1 Continuous Ore Roaster Setup & Operating Instructions 0. Unwrap the roaster pallet. (The cross bar has been unattached for shipping purposes. You will need one 120V outlet and one 220 outlet or two 220V, depending on your location. There is also a box of parts containing extra furnace insulation blanket, chain lube, shear pins, nuts/bolts and wheels (if you ordered the optional wheel assembly). 1. (Go to the next step if you did not order the Wheel Assembly.) Attach the wheels. YOU WILL NEED AT LEAST 2 PEOPLE TO DO THIS. Block the wheels before plugging in the unit. Always block the wheels before running any material. Optional Wheel Assembly
2 Cross bar Furnace chamber frame 2. For shipping purposes, the cross bar is bolted above the furnace chamber frame to hold everything in place. Remove the cross bar and go to the next step on page 4 to put it into position shown above. Insert insulation blanket at both ends of the furnace chamber to hold in heat. And between the 2 black feed pipe & 4 ore bin outlet Air hole - plug, inject air, or vacuum
3 Feed end view of chain drive mechanism Back view Feed auger - This pulls the ore into the unit and keeps it moving through the furnace.
4 Sprocket Adjustment collar Cross bar Furnace chamber frame Set the hydraulic jack in place and raise the unit about 4 (10cm) so you can add the cross bar and insert the bolts in the riser frame. Secure bolts with the nuts. Raise and lower the roaster depending on how fast you want to move your material through the roaster. Start in lowest setting (3 rise) and move higher as needed.
5 START UP PROCEDURE DO NOT ATTEMPT TO RUN ORE THROUGH THE ROASTER IN A LEV- EL POSITION. The steeper the drop, the faster the material will run through the roaster. Generally, you will usually use the first 3 hole settings. 1. Plug the 110/220 VAC temperature control unit cord and speed control into the outlet on the frame leg. This enables you to have one master power switch. Plug the 220 VAC furnace/temperature control unit cord into a 220 VAC 50 amp outlet. If you purchased the Wheel Assembly, block the wheels before plugging in the unit. 2. Turn on the speed control and ensure that it is running smoothly. With no ore in the unit, it will be making noises from the metal auger turning & rubbing on the inside the pipe. This is normal. Once there is ore moving through the unit, it will run quieter. 220 VAC cord Furnace/Temperature control 220 VAC Speed control 110/220 VAC Don t turn on the temperature control unit yet. TESTING PROCEDURE 1. With the feed drive running, fill up the hopper with ore and adjust the speed of the feed. Make any necessary adjustments to the tilt or speed of the roaster. Ore must be feeding through the unit smoothly before turning on the temperature control unit. 2. To determine the correct roasting temperature for your material: Turn on the temperature control unit. (Examine discharging ore after the unit is up to temperature for at least 10 minutes. Grab a sample of the ore coming out of the pipe.) Start at 750 F (399 C). Once it s up to temperature and ore is flowing through, check to see if that s a complete roast. If not, then re-run the material at 1150 F (621 C) and check it. If that s not enough, then re-run at 1350 F (732 C). If the material did not totally roast at 1350 F (732 C), it may have to be run again. Do not roast or dry your material above 1350 F (732 C) or
6 it s likely to melt to the inside of the pipe!!!. If it melts and clogs up the pipe, the auger will jam and you could seize the machine!!! While the Wheel Assembly makes it easy to move the Roaster around your lab, ALWAYS BLOCK THE WHEELS BEFORE RUNNING MATERIAL. Maintenance: The auger pulls the ore from the hopper and keeps it moving through the furnace. Over time, augers will be eaten up by the fumes coming off the ore. Before running each new batch of ore, check the condition of the auger. The roasting pipe (2 black iron pipe) will eventually need to be replaced as well. It all depends upon the ore you are roasting as to how long these items last. For this reason, we have made the pipe and auger easy to replace. TIP: High sulfide content will corrode the metal faster. Coat the inside of the pipe with a lime slurry to protect the metal pipe & auger. Set the temperature control to around 200 F (93 C) to dry the slurry as a coating on the inside of the pipe. This might help to keep the sulfides from sticking to the inside of the pipe. Or add some 1/4 limestone to your ore feed. This would absorb the sulfur and make calcium sulfate which would decrease the SO 2 gas. Remember, SO 2 gas + H 2 O = H 2 SO 4 (sulfuric acid). Use a heavy duty silicone spray, dry teflon chain lube, or graphite to lubricate the chains. Do NOT use a wet (oil) lubricant as sand/gravel will stick to it. Take the pipe and auger out (or at least verify no material is stuck to the sides) and clean thoroughly between runs. Caked material inside the pipe will cause damage to the unit by seizing up, bending the auger or pipe & eventually burning up the motor! As a safety feature if the unit does start to seize, the shear pin will break. Check every time before the next cycle: Before each start up of the roaster, check the auger & pipe for material stuck to the sides and clear it out. Refer to the Start Up & Testing Procedures on page 5. The unit should sound the same as when new. It should run smooth. With no ore in the unit, it will be making noises from the metal auger turning & rubbing on the inside the pipe. Again, if there is any sticking, take the auger and pipe out and clean thoroughly. Recommended temperatures for roasting sulfide ores are 750 F (399 C), 1150 F (621 C) and 1350 F (732 C)
7 Running the Roaster Always run the roaster under a fume hood while exhausting fumes through a scrubber. Wear a protective mask (we recommend using the acid gas cartridges) at all times. Recommended maximum feed size of material is -20 mesh (do not feed anything larger) Don t turn off the feed drive until the whole unit is down to under 100 F (38 C). If you turn off the feed speed control before the unit is cool, the pipe & auger can bend or sag. Do not turn off the feed speed control with material still in the hopper and/or pipe! Run until empty before turning off the feed speed control. The Air Hole - you can inject air (preferable), or attach a vacuum to the air hole to draw off the fumes, or plug (provided). Lubricate the chains as needed with graphite, dry teflon chain lube, or silicone spray. As a safety feature, a shear pin has been installed on the jackshaft drive sprocket. If the roaster gets jammed, the pin will break, keeping the motor from continuing to rotate the auger and pipe. Turn everything off! Once the unit has been cooled and cleared out, make sure everything is hooked back up (see Assembly & Disassembly section) and install a new shear pin (extras provided with your parts box).
