MAY 11, 2017 T-MC-107A & T-MC-107B1

Similar documents
Transcription:

Schedule of Bid Items - Part A ROADWAY 107A 201(A) - CLEARING AND GRUBBING - LSUM 1.00 30,000.00 30,000.00 $100,000.00 $100,000.00 $65,000.00 $65,000.00 $120,000.00 $120,000.00 $50,000.00 $50,000.00 $18,262.05 $18,262.05 202(A) - UNCLASSIFIED EXCAVATION - CY 144,942.00 6.00 869,652.00 $3.80 $550,779.60 $4.10 $594,262.20 $4.00 $579,768.00 $5.00 $724,710.00 $6.10 $884,146.20 205(A) - TYPE-A SALVAGED TOPSOIL - LSUM 1.00 39,000.00 39,000.00 $33,671.26 $33,671.26 $40,000.00 $40,000.00 $125,000.00 $125,000.00 $40,000.00 $40,000.00 $31,483.14 $31,483.14 221(C) - TEMPORARY SILT FENCE - LF 5,100.00 1.50 7,650.00 $1.88 $9,588.00 $1.08 $5,508.00 $1.30 $6,630.00 $1.01 $5,151.00 $1.01 $5,151.00 221(F) - TEMPORARY SILT DIKE - LF 714.00 7.00 4,998.00 $6.74 $4,812.36 $6.27 $4,476.78 $5.50 $3,927.00 $5.89 $4,205.46 $5.89 $4,205.46 227 - (SP) HIGH PERFORMANCE TURF REINFORCEMENT MAT - SY 8,795.00 20.00 175,900.00 $17.50 $153,912.50 $16.75 $147,316.25 $19.00 $167,105.00 $16.48 $144,941.60 $16.48 $144,941.60 230(A) - SOLID SLAB SODDING - SY 67,959.00 1.50 101,938.50 $0.92 $62,522.28 $0.96 $65,240.64 $1.00 $67,959.00 $0.94 $63,881.46 $0.90 $61,163.10 232(B) - SEEDING METHOD B - SY 28.00 400.00 11,200.00 $164.70 $4,611.60 $159.75 $4,473.00 $325.00 $9,100.00 $150.00 $4,200.00 $150.00 $4,200.00 233(A) - VEGETATIVE MULCHING - AC 14.00 350.00 4,900.00 $174.57 $2,443.98 $169.34 $2,370.76 $100.00 $1,400.00 $159.00 $2,226.00 $159.00 $2,226.00 241 - MOWING - AC 84.00 50.00 4,200.00 $63.68 $5,349.12 $61.77 $5,188.68 $50.00 $4,200.00 $58.00 $4,872.00 $58.00 $4,872.00 303(A) - AGGREGATE BASE TYPE A - CY 4,114.00 40.00 164,560.00 $34.60 $142,344.40 $32.00 $131,648.00 $32.00 $131,648.00 $65.00 $267,410.00 $48.00 $197,472.00 307(K) - STABILIZED SUBGRADE - SY 19,289.00 5.00 96,445.00 $4.34 $83,714.26 $4.60 $88,729.40 $4.50 $86,800.50 $5.65 $108,982.85 $6.00 $115,734.00 325 - SEPARATOR FABRIC - SY 23,528.00 1.10 25,880.80 $0.85 $19,998.80 $1.22 $28,704.16 $1.00 $23,528.00 $2.00 $47,056.00 $1.10 $25,880.80 402( E) - TRAFFIC BOUND SURFACE COURSE TYPE E - TON 2,688.00 15.00 40,320.00 $12.57 $33,788.16 $2.50 $6,720.00 $7.00 $18,816.00 $18.00 $48,384.00 $20.00 $53,760.00 404(G) - ULTRA-THIN BONDED WEARING COURSE (TYPE C) - TON 551.00 77.00 42,427.00 $121.06 $66,704.06 $106.50 $58,681.50 $110.00 $60,610.00 $250.00 $137,750.00 $150.00 $82,650.00 408 - PRIME COAT - GAL 11,340.00 3.00 34,020.00 $0.25 $2,835.00 $0.50 $5,670.00 $0.50 $5,670.00 $2.70 $30,618.00 $2.60 $29,484.00 411(B) - SUPERPAVE, TYPE S3 (PG 76-28 OK) - TON 1,048.00 65.00 68,120.00 $79.97 $83,808.56 $56.45 $59,159.60 $55.00 $57,640.00 $66.00 $69,168.00 $67.35 $70,582.80 411(B) - SUPERPAVE, TYPE S3 (PG 64-22 OK) - TON 9,939.00 55.00 546,645.00 $57.84 $574,871.76 $42.00 $417,438.00 $47.00 $467,133.00 $50.00 $496,950.00 $55.00 $546,645.00 411(C) - SUPERPAVE, TYPE S4 (PG 76-28 OK) - TON 822.00 80.00 65,760.00 $90.17 $74,119.74 $69.23 $56,907.06 $68.00 $55,896.00 $68.00 $55,896.00 $89.10 $73,240.20 411(C) - SUPERPAVE, TYPE S4 (PG 70-28 OK) - TON 1,960.00 72.50 142,100.00 $67.49 $132,280.40 $71.36 $139,865.60 $70.00 $137,200.00 $75.00 $147,000.00 $79.75 $156,310.00 412 - COLD MILLING PAVEMENT - SY 17,191.00 3.00 51,573.00 $0.54 $9,283.14 $0.82 $14,096.62 $0.90 $15,471.90 $3.50 $60,168.50 $1.50 $25,786.50 501(A) - STRUCTURAL EXCAVATION UNCLASSIFIED - CY 197.00 20.00 3,940.00 $19.02 $3,746.94 $21.30 $4,196.10 $30.00 $5,910.00 $20.00 $3,940.00 $20.00 $3,940.00 502 - TEMPORARY EARTH RETAINAGE - LSUM 1.00 70,000.00 70,000.00 $11,265.76 $11,265.76 $21,300.00 $21,300.00 $88,000.00 $88,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 509(A) - CLASS AA CONCRETE - CY 320.00 400.00 128,000.00 $383.03 $122,569.60 $317.37 $101,558.40 $550.00 $176,000.00 $298.00 $95,360.00 $298.00 $95,360.00 511(A) - REINFORCING STEEL - LBS 47,082.00 1.00 47,082.00 $1.00 $47,082.00 $0.85 $40,019.70 $0.85 $40,019.70 $0.80 $37,665.60 $0.80 $37,665.60 601(B) - TYPE 1-A PLAIN RIPRAP - TON 282.00 40.00 11,280.00 $32.02 $9,029.64 $46.86 $13,214.52 $32.00 $9,024.00 $66.00 $18,612.00 $52.06 $14,680.92 619(A) - REMOVAL OF STRUCTURES & OBSTRUCTIONS - LSUM 1.00 7,000.00 7,000.00 $22,886.30 $22,886.30 $1,463.66 $1,463.66 $15,326.97 $15,326.97 $6,500.00 $6,500.00 $3,532.65 $3,532.65 619(B) - REMOVAL OF FENCE - LF 1,977.00 1.50 2,965.50 $0.82 $1,621.14 $0.64 $1,265.28 $1.00 $1,977.00 $0.75 $1,482.75 $0.64 $1,265.28 619(B) - REMOVAL OF ASPHALT PAVEMENT - SY 4,667.00 3.50 16,334.50 $3.09 $14,421.03 $3.74 $17,454.58 $2.50 $11,667.50 $4.00 $18,668.00 $4.00 $18,668.00 619(B) - REMOVAL OF GUARDRAIL - LF 2,600.00 3.00 7,800.00 $2.19 $5,694.00 $1.87 $4,862.00 $2.00 $5,200.00 $3.19 $8,294.00 $2.00 $5,200.00 619(B) - REMOVAL OF CONCRETE MEDIAN BARRIER - LF 500.00 5.50 2,750.00 $5.98 $2,990.00 $4.93 $2,465.00 $6.00 $3,000.00 $6.50 $3,250.00 $6.20 $3,100.00 619(C) - SAWING PAVEMENT - LF 4,200.00 3.00 12,600.00 $1.10 $4,620.00 $1.96 $8,232.00 $2.00 $8,400.00 $5.50 $23,100.00 $5.00 $21,000.00 624(A) - FENCE, STYLE WWF - LF 1,914.00 5.00 9,570.00 $5.31 $10,163.34 $5.59 $10,699.26 $5.00 $9,570.00 $4.85 $9,282.90 $4.85 $9,282.90 877(A) - PORTABLE LONGITUDINAL BARRIER - LF 500.00 50.00 25,000.00 $40.46 $20,230.00 $46.51 $23,255.00 $40.00 $20,000.00 $55.00 $27,500.00 $45.00 $22,500.00 Schedule of Bid Items - Part A ROADWAY 107A $2,871,611.30 $2,427,758.73 $2,191,441.75 $2,539,597.57 $2,787,226.12 $2,794,391.20 Schedule of Bid Items - Part A - TRAFFIC PAVEMENT MARKING & SIGNING 107A 413(A) - RUMBLE STRIP-METHOD HMA-CON - LF 21,160.00 0.50 10,580.00 $0.30 $6,348.00 $0.31 $6,559.60 $0.35 $7,406.00 $0.27 $5,713.20 $0.16 $3,385.60 805(A) - (PL) REMOVAL OF EXISTING SIGNS - EA 2.00 50.00 100.00 $54.68 $109.36 $53.25 $106.50 $55.00 $110.00 $250.00 $500.00 $50.00 $100.00 850(A) - SHEET ALUMINUM SIGNS - SF 8.00 20.00 160.00 $17.50 $140.00 $17.04 $136.32 $17.00 $136.00 $45.00 $360.00 $16.00 $128.00 851(C) - 2" SQUARE TUBE POST - LF 20.00 9.00 180.00 $7.66 $153.20 $7.46 $149.20 $8.00 $160.00 $9.00 $180.00 $7.00 $140.00 853 - DELINEATORS (TYPE 1, CODE 1, FLEXIBLE) - EA 10.00 15.00 150.00 $32.82 $328.20 $31.95 $319.50 $33.00 $330.00 $45.00 $450.00 $30.00 $300.00 853 - BARRIER DELINEATORS (TYPE 2, CODE 1) - EA 10.00 10.00 100.00 $5.47 $54.70 $5.33 $53.30 $5.50 $55.00 $20.00 $200.00 $5.00 $50.00 856(A) - TRAFFIC STRIPE (MULTI-POLY.)