacy Quality Assurance Self-Assessment (Non -Sterile Compounding Hazardous and Non Hazardous)
College of Pharmacists of Manitoba 200 Tache Avenue, Winnipeg, Manitoba R2H 1A7 Phone (204) 233-1411 Fax: (204) 237-3468 E-mail: info@cphm.ca Website: www.cphm.ca Pharmacy Quality Assurance Self-Assessment
More informationcompounding area based on environmental sampling and cleaning product type. Antiseptics and determine the appropriate use of each.
The pharmacist will be able to: 1. Determine a best practice for cleaning their compounding area based on environmental sampling and cleaning product type. 2. Discuss the difference between Disinfectants
More informationCERTIFICATION REPORTS, WHAT DO I NEED TO KNOW?
Pharmacy Compounding Overview and Insanitary Conditions CERTIFICATION REPORTS, WHAT DO I NEED TO KNOW? 1 Introductions CDR Mary McGarry, BS, PharmD, MS, RAC, CPGP CDR Stacey Degarmo, PharmD, BCPS, CPH,
More information