8 Disassembly of Feed Pipe & Auger M 1. Remove nut, washers, and spring from motor plate tension bolt 2. Loosen both pipe sprocket set screw bolts 3. Loosen shaft collar on pipe 4. Remove pipe sprocket chain from sprocket on jack shaft 5. Remove the expanded metal chain guard over the auger drive chain and sprockets 6. Loosen both set screws on both the top and bottom auger drive sprockets
9 7. Once loose, remove sprockets together with chain 8. Loosen both set screws on the auger bearing 9. The auger and pipe should now both slide out together 10. Don t forget to catch the pipe sprocket and collar during removal 11. Installation should be the reverse of removal, just make sure all sprockets are parallel before tightening their set screws so that the chain tracks correctly
10 Quick Set Up & Running of Roaster 0. Attach the wheels. Using the jack to raise the feed bin, set the level of the roaster in the 1 st hole. Add the cross bar & insert the bolts. Tighten down with nuts provided. 1. Make sure the insulation blanket in in place. Position the roaster under a fume hood with scrubber which has a good exhaust. Lock the wheels. WEAR A PROTECTIVE FACE MASK (FOR FUMES) AT ALL TIMES WHILE RUNNING THE ROASTER. 2. Set up a metal bucket or metal collection tank for the discharged material. TIP: we use a piece of metal channel to act as a chute into a metal pail. 3. Plug in the temperature control unit/furnace and the speed control unit. 4. Turn on the speed control unit to high initially. 5. Fill up the hopper with ore and adjust the speed of the feed to ensure it s feeding smoothly. 6. Turn on the temperature control unit to 750 F (399 C) 7. Watch your discharged roasted ore. If it hasn t changed to the good color that you want, raise the temperature and give it some time before adjusting higher. DO NOT GO ABOVE 1350 F (732 C). You can also slow down the feed speed. 8. Assay your roasted samples to determine if you re getting the best recovery. Recommended temperatures for roasting sulfide ores are 750 F (399 C), 1150 F (621 C) and 1350 F (732 C) Production Volume: This roaster will run approximately 340 lbs/154.5 kg an hour at maximum speed. This is calculated on the amount of ore that will feed through the unit, NOT how well it roasts the material. Roasting speed and volume will depend upon the percentage of sulfides present.
11 BEFORE & AFTER PHOTOS SAMPLE 1 BEFORE SAMPLE 1 AT 750 F (399 C) SAMPLE 1 AT 1350 F (732 C) SAMPLE 2 BEFORE SAMPLE 2 AT 750 F (399 C) SAMPLE 2 AT 1350 F (732 C)
FW66 FORESTRY WINCH FW66. Owner s Manual 19/02/2016
FW66 FORESTRY WINCH FW66 19/02/2016 Owner s Manual TABLE OF CONTENTS INTRODUCTION ---------------------------------------------------------------------------------- 2 INTENDED USE -----------------------------------------------------------------------------------
More informationODYSSEY FLOOR MODEL. Owner s Manual. O-6400-F shown rev 118
Owner s Manual ODYSSEY FLOOR MODEL O-6400-F shown 67-1455 rev 118 3730 E. Southern Avenue, Phoenix, AZ 85040 USA 800-778-8779 Workhorseproducts.com 1 Table of Contents I. Introduction & Safety Information.
More informationSYSTEM 600 GENERAL MAINTENANCE AND ADJUSTMENT GUIDE
SYSTEM 600 GENERAL MAINTENANCE AND ADJUSTMENT GUIDE If you follow a routine maintenance schedule your system 600 will give you years of reliable service with a minimum of down time. This guide outlines
More informationKEEP FOR FUTURE REFERENCE MRT FORKLIFT ADAPTER READ ALL INSTRUCTIONS AND WARNINGS BEFORE USING THIS PRODUCT
KEEP FOR FUTURE REFERENCE P.O. Box 368 908 West Main Laurel, MT USA 59044 phone 800-548-7341 phone 406-628-8231 fax 406-628-8354 INSTRUCTIONS International Version STOCK NUMBER: 95722 MRT FORKLIFT ADAPTER
More informationREAD THIS MANUAL CAREFULLY BEFORE ASSEMBLY, TESTING & OPERATING
The Operator must thoroughly read and understand this manual before operating the dust collector or commencing any servicing. Care should be taken to follow all safety rules and warning instructions. READ
More informationUSER S OPERATING AND INSTRUCTION MANUAL
Grand Rapids, Michigan, U.S.A. 49504-5298 USER S OPERATING AND INSTRUCTION MANUAL MODEL 738 MINI CHIP SLICER 0738S20000-CV INDEX Section Description Document No. Page No. SAFETY INSTRUCTIONS --------------------------------------
More informationBucket elevators are comprised of three main assemblies: head terminal, boot terminal, and intermediate sections complete with components.
