The Ottawa River Great Lakes Legacy Act Cleanup Project. March 12, 2009

Similar documents
EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO

Lessons Learned, Innovations, and Successes from U.S. Great Lakes Areas of Concern Sediment Cleanups

Industry Perspective on the Great Lakes Legacy Act Sediment Remediation Program

Buffalo River, New York Great Lakes Restoration Initiative (GLRI) Dredging

APPLICATION FOR 2013 WEDA ENVIRONMENTAL EXCELLENCE AWARD ENVIRONMENTAL DREDGING CATEGORY RIVER RAISIN AREA OF CONCERN PROJECT, MONROE, MICHIGAN

Great Lakes Legacy Act. Marc Tuchman U.S. EPA Great Lakes National Program Office

OTTAWA RIVER REMEDIATION PROJECT DESIGNS (SEDIMENT AND HYDROLOGICAL INVESTIGATION)

Buffalo River Area of Concern Cleanup Public Meeting

The Great Lakes Legacy Program:

Lower River and Inner Harbor of the Sheboygan River

ASHTABULA RIVER SEDIMENT REMEDIATION: PLANNING, DESIGN, AND THE ASHTABULA RIVER PARTNERSHIP

Public Meeting June 22, :00 7:30 pm

PROPOSED PLAN FOR CLEANING UP THE LOWER 8 MILES OF THE LOWER PASSAIC RIVER

Remediation of Contaminated Sediment at the Unnamed Tributary to the Ottawa River

Great Lakes Legacy Act: Program Overview and Status of Lake Superior Projects

New York- New Jersey Harbor Estuary. Lower Passaic River

EAST WATERWAY HARBOR ISLAND SUPERFUND SITE CLEANUP CLEANING UP THE ENVIRONMENT, WHILE IMPROVING COMMERCE FOR THE PORT OF SEATTLE

CONSTRUCTION QUALITY ASSURANCE FOR OTTAWA RIVER DREDGING

Grand Calumet. River Revitalized

Is It Time to Create a National Legacy Act Program? Why Should the Great Lakes Have All the Fun?

CLEANUP GOAL EVALUATION AND SEDIMENT DISPOSAL FOR THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT

PORTLAND HARBOR SUPERFUND CLEANUP MOVING FORWARD TO A RESPONSIBLE, COLLABORATIVE SOLUTION

Excavation Of Pcb-Contaminated Sediment Adjacent To The Intake Of A 12-Mgd Drinking Water Plant

A One Water Approach to Restoring Sheboygan River and its Legacy

Newton Creek & Hog Island Inlet Contaminated Sediment Remediation Project

East Branch of Grand Calumet River, Reaches 4A/4B. WEDA WODCON XXI June 13-17, 2016 The Hyatt Regency, Miami, FL

U. S. Steel Duluth Works - Spirit Lake Cleanup Plan FAQs

Anacostia River Sediment Project Current Status. September 28, 2017

Great Lakes Legacy Act. Marc Tuchman U.S. EPA Great Lakes National Program Office

Ashtabula Harbor, Ohio Great Lakes Restoration Initiative (GLRI) Dredging

Joe Cappel Toledo-Lucas County Port Authority. Wednesday, March 14, Western Dredging Association 2018 Midwest Chapter Meeting

Lower Passaic River Study Area. Overview of Proposals for the Upper 9 Miles of the Lower Passaic River

Appendix D LPRSA RM 10.9 Removal Action and Pilot Tests - Statement of Work Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10.

