The Increased Recovery Project at the Phu Kham Copper-Gold Operation, Laos PDR. Authors: A Hoyle, D Bennett, and P Walker

Size: px
Start display at page:

Download "The Increased Recovery Project at the Phu Kham Copper-Gold Operation, Laos PDR. Authors: A Hoyle, D Bennett, and P Walker"

Transcription

1 The Increased Recovery Project at the Phu Kham Copper-Gold Operation, Laos PDR Authors: A Hoyle, D Bennett, and P Walker

2 IRP Presentation Summary 1. Phu Kham mineralogy and implications for process design 2. Process development to Grade-recovery improvement studies leading to the IRP 4. IRP design and engineering 5. IRP implementation and results

3 Phu Kham Operation - Laos Nam Ve Phu Nam Wan Pha Lek

4 Geology with Process Design Implications Extreme variability in rock type, alteration, weathering, and mineralogy across short distances Wide range of copper minerals native, oxides, secondary/arsenic sulphides in transition/supergene zones and bornite/chalcopyrite in primary zones Areas of high sphalerite, galena, pyrophyllite and kaolinite Wide chalcopyrite particle size range, insensitive to grind size Up to 25 times more pyrite than copper sulphide mineral in feed, and secondary copper mineral intergrowth with pyrite

5 Original Process Design Implications Bulk sulphide rougher flotation high recoveries in laboratory but concentrate specifications not achieved even for transition and supergene ore types Selective rougher flotation for pyrite depression resulted in poor recovery of slow-floating copper minerals and composites Original concentrator was a capital efficient, low-risk compromise

6 Original 12Mtpa Process Design 2008 GYRATORY CRUSHER SAG MILL MILL CYCLONES COARSE ORE STOCKPILE BALL MILL ROUGHER FLOTATION CELLS ROUGHER CYCLONES 1st CLEANER FLOTATION CELLS TAILINGS DAM ISAMILL 2nd CLEANER FLOTATION CELLS THICKENER 3rd CLEANER FLOTATION CELLS TANK FILTER STOCKPILE

7 Process Development - Incremental 2009 Conversion of conditioning tanks to flotation cells in roughers and 1 st cleaners FloatForce mechanisms installation in roughers, completed Tenth 200m³ rougher cell installed Jameson Cell installed in cleaner scalping duty

8 Process Development 2012 Upgrade MILL CYCLONES GYRATORY SAG MILL No.1 BALL MILL COARSE ORE STOCKPILE NEW MILL CYCLONES NEW No.2 BALL MILL NEW CYCLONE OVERFLOW TANK NEW ROUGHER FLOTATION CELLS ROUGHER FLOTATION CELLS ROUGHER CYCLONES 1st CLEANER FLOTATION CELLS TAILINGS DAM PROCESS WATER ISAMILL 2nd CLEANER FLOTATION CELLS JAMESON CELL Designed to maintain copper production with decreasing ore grade expected from 2013 NEW 3rd CLEANER FLOTATION CELLS Upgrade design to nominal 16Mtpa throughput, maximum 18Mtpa Major bottlenecks eliminated in ball milling, rougher flotation and 2 nd cleaner capacities THICKENER TANK FILTER STOCKPILE

9 Copper and Gold Recovery - Stalled Increased metal production capacity is not the same as increased recovery 100.0% 90.0% 80.0% 70.0% Recovery % 60.0% 50.0% 40.0% 30.0% 20.0% 10.0% 0.0% Copper Gold

10 Grade-Recovery Improvement Projects Commenced study in 2010 with process development work on Phu Kham tailings streams to increase copper recovery Monthly plant composites mineralogy data collected since 2008 provided critical information on copper deportment in tailings Reviewed geology and petrology information for clues on gold occurrence ADIS, diagnostic leaching, and laser ablation work conducted on plant samples for gold deportment in tailings

11 Copper Deportment in Tailings 45.0% % Copper Sulphide Loss by Size and Class 40.0% 35.0% 30.0% 25.0% 20.0% 15.0% 10.0% 5.0% 0.0% >106µm <106>53µm <53>33µm <33>16µm <16>12µm <12µm Liberated Copper Sulphide Binary with Pyrite Binary with Non-Sulphide Gangue Multiphase

12 Gold Deportment in Tailings Gold Loss to Tailings by Association Class Liberated Au Au-Copper Sulphide Au-Pyrite 30% 0% 90% Gn Ma He Py Py Cp Gn Au Area:192µm 2 Py Area:76µm 2 Au Py Gn Cp Area:5787µm 2 Au Py Unliberated: Locked in pyrite Composite with coarse pyrite Liberated: Too fat to float Fine gold due to high lime environment for pyrite depression Gn Area:38µm 2 Au

13 The Pilot Plant Tailings retreatment process developed by 2011 could increase copper recovery by 15% and gold recovery by 25% with Albion process 1.5tph M20 IsaMill and flotation pilot plant to make Albion leach feed Capital cost update received during pilot for tailings flotation and hydrometallurgical plants a lot higher than previous estimates Change of pilot plant focus to test a less selective rougher flotation concept encouraging results

14 Mineral Processing Alternatives Mainstream Inert Grinding Classification of rougher tailings stream -53µm fraction discharge to final tailings Regrind +53µm fraction to P80 53µm Scavenger flotation, tailings to final tailings, concentrate return to combine with rougher concentrate Particle size based mass balance, very predictable Approximately 7% additional copper and gold recovery achieved in bench tests Very high grinding energy requirement and capital cost Less Selective Flotation Become less selective in rougher flotation, increase rougher mass recovery Finer regrind due to lower quality composites in rougher concentrate Increase first cleaner capacity Mineralogy and liberation based mass balance, difficult to predict Risk of flooding cleaning with pyrite Approximately 7% additional copper and gold recovery achieved in bench and pilot tests Low capital and operating costs

15 Less Selective Flotation Work at bench and pilot scale indicated that lean Cs-NSG composites could be recovered into rougher concentrate, with finer regrind to achieve 80%Cs liberation Unlike other options, less selective flotation option was not a tailings retreatment process no risk of destroying project value with future plant improvements Full-scale plant trial conducted to test concept: Run plant at 50% of normal rate Increase rougher mass recovery from 10% to 20% of feed mass Maximise regrind power to get as fine a product as possible

16 Full Plant Trial Results Trial 1-15 January 2012 Trial 2-27 January 2012 Preliminary Trails Baseline LSF Difference Baseline LSF Difference Rougher Recovery (%) Overall Copper Recovery (%) Overall Gold Recovery (%) Trial results confirmed that the less selective flotation concept worked at full scale in 200m³ rougher cells Trail mineralogy samples showed a decrease in +53µm Cs-NSG composite quality in rougher tailings compared to baseline samples

