Contract: NZTA1234 Resurfacing - Method Example. Contract Documents. NZ Transport Agency Somac 2010 Standard Maintenance Contract

Similar documents
Transcription:

Contract: NZTA1234 Example Contract Documents NZ Transport Agency Somac 2010 Standard Maintenance Contract

Schedule of Prices

Contents Schedule of Prices The Schedule of Prices includes the following sections: 1 Contractor s Management 1 2 Level 1 Routine Maintenance 6 3 Tender Summary 7 4 Average Repair Size 8 5 Traffic Services 9

Management 1 Contractor's Management Schedule of Prices Item Description Type Unit Quantity Rate Amount ($) 1 Contractor s 1 Contract Works 1.1 Contract Management Review M ea 1 2 Contractor's Quality Plan 2.1 Preparation of CQP M LS 1 2.2 Management of CQP M ea 1 (The minimum tendered rate is $500.00 per monthly report. The maximum tendered rate is $600.00 per monthly report) 2.3 Quality Control Testing M Included in tendered rates 3 General Requirements M Included in tendered rates 4 Contractor's Programmes M Included in tendered rates 5 Contractor's Reports 5.1 Monthly Reports M ea 3 (The maximum tendered rate is $300.00/report) 5.2 Final and Maintenance Reports M Included in tendered rates 6 Traffic Management 6.1 Preparation of TMP M LS 1 6.2 Management of TMP M Included in tendered rates 6.3 Traffic Control 6.3.1 Level 1 Traffic Management M Included in tendered rates 6.4 Additional Traffic Control 6.4.1 Level 1 Traffic Management 6.4.1.1 Shoulder Closure U Day 50 6.4.1.2 Single Lane Closure U Day 100 6.4.1.3 Multi Lane Closure U Day 20 6.4.1.4 Mobile Closure U Day 5 SP 1

1 Contractor's Management Schedule of Prices Item Description Type Unit Quantity Rate Amount ($) 7 Environmental Management M Included in tendered rates 8 Unscheduled Works 8.1 Unscheduled Works U PS 1 $20,000.00 $20,000.00 8.1.1 8.2 Cost Fluctuations U PS 1 $10,000.00 $10,000.00 Section 1: Total Tender Sum (Transfer to Tender Summary) SP 2

2 Level 1 Routine Maintenance Schedule of Prices Item Description Type Unit Quantity Rate Amount ($) 9 Pre-surfacing Repairs 9.1 Surfacing 9.1.1 First Coat Sealing U Included in tendered rates 9.1.2 Crack Sealing 9.1.2.1 Sealing U m² 200 9.1.2.2 Additive U m² 100 9.1.3 Crack Filling U m 50 9.1.4 Scabbing and Stripping U m² 100 9.1.5 Flushing 9.1.5.1 Diluent and Chip U m² 4300 9.1.6 High Pressure Water Treatment U m² 1200 9.1.7 Cold Milling U m² 10000 9.1.8 Lichen and Vegetation Removal U m² 2500 9.2 Digouts 9.2.1 Digout Repairs U m² 400 9.2.2 Stabilisation Repairs U m² 1800 9.2.3 Digouts in A/C Pavements 9.2.3.1 0-60mm Depth U m² 100 9.2.3.2 61-150mm Depth U m² 100 9.2.4 Miscellaneous 9.2.4.1 Positive Drainage U m 40 9.2.4.2 Geotextile U m² 100 9.2.4.3 Surface Water Channels U m 50 9.2.4.4 Other U 9.3 Depressions 9.3.1 Rip and Remake 9.3.1.1 Chip Sealed Surface U m² 300 SP 3

2 Level 1 Routine Maintenance Schedule of Prices Item Description Type Unit Quantity Rate Amount ($) 9.3.1.2 Premix Surface U m² 150 9.3.2 Premix Reshaping 9.3.2.1 Chip Sealed Surface U m² 300 9.3.2.2 Premix Surface U m² 150 9.3.2.3 Cold Mill and Inlay - 0 to 30mm Depth U m² 1000 9.3.2.4 Cold Mill and Inlay - 31 to 65mm Depth U m² 500 9.4 Edge Break U m 1500 9.5 Service Covers for Pre-Reseal Repairs 9.6 Manhole Covers U ea 10 9.6.1 Valve Boxes and Hydrant Covers U ea 10 10 Pre-surfacing Treatments 10.1 Texturising 10.1.1 0-500m² per Site m² 2000 10.1.2 501-2,000m² per Site U m² 4000 10.1.3 Greater than 2,000m² per Site U m² 2000 10.2 Minor Levelling U m² 100 10.3 Cold Milling 10.3.1 Cold Milling U m² 4000 10.3.2 Asphalt Concrete Inlay U m² 1000 10.4 Membrane Seal 10.4.1 Membrane Seal U m² 8900 10.4.2 Polymer Modified Membrane Seal U m² 6500 11 Resealing 11.1 Preparation of Surface U m² 513100 11.2 Binder 11.2.1 Conventional Binder (All Grades) U l 750000 SP 4