Prioritizing Habitat Projects in Areas of Concern Throughout the Great Lakes

million cubic yards of PCB contaminated sediments from the Kalamazoo River on to the Allied

FOCUSED FEASIBILITY STUDY FOR PASSAIC RIVER SEDIMENTS: IDENTIFYING OPPORTUNITIES FOR EARLY ACTION

Portland Harbor Superfund Site. Jessica Hamilton. October 3, 2013

US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition

FORUM ON USE OF CAD CELLS IN NEWARK BAY VS. OFF-SITE DISPOSAL

ROCHESTER EMBAYMENT AREA OF CONCERN

Hudson River PCBs Superfund Site

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

Comprehensive Modeling of Dredge Resuspension and Residual Effects of Remedial Alternatives: Portland Harbor Feasibility Study

Esquimalt Graving Dock Waterlot Remediation Mega-Site (Phase 1B): Design, Contracting, and Construction Challenges

Existing Impairments. Whitefish Lake: PCBs and Mercury

Summary of Investigations & Remedial Activities

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011

Feasibility Study Work Plan. for the. Passaic River Study Area

Anacostia River Sediment Project Overview- For a Cleaner Anacostia River. Remedial Investigation May 12, 2015 Dev Murali, PG, RPM

D2 Project Environmental Remediation Briefing August 21, 2018

A Multifaceted Urban Stream Restoration Project for the Ottawa River at the University of Toledo Progress Report

PA-03. Honorable Mike Kelly. Pennsylvania 114th Congress. 3rd Congressional District. Miles

ST. JOHNS RIVER WATER MANAGEMENT DISTRICT

Portland Harbor Superfund Site - Introduction

Monthly Meeting Summary Thursday, February 8, 2018

Photo Optional. Using a PMP Approach to Attain TMDLs (An update to the PMP Approach to PCB Loading Reduction at Two Amtrak Facilities) Presented by:

2015 WEDA Environmental Excellence Award East Branch Grand Calumet River Remediation Reaches 4a and 4b GREAT LAKES SEDIMENT REMEDIATION, LLC

Detroit River. Area of Concern Canadian Section. Status of Beneficial Use Impairments September 2010

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION BROADWAY NEW YORK, NEW YORK 10007

Hudson River Cleanup and PCBs Community Advisory Group March 22, 2012

REUSE OF DREDGED SEDIMENTS

PLANNING AND ENGINEERING CONSIDERATIONS FOR A 1.5 MILLION CUBIC METER LAKE DREDGING PROJECT

Newtown Creek Superfund Site CAG Meeting October 11, 2017

Status of the Niagara River (New York) RAP

General Motors (Central Foundry Division) Cleanup Progress Update Massena, St. Lawrence County, NY

Greater Trinity River Bacteria TMDL Project

Environmental Remediation Services Draft Focused FS FGGM 83/OU-1 Former Skeet Range

Mid-Atlantic Contaminated Sediment Symposium: Navigating through Contaminated Sediments to Achieve our Vision of a World Class Harbor Estuary

City of Oregon Wastewater Treatment Plant (WWTP) Secondary Treatment Improvement Project Phases 1 & 2 FAQ Sheet

Kingston Steam Plant-Ash Spill Kingston Fossil Plant Fly Ash Spill

Portland Harbor in the Post-ROD World Integrating In-Water & Upland Remedies and Permitted Discharges --Legal Structure and Tools

Environmental Protection (NJDEP) The Louis Berger Group, Inc.

Paul Koval Ohio EPA (614)

2018 Monitoring Strategy for the Des Plaines River Watershed. Purpose

Identifying and Managing Key Cost Drivers During Investigation, Remedy Selection and Design at Contaminated Sediment Sites

Fernando Camargo, Hull & Associates, Inc. On behalf of Joe Cappel Toledo-Lucas County Port Authority. Thursday, December 7, 2017

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds

Dr. Peter defur Environmental Stewardship Concepts, LLC March 22, 2012

Port and Maritime. GOALS, OBJECTIVES, and PRIORITY ACTIONS. Loading of PCBs to the NY/NJ Harbor Estuary PORT AND MARITIME WORK GROUP

Lower Passaic River Restoration Planning

GRADING, EROSION AND SEDIMENTATION CONTROL

EPA S STORMWATER RULE

OH-13. Honorable Tim Ryan. Ohio 114th Congress. 13th Congressional District. Miles. 1, CG-CAP 205, Tinkers Creek

Sewer Separation and Stormwater Management (with Emphasis on Flood Control)