17 The Decision Results supported a $65M investment case approved February 2012 economics compelling even at +4% copper and gold recovery Less selective flotation re-branded as the Increased Recovery Project Long lead M10000 IsaMill (ex works 10 months) ordered immediately Critical design criteria confirmed: Regrind product size at 20µm to achieve 80% copper sulphide liberation Concentrate filtration rate with fine regrind too slow, another filter required Rougher mass recovery

18 Rougher Mass Recovery How Much? Flotation data indicated rougher copper recovery reached maximum at 20-25% mass recovery for most ore types 100 Rougher Copper Recovery (%) O r i g i n a l D e s i g n I R P D e s i g n tph 500 tph Rougher Mass Recovery (% of Rougher Feed) Overall Ore Types Chalcocite Transition Very High Pyrite High Pyrite Chalcocite Desseminated Chalcocite - Chalcopyrite Chalcopyrite Disseminated Chalcopyrite Primary

19 IRP Design and Engineering Compression of schedule to start construction in Q before Phu Kham Upgrade project (completed September 2012) resources demobilised Key issues in design for IRP: Cleaner circuit mass balance with lower grade rougher concentrate Integration with existing plant, already very crowded Modular design required with minimal impact on operating plant during construction Fix all niggling issues with existing plant, mainly slurry pumping

20 IRP Progress GR Engineering Services selected for FEED and EP FEED commenced March 2012 FEED completed May 2012, capital cost reduced to $45M EP complete September 2012 Phu Kham Upgrade construction completed August 2012 IRP construction commenced August 2012 All major equipment on site by February 2013 Construction complete and commissioning complete April 2013 Ramp-up underway May 2013, completed in July 2013 Final cost of project $35M

21 IRP Flowsheet GYRATORY CRUSHER SAG MILL No.1 BALL MILL No.1 MILL CYCLONES COARSE ORE STOCKPILE No.2 MILL CYCLONES No.2 BALL MILL CYCLONE OVERFLOW TANK ROUGHER FLOTATION CELLS ROUGHER FLOTATION CELLS NEW ROUGHER CYCLONES 1st CLEANER FLOTATION CELLS TAILINGS DAM PROCESS WATER ISAMILL No.1 NEW 1st CLEANER FLOTATION CELLS THICKENER NEW ISAMILL No.2 JAMESON CELL 2nd CLEANER FLOTATION CELLS 3rd CLEANER FLOTATION CELLS NEW FILTER SURGE TANKS FILTER STOCKPILES

22 What Went Wrong Regrind cyclone underflow splitter box bias, new IsaMill low flow and high temperatures not picked up - burned out the shell liner Faulty density gauge settings on new IsaMill feed high density nearly burned out the spare liner Existing pumps upgraded or swapped to new duties no-one had thought to check VFD settings or even check wet ends

23 What Went Wrong Assumption that process was simple just pull the roughers harder! Fill up the cleaning circuit! 12.0 IRP Immediate positive impact on rougher copper and gold recovery, but cleaner copper recovery worse no net copper recovery increase 10.0 CUSUM Copper Final Recovery % No Net Recovery Increase Shift Number

24 What Went Right The design objective was met.

25 What Went Right Copper recovery up by 6%, gold by over 10% during lower head grades and declining ore quality period, less than 1 year payback 100.0% 90.0% IRP Reconciled Recovery % 80.0% 70.0% 60.0% 50.0% 40.0% 30.0% 20.0% Copper Gold

26 IRP Summary 1. Understand the geology and process development history 2. Collection of monthly mineralogy, mineral association, and mineral liberation data since 2008 was critical 3. Focused test programs determined the greatest opportunities 4. Process concept proven at bench, pilot, and full-scale 5. Lowest risk and highest value option, easy to get support for development 6. Project outcomes certain

27 Thank You

Development of an Innovative Copper Flowsheet at Phu Kham. M F Young and I Crnkovic

Development of an Innovative Copper Flowsheet at Phu Kham. M F Young and I Crnkovic Development of an Innovative Copper Flowsheet at Phu Kham M F Young and I Crnkovic Phu Kham Location in Laos Phu Kham Plant Layout Plant Layout showing Primary Grinding Rougher Flotation IsaMill Regrinding

More information

Ivanhoe Mines giant Kamoa copper discovery in the DRC a metallurgical perspective

Ivanhoe Mines giant Kamoa copper discovery in the DRC a metallurgical perspective http://dx.doi.org/10.17159/2411-9717/2016/v116n6a9 Ivanhoe Mines giant Kamoa copper discovery in the DRC a metallurgical perspective by V.L. Nkuna*, T. Naidoo*, and S.R. Amos* Ivanhoe Mines Kamoa copper

More information

Evaluation of Grade Engineering using Enterprise Optimization. Michael Scott, Nick Redwood

Evaluation of Grade Engineering using Enterprise Optimization. Michael Scott, Nick Redwood Evaluation of Grade Engineering using Enterprise Optimization Michael Scott, Nick Redwood Who we are Not for Profit Research Organization Site implementation of stepchange innovation Grade Engineering

More information

PRE-FEASIBILITY METALLURGICAL TESTING GOLIATH GOLD PROJECT TREASURY METALS INCORPORATED KM2906. June 1, 2011

PRE-FEASIBILITY METALLURGICAL TESTING GOLIATH GOLD PROJECT TREASURY METALS INCORPORATED KM2906. June 1, 2011 PRE-FEASIBILITY METALLURGICAL TESTING GOLIATH GOLD PROJECT TREASURY METALS INCORPORATED KM2906 June 1, 2011 G&T METALLURGICAL SERVICES LTD. 2957 Bowers Place, Kamloops, B.C. Canada V1S 1W5 E-mail: info@gtmet.com,

More information

From base metals and back IsaMills and their advantages in African base metal operations

From base metals and back IsaMills and their advantages in African base metal operations The Southern African Institute of Mining and Metallurgy Base Metals Conference 2013 H. de Waal, K. Barns, and J. Monama From base metals and back IsaMills and their advantages in African base metal operations

More information

IsaMill Design Improvements and Operational Performance at Anglo Platinum

IsaMill Design Improvements and Operational Performance at Anglo Platinum IsaMill Design Improvements and Operational Performance at Anglo Platinum C Rule 1 and H de Waal 2 1. Head of Concentrators Technology, Anglo American Platinum, 55 Marshall Street, Marshall Town, Johannesburg,

More information

The Albion Process at the GPM Gold Project The success of a technology

The Albion Process at the GPM Gold Project The success of a technology The Albion Process at the GPM Gold Project The success of a technology Paul Voigt, Glencore Technology (paul.voigt@glencore.com.au) David Walker, Core Resources (dwalker@coreresources.com.au) CIM Conference