To obtain a more efficient elevator, we are furnishing industry standard chains, or using readily available multiple ply, allsynthetic carcass belting. We are also increasing speeds where applicable and
More informationEU150-EU200-EU400 CRIMPER OPERATORS MANUAL
EU50-EU00-EU00 CRIMPER OPERATORS MANUAL SAFETY PRECAUTIONS READ INSTRUCTIONS AND IDENTIFY ALL COMPONENT PARTS BEFORE USING CRIMPER KEEP HANDS AWAY FROM PINCH POINTS CONSULT HOSE AND FITTING MANUFACTURER
More informationSection 8 Technician Level Maintenance
Section 8 Technician Level Maintenance Page 8-1 Table of Contents 1. Warning: Maintenance Hazards 1.3 Scope of this Section 2. Gasifier 2.1 Overhaul Gasifier 2.2 Overhaul Hopper 2.3 Replace Gasifier 3.
More informationBakeMax Dough Mini Moulder BMMDM02
BakeMax Dough Mini Moulder BMMDM02 2 Instruction Manual 1. Preface ------------------------------------------- P2 2. Machine Introduction -------------------------------- P2 3. Machine Specification and
More informationInstruction Manual HK285. Note: The Owner/Operator must read carefully and understand all the information presented here before operation.
Instruction Manual HK285 Note: The Owner/Operator must read carefully and understand all the information presented here before operation. Contents Warnings and Safety Instructions 1 Receiving Instructions
More informationKEEP FOR FUTURE REFERENCE FORKLIFT ADAPTER FOR MRTA6 AND MRTA8 LIFTERS READ ALL INSTRUCTIONS AND WARNINGS BEFORE USING THIS PRODUCT
KEEP FOR FUTURE REFERENCE P.O. Box 368 908 West Main Laurel, MT USA 59044 phone 800-548-7341 phone 406-628-8231 fax 406-628-8354 INSTRUCTIONS International Version STOCK NUMBER: 95457 FORKLIFT ADAPTER
More informationCement Bucket. Bucket Elevator
Bucket Elevator Cement Bucket 289 YELLOW RIVER ROAD, XINXIANG CITY, HENAN PROVINCE Tel: +86-373-5799198 Fax: +86-373-5071699 www.pkmachinery.com info@pkmachinery.com 289 YELLOW RIVER ROAD, XINXIANG CITY,
More informationMill, Laboratory STANDARD OPERATING PROCEDURE
STANDARD OPERATING PROCEDURE Mill, Laboratory Model: Model 4 Manufacturer: Thomas Scientific Location: Dry Processing Pilot Plant, 1851 Food Sciences Building Publication Date: 05/06/2014 Iowa State University
More informationINSTALLATION GUIDE. 4-Post Lift. Model United States. United Arab Emirates. Egypt.
4-Post Lift INSTALLATION GUIDE United States 17779 Main Street Suite C Irvine, CA 92614 USA Tel: +1(949) 333-3800 Fax: +1(949) 333-3804 United Arab Emirates Model 46614 P.O. Box 121971 Saif Zone A2-032
More informationRecommendations for Cutting and Handling Melamine Boards
Recommendations for Cutting and Handling Melamine Boards The three main factors of this process which should be taken into account in order to achieve a well finished cut are: the machine, the cutting
More informationProweld Equipment Owner & Maintenance Manual FIELD 12 TRENCH (Widos 4900)
Proweld Equipment Owner & Maintenance Manual FIELD 12 TRENCH (Widos 4900) 35 Green Street, PO Box 653, Malden, MA 02148 Tel: (781) 321-5409 - Fax (781) 321-4421 - Toll Free: (800) 343-3618 www.asahi-america.com
More informationInstallation Instructions, Pressure Regulator Series Manual Model: 20313, Air motor Operated: F20313, Hydraulic Motor Operated: G20313
Installation Instructions, Pressure Regulator 20313 Series Manual Model: 20313, Air motor Operated: F20313, Hydraulic Motor Operated: G20313 1. GENERAL ------------------------------------------------------------------------------
More informationClutch Installation Kinze row unit
NOTE: Indented items indicate parts included in an assembly listed above Part Name/Description Part Number Quantity 4 row clutch installation kit Kinze Mechanical seed meter 4100568 1 Carriage bolt 1/4
More information2200-Lb. Stacker. Fixed Straddle Leg OWNER S MANUAL
2200-Lb. Stacker Fixed Straddle Leg OWNER S MANUAL WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety
More informationWelding & Fabrication Tools Mini VaR Tool Kit
With Volta Tools You Can Never Go Wrong! Fast and simple belt installation. Unique and versatile design - compact, rugged and easy-to-use. Designed for both shop and field use. Light-weight construction.