2 Level 1 Routine Maintenance Schedule of Prices Item Description Type Unit Quantity Rate Amount ($) 11.2.2 Lighting Kerosene U l 75000 11.2.3 Automotive Gas Oil U l 76000 11.2.4 Adhesion Agent U l 750000 11.2.5 Modified Binder U l 23000 11.3 Emulsions 11.3.1 Conventional Emulsion 11.3.1.1 55% Emulsion U l 35000 11.3.1.2 70% Emulsion U l 50100 11.3.1.3 Other U l 25000 11.3.2 Modified Emulsion U 11.4 Sealing Chip 11.4.1 Sealing Chip 11.4.1.1 Grade 2 U m² 35500 11.4.1.2 Grade 3 U m² 343900 11.4.1.3 Grade 4 U m² 108100 11.4.1.4 Grade 5 U m² 74900 11.4.1.5 Grade 6 U m² 45000 11.4.2 Pre-coated Sealing Chip 11.4.2.1 Grade 2 U m² 1200 11.4.2.2 Grade 3 U m² 54000 11.4.2.3 Grade 4 U m² 56000 11.4.2.4 Grade 5 U m² 8700 11.4.3 Dry Lock 11.4.3.1 Grade 4 U m² 3500 11.4.3.2 Grade 5 U m² 10000 11.4.3.3 Grade 6 U m² 65000 11.4.4 Supply of Higher Polished Stone Value (PSV) Aggregate 11.4.4.1 PSV 51-58 U Included in tendered rates 11.4.4.2 PSV 59-61 (Over-rate to Schedule) U m² 20000 SP 5

1 Routine Maintenance 2 Level 1 Routine Maintenance Schedule of Prices Item Description Type Unit Quantity Rate Amount ($) 11.4.4.3 PSV > 61 (Over-rate to Schedule) U m² 10000 12 Thin Asphaltic Surfacings 12.1 Asphalt Concrete 12.1.1 Preparation of Surface U m² 52200 12.1.2 Asphalt Concrete 12.1.2.1 Roundabouts U m² 5200 12.1.2.2 Intersections U m² 10100 12.1.2.3 Other Areas U m² 36900 12.2 Open Graded Porous Asphalt 12.2.1 Preparation of Surface U m² 151000 12.2.2 Porous Asphalt U m² 107100 12.2.3 Polymer Modified Porous Asphalt U m² 36900 12.3 Asphalt Concrete Ramps U m² 151000 12.4 Other Surfacings U 12.5 Service Covers for Thin Asphalt 12.5.1 Fire Hydrants and Valve Boxes U ea 35 12.5.2 Manhole Covers U ea 25 13 Traffic Services 13.1 Traffic Services U LS 1 (Rate transferred from Traffic Services Schedule) 2 Level Section 2: Total Tender Sum (Transfer to Tender Summary) SP 6

Summary 3 Tender Summary Schedule of Prices 3 Tender Section Description Total($) 1 Contractor's Management (from Section 1) 2 Level 1 Routine Maintenance (from Section 2) Total Tender Sum (All Sections) (Transfer to Tender Form) $ Tenderer's Signature: Tenderer's Name: Contact Person: Contact Person's Position: Contact Numbers: Phone Fax SP 7