More information

New project in Russia with semiautogenous mill selected according to the results of SAGDesign testing

New project in Russia with semiautogenous mill selected according to the results of SAGDesign testing New project in Russia with semiautogenous mill selected according to the results of SAGDesign testing ABSTRACT 507 Yury V. Kulikov, Arkady Y. Senchenko* John Starkey TOMS institute, Ltd., Russia TOMS institute,

More information

FEASIBILITY METALLURGICAL TESTING GOLIATH GOLD PROJECT TREASURY METALS INCORPORATED KM3406. September 4, 2012

FEASIBILITY METALLURGICAL TESTING GOLIATH GOLD PROJECT TREASURY METALS INCORPORATED KM3406. September 4, 2012 FEASIBILITY METALLURGICAL TESTING GOLIATH GOLD PROJECT TREASURY METALS INCORPORATED KM346 September 4, 212 ISO 91:28 Certificate No. FS 6317 ALS Metallurgy G&T METALLURGICAL SERVICES ADDRESS 2957 Bowers

More information

Sustainable Mining through Continuous Operational Cost Control and Decrease of It Over the Mine Life Saso Kitanoski Director Sales and Service CEE

Sustainable Mining through Continuous Operational Cost Control and Decrease of It Over the Mine Life Saso Kitanoski Director Sales and Service CEE Sustainable Mining through Continuous Operational Cost Control and Decrease of It Over the Mine Life Saso Kitanoski Director Sales and Service CEE Making the big difference to our customers Mining Industry

More information

The TMAC Resources Inc. Hope Bay Project An Innovative Approach. Gerhard Bezuidenhout

The TMAC Resources Inc. Hope Bay Project An Innovative Approach. Gerhard Bezuidenhout The TMAC Resources Inc. Hope Bay Project An Innovative Approach Gerhard Bezuidenhout Gekko s mission Global Footprint Global & Gold/Silver Focused - increasing coal/polymetallic focus Total 150 staff Team

More information

Recent Studies on the Application of Fluidised-Bed Flotation for Treating Sulphide Ores at a Coarser Grind

Recent Studies on the Application of Fluidised-Bed Flotation for Treating Sulphide Ores at a Coarser Grind Recent Studies on the Application of Fluidised-Bed Flotation for Treating Sulphide Ores at a Coarser Grind Massimiliano Zanin 1, Bellson Awatey 1 and Jaisen Kohmuench 2 1. University of South Australia

More information

Improvements in bi-metal production at the Brunswick plant, Costerfield.

Improvements in bi-metal production at the Brunswick plant, Costerfield. 1 Improvements in bi-metal production at the Brunswick plant, Costerfield. D Buchanan 1, V Cullinan 2 1. MAusIMM, Processing Plant Manager, Mandalay Resources Costerfield Operations, 1024 Heathcote Nagambie

More information

Ultra fine grinding of intermediate flotation concentrates in the PGM industry at the Pt Mile operation on Anglo Platinum tailings

Ultra fine grinding of intermediate flotation concentrates in the PGM industry at the Pt Mile operation on Anglo Platinum tailings text:text 9/26/08 1:57 PM Page 37 RULE, C.M., KNOPJES, L., and ATKINSON, R.J. Ultra fine grinding of intermediate flotation concentrates in the PGM industry at the Pt Mile operation on Anglo Platinum tailings.

More information

Eastern Finland Office C/MT/2011/13 Outokumpu. Beneficiation Tests. Taivaljärvi Ore

Eastern Finland Office C/MT/2011/13 Outokumpu. Beneficiation Tests. Taivaljärvi Ore Eastern Finland Office C/MT/2011/13 Outokumpu Beneficiation Tests on Taivaljärvi Ore C/MT/2011/13 GEOLOGICAL SURVEY OF FINLAND DOCUMENTATION PAGE Date / Rec. no. 2 nd May 2011 C/MT/2011/13 Authors Satu

More information

Flowsheet development for the Sukari gold project in Egypt

Flowsheet development for the Sukari gold project in Egypt RHODES, M. and PENNA, F. Flowsheet development for the Sukari gold project in Egypt. World Gold Conference 2009, The Southern African Institute of Mining and Metallurgy, 2009. Flowsheet development for

More information

Resource Efficient Mining Processes of Tomorrow

Resource Efficient Mining Processes of Tomorrow Metso Process Technology & Innovation (PTI) Resource Efficient Mining Processes of Tomorrow R&D Project Authors: K Duffy W Valery A Jankovic P Holtham www.metso.com General PTI presentation 2014 2015 A

More information

Sukari revise Gold production in Egypt

Sukari revise Gold production in Egypt Sukari revise Gold production in Egypt 1 2 Sukari Gold mines is located in the eastern desert of Egypt, 800 Km south of Cairo and about 25 Km west of The Red sea town Marsa Alam. Sukari gold is well located

More information

Effects of Process Parameters on Selective Flotation of Lead-Zinc Ore

Effects of Process Parameters on Selective Flotation of Lead-Zinc Ore Effects of Process Parameters on Selective Flotation of Lead-Zinc Ore Abstract R. Singh, B. Banerjee and J.P. Srivastava Mineral Processing Division, National Metallurgical Laboratory, Jamshedpur - 831

More information

Magnetic Conditioning of Flotation Feed to Increase Recovery of Fine Value Minerals at Boliden s Garpenberg Concentrator

Magnetic Conditioning of Flotation Feed to Increase Recovery of Fine Value Minerals at Boliden s Garpenberg Concentrator Magnetic Conditioning of Flotation Feed to Increase Recovery of Fine Value Minerals at Boliden s Garpenberg Concentrator Hamid-Reza Manouchehri (Ph.D.), Sandvik Mining, Sweden Hassna Aitahmed-Ali & Stellan

More information

First Chalcopyrite Copper Concentrate Leaching using Albion Process TM Technology. Glenn Stieper

First Chalcopyrite Copper Concentrate Leaching using Albion Process TM Technology. Glenn Stieper First Chalcopyrite Copper Concentrate Leaching using Albion Process TM Technology Glenn Stieper BACKGROUND Glencore has an operating plant, Sable Zinc, in Zambia that was being un-utilised due to the lack

More information

Kanowna Belle Pre-Oxidation Project

Kanowna Belle Pre-Oxidation Project Kanowna Belle Pre-Oxidation Project Kanowna Belle Processing Kanowna Belle treats both free milling and refractory ores with the free milling material being sourced predominantly from the East Kundana

More information

Mintek, a national resource of minerals processing expertise for platinum ores

Mintek, a national resource of minerals processing expertise for platinum ores DEEPLAUL, V and BRYSON, M. Mintek, a national resource of minerals processing expertise for platinum ores. International Platinum Conference Platinum Adding Value, The South African Institute of Mining