(6" WIDE) - LF 9,900.00 0.65 6,435.00 $1.20 $11,880.00 $1.17 $11,583.00 $1.20 $11,880.00 $0.80 $7,920.00 $1.10 $10,890.00 856(A) - TRAFFIC STRIPE (MULTI-POLY)(12" WIDE) - LF 2,250.00 1.10 2,475.00 $1.64 $3,690.00 $1.60 $3,600.00 $2.00 $4,500.00 $2.25 $5,062.50 $1.50 $3,375.00 Schedule of Bid Items - RAFFIC PAVEMENT MARKING & SIGNING 107A $20,180.00 $22,703.46 $22,507.42 $24,577.00 $20,385.70 $18,368.60 Schedule of Bid Items - Part A - TRAFFIC CONTROL 107A 857(A) - CONSTRUCTION TRAFFIC STRIPE (PAINT)(4" WIDE) - LF 57,980.00 0.11 6,377.80 $0.11 $6,377.80 $0.11 $6,377.80 $0.12 $6,957.60 $1.35 $78,273.00 $0.10 $5,798.00 857(F) - PAVEMENT MARKING REMOVAL (TRAFFIC STRIPE) - LF 70,000.00 0.15 10,500.00 $0.16 $11,200.00 $0.16 $11,200.00 $0.17 $11,900.00 $0.45 $31,500.00 $0.15 $10,500.00 871(B) - (SP) CONST. ZONE IMPACT ATTEN. - SD 730.00 12.00 8,760.00 $5.47 $3,993.10 $5.33 $3,890.90 $5.50 $4,015.00 $6.00 $4,380.00 $5.00 $3,650.00 871(C) - RELOCATION OF CONST. ZONE IMPACT ATTEN. - EA 3.00 1,100.00 3,300.00 $1,640.60 $4,921.80 $1,597.50 $4,792.50 $1,650.00 $4,950.00 $1,400.00 $4,200.00 $1,500.00 $4,500.00 876(A) - TRUCK MOUNTED ATTENUATOR - SD 150.00 19.00 2,850.00 $54.68 $8,202.00 $53.25 $7,987.50 $55.00 $8,250.00 $15.00 $2,250.00 $50.00 $7,500.00 877(B) - DELIVER PORTABLE LONGITUDINAL BARRIER - LF 4,500.00 20.00 90,000.00 $16.76 $75,420.00 $21.00 $94,500.00 $17.00 $76,500.00 $34.00 $153,000.00 $26.00 $117,000.00 877(C) - RELOCATION OF PORTABLE LONGITUDINAL BARRIER - LF 13,500.00 2.00 27,000.00 $1.67 $22,545.00 $0.60 $8,100.00 $2.00 $27,000.00 $4.50 $60,750.00 $3.00 $40,500.00 880(B) - CONSTRUCTION SIGNS 0 TO 6.25 SF - SD 7,300.00 0.35 2,555.00 $0.55 $4,015.00 $0.53 $3,869.00 $0.55 $4,015.00 $1.00 $7,300.00 $0.50 $3,650.00 880(B) - CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF - SD 8,760.00 0.65 5,694.00 $0.55 $4,818.00 $0.53 $4,642.80 $0.55 $4,818.00 $1.00 $8,760.00 $0.50 $4,380.00 880(B) - CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF - SD 9,290.00 1.50 13,935.00 $0.55 $5,109.50 $0.53 $4,923.70 $0.55 $5,109.50 $1.00 $9,290.00 $0.50 $4,645.00 880(C) - WING BARRICADES - SD 1,460.00 0.65 949.00 $0.55 $803.00 $0.53 $773.80 $0.55 $803.00 $0.50 $730.00 $0.50 $730.00 880(D) - VERTICAL PANELS - SD 3,000.00 0.40 1,200.00 $2.19 $6,570.00 $2.13 $6,390.00 $2.20 $6,600.00 $0.70 $2,100.00 $2.00 $6,000.00 880(E) - WARNING LIGHTS (TYPE A) - SD 9,290.00 0.15 1,393.50 $0.55 $5,109.50 $0.53 $4,923.70 $0.55 $5,109.50 $0.05 $464.50 $0.50 $4,645.00 882(A) - (SP)CHANGEABLE MESSAGE SIGN - SD 1,460.00 10.00 14,600.00 $5.47 $7,986.20 $5.33 $7,781.80 $5.50 $8,030.00 $8.00 $11,680.00 $5.00 $7,300.00 Schedule of Bid Items - Part A - TRAFFIC CONTROL 107A $189,114.30 $167,070.90 $170,153.50 $174,057.60 $374,677.50 $220,798.00 Schedule of Bid Items - Part A ROADWAY 107B1 201(A) - CLEARING AND GRUBBING - LSUM 1.00 250000 250,000.00 $500,000.00 $500,000.00 $330,000.00 $330,000.00 $550,000.00 $550,000.00 $550,000.00 $550,000.00 $209,238.50 $209,238.50 202(A) - UNCLASSIFIED EXCAVATION - CY 1,032,352.00 6 6,194,112.00 $3.80 $3,922,937.60 $4.10 $4,232,643.20 $4.00 $4,129,408.00 $4.95 $5,110,142.40 $5.10 $5,264,995.20 202(B) - MUCK EXCAVATION - CY 1,046.00 12 12,552.00 $8.75 $9,152.50 $10.54 $11,024.84 $5.00 $5,230.00 $9.50 $9,937.00 $8.55 $8,943.30

202(D) - UNCLASSIFIED BORROW - CY 25,000.00 5 125,000.00 $0.25 $6,250.00 $0.25 $6,250.00 $0.25 $6,250.00 $0.25 $6,250.00 $4.30 $107,500.00 203 - TEST ROLLING - LSUM 1.00 35000 35,000.00 $22,549.94 $22,549.94 $2,946.32 $2,946.32 $12,000.00 $12,000.00 $26,500.00 $26,500.00 $1,847.43 $1,847.43 205(A) - TYPE A-SALVAGED TOPSOIL - LSUM 1.00 325000 325,000.00 $303,041.36 $303,041.36 $240,000.00 $240,000.00 $140,000.00 $140,000.00 $257,500.00 $257,500.00 $190,604.47 $190,604.47 209 - MACHINE GRADING - LF 8,836.00 8 70,688.00 $6.16 $54,429.76 $6.14 $54,253.04 $8.00 $70,688.00 $6.91 $61,056.76 $3.28 $28,982.08 221(C) - TEMPORARY SILT FENCE - LF 10,625.00 1.5 15,937.50 $1.88 $19,975.00 $1.08 $11,475.00 $1.30 $13,812.50 $1.01 $10,731.25 $1.01 $10,731.25 221(D) - TEMPORARY SEDIMENT FILTER - EA 17.00 150 2,550.00 $130.26 $2,214.42 $159.75 $2,715.75 $350.00 $5,950.00 $150.00 $2,550.00 $150.00 $2,550.00 221(F) - TEMPORARY SILT DIKE - LF 7,175.00 7 50,225.00 $6.74 $48,359.50 $6.27 $44,987.25 $5.50 $39,462.50 $5.89 $42,260.75 $5.89 $42,260.75 221(G) - TEMPORARY ROCK FILTER DAM TYPE 2 - CY 244.00 100 24,400.00 $101.89 $24,861.16 $94.56 $23,072.64 $70.00 $17,080.00 $88.79 $21,664.76 $88.79 $21,664.76 221(G) - TEMPORARY ROCK FILTER DAM TYPE 3 - CY 536.00 120 64,320.00 $74.87 $40,130.32 $114.66 $61,457.76 $100.00 $53,600.00 $107.66 $57,705.76 $107.66 $57,705.76 227 - (SP) HIGH PERFORMANCE TURF REINFORCEMENT MAT - SY 41,064.00 20 821,280.00 $17.50 $718,620.00 $15.25 $626,226.00 $19.00 $780,216.00 $16.48 $676,734.72 $16.48 $676,734.72 230(A) - SOLID SLAB SODDING - SY 357,454.00 1.5 536,181.00 $0.92 $328,857.68 $0.96 $343,155.84 $1.00 $357,454.00 $0.91 $325,283.14 $0.90 $321,708.60 232(B) - SEEDING METHOD B - AC 147.75 400 59,100.00 $164.70 $24,334.43 $159.75 $23,603.06 $325.00 $48,018.75 $150.00 $22,162.50 $150.00 $22,162.50 233(A) - VEGETATIVE MULCHING - AC 73.89 350 25,861.50 $174.57 $12,898.98 $169.34 $12,512.53 $100.00 $7,389.00 $150.00 $11,083.50 $159.00 $11,748.51 241 - MOWING - AC 443.00 50 22,150.00 $63.68 $28,210.24 $61.77 $27,364.11 $50.00 $22,150.00 $58.00 $25,694.00 $58.00 $25,694.00 242 - (PL) STABILIZED CONSTRUCTION EXIT - EA 12.00 2500 30,000.00 $1,539.22 $18,470.64 $1,500.00 $18,000.00 $2,500.00 $30,000.00 $5,500.00 $66,000.00 $1,357.96 $16,295.52 303(A) - AGGREGATE BASE TYPE A - CY 53,011.00 40 2,120,440.00 $32.69 $1,732,929.59 $32.00 $1,696,352.00 $32.00 $1,696,352.00 $65.00 $3,445,715.00 $48.00 $2,544,528.00 307(K) - STABILIZED SUBGRADE - SY 224,261.00 5 1,121,305.00 $3.59 $805,096.99 $4.60 $1,031,600.60 $4.50 $1,009,174.50 $5.65 $1,267,074.65 $6.00 $1,345,566.00 310(B) - SUBGRADE, METHOD B - SY 27,256.00 3 81,768.00 $0.90 $24,530.40 $1.63 $44,427.28 $0.50 $13,628.00 $1.50 $40,884.00 $2.15 $58,600.40 325.0 - SEPARATOR FABRIC - SY 301,558.00 1.1 331,713.80 $0.85 $256,324.30 $1.22 $367,900.76 $1.00 $301,558.00 $1.20 $361,869.60 $1.10 $331,713.80 326(A) - GEOTEXTILE REINFORCEMENT - SY 494.00 5 2,470.00 $0.85 $419.90 $4.05 $2,000.70 $5.00 $2,470.00 $5.50 $2,717.00 $10.00 $4,940.00 402(E) - TRAFFIC BOUND SURFACE COURSE TYPE E - TON 72,825.00 15 1,092,375.00 $12.57 $915,410.25 $2.50 $182,062.50 $7.00 $509,775.00 $17.50 $1,274,437.50 $20.00 $1,456,500.00 408 - PRIME COAT - GAL 164,973.00 3 494,919.00 $0.25 $41,243.25 $0.50 $82,486.50 $0.50 $82,486.50 $2.50 $412,432.50 $2.60 $428,929.80 411(B) - SUPERPAVE, TYPE S3(PG 64-22 OK) - TON 96,660.00 55 5,316,300.00 $48.71 $4,708,308.60 $42.00 $4,059,720.00 $47.00 $4,543,020.00 $48.00 $4,639,680.00 $53.05 $5,127,813.00 411(C) - SUPERPAVE, TYPE S4(PG 64-22 OK) - TON 25,833.00 65 1,679,145.00 $53.05 $1,370,440.65 $50.06 $1,293,199.98 $49.00 $1,265,817.00 $51.50 $1,330,399.50 $57.90 $1,495,730.70 411(H) - SUPERPAVE, TYPE S3 (PATCHING) - TON 200.00 150 30,000.00 $58.77 $11,754.00 $61.77 $12,354.00 $55.00 $11,000.00 $155.00 $31,000.00 $85.75 $17,150.00 411(I) - SUPERPAVE, TYPE S4 (PATCHING) - TON 663.00 120 79,560.00 $68.19 $45,209.97 $63.90 $42,365.70 $55.00 $36,465.00 $165.00 $109,395.00 $89.10 $59,073.30 412 - COLD MILLING PAVEMENT - SY 153,263.00 3 459,789.00 $0.54 $82,762.02 $0.82 $125,675.66 $0.90 $137,936.70 $3.00 $459,789.00 $1.00 $153,263.00 414(A) - P.C. CONCRETE PAVEMENT (PLACEMENT) - SY 66,712.00 5 333,560.00 $6.92 $461,647.04 $7.15 $476,990.80 $7.50 $500,340.00 $7.00 $466,984.00 $8.00 $533,696.00 414(B) - DOWEL JOINTED P.C.C. PAVEMENT (PLACEMENT) - SY 235,967.00 10 2,359,670.00 $10.28 $2,425,740.76 $8.50 $2,005,719.50 $10.00 $2,359,670.00 $8.67 $2,045,833.89 $14.00 $3,303,538.00 414(G) - P.C. CONCRETE FOR PAVEMENT - CY 97,110.00 80 7,768,800.00 $85.00 $8,254,350.00 $88.00 $8,545,680.00 $92.00 $8,934,120.00 $90.00 $8,739,900.00 $80.00 $7,768,800.00 501(A) - STRUCTURAL EXCAVATION UNCLASSIFIED - CY 250.00 20 5,000.00 $19.02 $4,755.00 $21.30 $5,325.00 $30.00 $7,500.00 $20.00 $5,000.00 $20.00 $5,000.00 501(G) - CLSM BACKFILL - CY 584.00 130 75,920.00 $142.61 $83,284.24 $138.45 $80,854.80 $80.00 $46,720.00 $130.00 $75,920.00 $130.00 $75,920.00 506(A) - STRUCTURAL STEEL - LB 198.00 5 990.00 $2.42 $479.16 $0.85 $168.30 $3.75 $742.50 $0.80 $158.40 $0.80 $158.40 509(A) - CLASS AA CONCRETE - CY 948.00 400 379,200.00 $383.03 $363,112.44 $317.37 $300,866.76 $615.00 $583,020.00 $298.00 $282,504.00 $298.00 $282,504.00 511(A) - REINFORCING STEEL - LB 149,003.00 1 149,003.00 $1.00 $149,003.00 $0.85 $126,652.55 $0.85 $126,652.55 $0.80 $119,202.40 $0.80 $119,202.40 601(B) - TYPE I-A PLAIN RIPRAP - TON 852.00 40 34,080.00 $61.04 $52,006.08 $44.00 $37,488.00 $32.00 $27,264.00 $66.00 $56,232.00 $52.19 $44,465.88 601(C) - TYPE I-A FILTER BLANKET - TON 200.00 35 7,000.00 $21.07 $4,214.00 $53.11 $10,622.00 $32.00 $6,400.00 $67.00 $13,400.00 $32.54 $6,508.00 601(I) - FILTER FABRIC (RIPRAP) - SY 738.00 4 2,952.00 $1.47 $1,084.86 $2.30 $1,697.40 $2.00 $1,476.00 $5.50 $4,059.00 $3.17 $2,339.46 611(A) - MANHOLE (4' DIAMETER) - EA 3.00 3000 9,000.00 $3,094.18 $9,282.54 $3,063.86 $9,191.58 $5,000.00 $15,000.00 $3,913.54 $11,740.62 $3,584.86 $10,754.58 611(A) - MANHOLE (5' DIAMETER) - EA 2.00 4000 8,000.00 $4,979.63 $9,959.26 $4,656.92 $9,313.84 $6,000.00 $12,000.00 $5,755.34 $11,510.68 $6,118.46 $12,236.92 611(A) - MANHOLE (6' DIAMETER) - EA 1.00 5000 5,000.00 $4,761.56 $4,761.56 $4,986.29 $4,986.29 $7,000.00 $7,000.00 $5,319.21 $5,319.21 $4,923.36 $4,923.36 611(G) - INLET GPI TYPE 2 (DES. 10) - EA 1.00 3800 3,800.00 $3,935.37 $3,935.37 $5,205.40 $5,205.40 $4,000.00 $4,000.00 $4,680.00 $4,680.00 $4,629.37 $4,629.37 611(G) - INLET GPI TYPE 2 (DES. 11) - EA 1.00 4000 4,000.00 $3,935.37 $3,935.37 $4,452.00 $4,452.00 $4,400.00 $4,400.00 $4,680.00 $4,680.00 $4,629.37 $4,629.37 611(G) - INLET GPI TYPE 2 (DES. 11A) - EA 1.00 4200 4,200.00 $3,935.37 $3,935.37 $4,200.86 $4,200.86 $4,500.00 $4,500.00 $4,680.00 $4,680.00 $4,629.37 $4,629.37 611(G) - INLET (SMD-TYPE 2) - EA 15.00 3000 45,000.00 $1,853.76 $27,806.40 $1,500.00 $22,500.00 $3,500.00 $52,500.00 $2,646.60 $39,699.00 $2,694.51 $40,417.65 613(A) - 12" R.C.PIPE CLASS III - LF 97.00 65 6,305.00 $58.03 $5,628.91 $28.54 $2,768.38 $65.00 $6,305.00 $62.13 $6,026.61 $42.34 $4,106.98 613(A) - 18" R.C.PIPE CLASS III - LF 779.00 70 54,530.00 $49.62 $38,653.98 $47.04 $36,644.16 $70.00 $54,530.00 $82.73 $64,446.67 $46.92 $36,550.68 613(A) - 24" R.C.PIPE CLASS III - LF 1,637.00 80 130,960.00 $58.67 $96,042.79 $47.50 $77,757.50 $72.00 $117,864.00 $95.88 $156,955.56 $55.24 $90,427.88 613(A) - 30" R.C.PIPE CLASS III - LF 789.00 90 71,010.00 $92.00 $72,588.00 $67.25 $53,060.25 $95.00 $74,955.00 $112.15 $88,486.35 $65.36 $51,569.04 613(A) - 36" R.C.PIPE CLASS III - LF 65.00 110 7,150.00 $105.28 $6,843.20 $118.03 $7,671.95 $130.00 $8,450.00 $122.28 $7,948.20 $96.76 $6,289.40 613(A) - 42" R.C.PIPE CLASS III - LF 426.00 140 59,640.00 $117.42 $50,020.92 $108.00 $46,008.00 $145.00 $61,770.00 $139.01 $59,218.26 $111.12 $47,337.12 613(A) - 48" R.C.PIPE CLASS III - LF 88.00 180 15,840.00 $246.91 $21,728.08 $156.29 $13,753.52 $180.00 $15,840.00 $206.12 $18,138.56 $135.12 $11,890.56 613(A) - 54" R.C.PIPE CLASS IV - LF 467.00 220 102,740.00 $215.79 $100,773.93 $192.23 $89,771.41 $200.00 $93,400.00 $192.55 $89,920.85 $151.27 $70,643.09 613(A) - 54" R.C.PIPE CLASS V - LF 804.00 250 201,000.00 $224.57 $180,554.28 $218.50 $175,674.00 $230.00 $184,920.00 $218.51 $175,682.04 $160.57 $129,098.28 613(B) - 15" CORR. GALV. STEEL PIPE - LF 32.00 30 960.00 $35.08 $1,122.56 $31.75 $1,016.00 $50.00 $1,600.00 $25.81 $825.92 $34.72 $1,111.04 613(B) - 18" CORR. GALV. STEEL PIPE - LF 439.00 30 13,170.00 $41.46 $18,200.94 $36.43 $15,992.77 $50.00 $21,950.00 $28.09 $12,331.51 $36.72 $16,120.08 613(B) - 24" CORR. GALV. STEEL PIPE - LF 36.00 40 1,440.00 $41.20 $1,483.20 $36.37 $1,309.32 $55.00 $1,980.00 $32.33 $1,163.88 $40.45 $1,456.20 613(B) - 42" CORR. GALV. STEEL PIPE - LF 232.00 65 15,080.00 $106.20 $24,638.40 $102.71 $23,828.72 $85.00 $19,720.00 $52.09 $12,084.88 $60.09 $13,940.88 613(J) - EDGE DRAIN CONDUIT-PERFORATED - LF 1,970.00 15 29,550.00 $6.99 $13,770.30 $8.18 $16,114.60 $9.00 $17,730.00 $17.00 $33,490.00 $15.00 $29,550.00 613(K) - EDGE DRAIN OUTLET LATERAL-NONPERFORATED - LF 93.00 20 1,860.00 $10.67 $992.31 $7.21 $670.53 $9.00 $837.00 $17.00 $1,581.00 $20.00 $1,860.00 613(L) - 15" PREFAB. CULVERT END SECTION, ROUND - EA 2.00 500 1,000.00 $183.46 $366.92 $417.67 $835.34 $700.00 $1,400.00 $782.17 $1,564.34 $242.12 $484.24 613(L) - 18" PREFAB. CULVERT END SECTION, ROUND - EA 12.00 400 4,800.00 $277.24 $3,326.88 $497.35 $5,968.20 $725.00 $8,700.00 $723.23 $8,678.76 $308.99 $3,707.88 613(L) - 24" PREFAB. CULVERT END SECTION, ROUND - EA 10.00 600 6,000.00 $873.25 $8,732.50 $944.00 $9,440.00 $800.00 $8,000.00 $994.12 $9,941.20 $683.77 $6,837.70 613(L) - 30" PREFAB. CULVERT END SECTION, ROUND - EA 6.00 800 4,800.00 $1,176.02 $7,056.12 $1,219.59 $7,317.54 $900.00 $5,400.00 $2,028.72 $12,172.32 $915.02 $5,490.12 613(L) - 36" PREFAB. CULVERT END SECTION, ROUND - EA 1.00 1200 1,200.00 $1,567.18 $1,567.18 $1,650.43 $1,650.43 $1,200.00 $1,200.00 $1,753.95 $1,753.95 $1,276.54 $1,276.54 613(L) - 42" PREFAB. CULVERT END SECTION, ROUND - EA 3.00 1500 4,500.00 $2,096.87 $6,290.61 $2,134.68 $6,404.04 $1,600.00 $4,800.00 $2,281.77 $6,845.31 $1,933.06 $5,799.18 613(L) - 48" PREFAB. CULVERT END SECTION, ROUND - EA 1.00 2000 2,000.00 $2,731.68 $2,731.68 $2,376.79 $2,376.79 $2,000.00 $2,000.00 $2,417.60 $2,417.60 $2,136.23 $2,136.23 613(O) - SPECIAL END SECTIONS OF REINFORCED CONCRETE - EA 4.00 12000 48,000.00 $4,473.31 $17,893.24 $4,998.41 $19,993.64 $15,000.00 $60,000.00 $4,500.00 $18,000.00 $4,500.00 $18,000.00 613(Q) - OUTLET LATERAL HEADWALL - EA 3.00 800 2,400.00 $278.19 $834.57 $225.00 $675.00 $700.00 $2,100.00 $1,100.00 $3,300.00 $1,750.00 $5,250.00 613(W) - 24" JACKED CONDUIT - LF 240.00 400 96,000.00 $881.99 $211,677.60 $556.85 $133,644.00 $800.00 $192,000.00 $531.77 $127,624.80 $1,102.43 $264,583.20

613(W) - 30" JACKED CONDUIT - LF 265.00 700 185,500.00 $894.66 $237,084.90 $668.90 $177,258.50 $1,100.00 $291,500.00 $633.49 $167,874.85 $1,069.48 $283,412.20 613(W) - 42" JACKED CONDUIT - LF 304.00 1000 304,000.00 $1,077.98 $327,705.92 $830.01 $252,323.04 $1,300.00 $395,200.00 $776.19 $235,961.76 $882.61 $268,313.44 613(W) - 54" JACKED CONDUIT - LF 410.00 1200 492,000.00 $1,077.02 $441,578.20 $1,363.90 $559,199.00 $1,800.00 $738,000.00 $1,268.52 $520,093.20 $827.69 $339,352.90 616(I) - 12" STEEL CASING - LF 81.00 50 4,050.00 $59.45 $4,815.45 $39.68 $3,214.08 $120.00 $9,720.00 $110.00 $8,910.00 $250.00 $20,250.00 619(A) - REMOVAL OF STRUCTURES & OBSTRUCTIONS - LSUM 1.00 55000 55,000.00 $22,886.30 $22,886.30 $27,154.42 $27,154.42 $215,000.00 $215,000.00 $27,600.00 $27,600.00 $62,252.66 $62,252.66 619(B) - REMOVAL OF FENCE - LF 51,607.00 1.5 77,410.50 $0.77 $39,737.39 $0.64 $33,028.48 $1.00 $51,607.00 $0.75 $38,705.25 $0.64 $33,028.48 619(B) - REMOVAL OF CONCRETE PAVEMENT - SY 1,499.00 10 14,990.00 $4.96 $7,435.04 $3.54 $5,306.46 $10.00 $14,990.00 $15.00 $22,485.00 $2.26 $3,387.74 619(B) - REMOVAL OF ASPHALT PAVEMENT - SY 91,093.00 3.5 318,825.50 $3.09 $281,477.37 $3.45 $314,270.85 $2.50 $227,732.50 $3.00 $273,279.00 $3.50 $318,825.50 619(B) - REMOVAL OF GUARDRAIL - LF 7,799.00 3 23,397.00 $2.19 $17,079.81 $1.87 $14,584.13 $2.00 $15,598.00 $2.86 $22,305.14 $2.00 $15,598.00 619(B) - REMOVAL OF CONCRETE MEDIAN BARRIER - LF 22,266.00 8 178,128.00 $5.98 $133,150.68 $4.93 $109,771.38 $6.00 $133,596.00 $6.50 $144,729.00 $6.20 $138,049.20 623(A) - BEAM GUARDRAIL W-BEAM SINGLE - LF 762.50 20 15,250.00 $21.88 $16,683.50 $21.30 $16,241.25 $19.80 $15,097.50 $15.41 $11,750.13 $20.00 $15,250.00 623(F) - GUARDRAIL TRAIL END TURNDOWN (31") - EA 3.00 1600 4,800.00 $1,055.44 $3,166.32 $1,027.73 $3,083.19 $550.00 $1,650.00 $975.00 $2,925.00 $965.00 $2,895.00 623(G) - GUARDRAIL END TREATMENT (31") - EA 9.00 2500 22,500.00 $2,679.63 $24,116.67 $2,609.25 $23,483.25 $2,475.00 $22,275.00 $2,155.00 $19,395.00 $2,450.00 $22,050.00 623(I) - GUARDRAIL BRIDGE CONN-THRIE BEAM (31") - EA 12.00 1700 20,400.00 $1,640.60 $19,687.20 $1,597.50 $19,170.00 $1,815.00 $21,780.00 $1,978.00 $23,736.00 $1,500.00 $18,000.00 624(A) - FENCE-STYLE WWF - LF 25,848.00 5 129,240.00 $5.31 $137,252.88 $5.59 $144,490.32 $5.00 $129,240.00 $4.85 $125,362.80 $4.85 $125,362.80 624(B) - GATES-STYLE WWF (4.5'HIGH X 18'LONG) - EA 1.00 1200 1,200.00 $765.61 $765.61 $372.75 $372.75 $770.00 $770.00 $700.00 $700.00 $700.00 $700.00 624(B) - GATES-STYLE WWF (4.5'HIGH X 20'LONG) - EA 2.00 1500 3,000.00 $765.61 $1,531.22 $426.00 $852.00 $770.00 $1,540.00 $700.00 $1,400.00 $700.00 $1,400.00 624(C) - FENCE-STYLE SWF (5 BARBED WIRE) - LF 4,662.00 4.5 20,979.00 $4.38 $20,419.56 $4.47 $20,839.14 $4.50 $20,979.00 $4.00 $18,648.00 $4.00 $18,648.00 627(A) - CONCRETE LONGITUDINAL BARRIER, DESIGN 1 - LF 20,405.00 40 816,200.00 $28.00 $571,340.00 $32.00 $652,960.00 $51.00 $1,040,655.00 $48.00 $979,440.00 $58.00 $1,183,490.00 629(E) - REMOVE AND RESET MAILBOX - EA 2.00 150 300.00 $218.75 $437.50 $213.00 $426.00 $150.00 $300.00 $550.00 $1,100.00 $175.00 $350.00 871(A) - (PL) IMPACT ATTENUATOR - EA 3.00 25000 75,000.00 $21,874.56 $65,623.68 $21,300.00 $63,900.00 $26,000.00 $78,000.00 $18,950.00 $56,850.00 $20,000.00 $60,000.00 878 - (SP) EMERGENCY-ACCESS BARRIER GATE - EA 1.00 25000 25,000.00 $46,483.45 $46,483.45 $45,262.50 $45,262.50 $43,000.00 $43,000.00 $38,285.00 $38,285.00 $42,500.00 $42,500.00 896 - DECOMISSION OF SEWAGE LAGOON - LSUM 1.00 49795 49,795.00 $55,517.46 $55,517.46 $79,708.48 $79,708.48 $75,000.00 $75,000.00 $55,100.00 $55,100.00 $28,065.60 $28,065.60 Schedule of Bid Items - Part A ROADWAY 107B1 $36,388,216.80 $31,312,511.11 $29,980,993.41 $33,102,377.50 $36,267,387.19 $36,096,225.95 Schedule of Bid Items - Part A - BRIDGE 107B1; TPU 68.20 504(E) - CONCRETE PARAPET - LF 1,525.00 135.00 205,875.00 $76.49 $116,647.25 $141.21 $215,345.25 $90.00 $137,250.00 $88.00 $134,200.00 $88.00 $134,200.00 509(B) - CLASS A CONCRETE - CY 941.10 600.00 564,660.00 $169.07 $159,111.78 $228.98 $215,493.08 $350.00 $329,385.00 $215.00 $202,336.50 $215.00 $202,336.50 509(D) - CLASS C CONCRETE - CY 64.90 600.00 38,940.00 $376.84 $24,456.92 $213.00 $13,823.70 $450.00 $29,205.00 $200.00 $12,980.00 $200.00 $12,980.00 510(C) - SLOPEWALL (5") - SY 1,423.40 95.00 135,223.00 $78.55 $111,808.07 $106.50 $151,592.10 $105.00 $149,457.00 $100.00 $142,340.00 $100.00 $142,340.00 511(B) - EPOXY COATED REINFORCING STEEL - LB 171,146.00 1.05 179,703.30 $0.90 $154,031.40 $1.04 $177,991.84 $1.50 $256,719.00 $0.98 $167,723.08 $0.98 $167,723.08 613(H) - 6" PERFORATED PIPE UNDERDRAIN ROUND - LF 765.00 30.00 22,950.00 $15.59 $11,926.35 $15.98 $12,224.70 $9.00 $6,885.00 $15.00 $11,475.00 $15.00 $11,475.00 613(I) - 