Repair Size 4 Average Repair Size Schedule of Prices 4 Average The following Schedule sets out the indicative Average Repair Sizes, depths and Annual Quantities for some Scheduled items, and includes: a) average repair size or b) indicative number or quantity (as appropriate) that can be expected to be completed on an annual basis c) indicative average annual number or quantity of digout repairs greater than 300 mm deep. These indicative quantities are provided for the tenderer s information and are based on quantities over the last 3 years. The information provided in no way gives an indication of the final quantities of work. Level 1 Traffic Management (see Section 2): Schedule of Average Repair Sizes Item Description Unit Average Repair Size 10.1.1 Digout Repairs m 2 Consultant to complete 10.1.1.1 0-60mm Depth m 2 10.1.1.2 61-150mm Depth m 2 10.1.1.3 Surface Water Channels m 2 10.1.1.4 Digout Repairs less than 300mm deep m 2 10.1.1.5 Digout Repairs greater than 300mm deep m 2 SP 8

Services 5 Traffic Services Schedule of Prices 5 Traffic Tenderers must complete the Traffic Services Schedule and transfer the Total Amount to the amount column of Section 2, Schedule Item 13.1. The tendered rates will be used to value all work completed under Schedule Item 13.1. To complete this schedule, tenderers must: a) for each item, enter their tendered rate and determine the amount by multiplying the quantity by the tendered rate. b) sum all amounts to determine the total value and transfer this value to the rate column of Section 2, Schedule Item 13.1 Tenderers are advised: i) R means reflective markings ii) iii) NR means non-reflective markings the tendered rates must include all costs associated with establishing all plant at each site. Level 1 Traffic Management (see Section 2): Traffic Services Schedule Item Description Type Unit Quantity Rate ($) Amount ($) 13.1.1 White Continuous 13.1.1.1 75mm NR km 15000 Complete 13.1.1.2 100mm R km 10000 13.1.1.3 150mm R km 6500 13.1.1.4 200mm R km 7600 13.1.1.5 300mm R km 2500 13.1.1.6 400mm NR km 5000 13.1.1.7 450mm NR km 500 13.1.1.8 600mm R km 200 13.1.1.9 900mm R km 100 13.1.1.10 1000mm R km 50 13.1.2 White Intermittent 13.1.2.1 100mm, 3m line, 7m gap NR km 4000 13.1.2.2 150mm, 1m line, 3m gap NR km 1200 13.1.2.3 150mm, 1m line, 5m gap NR km 50 13.1.2.4 200mm, 1m line, 5m gap NR km 670 13.1.3 Yellow Continuous 13.1.3.1 100mm R km 3000 13.1.3.2 200mm R km 1000 13.1.3.3 300mm R km 355 13.1.3.4 150mm R km 450 SP 9

5 Traffic Services Schedule of Prices Level 1 Traffic Management (see Section 2): Traffic Services Schedule Item Description Type Unit Quantity Rate ($) Amount ($) 13.1.3.5 600mm R km 100 13.1.3.6 900mm R km 80 13.1.3.7 1200mm R km 35 13.1.4 Yellow Intermittent 13.1.4.1 No Stopping 1m line, 1m gap NR km 560 13.1.4.2 No Stopping 1m line, 2m gap NR km 870 13.1.4.3 Miscellaneous Markings 13.1.4.4 Stop (word) R ea 20 13.1.4.5 Give Way (word) R ea 45 13.1.4.6 500mm High Lettering R ea 250 13.1.4.7 1.2m High Lettering R ea 500 13.1.4.8 2.4m High Lettering R ea 500 13.1.4.9 3.6m High Lettering R ea 500 13.1.4.10 Disabled Sign R ea 45 13.1.4.11 Hydrant R ea 80 13.1.4.12 Pedestrian Crossing Diamond R ea 54 13.1.4.13 Straight Arrow R ea 67 13.1.4.14 Turn Arrow R ea 25 13.1.4.15 Double Arrow R ea 25 13.1.4.16 Survey Cross R ea 3 13.1.5 Raised Pavement Markers 13.1.5.1 Type A Markers ea 4500 13.1.5.2 Type B Markers ea 6000 13.1.6 LRMS Markings 13.1.6.1 Yellow square (300 x 300) NR ea 13.1.6.2 Yellow line NR ea Total Amount (Transfer to Section 2, Schedule Item 13.1) $ SP 10