More information

The benefit of separate milling of silicate and chromite particles for chromite-rich UG-2 ores

The benefit of separate milling of silicate and chromite particles for chromite-rich UG-2 ores The benefit of separate milling of silicate and chromite particles for chromite-rich UG-2 ores L. Maharaj *, B.K. Loveday, J. Pocock School of Chemical Engineering, University of KwaZulu-Natal, Durban,

More information

SAG Page 1. Page 2

SAG Page 1. Page 2 Page 1 Page 2 SAG 2 0 0 6 DEPARTMENT OF MINING ENGINEERING UNIVERSITY OF BRITISH COLUMBIA Vancouver, B. C., Canada grade Cannington resource is classified at 42 million tonnes, 551ppm silver, 12.1% lead

More information

The implications of ore hardness variability on comminution circuit energy efficiency (and some other thoughts)

The implications of ore hardness variability on comminution circuit energy efficiency (and some other thoughts) The implications of ore hardness variability on comminution circuit energy efficiency (and some other thoughts) Peter Amelunxen Thursday 6 December 2012 Capital (Millions) Current Cu/Mo Mill Design (a

More information

Increasing the Energy Efficiency of Processing

Increasing the Energy Efficiency of Processing Increasing the Energy Efficiency of Processing Joe Pease General Manager Xstrata Technology August 2007 1 Can we double the energy efficiency of grinding? Diminishing returns on research? Radical new technologies?

More information

Figure 1: Schematic block-diagram of the project test work

Figure 1: Schematic block-diagram of the project test work METHODOLOGY A brief schematic diagram for the project test work is presented in Figure 1 and comprises the following main steps: sample collection, sample preparation, chemical characterization, grinding

More information

The importance of middlings in the beneficiation technology of Polish copper ore and new possibilities of their processing

The importance of middlings in the beneficiation technology of Polish copper ore and new possibilities of their processing The importance of middlings in the beneficiation technology of Polish copper ore and new possibilities of their processing Bozena Skorupska 1,*, Andrzej Wieniewski 1, and Norbert Kubacz 1 1 Institute of

More information

From Tribulation to Triumph Flotation Improvements at the New Lac des Iles Concentrator

From Tribulation to Triumph Flotation Improvements at the New Lac des Iles Concentrator SGS MINERALS SERVICES TECHNICAL PAPER 2002-10 2002 From Tribulation to Triumph Flotation Improvements at the New Lac des Iles Concentrator Chris Martin - SGS; Tom Ohrling and Tom Olsen - North American

More information

TECHNOLOGICAL POSSIBILITIES FOR PULP DENSITY ALTERATION AT ELATZITE FLOTATION MILL

TECHNOLOGICAL POSSIBILITIES FOR PULP DENSITY ALTERATION AT ELATZITE FLOTATION MILL Annual of the University of Mining and Geology "t. Ivan Rilski" vol. 44-45, part II, Mining and Mineral Processing, ofia, 2002, pp. 61-65 TECHNOLOGICAL POIBILITIE FOR PULP DENITY ALTERATION AT ELATZITE

More information

METAL MINING TECHNOLOGY IN JAPAN

METAL MINING TECHNOLOGY IN JAPAN METALMINING TECHNOLOGY IN JAPAN Foreword The Ministry of International Trade and Industry(MITI),the Government of Japan, decided to make Mining Expert Training materials for technical cooperation program

More information

PYTHON UNDERGROUND PROCESSING PLANT CRITICAL DESIGN

PYTHON UNDERGROUND PROCESSING PLANT CRITICAL DESIGN PYTHON UNDERGROUND PROCESSING PLANT CRITICAL DESIGN S Gray 1 ABSTRACT The use of continuous gravity recovery in combination with a controlled breakage fine crushing and screening system followed by flash

More information

DEVELOPMENTS IN GRAVITY CONCENTRATION CIRCUIT IN ASHANTI GOLDFIELDS COMPANY, OBUASI

DEVELOPMENTS IN GRAVITY CONCENTRATION CIRCUIT IN ASHANTI GOLDFIELDS COMPANY, OBUASI DEVELOPMENTS IN GRAVITY CONCENTRATION CIRCUIT IN ASHANTI GOLDFIELDS COMPANY, OBUASI By: George M. Potter 1, Samuel Oti-Atakorah 2, and Casper Dzomeku 3 ABSTRACT The Ashanti ore deposit at Obuasi can be

More information

Environmental Monitoring Results Summary

Environmental Monitoring Results Summary Environmental Monitoring Results Summary Quarter 1 2016 Name of Mine: CSA Mine Environment Protection Licence: EPL 1864 Licensee Name and Operator: Cobar Management Pty Ltd Licensee Address: PO Box 31,

More information

The separation of pentlandite from chalcopyrite, pyrrhotite and gangue in nickel projects throughout the world

The separation of pentlandite from chalcopyrite, pyrrhotite and gangue in nickel projects throughout the world The separation of pentlandite from chalcopyrite, pyrrhotite and gangue in nickel projects throughout the world V. Lawson, G. Hill, L. Kormos, G. Marrs AusIMM Mill Operators Conference Sep 1-3 2014 Townsville

More information

High pressure grinding rolls applications for the platinum industry

High pressure grinding rolls applications for the platinum industry KNECHT, J. and PATZELT, N. High pressure grinding rolls applications for the platinum industry. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy,

More information

Fine grinding Developments in ceramic media technology and resulting improved plant performance at Anglo Platinum

Fine grinding Developments in ceramic media technology and resulting improved plant performance at Anglo Platinum Paper 83_Rule:Paper 83_Rule 9/26/08 1:59 PM Page 53 RULE, C.M., KNOPJES, L., CLERMONT, B. and PHILIPPE, C. Fine grinding developments in ceramic media technology and resulting improved plant performance

More information

GRAVITY CONCENTRATION AND FLOTATION OF SPANISH MOUNTAIN COMPOSITES

GRAVITY CONCENTRATION AND FLOTATION OF SPANISH MOUNTAIN COMPOSITES GRAVITY CONCENTRATION AND FLOTATION OF SPANISH MOUNTAIN COMPOSITES SEPTEMBER 2010 2 1.0 SUMMARY 3 Gravity concentration and flotation testwork has been carried out on three composite samples from the Spanish

More information

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING 8 October 2015 ASX Release ASX Code: CXX Highlights PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING Tremont has paid the final tranche of US$5 million Integrated pilot plant testing confirms