More informationOWNER'S MANUAL. Drum Handling Solutions DRUM CARRIER / ROTATOR SERIES DCR-205
VESTIL MANUFACTURING CORPORATION 999 North Wayne St., Angola, IN 70 Phone (0) -78 Fax (0) -9 E-mail: sales@vestil.com www.vestil.com Drum Handling Solutions Contents Warnings and Safety Instructions...
More informationMODEL 185R Kontrol-Karrier Operator s Manual for Morse Kontrol-Karrier
Contents Page Receiving Procedures.................... 1 Warranty............................. 1 Safety Information..................... 1-2 Machine Description................... 3 Operating Instructions....................
More informationOperating & Maintenance Manual JEC JCP Series. Centrifugal Pumps
Operating & Maintenance Manual JEC JCP Series Centrifugal Pumps JEC LTD. 408, Cheongyo-ri, Bibong-myun, Hwaseong-si, Gyeonggi-do, South Korea Tel: +82 31 355 0316 Fax: +82 31 355 0319 www.jecpump.com E-mail:
More informationClutch Installation John Deere row unit
Ag Leader Technology SeedCommand NOTE: Indented items indicate parts included in an assembly listed above Part Name/Description Part Number Quantity 4 row clutch installation kit John Deere NON INTERPLANT
More informationThank you for purchasing our product. *Please read these instructions and follow them step by step.
PAGE 1 OF 5 PORTA-DOCK, INC. AD01- DS 4'x 16'SW-AA - AP01- DS 4'x 16'SW-APD AW01- DS 4'X 16'SW-CPD ALUMINUM PORTA-DOCK *For Beige Decking Add the Letter B to the Model* Thank you for purchasing our product.
More informationService Manual For the E Ride 26
Service Manual For the E Ride 26 For: Training Troubleshooting Adjustments Contents 1 Cautions ------------------------------------------------------------------------ 2 Safety Information ----------------------------------------------------------
More informationUSER S OPERATING AND INSTRUCTION MANUAL
Grand Rapids, Michigan, U.S.A. 49504-5298 USER S OPERATING AND INSTRUCTION MANUAL MODEL 619-MDP DOUGH PRESS 0619S20000-CV3 619-MDP DOUGH PRESS INDEX Section Description Document No. Page No. SAFETY INSTRUCTIONS
More informationV-STACK36 Vertical Stacker
V-STACK36 Vertical Stacker 11/2013 OPERATOR MANUAL FIRST EDITION TABLE OF CONTENTS TOPIC PAGE Description 1 Specifications 1 Unpacking 1 Configurations 2 Setup and Operation 3 Description The V-Stack36
More informationPallet Jack 4,400 Lbs Capacity Model #31001
SKU # 217-0162 Pallet Jack 4,400 Lbs Capacity Model #31001 Owner s Manual and Assembly Instructions Questions? Problems? DO NOT RETURN TO STORE Please call our customer help line: (888) 315-3080 M-F 8-5
More informationREVERSE OSMOSIS SYSTEM USER'S MANUAL. Excellent Product, Excellent Water! My PurePro X6
REVERSE OSMOSIS SYSTEM USER'S MANUAL UV Plus! Excellent Product, Excellent Water! My PurePro X6 PUREPRO X6 Thank you very much for selecting Pure-Pro Water Corp. In order to bring the best use of your
More informationSERVICE PARTS LIST SPECIFY CATALOG NO. AND SERIAL NO. WHEN ORDERING PARTS. 120V Permanent Magnet Drill STARTING SERIAL NUMBER.
69(5x) CATALOG NO. SERVICE PARTS LIST SPECIFY CATALOG NO. AND SERIAL NO. WHEN ORDERING PARTS 120V Permanent Magnet Drill 2-20 STARTING SERIAL NUMBER G85A BULLETIN NO. 5-6-00 REVISED BULLETIN DATE Apr.
More informationCBE 600 SERIES GRAVITY PACKER
CBE 600 SERIES GRAVITY PACKER Safety - Installation - Operation - Maintenance 1 OF 16 FOREWARD This manual has been prepared to assist you with your Choice Bagging Equipment, Ltd. bag packaging equipment.