Former Potrero Power Plant Site Remediation WELCOME. PG&E Community Open House

Summary: project description: goals, objectives, accomplishments

Cleveland Harbor Open Lake Placement

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017

John Hull, P.E., BCEE, Hull & Associates, Inc. Ted Smith, Marine Tech LLC. Thursday, December 7, 2017

Newtown Creek Superfund Site Point Sources Sampling CAG Meeting March 22, 2016

Lower Passaic River Restoration Project & Newark Bay Study

87th Air Base Wing Joint Base McGuire-Dix-Lakehurst Public Meeting December 13, 2017 Proposed Plan McGuire Operable Unit-3

PROJECT OVERVIEW. Site Assessment for Proposed Coke Point Dredged Material Containment Facility at Sparrows Point

St. Louis River Area of Concern A Great Lakes Restoration Initiative - MN Legacy Fund Partnership

SEDIMENT CHOREOGRAPHY

National Pollutant Discharge Elimination System (NPDES) Permit Program F A C T S H E E T

Oregon DEQ's Perspectives on Portland Harbor

FACT PATTERN THE RESERVATION

Proposed Plan Closed Sanitary Landfill

Hamilton Harbour. Area of Concern Status of Beneficial Use Impairments September 2010

Transcription:

The Ottawa River Great Lakes Legacy Act Cleanup Project March 12, 2009

Ottawa River Project Timeline January 1998 to December 2007 Various entities sample the site, source control implemented (including sediment remediation in Unnamed Tributary) June 2005 USFWS sends interest letters to PRPs August 2007 OEPA assembles PRPs January 2008 Companies form ORG March 2008 ORG applies for GLLA funding for design of a remedy for the Ottawa River (includes additional investigations) June 2008 ORG and USEPA sign a $1.5M costsharing agreement for sampling and design work June-August 2008 ORG/USEPA investigation

Ottawa River Project Timeline September 2008: ORG completes alternatives analysis October 2008: ORG completes Preliminary Design Document October 2008 ORG applies for GLLA funding for remediation of the Ottawa River December 2008 ORG submits pre-final design December 2008 Public meeting in Toledo, Ohio to present and discuss project January 2009 ORG addresses comments on the prefinal design from stakeholders January 2009 ORG and USEPA signs Project Agreement with USEPA for remediation funding

OTTAWA RIVER PROJECT TIMELINE February 2009 to August 2010: Public outreach, communications, and project updates. March 2009 Public Meeting? July 2009: Mobilization and construction activities begin at Hoffman Road Landfill August 2009 to December 2009 Dredging activities initiated. All TSCA sediments dredged, dewatered and disposed. April 2010 Dredging activities restart August 2010 Dredging Complete October 2010 Dewatering activities complete; Cover layer placement complete December 2010 All construction activities complete

OTTAWA RIVER GROUP Allied Waste Industries, Inc. Chrysler LLC City of Toledo DuPont Co. GenCorp Inc. Honeywell International Inc. Illinois Tool Works, Inc. United Technologies Unnamed Tributary Group 5

OUTLINE OF PROPOSAL PRESENTATION I. INTRODUCTION AND HISTORY II. PROPOSED PROJECT III. SCHEDULE AND COSTS IV. CONCLUSION 6

I. INTRODUCTION AND HISTORY 7

LOCATION The Ottawa River is located in Toledo, Ohio. The Project is within an Area of Concern as defined by the International Joint Commission. 8

OTTAWA RIVER HISTORY Ottawa River is a tributary to Maumee Bay Contaminant sources included, but are not limited to: Multiple Landfills Combined Sewer and Sanitary Sewer Overflows (6 CSOs and 2 SSOs still active) Unnamed Tributary (Fraleigh Creek) Stickney West Industrial Park (SWIP) and Royster Fertilizer Toledo Tie Treatment Facility XXKem 9