More information

InLine Pressure Jig Pre-Concentration Plant at the Pirquitas Mine

InLine Pressure Jig Pre-Concentration Plant at the Pirquitas Mine 1 InLine Pressure Jig Pre-Concentration Plant at the Pirquitas Mine A H Gray 1, G Delemontex 2, N Grigg 3 and T Yeomans 4 1. A H (Sandy) Gray Technical Director Gekko Systems Pty Ltd. 321 Learmonth Road,

More information

For personal use only

For personal use only Positive Scoping Study: Aphrodite Gold Project 9 February 2012 Company Announcements Office Australian Securities Exchange Limited Positive Scoping Study for Aphrodite Gold Project Potential to Become

More information

Relationship between ore mineralogy and copper recovery across different processing circuits at Kansanshi mine

Relationship between ore mineralogy and copper recovery across different processing circuits at Kansanshi mine http://dx.doi.org/10.17159/2411-9717/2018/v118n11a5 Relationship between ore mineralogy and copper recovery across different processing circuits at Kansanshi mine by L. Little, Q. Mclennan, A. Prinsloo,

More information

TOWER FINE MILLING EXPERIENCE AT MOUNT ISA MINES

TOWER FINE MILLING EXPERIENCE AT MOUNT ISA MINES TOWER FINE MILLING EXPERIENCE AT MOUNT ISA MINES Aleksandar Jankovic, Michael Young, David Hinds Mount Isa Mines Ltd Mount Isa, Queensland 4825 Abstract -. Over the last ten years Tower mills were studied

More information

REPORT 1001 MINERAL RESEARCH SERIES

REPORT 1001 MINERAL RESEARCH SERIES LEGISLATIVE REFERENCE LIBRARY Ti~~~1~i1m~~r1111im~11111111111111111111 3 0307 00048 2540 REPORT 1001 MINERAL RESEARCH SERIES INVESTIGATION INTO THE PRODUCTION OF IRON ORE CONCENTRATES WITH LESS THAN 3

More information

Minto Mine. Mill Operations Plan

Minto Mine. Mill Operations Plan Minto Mine Mill Operations Plan 2018-01 Prepared by: Minto Explorations Ltd. Minto Mine January 2018 Minto Explorations Ltd. Minto Mine 2018 Mill Operations Plan Table of Contents 1 Introduction...1 1.1

More information

IMPROVEMENTS IN SAG MILL THROUGHPUT FROM FINER FEED SIZE AT THE NEWMONT AHAFO OPERATION

IMPROVEMENTS IN SAG MILL THROUGHPUT FROM FINER FEED SIZE AT THE NEWMONT AHAFO OPERATION IMPROVEMENTS IN SAG MILL THROUGHPUT FROM FINER FEED SIZE AT THE NEWMONT AHAFO OPERATION *Adrian Dance 1, Sonny Mwansa 2, Walter Valery 2, George Amonoo 3 and Bryon Bisiaux 3 1 SRK Consulting (Canada) Inc

More information

PHOSPHATE PRODUCERS IMPROVE PLANT PERFORMANCE USING C.P.T. INC FLOTATION TECHNOLOGY

PHOSPHATE PRODUCERS IMPROVE PLANT PERFORMANCE USING C.P.T. INC FLOTATION TECHNOLOGY PHOSPHATE PRODUCERS IMPROVE PLANT PERFORMANCE USING C.P.T. INC FLOTATION TECHNOLOGY Harold E. Wyslouzil - P.Eng President Canadian Process Technologies Inc. Vancouver, B.C. CANADA Column flotation cells

More information

COPPER SUPER CONCENTRATE PRODUCTION TECHNOLOGY FOR OPERATING COPPER MOLYBDENUM PROCESSING PLANTS

COPPER SUPER CONCENTRATE PRODUCTION TECHNOLOGY FOR OPERATING COPPER MOLYBDENUM PROCESSING PLANTS UDC 622.765 YU. P. NAZAROV (RIVS Science and Production Association) COPPER SUPER CONCENTRATE PRODUCTION TECHNOLOGY FOR OPERATING COPPER MOLYBDENUM PROCESSING PLANTS YU. P. NAZAROV, Director of Board,

More information

SAVANNAH RESOURCES PLC AIM: SAV. Savannah Resources Plc. Savannah Resources Plc / Index: AIM / Epic: SAV / Sector: Mining RNS 06 February 2017

SAVANNAH RESOURCES PLC AIM: SAV. Savannah Resources Plc. Savannah Resources Plc / Index: AIM / Epic: SAV / Sector: Mining RNS 06 February 2017 Savannah Resources Plc SAVANNAH RESOURCES PLC AIM: SAV Savannah Resources Plc / Index: AIM / Epic: SAV / Sector: Mining RNS 06 February 2017 PROJECT PORTFOLIO MINERAL SANDS MOZAMBIQUE (CONSORTIUM AGREEMENT

More information

NECESSITY DRIVING CHANGE AND IMPROVEMENT TO THE CLEANER CIRCUIT AT LUMWANA COPPER CONCENTRATOR

NECESSITY DRIVING CHANGE AND IMPROVEMENT TO THE CLEANER CIRCUIT AT LUMWANA COPPER CONCENTRATOR NECESSITY DRIVING CHANGE AND IMPROVEMENT TO THE CLEANER CIRCUIT AT LUMWANA COPPER CONCENTRATOR *R. Araya 1, G. Cordingley 2, A. Mwanza 2 and L. Huynh 3 1 Xstrata Technology Canada Level 10-700 West Pender

More information

Development and Implementation of the new 2240 kw (3000 HP) VERTIMILL Grinding Mill for Newcrest

Development and Implementation of the new 2240 kw (3000 HP) VERTIMILL Grinding Mill for Newcrest Development and Implementation of the new 2240 kw (3000 HP) VERTIMILL Grinding Mill for Newcrest Cadia Valley Operations Jonathan Allen and Brian Knorr Presenter: Raul Noriega Previous Scale Up Previous

More information

INTERPRETATION OF FLOTATION DATA FOR THE DESIGN OF PROCESS PLANTS

INTERPRETATION OF FLOTATION DATA FOR THE DESIGN OF PROCESS PLANTS INTERPRETATION OF FLOTATION DATA FOR THE DESIGN OF PROCESS PLANTS Robert C Dunne Group Consulting Metallurgist, Newcrest Mining Ltd, Perth, Western Australia Greg S Lane Principal Process Engineer, GRD

More information

EMC FLOTATION TEST PROCEDURE 2 LABORATORY FLOTATION TEST PROCEDURE FOR MF1 AND MF2 TESTS AND REGRINDING OF CLEANER TAILINGS

EMC FLOTATION TEST PROCEDURE 2 LABORATORY FLOTATION TEST PROCEDURE FOR MF1 AND MF2 TESTS AND REGRINDING OF CLEANER TAILINGS EMC FLOTATION TEST PROCEDURE 2 LABORATORY FLOTATION TEST PROCEDURE FOR MF1 AND MF2 TESTS AND REGRINDING OF CLEANER TAILINGS SYNOPSIS Performing a flotation rate test characterises the ore. The results

More information

Copyright in this document is wholly reserved to Ausenco Services Pty Ltd.