More informationOPERATOR S MANUAL. LINKIT Series LKS300/LKS450 Portable Conveyor. InterQuip USA LLC interquip.net DISTRIBUTED BY: OPERATOR S MANUAL
OPERATOR S MANUAL LINKIT Series LKS300/LKS450 Portable Conveyor DISTRIBUTED BY: InterQuip USA LLC 203.322.2600 interquip.net 1 IMPORTANT Read, understand and obey these safety rules and operating instructions
More informationTube-Line Bale Feeder BF-5600SL. Operator's Manual
Tube-Line Bale Feeder BF-5600SL Operator's Manual 2 Contents Safety.......5 Operation.....7 Maintenance...7 Troubleshooting....9 Parts.....11 Specifications Weight : 1960 lbs (empty) Capacity : 2 Bales,
More informationNiklas portable freestand
USER`S MANUAL Niklas portable freestand The Niklas portable freestand offers you the unique possibility to lift and move a patient easily and safely without straining the patient or the caregiver. The
More informationLUBRICATION PUMP Z2 CENTRAL LUBRICATION
LUBRICATION PUMP APPLICATION Lubrication pumps are used as a source of pressure lubricant in the circuits of two-line central lubrication systems. Pumps can be used for lubrication of high number of lubricated
More informationCONVEYOR SYSTEMS GENERAL OPERATIONAL MANUAL
CONVEYOR SYSTEMS GENERAL OPERATIONAL MANUAL WIRE MESH TRANSFER INCLINED BAG FLATTENER BAG TURNER INCLINED BAG HANDLING BAG CLOSER WITH BAG KICKER WIRE MESH DISCHARGE GRAVITY ROLLER CUSTOM DESIGNS NOTES
More informationUSER S OPERATING AND INSTRUCTION MANUAL
Grand Rapids, Michigan, U.S.A. 49504-5298 USER S OPERATING AND INSTRUCTION MANUAL MODEL 777-N VARIETY SLICER 0777S20000-CV3 INDEX Section Description Document No. Page No. SAFETY INSTRUCTIONS -------------------------------
More informationOPERATOR S SAFETY MANUAL
June 2011 OPERATOR S SAFETY MANUAL Sumner Pipe Jacks www.sumner.com 7514 Alabonson Road Houston, TX 77088 U.S.A ph: 281.999.6900 fax: 281.999.6966 470 Collier MacMillan Drive Unit 2 & 3 Cambridge, ON N1R
More informationTABLE OF CONTENTS. Vacuum Cleaner. Model No. MC-CG Bagless Canister Red North America
Order No.: MAC1412002CE Vacuum Cleaner Model No. MC-CG902-02 Bagless Canister Red North America TABLE OF CONTENTS PAGE 1 Specifications ----------------------------------------------------- 2 2 Disassembly
More informationSERVICE PARTS LIST BULLETIN NO M18 FUEL 1-1/2" Magnetic Drill CATALOG NO. G96A
65(7x) 48 64 CATALOG NO. SERVICE PARTS LIST SPECIFY CATALOG NO. AND SERIAL NO. WHEN ORDERING PARTS M18 FUEL 1-1/2" Magnetic Drill 67 76 2787-059 77 83(3x) STARTING SERIAL NUMBER 79 G96A Torque Chart on
More informationOPERATION MANUAL BISON LIFTER (ABL150)
ABACO MACHINES OPERATION MANUAL BISON LIFTER (ABL150) ABACO MACHINES (USA) 14508 S. Garfield Ave., Paramount, CA 90723, USA Tel : 310-532-0366 Fax : 310-532-0499 Email : sales@abacomachines.com Website
More informationLonger Wearlife Parts For Asphalt Plants
Longer Wearlife Parts For Asphalt Plants Still proudly made in the USA Kenco Engineering, Inc. Roseville, CA 800-363-9859 www.kencoengineering.com helps keep your plant working at day one productivity
More informationU-LAP. UTR-30 & UTR-70 Recipro Air Lappers Repair Manual. BORIDE Engineered Abrasives 2615 Aero Park Dr. Traverse City, MI
U-LAP UTR-30 & UTR-70 Recipro Air Lappers Repair Manual UTR-20-30-70 Repair Instruction Manual Repair Instruction Manual Content Exploded View --------------------------------------------------------------------Page
More informationHALSEY TAYLOR OWNERS MANUAL Classic TM Series Barrier-Free Water Coolers Refrigerated Fountains with Back Panel
HALSEY TAYLOR OWNERS MANUAL Classic TM Series BarrierFree Water Coolers Refrigerated Fountains with Back Panel Figure HTERQ Figure HTSRQ Figure 3 HTSERQ Figure HTESRQ Figure 3 Model HTERQ HTSRQ HTSERQ
More informationHALSEY TAYLOR OWNERS MANUAL Classic TM Series Barrier-Free Water Coolers Refrigerated Fountains with Back Panel
HALSEY TAYLOR OWNERS MANUAL Classic TM Series BarrierFree Water Coolers Refrigerated Fountains with Back Panel Figure HTERQ Figure HTSRQ Figure 3 HTSERQ Figure HTESRQ Figure 3 Model HTERQ HTSRQ HTSERQ
More informationWeir Specialty Pumps. WEMCO Torque-Flow
Weir Specialty Pumps WEMCO Torque-Flow HIGH LOW OIL LEVEL WEMCO Torque-Flow Model C WEMCO Torque-Flow Model C Materials of Construction Ni-Hard, High Chrome Configurations Horizontal Sealing Multiple options
More informationG2S. Vertical Sump Pump
G2S Vertical Sump Pump G2S Our process-duty vertical sump pump for water, hydrocarbons, and acid and alkaline solutions. Modular in design, the G2S sump pump is made This pump comes standard with lip seals
More information3.2 SuperTie 50K Installation Guide
3.2 SuperTie 50K Installation Guide FORM ERECTION 1. This G50K Gripper has been shipped partially disassembled. It is necessary for you only to attach the base plate. The Gripper Body, Base Plate, and
More informationMATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 1850 APRIL 2018 (Formerly OPSS 1850, April 2013) Note: The PROV published in April 2018 replaces OPSS 1850 COMMON, April 2013 with no technical content
More informationPacific Conveyors Ltd.