6" NON-PERFORATED PIPE UNDERDRAIN ROUND - LF 20.00 25.00 500.00 $9.57 $191.40 $21.30 $426.00 $9.00 $180.00 $20.00 $400.00 $20.00 $400.00 616(B) - 10" POLYVINYL CHOLORIDE (PVC) PIPE - LF 34.00 25.00 850.00 $28.29 $961.86 $213.00 $7,242.00 $45.00 $1,530.00 $20.00 $680.00 $50.00 $1,700.00 619(B) - REMOVAL OF SPECIFIED ITEMS - LSUM 1.00 10,000.00 10,000.00 $18,029.49 $18,029.49 $29,820.00 $29,820.00 $85,000.00 $85,000.00 $28,000.00 $28,000.00 $28,000.00 $28,000.00 Schedule of Bid Items - Part A - BRIDGE 107B1; TPU 68.20 $1,158,701.30 $597,164.52 $823,958.67 $995,611.00 $700,134.58 $701,154.58 Schedule of Bid Items - Part A - BRIDGE 107B1; TPO 68.62 202(A) - UNCLASSIFIED EXCAVATION - CY 10,926.00 11.00 120,186.00 $3.38 $36,929.88 $4.10 $44,796.60 $4.00 $43,704.00 $5.30 $57,907.80 $4.30 $46,981.80 202(D) - UNCLASSIFIED BORROW - CY 7,416.00 10.00 74,160.00 $0.25 $1,854.00 $0.25 $1,854.00 $0.25 $1,854.00 $8.50 $63,036.00 $4.80 $35,596.80 501(A) - STRUCTURAL EXCAVATION, UNCLASSIFIED - CY 313.00 18.00 5,634.00 $19.02 $5,953.26 $21.30 $6,666.90 $30.00 $9,390.00 $20.00 $6,260.00 $20.00 $6,260.00 502 - TEMPORARY EARTH RETAINAGE - LSUM 1.00 98,334.00 98,334.00 $11,265.76 $11,265.76 $12,780.00 $12,780.00 $250,000.00 $250,000.00 $12,000.00 $12,000.00 $12,000.00 $12,000.00 509(A) - CLASS AA CONCRETE - CY 981.80 550.00 539,990.00 $383.03 $376,058.85 $317.37 $311,593.87 $400.00 $392,720.00 $298.00 $292,576.40 $298.00 $292,576.40 511(A) - REINFORCING STEEL - LB 139,250.00 1.00 139,250.00 $1.00 $139,250.00 $0.85 $118,362.50 $0.80 $111,400.00 $0.80 $111,400.00 $0.80 $111,400.00 601(A) - TYPE I - PLAIN RIPRAP - TON 333.00 42.00 13,986.00 $32.02 $10,662.66 $70.29 $23,406.57 $32.00 $10,656.00 $66.00 $21,978.00 $66.00 $21,978.00 619(D) - REMOVAL OF EXISTING BRIDGE STRUCTURE - LSUM 1.00 25,000.00 25,000.00 $60,000.00 $60,000.00 $21,300.00 $21,300.00 $125,000.00 $125,000.00 $20,000.00 $20,000.00 $20,000.00 $20,000.00 Schedule of Bid Items - Part A - BRIDGE 107B1; TPO 68.62 $1,016,540.00 $641,974.41 $540,760.44 $944,724.00 $585,158.20 $546,793.00 Schedule of Bid Items - Part A - BRIDGE 107B1; TPO 69.10 501(B) - SUBSTRUCTURE EXCAVATION, COMMON - CY 526.00 25.00 13,150.00 $12.54 $6,596.04 $25.00 $13,150.00 $45.00 $23,670.00 $75.00 $39,450.00 $75.00 $39,450.00 501(G) - CLSM BACKFILL - CY 826.00 130.00 107,380.00 $127.87 $105,620.62 $85.00 $70,210.00 $80.00 $66,080.00 $105.00 $86,730.00 $105.00 $86,730.00 502 - TEMPORARY EARTH RETAINAGE - LSUM 1.00 44,710.00 44,710.00 $29,211.84 $29,211.84 $65,000.00 $65,000.00 $290,000.00 $290,000.00 $160,000.00 $160,000.00 $25,000.00 $25,000.00 503(A) - PRESTRESSED CONCRETE BEAMS (TYPE III) - LF 2,050.80 220.00 451,176.00 $159.10 $326,282.28 $165.00 $338,382.00 $190.00 $389,652.00 $180.00 $369,144.00 $175.00 $358,890.00 503(A) - PRESTRESSED CONCRETE BEAMS (TYPE IV) - LF 1,274.80 250.00 318,700.00 $194.03 $247,349.44 $210.00 $267,708.00 $235.00 $299,578.00 $220.00 $280,456.00 $215.00 $274,082.00 504(A) - APPROACH SLAB - SY 1,019.60 210.00 214,116.00 $164.42 $167,642.63 $125.00 $127,450.00 $165.00 $168,234.00 $135.00 $137,646.00 $135.00 $137,646.00 504(B) - SAW-CUT GROOVING - SY 4,017.30 5.00 20,086.50 $3.83 $15,386.26 $3.73 $14,984.53 $3.85 $15,466.61 $3.65 $14,663.15 $3.65 $14,663.15 504(C) - EXPANSION JOINT - LF 152.10 125.00 19,012.50 $71.09 $10,812.79 $85.00 $12,928.50 $80.00 $12,168.00 $75.00 $11,407.50 $75.00 $11,407.50 504(E) - 42" F-SHAPED PARAPET - LF 1,081.40 85.00 91,919.00 $66.71 $72,140.19 $67.00 $72,453.80 $55.00 $59,477.00 $55.00 $59,477.00 $55.00 $59,477.00 504(G) - RAPID CURE JOINT SEALANT - LF 420.70 30.00 12,621.00 $17.23 $7,248.66 $20.00 $8,414.00 $35.00 $14,724.50 $30.00 $12,621.00 $30.00 $12,621.00 506(A) - STRUCTURAL STEEL - LB 5,152.00 4.00 20,608.00 $1.45 $7,470.40 $2.00 $10,304.00 $3.75 $19,320.00 $2.00 $10,304.00 $2.00 $10,304.00 507(A) - (SP) STAINLESS STEEL FIXED BEARING ASSEMBLY - EA 32.00 1,700.00 54,400.00 $1,109.85 $35,515.20 $900.00 $28,800.00 $2,100.00 $67,200.00 $1,500.00 $48,000.00 $1,500.00 $48,000.00 507(B) - (SP) STAINLESS STEEL EXPANSION BEARING ASSEMBLY - EA 64.00 1,700.00 108,800.00 $1,058.99 $67,775.36 $900.00 $57,600.00 $2,100.00 $134,400.00 $1,500.00 $96,000.00 $1,500.00 $96,000.00 509 - (SP) SPECIAL CONCRETE FINISH - SY 468.00 90.00 42,120.00 $100.90 $47,221.20 $100.00 $46,800.00 $85.00 $39,780.00 $65.00 $30,420.00 $65.00 $30,420.00 509(A) - CLASS AA CONCRETE - CY 910.50 550.00 500,775.00 $598.21 $544,670.21 $390.00 $355,095.00 $700.00 $637,350.00 $475.00 $432,487.50 $480.00 $437,040.00 509(B) - CLASS A CONCRETE - CY 620.20 600.00 372,120.00 $513.17 $318,268.03 $460.00 $285,292.00 $500.00 $310,100.00 $475.00 $294,595.00 $450.00 $279,090.00 509(D) - CLASS C CONCRETE - CY 19.10 600.00 11,460.00 $376.84 $7,197.64 $1,200.00 $22,920.00 $450.00 $8,595.00 $700.00 $13,370.00 $700.00 $13,370.00 511 - MECHANICAL SPLICES - EA 2,064.00 35.00 72,240.00 $12.88 $26,584.32 $14.00 $28,896.00 $25.00 $51,600.00 $12.00 $24,768.00 $12.00 $24,768.00 511(B) - EPOXY COATED REINFORCING STEEL - LB 400,890.00 1.05 420,934.50 $0.90 $360,801.00 $0.93 $372,827.70 $1.50 $601,335.00 $1.10 $440,979.00 $1.00 $400,890.00 514(A) - PILES, FURNISHED (HP 10X42) - LF 227.00 32.00 7,264.00 $23.37 $5,304.99 $24.00 $5,448.00 $25.00 $5,675.00 $35.00 $7,945.00 $35.00 $7,945.00

514(A) - PILES, FURNISHED (HP 12X53) - LF 2,848.00 35.00 99,680.00 $26.77 $76,240.96 $28.00 $79,744.00 $30.00 $85,440.00 $35.00 $99,680.00 $35.00 $99,680.00 514(B) - PILES, DRIVEN (HP 10X42) - LF 227.00 18.00 4,086.00 $21.31 $4,837.37 $27.00 $6,129.00 $15.00 $3,405.00 $10.00 $2,270.00 $10.00 $2,270.00 514(B) - PILES, DRIVEN (HP 12X53) - LF 2,848.00 18.00 51,264.00 $21.31 $60,690.88 $27.00 $76,896.00 $15.00 $42,720.00 $10.00 $28,480.00 $10.00 $28,480.00 514(L) - PILE SPLICE (NON-BIDDABLE) - EA 1.00 400.00 400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 515(A) - WATER REPELLENT (VISUALLY INSPECTED) - SY 6,096.00 4.00 24,384.00 $3.28 $19,994.88 $3.20 $19,507.20 $3.30 $20,116.80 $3.10 $18,897.60 $3.10 $18,897.60 516(A) - DRILLED SHAFTS 60" DIAMETER - LF 824.00 800.00 659,200.00 $627.87 $517,364.88 $710.00 $585,040.00 $930.00 $766,320.00 $750.00 $618,000.00 $650.00 $535,600.00 516(C) - CROSSHOLE SONIC LOGGING - EA 4.00 3,000.00 12,000.00 $1,695.28 $6,781.12 $1,500.00 $6,000.00 $8,500.00 $34,000.00 $2,300.00 $9,200.00 $2,300.00 $9,200.00 523(A) - SEALER CRACK PREPARATION - LF 574.00 4.00 2,296.00 $6.56 $3,765.44 $3.20 $1,836.80 $3.30 $1,894.20 $3.30 $1,894.20 $3.30 $1,894.20 523(B) - SEALER RESIN - GAL 1.30 90.00 117.00 $218.75 $284.38 $213.00 $276.90 $220.00 $286.00 $205.00 $266.50 $205.00 $266.50 601(B) - TYPE I-A - PLAIN RIPRAP - TON 3,887.00 45.00 174,915.00 $32.02 $124,461.74 $35.00 $136,045.00 $32.00 $124,384.00 $30.00 $116,610.00 $30.00 $116,610.00 601(C) - TYPE I-A - FILTER BLANKET - TON 655.00 36.00 23,580.00 $21.07 $13,800.85 $32.00 $20,960.00 $32.00 $20,960.00 $28.00 $18,340.00 $28.00 $18,340.00 613(H) - 6" PERFORATED PIPE UNDERDRAIN ROUND - LF 308.00 30.00 9,240.00 $15.59 $4,801.72 $40.00 $12,320.00 $9.00 $2,772.00 $17.00 $5,236.00 $17.00 $5,236.00 613(I) - 6" NON-PERFORATED PIPE UNDERDRAIN ROUND - LF 86.00 25.00 2,150.00 $9.57 $823.02 $30.00 $2,580.00 $9.00 $774.00 $17.00 $1,462.00 $17.00 $1,462.00 619(D) - REMOVAL OF EXISTING BRIDGE STRUCTURE - LSUM 1.00 120,606.00 120,606.00 $43,838.42 $43,838.42 $145,000.00 $145,000.00 $175,000.00 $175,000.00 $140,000.00 $140,000.00 $100,000.00 $100,000.00 Schedule of Bid Items - Part A - BRIDGE 107B1; TPO 69.10 $4,087,510.50 $3,287,184.76 $3,297,398.43 $4,492,877.11 $3,631,199.45 $3,306,129.95 Schedule of Bid Items - Part A - BRIDGE 107B1; TPU 69.30 501(B) - SUBSTRUCTURE EXCAVATION, COMMON - CY 83.00 25.00 2,075.00 $12.54 $1,040.82 $35.00 $2,905.00 $45.00 $3,735.00 $75.00 $6,225.00 $75.00 $6,225.00 501(C) - SUBSTRUCTURE EXCAVATION, ROCK - CY 94.00 50.00 4,700.00 $28.90 $2,716.60 $150.00 $14,100.00 $45.00 $4,230.00 $150.00 $14,100.00 $150.00 $14,100.00 501(G) - CLSM BACKFILL - CY 259.00 130.00 33,670.00 $127.87 $33,118.33 $85.00 $22,015.00 $80.00 $20,720.00 $105.00 $27,195.00 $105.00 $27,195.00 503(A) - PRESTRESSED CONCRETE BEAMS (TYPE J BT) - LF 1,582.70 275.00 435,242.50 $227.28 $359,716.06 $235.00 $371,934.50 $270.00 $427,329.00 $270.00 $427,329.00 $265.00 $419,415.50 504(A) - APPROACH SLAB - SY 290.00 210.00 60,900.00 $164.42 $47,681.80 $125.00 $36,250.00 $165.00 $47,850.00 $125.00 $36,250.00 $125.00 $36,250.00 504(B) - SAW-CUT GROOVING - SY 1,173.90 5.00 5,869.50 $3.83 $4,496.04 $3.73 $4,378.65 $3.85 $4,519.52 $3.65 $4,284.74 $3.65 $4,284.74 504(C) - EXPANSION JOINT - LF 71.00 125.00 8,875.00 $71.09 $5,047.39 $85.00 $6,035.00 $80.00 $5,680.00 $75.00 $5,325.00 $75.00 $5,325.00 504(D) - CONCRETE RAIL (TR4) - LF 990.10 105.00 103,960.50 $80.07 $79,277.31 $60.00 $59,406.00 $60.00 $59,406.00 $40.00 $39,604.00 $40.00 $39,604.00 504(E) - CONCRETE PARAPET - LF 390.00 105.00 40,950.00 $53.10 $20,709.00 $141.21 $55,071.90 $90.00 $35,100.00 $70.00 $27,300.00 $70.00 $27,300.00 506(A) - STRUCTURAL STEEL - LB 3,613.00 4.00 14,452.00 $1.45 $5,238.85 $2.00 $7,226.00 $3.75 $13,548.75 $2.00 $7,226.00 $2.00 $7,226.00 507(A) - (SP) STAINLESS STEEL FIXED BEARING ASSEMBLY - EA 16.00 1,700.00 27,200.00 $1,109.85 $17,757.60 $1,400.00 $22,400.00 $2,500.00 $40,000.00 $1,500.00 $24,000.00 $1,500.00 $24,000.00 507(B) - (SP) STAINLESS STEEL EXPANSION BEARING ASSEMBLY - EA 16.00 1,700.00 27,200.00 $1,058.99 $16,943.84 $1,400.00 $22,400.00 $2,500.00 $40,000.00 $1,500.00 $24,000.00 $1,500.00 $24,000.00 509 - (SP) SPECIAL CONCRETE FINISH - SY 170.00 90.00 15,300.00 $100.90 $17,153.00 $100.00 $17,000.00 $85.00 $14,450.00 $65.00 $11,050.00 $65.00 $11,050.00 509(A) - CLASS AA CONCRETE - CY 403.50 550.00 221,925.00 $598.21 $241,377.74 $490.00 $197,715.00 $700.00 $282,450.00 $535.00 $215,872.50 $535.00 $215,872.50 509(B) - CLASS A CONCRETE - CY 672.20 600.00 403,320.00 $513.17 $344,952.87 $380.00 $255,436.00 $500.00 $336,100.00 $450.00 $302,490.00 $450.00 $302,490.00 509(D) - CLASS C CONCRETE - CY 46.70 600.00 28,020.00 $376.84 $17,598.43 $1,200.00 $56,040.00 $450.00 $21,015.00 $400.00 $18,680.00 $400.00 $18,680.00 510(C) - SLOPEWALL (5") - SY 1,411.90 95.00 134,130.50 $78.55 $110,904.75 $100.00 $141,190.00 $105.00 $148,249.50 $110.00 $155,309.00 $110.00 $155,309.00 511(A) - REINFORCING STEEL - LB 19,284.00 1.00 19,284.00 $0.89 $17,162.76 $0.84 $16,198.56 $0.80 $15,427.20 $1.00 $19,284.00 $1.00 $19,284.00 511(B) - EPOXY COATED REINFORCING STEEL - LB 198,003.00 1.05 207,903.15 $0.90 $178,202.70 $0.93 $184,142.79 $1.50 $297,004.50 $1.10 $217,803.30 $1.00 $198,003.00 514(A) - PILES, FURNISHED (HP 10X42) - LF 84.00 32.00 2,688.00 $23.37 $1,963.08 $30.00 $2,520.00 $25.00 $2,100.00 $35.00 $2,940.00 $35.00 $2,940.00 514(A) - PILES, FURNISHED (HP 12X53) - LF 147.00 35.00 5,145.00 $26.77 $3,935.19 $37.00 $5,439.00 $30.00 $4,410.00 $40.00 $5,880.00 $40.00 $5,880.00 514(B) - PILES, DRIVEN (HP 10X42) - LF 84.00 18.00 1,512.00 $21.31 $1,790.04 $45.00 $3,780.00 $20.00 $1,680.00 $18.00 $1,512.00 $18.00 $1,512.00 514(B) - PILES, DRIVEN (HP 12X53) - LF 147.00 18.00 2,646.00 $21.31 $3,132.57 $50.00 $7,350.00 $20.00 $2,940.00 $18.00 $2,646.00 $18.00 $2,646.00 514(K) - PILOT HOLES - LF 198.00 130.00 25,740.00 $125.76 $24,900.48 $190.00 $37,620.00 $120.00 $23,760.00 $150.00 $29,700.00 $150.00 $29,700.00 514(L) - PILE SPLICE (NON-BIDDABLE) - EA 1.00 400.00 400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 515(A) - WATER REPELLENT (VISUALLY INSPECTED) - SY 3,438.00 4.00 13,752.00 $3.28 $11,276.64 $3.20 $11,001.60 $3.30 $11,345.40 $3.10 $10,657.80 $3.10 $10,657.80 516(A) - DRILLED SHAFTS 18" DIAMETER - LF 80.50 350.00 28,175.00 $468.25 $37,694.13 $410.00 $33,005.00 $310.00 $24,955.00 $400.00 $32,200.00 $400.00 $32,200.00 516(A) - DRILLED SHAFTS 36" DIAMETER - LF 80.00 525.00 42,000.00 $381.44 $30,515.20 $570.00 $45,600.00 $500.00 $40,000.00 $550.00 $44,000.00 $550.00 $44,000.00 516(A) - DRILLED SHAFTS 66" DIAMETER - LF 97.00 975.00 94,575.00 $1,117.02 $108,350.94 $1,175.00 $113,975.00 $1,230.00 $119,310.00 $1,575.00 $152,775.00 $1,450.00 $140,650.00 516(C) - CROSSHOLE SONIC LOGGING - EA 4.00 3,000.00 12,000.00 $1,695.28 $6,781.12 $1,500.00 $6,000.00 $8,500.00 $34,000.00 $2,300.00 $9,200.00 $2,300.00 $9,200.00 523(A) - SEALER CRACK PREPARATION - LF 36.90 4.00 147.60 $3.28 $121.03 $6.40 $236.16 $6.60 $243.54 $6.25 $230.63 $6.25 $230.63 523(B) - SEALER RESIN - GAL 0.30 90.00 27.00 $218.75 $65.63 $213.00 $63.90 $220.00 $66.00 $205.00 $61.50 $205.00 $61.50 613(H) - 6" PERFORATED PIPE UNDERDRAIN ROUND - LF 602.00 30.00 18,060.00 $15.59 $9,385.18 $25.00 $15,050.00 $9.00 $5,418.00 $17.00 $10,234.00 $17.00 $10,234.00 