Copyright in this document is wholly reserved to Ausenco Services Pty Ltd. DISCLAIMER This document is for the private information and benefit only of the client for whom it was prepared and the particular purpose previously advised to Ausenco Services Pty Ltd. The contents of

More information

THE USE OF PULP POTENTIAL CONTROL TO SEPARATE COPPER AND ARSENIC AN OVERVIEW BASED ON SELECTED CASE STUDIES

THE USE OF PULP POTENTIAL CONTROL TO SEPARATE COPPER AND ARSENIC AN OVERVIEW BASED ON SELECTED CASE STUDIES Paper No. 321 THE USE OF PULP POTENTIAL CONTROL TO SEPARATE COPPER AND ARSENIC AN OVERVIEW BASED ON SELECTED CASE STUDIES L K Smith 1, *, K J Davey 2 and W J Bruckard 3 ABSTRACT Flotation work conducted

More information

GALVANOX TM A Novel Process for the Treatment of Copper Concentrates

GALVANOX TM A Novel Process for the Treatment of Copper Concentrates GALVANOX TM A Novel Process for the Treatment of Copper Concentrates David G. Dixon UBC Hydrometallurgy PRESENTATION OUTLINE GALVANOX HISTORY GALVANOX FEATURES GALVANOX CHEMISTRY BATCH LEACHING RESULTS

More information

DEVELOPMENT AND APPLICATION OF AN ENERGY BENCHMARKING MODEL FOR MINERAL COMMINUTION. *S. Nadolski, B. Klein, D. Gong, Z. Davaanyam 1 and A.

DEVELOPMENT AND APPLICATION OF AN ENERGY BENCHMARKING MODEL FOR MINERAL COMMINUTION. *S. Nadolski, B. Klein, D. Gong, Z. Davaanyam 1 and A. DEVELOPMENT AND APPLICATION OF AN ENERGY BENCHMARKING MODEL FOR MINERAL COMMINUTION *S. Nadolski, B. Klein, D. Gong, Z. Davaanyam 1 and A. Cooper 2 1 Norman B. Keevil Institute of Mining, University of

More information

INCREASE OF COPPER RECOVERY FROM POLYMETALLIC ORES

INCREASE OF COPPER RECOVERY FROM POLYMETALLIC ORES Journal ofmining and Metallurgy, 36 (l-2)a (2000) J1-22. INCREASE OF COPPER RECOVERY FROM POLYMETALLIC ORES M. Adamovic, S. Radosavljevic" and M. Marinko Institute for Technology of Nuclear and Other Mineral

More information

Communition Abstract. Fine grind attritional mills; can they or should they go coarser. D Capstick and B Currie

Communition Abstract. Fine grind attritional mills; can they or should they go coarser. D Capstick and B Currie Communition 2012 Abstract Fine grind attritional mills; can they or should they go coarser D Capstick and B Currie Since the introduction of fine grind attritional mills a number of years ago they have

More information

Crushing. Comminution

Crushing. Comminution Comminution In order to separate the minerals from gangue (the waste minerals), it is necessary to crush and grind the rock to unlock, or liberate, valuable minerals so that they are partially or fully

More information

ENGINEERING SERVICES

ENGINEERING SERVICES ENGINEERING SERVICES www.elb.co.za Processing Solutions ABOUT ELB ENGINEERING SERVICES ELB Engineering Services (ELB) is an internationally recognised technology driven holistic solutions provider to the

More information

For personal use only

For personal use only Mutiny makes substantial metallurgical performance gains Forecast copper recoveries increased from 58.5% to 64% in the oxide zone and copper concentrate grade increased from 21.5% Cu to 35% Cu Forecast

More information

EMC FLOTATION TEST PROCEDURE 2 LABORATORY FLOTATION TEST PROCEDURE FOR MF1 AND MF2 TESTS AND REGRINDING OF CLEANER TAILINGS

EMC FLOTATION TEST PROCEDURE 2 LABORATORY FLOTATION TEST PROCEDURE FOR MF1 AND MF2 TESTS AND REGRINDING OF CLEANER TAILINGS EMC FLOTATION TEST PROCEDURE 2 LABORATORY FLOTATION TEST PROCEDURE FOR MF1 AND MF2 TESTS AND REGRINDING OF CLEANER TAILINGS SYNOPSIS Performing a flotation rate test characterises the ore. The results

More information

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum ASX ANNOUNCEMENT 29 March 2010 Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum PanAust is pleased to announce that the Board of Directors

More information

Waste Liberation: Improving mill feed from a miner s perspective. Bob McCarthy, SRK Consulting Dr. Bern Klein, University of British Columbia

Waste Liberation: Improving mill feed from a miner s perspective. Bob McCarthy, SRK Consulting Dr. Bern Klein, University of British Columbia Waste Liberation: Improving mill feed from a miner s perspective Bob McCarthy, SRK Consulting Dr. Bern Klein, University of British Columbia Outline Introduction Ore Deposit Heterogeneity Impacts of Mining

More information

PROCESS DEVELOPMENT OF THE NKOMATI PCMZ BASE METALS SULPHIDE ORE. Mr R L Bowers Mr D S Smit NKOMATI JOINT VENTURE

PROCESS DEVELOPMENT OF THE NKOMATI PCMZ BASE METALS SULPHIDE ORE. Mr R L Bowers Mr D S Smit NKOMATI JOINT VENTURE PROCESS DEVELOPMENT OF THE NKOMATI PCMZ BASE METALS SULPHIDE ORE Mr R L Bowers Mr D S Smit NKOMATI JOINT VENTURE ABSTRACT In light of soaring commodity prices, Nkomati has investigated the potential of

More information

CHAPTER EIGHT - COAL BENEFICIATION MODELLING OF BENEFICIATION OPTIONS

CHAPTER EIGHT - COAL BENEFICIATION MODELLING OF BENEFICIATION OPTIONS CHAPTER EIGHT - COAL BENEFICIATION MODELLING OF BENEFICIATION OPTIONS This Section presents coal processing circuits that could be used to achieve various outcomes linked to different grade products. 8.1

More information

Gekko Systems. Operations & Maintenance Training Introduction to Gravity Heia Safari Lodge - Feb 2008

Gekko Systems. Operations & Maintenance Training Introduction to Gravity Heia Safari Lodge - Feb 2008 Gekko Systems Operations & Maintenance Training Introduction to Gravity Heia Safari Lodge - Feb 2008 What is of Gravity Separation? The separation of different mineral species from one another based on