Pacific Conveyors Ltd. OPERATION AND MAINTENANCE MANUAL Model CP2004 Airport Pallet Loop Conveyor Also applicable to Matthews "Cresflight" carousel INDE 1). INTRODUCTION... 1-1 2). MAINTENANCE PRACTICES...
More informationProduct Catalog. Designers and manufacturers of safe, simple modular conveyors SAFE SIMPLE SOLUTIONS
Product Catalog Designers and manufacturers of safe, simple modular conveyors SAFE SIMPLE SOLUTIONS Revision 071514 Introduction Can t find a conveyor? Finding a conveyor to meet your application needs
More informationOperating Instructions
028028 Operating Instructions Monarch 928 Stacker 23456 78901 Fishing Tackle $40.00 23456 78901 Fishing Tackle $40.00 23456 78901 Fishing Tackle $40.00 23456 78901 Fishing Tackle $40.00 TC0928OI Rev. AJ
More informationBase Models: 1-22SV Major Components GOULDS PUMPS. Commercial Water
Base Models: 1-22SV Base Models: 1-22SV F, P, R VERSIONS 1 Pump Body Stainless Steel AISI 304 EN 10088-1-X5-CrNi-10 (1.4301) 2 Impeller Stainless Steel AISI 304 EN 10088-1-X5-CrNi-10 (1.4301) 3 Diffuser
More informationSECURITY WITH SOPHISTICATED STYLE
SECURITY WITH SOPHISTICATED STYLE The attractive Roll-Vision model protects against theft and keeps out debris while allowing full view of what s inside. Unlike competitors grilles, our unique design uses
More informationMill, Burr STANDARD OPERATING PROCEDURE
STANDARD OPERATING PROCEDURE Mill, Burr Model: DK-15LS Manufacturer: Mahlkonig Gmbh & Company KG/Mahlkonig USA Location: Dry Processing Pilot Plant, 1851 Food Sciences Building Publication Date: 04/30/2015
More informationInstructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000
Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000 (How to move your pallet racking using the Link 4 Pallet Rack Lifter) This process is for a typical rack move and reset. Each
More informationEU1000 CRIMPER OPERATORS MANUAL WITH ACTTM CONTROLLER
EU1000 CRIMPER OPERATORS MANUAL WITH ACTTM CONTROLLER SAFETY PRECAUTIONS READ INSTRUCTIONS AND IDENTIFY ALL COMPONENT PARTS BEFORE USING CRIMPER KEEP HANDS AWAY FROM PINCH POINTS CONSULT HOSE AND FITTING
More informationLANAP300 Installation Instructions
LANAP300 Installation Instructions Converts Early Model Belt Pick-Up Heads to 50, 60, & 70 Series Combines DO NOT USE THIS KIT FOR 12 PICK UP HEADS & WIDE BODIED COMBINES (i.e. 9600, 9610, 9650W) 270 West
More informationServices to Technology Providers
Services to Technology Providers Training and Capacity building activities with HP boiler manufacturers Session 3: firing systems Trainer: Frans Baltussen Date: first half 2015 Overview combustion technology
More informationBravo Platform Unpacking Guide
This guide describes how to unpack the Bravo device from the shipping carton. Depending on the order, the shipment can include additional packages for the Bravo utilities, pipetting head, computer, and
More informationMagnetic Separators. Flow Ezy Filters Ann Arbor, MI or
Magnetic Separators Flow Ezy Filters Ann Arbor, MI 48106 800-237-1165 or 734-665-8777 flowezy@flowezyfilters.com www.flowezyfilters.com Contents 2 Rod Sampling probe Circular grid 3 Square grid Sieve magnet
More informationDR CHIPPER ATTACHMENT for the DR FIELD and BRUSH MOWER SAFETY & OPERATING INSTRUCTIONS. Serial No. Order No.