613(I) - 6" NON-PERFORATED PIPE UNDERDRAIN ROUND - LF 82.00 25.00 2,050.00 $9.57 $784.74 $35.00 $2,870.00 $9.00 $738.00 $17.00 $1,394.00 $17.00 $1,394.00 619(D) - REMOVAL OF EXISTING BRIDGE STRUCTURE - LSUM 1.00 51,600.00 51,600.00 $27,709.01 $27,709.01 $75,000.00 $75,000.00 $125,000.00 $125,000.00 $55,000.00 $55,000.00 $45,000.00 $45,000.00 Schedule of Bid Items - Part A - BRIDGE 107B1; TPU 69.30 $2,095,494.75 $1,789,900.87 $1,851,755.06 $2,213,180.41 $1,942,158.47 $1,892,319.67 Schedule of Bid Items - Part A - BRIDGE 107B1; TPU 71.30 501(B) - SUBSTRUCTURE EXCAVATION, COMMON - CY 160.00 25 4,000.00 $12.54 $2,006.40 $35.00 $5,600.00 $45.00 $7,200.00 $75.00 $12,000.00 $75.00 $12,000.00 501(G) - CLSM BACKFILL - CY 259.00 130 33,670.00 $127.87 $33,118.33 $85.00 $22,015.00 $80.00 $20,720.00 $105.00 $27,195.00 $105.00 $27,195.00 503(A) - PRESTRESSED CONCRETE BEAMS (TYPE J BT) - LF 1,298.70 275 357,142.50 $228.77 $297,103.60 $235.00 $305,194.50 $270.00 $350,649.00 $270.00 $350,649.00 $265.00 $344,155.50 504(A) - APPROACH SLAB - SY 290.00 210 60,900.00 $164.42 $47,681.80 $125.00 $36,250.00 $165.00 $47,850.00 $125.00 $36,250.00 $125.00 $36,250.00 504(B) - SAW-CUT GROOVING - SY 1,000.30 5 5,001.50 $3.83 $3,831.15 $3.70 $3,701.11 $3.85 $3,851.16 $3.65 $3,651.10 $3.65 $3,651.10 504(C) - EXPANSION JOINT - LF 71.00 125 8,875.00 $71.09 $5,047.39 $85.00 $6,035.00 $80.00 $5,680.00 $75.00 $5,325.00 $75.00 $5,325.00 504(D) - CONCRETE RAIL (TR4) - LF 848.10 105 89,050.50 $80.07 $67,907.37 $60.00 $50,886.00 $60.00 $50,886.00 $40.00 $33,924.00 $40.00 $33,924.00 506(A) - STRUCTURAL STEEL - LB 3,391.00 4 13,564.00 $1.45 $4,916.95 $1.75 $5,934.25 $3.75 $12,716.25 $2.00 $6,782.00 $2.00 $6,782.00 507(A) - (SP) STAINLESS STEEL FIXED BEARING ASSEMBLY - EA 16.00 1700 27,200.00 $1,109.85 $17,757.60 $1,400.00 $22,400.00 $2,500.00 $40,000.00 $1,500.00 $24,000.00 $1,500.00 $24,000.00 507(B) - (SP) STAINLESS STEEL EXPANSION BEARING ASSEMBLY - EA 16.00 1700 27,200.00 $1,058.99 $16,943.84 $1,400.00 $22,400.00 $2,500.00 $40,000.00 $1,500.00 $24,000.00 $1,500.00 $24,000.00 509 - (SP) SPECIAL CONCRETE FINISH - SY 170.00 90 15,300.00 $100.90 $17,153.00 $100.00 $17,000.00 $85.00 $14,450.00 $65.00 $11,050.00 $65.00 $11,050.00 509(A) - CLASS AA CONCRETE - CY 338.80 550 186,340.00 $598.21 $202,673.55 $490.00 $166,012.00 $700.00 $237,160.00 $600.00 $203,280.00 $600.00 $203,280.00 509(B) - CLASS A CONCRETE - CY 463.20 600 277,920.00 $513.17 $237,700.34 $400.00 $185,280.00 $500.00 $231,600.00 $450.00 $208,440.00 $450.00 $208,440.00 509(D) - CLASS C CONCRETE - CY 11.70 600 7,020.00 $376.84 $4,409.03 $1,200.00 $14,040.00 $450.00 $5,265.00 $675.00 $7,897.50 $675.00 $7,897.50 510(C) - SLOPEWALL (5") - SY 952.40 95 90,478.00 $78.55 $74,811.02 $100.00 $95,240.00 $105.00 $100,002.00 $110.00 $104,764.00 $110.00 $104,764.00

511(A) - REINFORCING STEEL - LB 18,462.00 1 18,462.00 $0.89 $16,431.18 $0.84 $15,508.08 $0.80 $14,769.60 $1.00 $18,462.00 $1.00 $18,462.00 511(B) - EPOXY COATED REINFORCING STEEL - LB 152,236.00 1.05 159,847.80 $0.90 $137,012.40 $0.93 $141,579.48 $1.50 $228,354.00 $1.10 $167,459.60 $1.00 $152,236.00 514(A) - PILES, FURNISHED (HP 10X42) - LF 249.00 32 7,968.00 $23.37 $5,819.13 $26.00 $6,474.00 $25.00 $6,225.00 $35.00 $8,715.00 $35.00 $8,715.00 514(A) - PILES, FURNISHED (HP 12X53) - LF 406.00 35 14,210.00 $26.77 $10,868.62 $33.00 $13,398.00 $30.00 $12,180.00 $40.00 $16,240.00 $40.00 $16,240.00 514(B) - PILES, DRIVEN (HP 10X42) - LF 249.00 18 4,482.00 $21.31 $5,306.19 $40.00 $9,960.00 $15.00 $3,735.00 $15.00 $3,735.00 $15.00 $3,735.00 514(B) - PILES, DRIVEN (HP 12X53) - LF 406.00 18 7,308.00 $21.31 $8,651.86 $45.00 $18,270.00 $15.00 $6,090.00 $15.00 $6,090.00 $15.00 $6,090.00 514(K) - PILOT HOLES - LF 203.00 130 26,390.00 $125.76 $25,529.28 $140.00 $28,420.00 $120.00 $24,360.00 $150.00 $30,450.00 $150.00 $30,450.00 514(L) - PILE SPLICE (NON-BIDDABLE) - EA 1.00 400 400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 515(A) - WATER REPELLENT (VISUALLY INSPECTED) - SY 2,892.00 4 11,568.00 $3.28 $9,485.76 $3.20 $9,254.40 $3.30 $9,543.60 $3.10 $8,965.20 $3.10 $8,965.20 516(A) - DRILLED SHAFTS 66" DIAMETER - LF 138.00 975 134,550.00 $995.81 $137,421.78 $1,100.00 $151,800.00 $1,230.00 $169,740.00 $1,575.00 $217,350.00 $1,270.00 $175,260.00 516(C) - CROSSHOLE SONIC LOGGING - EA 3.00 3000 9,000.00 $1,695.28 $5,085.84 $1,500.00 $4,500.00 $8,500.00 $25,500.00 $2,300.00 $6,900.00 $2,300.00 $6,900.00 523(A) - SEALER CRACK PREPARATION - LF 36.90 4 147.60 $6.56 $242.06 $6.39 $235.79 $6.60 $243.54 $6.25 $230.63 $6.25 $230.63 523(B) - SEALER RESIN - GAL 0.30 90 27.00 $218.75 $65.63 $213.00 $63.90 $220.00 $66.00 $205.00 $61.50 $205.00 $61.50 613(H) - 6" PERFORATED PIPE UNDERDRAIN ROUND - LF 531.00 30 15,930.00 $15.59 $8,278.29 $20.00 $10,620.00 $9.00 $4,779.00 $17.00 $9,027.00 $17.00 $9,027.00 613(I) - 6" NON-PERFORATED PIPE UNDERDRAIN ROUND - LF 78.00 25 1,950.00 $9.57 $746.46 $20.00 $1,560.00 $9.00 $702.00 $17.00 $1,326.00 $17.00 $1,326.00 619(D) - REMOVAL OF EXISTING BRIDGE STRUCTURE - LSUM 1.00 62400 62,400.00 $35,663.91 $35,663.91 $95,000.00 $95,000.00 $125,000.00 $125,000.00 $65,000.00 $65,000.00 $55,000.00 $55,000.00 Schedule of Bid Items - Part A - BRIDGE 107B1; TPU 71.30 $1,678,301.90 $1,440,069.76 $1,465,031.51 $1,799,717.15 $1,619,619.53 $1,545,812.43 Schedule of Bid Items - Part A - TRAFFIC PAVEMENT MARKING & SIGNING 107B1 413(C) - RUMBLE STRIP-METHOD PCC-CYC - LF 12,024.00 0.5 6,012.00 $0.30 $3,607.20 $0.31 $3,727.44 $0.60 $7,214.40 $0.31 $3,727.44 $0.29 $3,486.96 413(D) - RUMBLE STRIP-METHOD PCC-CON - LF 44,459.00 0.5 22,229.50 $0.30 $13,337.70 $0.31 $13,782.29 $0.40 $17,783.60 $0.21 $9,336.39 $0.29 $12,893.11 805(A) - REMOVAL OF (EXISTING SIGNS) - EA 20.00 50 1,000.00 $5.47 $109.40 $5.33 $106.60 $55.00 $1,100.00 $105.00 $2,100.00 $5.00 $100.00 850(A) - SHEET ALUMINUM SIGNS - SF 317.00 20 6,340.00 $17.50 $5,547.50 $17.04 $5,401.68 $17.00 $5,389.00 $17.00 $5,389.00 $16.00 $5,072.00 851(C) - 2" SQUARE TUBE POST - LF 88.00 9 792.00 $7.66 $674.08 $7.46 $656.48 $8.00 $704.00 $10.00 $880.00 $7.00 $616.00 851(C) - 2 1/2" SQUARE TUBE POST - LF 140.00 10 1,400.00 $8.75 $1,225.00 $8.52 $1,192.80 $9.00 $1,260.00 $10.00 $1,400.00 $8.00 $1,120.00 853.0 - DELINEATORS(TYPE 1, CODE 1) - EA 225.00 15 3,375.00 $32.82 $7,384.50 $31.95 $7,188.75 $33.00 $7,425.00 $39.00 $8,775.00 $30.00 $6,750.00 853.0 - DELINEATORS(TYPE 2, CODE 1) - EA 30.00 20 600.00 $32.82 $984.60 $31.95 $958.50 $33.00 $990.00 $41.00 $1,230.00 $30.00 $900.00 853.0 - DELINEATORS(TYPE 2, CODE 3) - EA 46.00 25 1,150.00 $32.82 $1,509.72 $31.95 $1,469.70 $33.00 $1,518.00 $43.00 $1,978.00 $30.00 $1,380.00 853.0 - BARRIER DELINEATORS(TYPE 2, CODE 1) - EA 450.00 10 4,500.00 $5.47 $2,461.50 $5.33 $2,398.50 $5.50 $2,475.00 $12.50 $5,625.00 $5.00 $2,250.00 853.0 - GUARDRAIL DELINEATORS(TYPE 1, CODE 1) - EA 20.00 15 300.00 $13.67 $273.40 $13.31 $266.20 $13.75 $275.00 $11.85 $237.00 $12.50 $250.00 853.0 - GUARDRAIL DELINEATORS(TYPE 2, CODE 1) - EA 25.00 15 375.00 $13.67 $341.75 $13.31 $332.75 $13.75 $343.75 $12.32 $308.00 $12.50 $312.50 854(A) - TRAFFIC STRIPE PAINT (4" WIDE) - LF 23,714.00 0.2 4,742.80 $0.27 $6,402.78 $0.27 $6,402.78 $0.30 $7,114.20 $0.17 $4,031.38 $0.25 $5,928.50 856(A) - TRAFFIC STRIPE (MULTI-POLYMER)(6"WIDE) - LF 138,696.00 0.65 90,152.40 $0.60 $83,217.60 $0.59 $81,830.64 $0.60 $83,217.60 $1.94 $269,070.24 $0.55 $76,282.80 856(B) - TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS, ETC.) - EA 7.00 200 1,400.00 $546.87 $3,828.09 $532.50 $3,727.50 $550.00 $3,850.00 $250.00 $1,750.00 $500.00 $3,500.00 880(C) - CONSTRUCTION BARRICADES (TYPE III) - EA 2.00 500 1,000.00 $1,093.73 $2,187.46 $1,065.00 $2,130.00 $1,100.00 $2,200.00 $285.00 $570.00 $1,000.00 $2,000.00 Schedule of Bid Items - Part A - TRAFFIC PAVEMENT MARKING & SIGNING 107B1 $145,368.70 $133,092.28 $131,572.61 $142,859.55 $316,407.45 $122,841.87 Schedule of Bid Items - Part A - TRAFFIC LIGHTING 107B1 501(G) - CLSM BACKFILL - CY 360.00 130.00 46,800.00 $250.00 $90,000.00 $55.00 $19,800.00 $110.00 $39,600.00 $275.00 $99,000.00 $200.00 $72,000.00 802(A) - 2" GALV. STEEL ELECTRICAL CONDUIT EXPOSED - LF 25,100.00 15.00 376,500.00 $12.03 $301,953.00 $10.65 $267,315.00 $11.00 $276,100.00 $11.00 $276,100.00 $10.00 $251,000.00 802(B) - 2" PVC SCH.40 PLASTIC CONDUIT BORED - LF 150.00 25.00 3,750.00 $38.28 $5,742.00 $31.95 $4,792.50 $33.00 $4,950.00 $35.00 $5,250.00 $30.00 $4,500.00 802(B) - 2" PVC SCH.40 PLASTIC CONDUIT TRENCHED - LF 400.00 7.00 2,800.00 $17.67 $7,068.00 $8.52 $3,408.00 $8.80 $3,520.00 $16.15 $6,460.00 $8.00 $3,200.00 803(A) - PULL BOX - EA 136.00 1,500.00 204,000.00 $1,410.91 $191,883.76 $532.50 $72,420.00 $550.00 $74,800.00 $1,290.00 $175,440.00 $500.00 $68,000.00 804(A) - STRUCTURAL CONCRETE - CY 1,117.00 500.00 558,500.00 $200.00 $223,400.00 $778.87 $869,997.79 $660.00 $737,220.00 $300.00 $335,100.00 $600.00 $670,200.00 804(B) - REINFORCING STEEL - LB 96,120.00 1.00 96,120.00 $1.00 $96,120.00 $1.54 $148,024.80 $1.10 $105,732.00 $1.25 $120,150.00 $1.00 $96,120.00 806(C) - 40' MTG.HT.POLE & TWIN H.L.MST.ARM (G.STL.) - EA 133.00 2,500.00 332,500.00 $2,351.51 $312,750.83 $2,108.70 $280,457.10 $2,200.00 $292,600.00 $2,150.00 $285,950.00 $1,980.00 $263,340.00 809(A) - ROADWAY LUMINAIRE - EA 266.00 2,200.00 585,200.00 $2,206.05 $586,809.30 $1,746.60 $464,595.60 $1,800.00 $478,800.00 $2,017.00 $536,522.00 $1,640.00 $436,240.00 809(B) - UNDERPASS LUMINAIRE - EA 8.00 1,500.00 12,000.00 $2,149.17 $17,193.36 $1,796.66 $14,373.28 $1,900.00 $15,200.00 $1,965.00 $15,720.00 $1,687.00 $13,496.00 810(A) - SERVICE POLE - EA 2.00 40,000.00 80,000.00 $36,120.38 $72,240.76 $28,755.00 $57,510.00 $30,000.00 $60,000.00 $33,025.00 $66,050.00 $27,000.00 $54,000.00 811.0-1/C NO.00 ELECTRICAL CONDUCTOR - LF 30,500.00 4.00 122,000.00 $3.45 $105,225.00 $3.20 $97,600.00 $3.30 $100,650.00 $3.15 $96,075.00 $3.00 $91,500.00 811.0-1/C NO.0 ELECTRICAL CONDUCTOR - LF 56,000.00 3.00 168,000.00 $2.90 $162,400.00 $2.72 $152,320.00 $2.80 $156,800.00 $3.19 $178,640.00 $2.55 $142,800.00 811.0-1/C NO.2 ELECTRICAL CONDUCTOR - LF 22,000.00 2.00 44,000.00 $2.24 $49,280.00 $1.97 $43,340.00 $2.00 $44,000.00 $3.41 $75,020.00 $1.85 $40,700.00 811.0-1/C NO.10 ELECTRICAL CONDUCTOR - LF 17,000.00 1.00 17,000.00 $0.98 $16,660.00 $0.91 $15,470.00 $0.90 $15,300.00 $0.90 $15,300.00 $0.85 $14,450.00 Schedule of Bid Items - Part A - TRAFFIC LIGHTING 107B1 $2,649,170.00 $2,238,726.01 $2,511,424.07 $2,405,272.00 $2,286,777.00 $2,221,546.00 Schedule of Bid Items - Part A - TRAFFIC CONTROL 107B1 823.0 - (SP)PORTABLE TRAFFIC SIGNAL SYSTEM - SD 180.00 200.00 36,000.00 $164.06 $29,530.80 $159.75 $28,755.00 $165.00 $29,700.00 $70.50 $12,690.00 $150.00 $27,000.00 857(A) - CONSTRUCTION TRAFFIC STRIPE(PAINT) - LF 130,478.00 0.20 26,095.60 $0.11 $14,352.58 $0.11 $14,352.58 $0.12 $15,657.36 $0.13 $16,962.14 $0.10 $13,047.80 857(C) - REMOVABLE PAVEMENT MARKING TAPE - LF 104,311.00 0.85 88,664.35 $0.65 $67,802.15 $0.63 $65,715.93 $0.65 $67,802.15 $1.35 $140,819.85 $0.59 $61,543.49 871.0 - (SP) CONSTRUCTION ZONE IMPACT ATTENUATOR - SD 11,435.00 12.00 137,220.00 $5.47 $62,549.45 $5.33 $60,948.55 $5.50 $62,892.50 $4.00 $45,740.00 $5.00 $57,175.00 877(A) - DELIVER PORTABLE LONGITUDINAL BARRIER - LF 48,250.00 20.00 965,000.00 $34.00 $1,640,500.00 $21.00 $1,013,250.00 $17.00 $820,250.00 $30.00 $1,447,500.00 $26.00 $1,254,500.00 877(B) - RELOCATION OF PORT. LONGITUDINAL BARRIER - LF 104,625.00 2.00 209,250.00 $1.70 $177,862.50 $0.60 $62,775.00 $2.00 $209,250.00 $2.20 $230,175.00 $3.00 $313,875.00 880(A) - (SP) ARROW DISPLAY (TYPE C) - SD 1,460.00 7.50 10,950.00 $1.09 $1,591.40 $1.07 $1,562.20 $1.10 $1,606.00 $1.00 $1,460.00 $1.00 $1,460.00 880(B) - (SP) CONSTRUCTION SIGNS 0 TO 6.25 SF - SD 18,120.00 0.35 6,342.00 $1.09 $19,750.80 $1.07 $19,388.40 $1.10 $19,932.00 $0.05 $906.00 $1.00 $18,120.00 880(B) - (SP) CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF - SD 38,960.00 0.65 25,324.00 $0.05 $1,948.00 $0.05 $1,948.00 $0.06 $2,337.60 $0.05 $1,948.00 $0.05 $1,948.00 880(B) - (SP) CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF - SD 43,690.00 1.50 65,535.00 $0.05 $2,184.50 $0.05 $2,184.50 $0.06 $2,621.40 $0.05 $2,184.50 $0.05 $2,184.50 880(C) - (SP) CONSTRUCTION BARRICADES - SD 11,435.00 1.00 11,435.00 $0.05 $571.75 $0.05 $571.75 $0.06 $686.10 $0.27 $3,087.45 $0.05 $571.75 880(D) - (SP) VERTICAL PANELS - SD 79,530.00 0.40 31,812.00 $0.27 $21,473.10 $0.27 $21,473.10 $0.30 $23,859.00 $0.75 $59,647.50 $0.25 $19,882.50 880(E) - (SP) WARNING LIGHTS (TYPE A) - SD 28,020.00 0.15 4,203.00 $1.09 $30,541.80 $1.07 $29,981.40 $1.10 $30,822.00 $0.75 $21,015.00 $1.00 $28,020.00