More information

Maximizing the recovery of fine iron ore using magnetic separation

Maximizing the recovery of fine iron ore using magnetic separation Maximizing the recovery of fine iron ore using magnetic separation by M. Dworzanowski* Synopsis The beneficiation of fine iron ore will increase in importance in the future because most new iron ore resources

More information

STIRRED MILLING TECHNOLOGY

STIRRED MILLING TECHNOLOGY STIRRED MILLING TECHNOLOGY Xstrata Technology Important expertise in Grinding, Flotation, Smelting, Leaching & Refining Technology Centre Sudbury North America Vancouver Tankhouse Technologies Townsville

More information

VertiMill Performance Updates in Secondary and Regrind Duties at Cannington Mine, BHP-B

VertiMill Performance Updates in Secondary and Regrind Duties at Cannington Mine, BHP-B VertiMill Performance Updates in Secondary and Regrind Duties at Cannington Mine, BHP-B Sam Palaniandy, Malcolm Powell and Marko Hilden (JKMRC) Jonathan Allen and Kamran Kermanshahi (Metso Minerals) Bill

More information

The modular Python processing plant designed for underground preconcentration

The modular Python processing plant designed for underground preconcentration The modular Python processing plant designed for underground preconcentration T.R. Hughes and A.H. Gray Gekko Systems Pty. Ltd. Ballarat, Victoria, Australia Abstract How do you fit a processing plant

More information

Testing Requirements and Insight for Gravity Gold Circuit Design. André R. Laplante. Presented at the Randol Gold & Silver Forum 2000, Vancouver

Testing Requirements and Insight for Gravity Gold Circuit Design. André R. Laplante. Presented at the Randol Gold & Silver Forum 2000, Vancouver Testing Requirements and Insight for Gravity Gold Circuit Design André R. Laplante Presented at the Randol Gold & Silver Forum 2000, Vancouver Abstract Gravity gold recovery can be of significant economic

More information

Determining in-depth plant performance

Determining in-depth plant performance 0 Determining in-depth plant performance The primary tool for optimising your plant process Philip Stewart Plant Analysis Don t try to solve a problem until you know what the problem really is. Find out

More information

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT 4 JULY 2017 RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT HIGHLIGHTS Robust economics: NPV 8% of A$260M (pre-tax) and IRR of 37% 1 ; Cash operating cost of

More information

Developing Process Control Standards for Optimal Plant Performance at PanAust Limited

Developing Process Control Standards for Optimal Plant Performance at PanAust Limited Developing Process Control Standards for Optimal Plant Performance at PanAust Limited D Baas 1, D Bennett 2 and P Walker 3 ABSTRACT This paper describes how Brisbane-based PanAust Limited develops process

More information

Practice Brief GOLD PROCESSING. Revision Date: October 23, 2015

Practice Brief GOLD PROCESSING. Revision Date: October 23, 2015 Practice Brief GOLD PROCESSING Revision Date: October 23, 2015 Prepared by 330 Alison Blvd. Fredericton, New Brunswick Canada, E3C 0A9 Telephone: (506) 454-2359 www.thibault-process-engineering.ca Gold

More information

METALLURGICAL PROCESS DEVELOPMENT FOR PLANT DESIGN

METALLURGICAL PROCESS DEVELOPMENT FOR PLANT DESIGN MINDEV 97 PAPER NO 10 METALLURGICAL PROCESS DEVELOPMENT FOR PLANT DESIGN DAVID LUNT, IAN RITCHIE, JOHN FLEAY MINPROC ENGINEERS LIMITED LEVEL 8, 140 ST GEORGE S TERRACE PERTH WA 6000 TELEPHONE 08 9347 4777

More information

CYCLOSIZER. For Sub-Sieve Sizing SEPOR INC 718 N. FRIES AVE P.O.BOX 578 WILMINGTON, CA PHONE: FAX :

CYCLOSIZER. For Sub-Sieve Sizing SEPOR INC 718 N. FRIES AVE P.O.BOX 578 WILMINGTON, CA PHONE: FAX : CYCLOSIZER For Sub-Sieve Sizing SEPOR INC 718 N. FRIES AVE P.O.BOX 578 WILMINGTON, CA 90748 PHONE: 310-830-6601 FAX : 310-830-9336 INTRODUCTION The Cyclosizer is a laboratory precision apparatus for the

More information

Stirred Milling machine development and application extension. Jon Allen Metso Global product manager, Stirred Mills

Stirred Milling machine development and application extension. Jon Allen Metso Global product manager, Stirred Mills Stirred Milling machine development and application extension Jon Allen Metso Global product manager, Stirred Mills Current technologies Efficiency and application range development Contents Machine development

More information

KANMANTOO COPPER MINE PRIMARY TO OXIDE HAYDEN ARBON IIIII MINE GEOLOGIST BEN ALEXANDER IIIII METALLURGICAL SUPERINTENDENT 5 DECEMBER 2014

KANMANTOO COPPER MINE PRIMARY TO OXIDE HAYDEN ARBON IIIII MINE GEOLOGIST BEN ALEXANDER IIIII METALLURGICAL SUPERINTENDENT 5 DECEMBER 2014 KANMANTOO COPPER MINE PRIMARY TO OXIDE HAYDEN ARBON IIIII MINE GEOLOGIST BEN ALEXANDER IIIII METALLURGICAL SUPERINTENDENT 5 DECEMBER 2014 KANMANTOO COPPER MINE AND LEASE AREAS 100%-owned by Hillgrove 55km

More information

Influence of liberation of sulphide minerals on flotation of sedimentary copper ore

Influence of liberation of sulphide minerals on flotation of sedimentary copper ore E3S Web of Conferences 18, 125 (217 ) DOI:1.151/e3sconf/2171125 Influence of liberation of sulphide minerals on flotation of sedimentary copper ore Alicja Bakalarz 1,*, Magdalena Duchnowska 1, and Andrzej

More information

Mill Development and Operations Plan

Mill Development and Operations Plan Mill Development and Operations Plan Quartz Mining Licence QML-0009 November 2009 BELLEKENO PROJECT ALEXCO KENO HILL MINING CORP. BELLEKENO PROJECT QUARTZ MINING LICENCE MILL DEVELOPMENT AND OPERATIONS

More information

IMAGING TECHNOLOGIES TO UNDERSTAND GRINDING AT PARTICLE SCALE IN A UG-2 PLATINUM ORE PROCESSING PLANT

IMAGING TECHNOLOGIES TO UNDERSTAND GRINDING AT PARTICLE SCALE IN A UG-2 PLATINUM ORE PROCESSING PLANT Paper No. 71 IMAGING TECHNOLOGIES TO UNDERSTAND GRINDING AT PARTICLE SCALE IN A UG-2 PLATINUM ORE PROCESSING PLANT S Leroy 1, * and E Pirard ABSTRACT Grinding is the most energy consuming step in mineral