DR CHIPPER ATTACHMENT for the DR FIELD and BRUSH MOWER SAFETY & OPERATING INSTRUCTIONS Serial No. Order No. DR Power Equipment Toll-free phone: 1-800-DR-OWNER (376-9637) Fax: 1-802-877-1213 Web site: www.drpower.com
More informationSAFE SYSTEMS FOR PILING OPERATIONS
SAFE SYSTEMS FOR PILING OPERATIONS TYPE & METHOD OF CONSTRUCTION OF PILE BORED CAST-IN-SITU (BCIS) BCIS WITH CONVENTIONAL RIG BCIS WITH ROTARY RIG DRIVEN CAST-IN-SITU (DCIS) DCIS WITH CONVENTIONAL DP RIG
More informationCusters. Camino CHIMNEY SCAFFOLDING ASSEMBLY AND USER S INSTRUCTIONS. Nov. 2003
ASSEMBLY AND USER S INSTRUCTIONS Custers Camino CHIMNEY SCAFFOLDING 9505.903.001 ENG / (9505.202.015/016) Nov. 2003 CUSTERS HYDRAULICA B.V. Smakterweg 33, 5804 AE VENRAY NL Telephone : +31 (0) 478 55 30
More informationCovered by one or more of the following patents: 3, ,368,429 5,984,605 7,556,464 7,726,901 7,828,506 7,726,901 Other patents pending
Covered by one or more of the following patents: 3,828942 5,368,429 5,984,605 7,556,464 7,726,901 7,828,506 7,726,901 Other patents pending O P E R AT O R S M A N U A L For Model 460 WA R N IN G Re a d
More informationINSTALLATION MANUAL MOSER STAINLESS STEEL KITCHEN FAUCET MODEL MANCHESTER
INSTALLATION MANUAL MOSER STAINLESS STEEL KITCHEN FAUCET MODEL MANCHESTER Thank you for your purchase of a MoSER faucet. With proper care and maintenance, your new faucet will bring you years of trouble
More informationAdvanced Life Support Basic Life Support Trainer
Advanced Life Support Basic Life Support Trainer Model numbers 101-080 and 101-085 Phone: (845)-679-2475 (800)-431-4310 Fax: (845)-679-8996 www.simulaids.com Intubation Head Installation: Connect color
More information1.6S PP SPUNBOND NONWOVEN PRODUCTION LINE. Ⅰ. Application
1.6S PP SPUNBOND NONWOVEN PRODUCTION LINE Ⅰ. Application This equipment is suitable for the production of spunbond nonwovens with a variety of colors and different properties using PP chips as main material
More information11, 000- L b. E x t r e m e - D u t y P a l l e t Tr u c k OWNER S MANUAL
11, 000- L b. E x t r e m e - D u t y P a l l e t Tr u c k OWNER S MANUAL WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules
More informationWISCONSIN WOODLANDS. Getting Ready Safety Equipment. Adjusting chain tension G3205
- G3205 WISCONSIN WOODLANDS The chain saw is a versatile and efficient tool, but many accidents result from its improper use. This publication covers the fundamentals of safe tree harvesting with a chain
More informationThe following document can be provided to an Engineer, Contractor, or Owner to allow them to properly specify MESAN s MXR-KM series Cooling Towers.
MESAN MXR-KM Engineering Guide Specifications The following document can be provided to an Engineer, Contractor, or Owner to allow them to properly specify MESAN s MXR-KM series Cooling Towers. 15XXX-
More informationGeneral Guidelines. Tools Required. Instructions for Part # SC500-AF. Safety
Instructions for Part # SC500-AF General Guidelines It is the user s responsibility to read and follow all instructions. Keep these instructions with the product at all times and review before each use.
More informationMODEL 285A-HD Heavy-Duty Forklift-Karrier Operator s Manual for Morse Heavy-Duty Forklift-Karrier Model 285A-HD
Contents Page Receiving Procedures.................... 1 Warranty............................. 1 Safety Information..................... 1-2 Machine Description................... 3-4 Operating Instructions....................
More informationSUGGESTED SPECIFICATIONS
SUGGESTED SPECIFICATIONS SERIES 3000 SUSPENDED, SCREENED WET-PIT PUMPS PART 1 GENERAL 1.1 DESCRIPTION Work Included: Under this section, the contractor shall provide all labor, equipment and material necessary
More informationMATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 1850 NOVEMBER 2018 MATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS TABLE OF CONTENTS 1850.01 SCOPE 1850.02 REFERENCES 1850.03 DEFINITIONS
More informationDrag Chain Conveyor Installation and Operation Manual
Drag Chain Conveyor Installation and Operation Manual Material Handling Equipment Sales, Incorporated 310 S. Section Line Rd Delaware, OH 43015 Phone: (989) 430-4005 Fax: (740) 363-9004 WARRANTY MATERIAL
More informationSection 5 Roller Chain Drive Components
8981 00 269 08/14 TSplus Assembly Conveyors -1 Roller Chain Components Section Roller Chain Components TSplus roller chain drives provide the largest payload carrying capacity of the three conveying media
More informationTECH HANDBOOK. Aftersort Inc. EXPANDABLE CONVEYORS. DO NOT OPERATE BEFORE READING THIS HANDBOOK Important Safety Information Enclosed
EXPANDABLE CONVEYORS TECH HANDBOOK Installing and Maintaining Your Expandable Conveyor Aftersort Inc. DO NOT OPERATE BEFORE READING THIS HANDBOOK Important Safety Information Enclosed KEEP IN SAFE PLACE--DO
More informationH07 H09. BENCH FUME HOOD with Combination Sash. Fume Hoods. Installation Instructions. 48"- 60"- 72"- 96" long