10

OTTAWA RIVER HISTORY (Cont d) Recent Cleanup Actions Stickney and Tyler landfills capped in 1998 XXKem Site capped and extraction trench installed in 1998 GenCorp / Textileather Cleanup completed 1998 AquaBlock TM Project Toledo Tie Treatment sediment removed and barrier installed in 1998 Dura Landfill capped in 2001 SWIP Property cleaned up and developed as Brownfield CSO work identified and scheduled by City of Toledo 11

STATEMENT OF COMMITMENT FROM ORG Investigations, feasibility and design studies are complete. Alternatives have been evaluated and compared. Project design activities currently ongoing. The proposed comprehensive cleanup plan presented today is ready to be implemented, subject to appropriate public participation. The Ottawa River Group is prepared to fund up to 50% of the local share and accept complete responsibility for the long-term operation, maintenance and monitoring of the disposal facility (as necessary). 12

II. PROPOSED PROJECT 13

OTTAWA RIVER PROJECT AREA The Ottawa River Project Area was determined based upon extensive sampling and analyses events from 1998 to 2008. The Ottawa River Project Area has generally been delineated into 4 segments: Reach 1: Maumee Bay to approximately river mile (RM) 3.2 Reach 2 and Stickney Avenue Depositional Zone (SADZ): RM 3.2 to approximately RM 4.9 Reach 3 and Sibley Creek: Approximately RM 4.9 to approximately RM 6.5 Reach 4: Approximately RM 6.5 to RM 8.8 14

PROJECT AREA 15

PROJECT AREA 16

OTTAWA RIVER PROJECT OBJECTIVES Remove a significant volume of contaminated sediment mass Contain the removed sediment in a disposal facility Reduce human health and ecological risks to acceptable levels Improve the chemical, physical and biological integrity of the Ottawa River ecosystem Provide a revitalized Ottawa River ecosystem to the community Eliminate a hydrologic unit from an Area of Concern in the Great Lakes 17

OTTAWA RIVER SEDIMENT CONDITIONS Primary Contaminants of Concern are: Polychlorinated Biphenyls ( PCBs ) Polyaromatic Hydrocarbons ( PAHs ) Lead Oil and Grease 18

TYPICAL CONTAMINANT DISPERSION IN A RIVER SYSTEM Approximate Dredge Prism 19

POTENTIAL ROUTES OF HUMAN EXPOSURE Direct Contact PCBs present at concentrations up to 451 mg/kg in top 4- inches of sediment (2007) Direct contact advisories within the Project Area Fish Consumption Elevated concentrations of PCBs detected in carp tissue in 2007 (1.6 to 5.5 mg/kg). Do Not Eat level is 2.0 mg/kg. Fish advisories exist for all species from within the Project Area 20

EXCEEDENCES OF APPLICABLE SEDIMENT SCREENING LEVELS (From EPA 2007 Study) Probable Effect Concentrations (PEC) (level above which harmful effects are likely to be observed) PCBs 7 of 10 sample locations exceeded PEC PAHs 8 of 10 sample locations exceeded PEC for 2 or more PAH compounds Lead 3 of 10 sample locations exceeded PEC 21

GENERAL CONSIDERATIONS FOR REMEDIAL OPTIONS Evaluation of major sources of chemical contamination storm or sanitary sewer discharges, landfills, spills, etc. Sediment removal using environmental dredging techniques Dewatering/disposal of contaminated sediments 22

OTTAWA RIVER PROJECT COMPONENTS Environmental dredging Sediment cover (if appropriate) Transportation Dewatering Disposal Monitoring during operations Operation and Maintenance (as necessary) 23

GUIDELINES FOR DREDGING SCENARIO Prepare cross sections every 100 ft Interpolation of PCB, PAH, lead and oil & grease data at various depths Plot isoconcentration lines Evaluate cross sections evaluated (utilize co-located chemistry as part of developing design) Develop dredging scenarios (cutlines) development 24

Typical Cross Sections

SCREENED REMEDIAL ALTERNATIVES No Action Monitored Natural Recovery Capping Post dredging Objective Long Term Objective Cover System Natural Recovery 26