More information

SLON MAGNETIC SEPARATORS APPLIED IN THE ILMENITE PROCESSING INDUSTRY

SLON MAGNETIC SEPARATORS APPLIED IN THE ILMENITE PROCESSING INDUSTRY Physical Separation in Science and Engineering, September December 2004, Vol. 13, No. 3 4, pp. 119 126 SLON MAGNETIC SEPARATORS APPLIED IN THE ILMENITE PROCESSING INDUSTRY XIONG DAHE* Ganzhou Nonferrous

More information

TAKING CONTROL OF THE MILL FEED: CASE STUDY - PARTIAL SECONDARY CRUSHING MT RAWDON. Brian Putland, Bernie Siddall and Andrew Gunstone

TAKING CONTROL OF THE MILL FEED: CASE STUDY - PARTIAL SECONDARY CRUSHING MT RAWDON. Brian Putland, Bernie Siddall and Andrew Gunstone TAKING CONTROL OF THE MILL FEED: CASE STUDY - PARTIAL SECONDARY CRUSHING MT RAWDON Brian Putland, Bernie Siddall and Andrew Gunstone MET PLANT 2004 CONFERENCE 6-7 September 2004 Perth, WA Contact:Bernie

More information

For personal use only

For personal use only Corporate Details Ordinary Shares: 795,237,123 Market Capitalisation: ~$180 million Cash, bullion and available financing facilities at 31 December 2018: $18.2 million Debt at 31 December 2018: $5 million

More information

For personal use only

For personal use only ASX/Media Announcement 6 September 2016 PILBARA COMPLETES KEY METALLURGICAL TESTWORK PROGRAM AHEAD OF PILGANGOORA DEFINITIVE FEASIBILITY STUDY Phase 2 metallurgical testwork and process design completed

More information

THE EVALUATION OF A COPPER FLOTATION PLANT PERFORMANCE BY PLANT SURVEY AND LABORATORY TESTS

THE EVALUATION OF A COPPER FLOTATION PLANT PERFORMANCE BY PLANT SURVEY AND LABORATORY TESTS Physicochemical Problems of Mineral Processing, 38 (2004) 95-102 Fizykochemiczne Problemy Mineralurgii, 38 (2004) 95-102 Levent ERGÜN *, Zafir EKMEKÇİ *, Özcan GÜLSOY *, Hakan BENZER * THE EVALUATION OF

More information

MODELLING STUDIES ON A 100 mm WATER-INJECTION CYCLONE

MODELLING STUDIES ON A 100 mm WATER-INJECTION CYCLONE Physical Separation in Science and Engineering, September December 4, Vol. 13, No. 3 4, pp. 89 99 MODELLING STUDIES ON A 1 mm WATER-INJECTION CYCLONE K. UDAYA BHASKAR a, *, B. GOVINDARAJAN a, J.P. BARNWAL

More information

THE USE OF COLUMN FLOTATION FOR THE RECOVERY OF ULTRA-FINE PHOSPHATES

THE USE OF COLUMN FLOTATION FOR THE RECOVERY OF ULTRA-FINE PHOSPHATES THE USE OF COLUMN FLOTATION FOR THE RECOVERY OF ULTRA-FINE PHOSPHATES Abstract Harold E. Wyslouzil President - Canadian Process Technologies Inc. Vancouver BC, Canada Brazil currently produces around 4.0

More information

Gravity Gold Recovery at President Steyn Mine. P. F. Van den Steen

Gravity Gold Recovery at President Steyn Mine. P. F. Van den Steen Gravity Gold Recovery at President Steyn Mine P. F. Van den Steen Knelson Concentrators Africa (Pty) Ltd July 2000 Introduction President Steyn Gold Mine (Freestate) (Pty) Ltd (PSGM) is a privately owned

More information

VXP2500 STIRRED MILL OPTIMIZATION AT CASMYN MINING TURK MINE

VXP2500 STIRRED MILL OPTIMIZATION AT CASMYN MINING TURK MINE VXP2500 STIRRED MILL OPTIMIZATION AT CASMYN MINING TURK MINE *S. Reddick 1, D. Rahal 1, B Hines 1, I. Shah 1 1 FLSmidth Minerals 7158 S FLSmidth Drive Midvale, UT, 84047 USA (*Corresponding author: scott.reddick@flsmidth.com)

More information

Fast Tracking the Superior Lake Project Re-Start Plan

Fast Tracking the Superior Lake Project Re-Start Plan ASX Announcement ASX: SUP 12 July 2018 superiorlake.com.au Fast Tracking the Superior Lake Project Re-Start Plan Highlights Historical review of mining operations and remaining infrastructure at Superior

More information

Effect of Water Composition on Flotation of Lead and Zinc Sulphide Ore

Effect of Water Composition on Flotation of Lead and Zinc Sulphide Ore ABSTRACT 533 Effect of Water Composition on Flotation of Lead and Zinc Sulphide Ore Ünzile Yenial*, Gülay Bulut Mineral Processing Engineering Department, Mining Faculty, Istanbul Technical University,

More information

The Australian treatment

The Australian treatment The Australian treatment Wes Mackinnon and Andrew Swanson, QCC Resources Pty Ltd, Australia, detail the coal preparation techniques typically employed in the Australian coal industry. A ustralia has abundant

More information

Two-stage classification in one unit

Two-stage classification in one unit CAVEX ReCyclone Slurry Equipment Solutions Two-stage classification in one unit Cavex ReCyclone For many years Weir Minerals have applied their experience of slurry handling technology in the design and

More information

FIGURE 1 Typical industrial column flotation cell FIGURE 2. More information is available at

FIGURE 1 Typical industrial column flotation cell FIGURE 2. More information is available at The USE of Column Flotation for the Recovery of Ultra-Fine Phosphates Harold E. Wyslouzil Executive Managing Director Eriez Flotation Division Delta, B.C. - Canada ABSTRACT Brazil currently produces around

More information

FOR IMMEDIATE RELEASE 30 August 2018 TSX-V: AZR

FOR IMMEDIATE RELEASE 30 August 2018 TSX-V: AZR FOR IMMEDIATE RELEASE 30 August 2018 TSX-V: AZR AZARGA METALS ANNOUNCES POSITIVE, INDEPENDENT, PRELIMINARY ECONOMIC ASSESSMENT ( PEA ) ON UNKUR COPPER-SILVER PROJECT HIGHLIGHTS: Positive PEA result achieved

More information