Installation Instructions Supreme Air BENCH FUME HOOD with Combination Sash H07 H09 S T Y L E Fume Hoods 48"- 60"- 72"- 96" long Publication No. IIH07-SA 07/06 Part Number: IMAN-H07 FUME HOOD END PANEL
More informationH50. DYNAMIC BARRIER Bench Fume Hood. Fume Hoods. Installation Instructions. 48"- 60"- 72"- 96" long
Installation Instructions Supreme Air DYNAMIC BARRIER Bench Fume Hood H50 S T Y L E Fume Hoods 48"- 60"- 72"- 96" long Publication No. IIH50-SA 06/01 Part Number: IMAN-H50 Kewaunee Scientific Corporation
More informationS-5 Bulk Filler System
Logical Machines 1158 Roscoe Road Charlotte, Vermont 05445 802.425.2888 www.logicalmachines.com S-5 Bulk Filler System What is the Logical Machines S-5 The S-5 is used to fill containers with an operator
More information1001-B PRECISION GARDEN SEEDER ASSEMBLY and OPERATING INSTRUCTIONS
1001-B PRECISION GARDEN SEEDER ASSEMBLY and OPERATING INSTRUCTIONS HELPFUL HINTS: READ THE DIRECTIONS BEFORE ASSEMBLY 5 This seeder comes partially assembled, requiring you to install the wheels, handle
More informationDough Sheeter. Instruction Manual
Dough Sheeter Item No. 27960 Instruction Manual Version 1 3115 Pepper Mill Court, Mississauga, ON, L5L 4X5 4450 Witmer Industrial Estates, Unit 4, Niagara Falls, NY, 14305 1-800-465-0234 www.omcan.com
More informationMATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS 1850 APRIL 2018 (Formerly OPSS 1850, April 2013) Note: The MUNI implemented in April 2018 replaces OPSS 1850 COMMON, April 2013 with no technical content
More informationLCD INSTALLATION MANUAL V.1
X2 LCD INSTALLATION MANUAL V.1 www.odesutvs.com INDEX Steps 1-5: Uncrating ------------------------------------------------------------------------- Pgs. 1 /2 Steps 6-9: Dash Removal ------------------------------------------------------------------
More informationHL STOKER AUGER PACKER
HL STOKER AUGER PACKER SAFETY INSTALLATION OPERATION MAINTENANCE 1 OF 26 FOREWARD This manual has been prepared to assist you with your Choice Bagging Equipment, Ltd. bag packaging equipment. The text
More informationSICO Roll N Set Folding Leg Stage. A mobile multiple-height performance stage system for large venues.
SICO Roll N Set Folding Leg Stage A mobile multiple-height performance stage system for large venues. Features, Advantages & Benefits Structural Deck (SICO Venue Maker) 4 x8 deck sections provide a sturdy,
More informationEndura 8000 Series Swivel Manual Dual Split Flange (DSF) Swivel Joint
Leading The Way in Fluid Handling Solutions Worldwide Endura 8000 Series Swivel Manual Dual Split Flange (DSF) Swivel Joint Document No. H32001PA Revised: January, 2016 The Endura Dual Split Flange (DSF)
More informationMATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1850 APRIL 2013 MATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS TABLE OF CONTENTS 1850.01 SCOPE 1850.02 REFERENCES 1850.03 DEFINITIONS
More informationONTARIO PROVINCIAL STANDARD SPECIFICATION
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1850 NOVEMBER 2003 MATERIAL SPECIFICATION FOR FRAMES, GRATES, COVERS, AND GRATINGS TABLE OF CONTENTS 1850.01 SCOPE 1850.02 REFERENCES 1850.03 DEFINITIONS
More informationService Manual For the E Ride 26
Service Manual For the E Ride 26 For: Training Troubleshooting Adjustments Rev. 04/2013 Contents 1 Cautions ------------------------------------------------------------------------- Page 4 2 Safety Information
More informationIN-TANK TECHNOLOGY INSTRUCTIONS FOR USING FLO KING IN-TANK CARBON BAG
Carbon Bag Instructions Page 1 INSTRUCTIONS FOR USING FLO KING IN-TANK CARBON BAG Do not attempt to carbon treat a solution before you have thoroughly filtered it! This almost certainly will result in
More informationTable of contents Our products We are offering three product groups: Quality and Service Our product groups Basic products-panels EURO, Light Version, Compensatory, Round Top Gates and Pedestrian Gates
More information5500-Lb. Capacity Pallet Jack
5500-Lb. Capacity Pallet Jack Owner s Manual WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions
More informationInstruction Manual Span Scaffolds! W A R N I N G! Before using Instant UpRight Scaffolds, read, understand and follow all Safety Rules, Erection Instructions and Maintenance Rules. Keep this manual for
More informationCR-3000 Car Rotator Capacity 3,000 lbs Installation Manual 2016 Mar
Car Rotator Capacity 3,000 lbs Installation Manual 2016 Mar INDEX 1. OWNER / USER RESPONSIBILITIES---------------------------------------- PAGE 3 2. SAFETY PROCEDURES---------------------------------------------------------
More informationOperating Instructions
Operating Instructions Series B37000 Hose Reels BB37118 L CB37118 L EB37118 L12D BB37122 L CB37122 L EB37122 L12D BB37128 L CB37128 L EB37128 L12D Dimensional Data C A B D Part # A B C D BB/CB37118 L 31
More informationOPERATOR S MANUAL Model 56A Prefeed / Dereeler
110 Fairgrounds Drive P.O. Box 188 Manlius, NY 13104-0188 USA 315.682.9176 FAX: 315.682.9160 OPERATOR S MANUAL Model 56A Prefeed / Dereeler PRODUCTION WIRE PROCESSING EQUIPMENT Website: www.carpentermfg.com
More information