REMEDIAL ALTERNATIVES SCREENING CRITERIA EFFECTIVENESS Short- and long- term effects on human health and environment PCB, PAH, lead and oil & grease removed from system Risk reduction IMPLEMENTABILITY Quantities of sediment dredged Public acceptance Disposal options Access COSTS Capital and In-Kind O &M 27

PROPOSED REMEDIAL OPTION Hydraulically dredge approximately 250,000 cubic yards of sediment (approximately 25,000 TSCA) Transport sediments via pipeline Dewater sediments utilizing geotextile tubes Treatment of weep water to Ohio water quality standards Dispose sediments in a permitted facility Perform operations and maintenance program Allow natural recovery of system 28

ANTICIPATED BENEFITS OF PROPOSED OPTION Removes majority of contaminant mass (e.g. approximately 90% of PCBs) Properly treats water and securely contains contaminated sediments Reduces human health and ecological risks to acceptable levels Broadly improves the Ottawa River ecosystem; Revitalizes a community resource the Ottawa River Restores beneficial uses to a Great Lakes Area of Concern 29

DESIGN BASIS FOR PROPOSED PROJECT Dredging cutlines based on target concentrations PCB- 5 mg/kg PAH 30 mg/kg Lead 200 mg/kg Estimated post dredging surface weighted average concentration (SWAC) PCBs 1.5 mg/kg Total PAHs (16) 30 mg/kg Lead 200 mg/kg Long Term SWAC / natural recovery goals PCBs 0.75 mg/kg Total PAHs (16) 22.8 mg/kg Lead 128 mg/kg 30

Dewatering Process

PROPOSED PROJECT DESIGN ELEMENTS Hydraulic dredging upstream to downstream Turbidity monitoring before, during, and after dredging Option A - Transporting TSCA sediment via pipeline to dewatering facility with geotextile tubes, Transferring dewatered sediment to TSCA facility Option B- Transporting remaining sediments via pipeline to either the existing Hoffman Landfill, a newly constructed cell or another commercial facility Dewatering sediments through use of geotextile tubes; Disposing non-tsca sediments Treating and discharging weep water to Ottawa River through NPDES Allowing re-sedimentation of river (estimated to be 0.4 cm/year anticipated to be higher in dredged area) 32

III. SCHEDULE AND COSTS 33

PROPOSED SCHEDULE Final Design and Specifications Design/Permit Approval/Procurement Contracting and Mobilization for Disposal Facility Construction Begin Disposal Facility Construction Begin WTP Construction Procurement/Contracting and Mobilization for Dredging Begin Dredging Sediments Dredging Complete Placement of Landfill Cover Begin Post-Closure O&M March 2009 April 2008 April 2009 April 2009 May 2009 June 2009 June 2009 September 2010 August 2010 October 2010 34

COST ESTIMATE Design & Land Acquisition $ 1,400,000 Site Setup and Construction Activities $ 1,000,000 Landfill Costs (based on constructing cell) $ 8,000,000 Material Placement $ 2,000,000 Water Treatment $ 6,300,000 Dredging $ 9,000,000 Transportation $ 3,700,000 Administrative $ 2,700,000 Contingency 20% $ 6,820,000 Total Funding $ 40,920,000 Total Local Share (50%): $ 20,460,000 Total GLLA Share (50%): $ 20,460,000 Total Project Cost: $ 40,920,000 35

CONCLUSION Design for remediation is underway Bid specifications being prepared Project team is experienced with GLNPO process Project implementation can be phased to accommodate multi-year funding (if necessary) Ottawa River Group is a viable Local Sponsor The Ottawa River Group s project - SATISFIES THE GLLA STATUTORY QUALIFICATIONS AS A PRIORITY PROJECT; REMEDIATES A SIGNIFICANT PORTION OF AN AOC; and IS READY TO BE IMPLEMENTED. 36

Questions T. Casey Stephens Commissioner, Public Service Hoffman Road Landfill 3962 Hoffman Road Toledo, OH 43611 419.936.2643 Casey.Stephens@toledo.oh.gov