Basis of Payment

Contents Basis of Payment Preamble 1 Payment 1. Contract Works 4 1.1 Contract Management Review 4 2. Contractor s Quality Plan 4 2.1 Preparation of CQP 4 2.2 Management of CQP 4 2.3 Quality Control Testing 4 3. General Requirements 5 4. Contractor's Programmes 5 5. Contractor's Reports 5 5.1 Monthly Reports 5 5.2 Final and Maintenance Reports 5 6. Traffic Management 5 6.1 Preparation of Traffic Management Plan (TMP) 5 6.2 Management of TMP 5 6.3 Traffic Control 6 6.4 Additional Traffic Control 6 7. Environmental Management 6 8. Unscheduled Works 6 8.1 Unscheduled Works 6 8.2 Cost Fluctuations 7 9. Pre-surfacing Repairs 7 9.1 Surfacing 7 9.2 Digouts 8 9.3 Depressions 10 9.4 Edge Break 11 9.5 Service Covers for Pre-Reseal Repairs 11 10. Pre-surfacing Treatments 11 10.1 Texturising 11 10.2 Minor Levelling 11 10.3 Cold Milling 12 10.4 Membrane Seal 12 11. Resealing 13 11.1 Preparation of Surface 13 11.2 Binder 13 11.3 Emulsions 14 11.4 Sealing Chip 14

Contents Basis of Payment 12. Thin Asphaltic Surfacings 15 12.1 Asphalt Concrete 15 12.2 Open Graded Porous Asphalt 16 12.3 Other Surfacings 16 12.4 Service Covers 17 13. Traffic Services 17 13.1 Traffic Services 17

1 Preamble Basis of Payment The following Clauses apply to all Items included in the Schedule of Prices. i. Annual Contract Value The annual contract value is expected to fall between -15% and +0% of the value stated in Request for Tender, Clause 1.8. ii. Abbreviations Units of measurement shown in the unit column of the Schedule of Prices are abbreviated as follows: % = Percent /100ea = 100 each (per 100 additional potholes) EMP = Edge Marker Post RPM = Raised Pavement Marker Day = Day ea = each Hr = Hour Km = Kilometre Km.mth = Kilometres Monthly l = Litre LS = Lump Sum LS/mth = Lump Sum per Month LS/Remark = Lump Sum per Remark m = Metre m² = Square Metre m 3 = Cubic Metre t = Tonne kg = Kilogram PS = Provisional Sum $ = Dollar iii. Definitions Task types shown in the Task column of the Schedule of Prices are abbreviated as follows: M U C = Management Task = Unit Rate Task = Cyclic Maintenance Task First Schedule Part B, clause 1.2 defines each task. iv. Measurement Payment for all work completed will be based on the quantities stated on the agreed Programme. No payment will be made for any work completed by the Contractor that was: BP 1

1 Preamble Basis of Payment a) not agreed with the Engineer b) not on an agreed Programme c) deleted by the Engineer from any Programme d) not fully complete at the time of measurement. No additional payment will be made for any increase in the extent of work required to complete Task(s) if this happened only because the Task(s) were not completed by the date shown on the agreed Programme. v. Engineer's Assessment and Measurement If the Engineer's reviews and inspections of the Contract Works show: a) the quality assurance records are incomplete and/or b) some aspects of the Contract Works are non-complying, the Engineer may: value the works according to General Conditions, Clause 12.1.3 instruct the Contractor to identify and rectify all non-complying work arrange for the work to be completed by any such means the Engineer considers appropriate. If time permits, the Contractor will be advised of the Engineer's intentions and given the opportunity to complete the work within the time frame agreed with the Engineer. All costs of initiating, managing and completing any such work may be deducted from the Contractor's payments. These costs will be based on the rates stated under Conditions of Contract, First Schedule, Clause 6.4.6. If the remedial work is completed, the Engineer may: i) reassess and value the work ii) instruct the Contractor to complete further remedial work. No additional payment will be made for any increase in the extent of work required to complete Task(s) if this happened only because the Task(s) were not completed by the date shown on the agreed Programme. vi. Inspections The tendered rates must include all the Contractor's costs associated with undertaking and completing all routine and joint inspections. vii. Stockpile and Disposal Areas BP 2

1 Preamble Basis of Payment The tendered rates must include all the Contractor's costs associated with the use, management and tidy up of all stockpile and disposal areas (see, Section 3 Stockpile and Disposal Areas). viii. Renegotiated Rates If the number and/or extent of pavement repairs within a 100m treatment length exceed 100m² the Contractor must: a) complete the work as an area treatment b) renegotiate the rates for the work to reflect the savings associated with completing larger area treatments rather than smaller individual repairs. ix. Site Investigation and Materials Testing The tendered rates must include all the Contractor's costs associated with completing site investigations and materials testing. x. On-site and Off-site Overheads and Profit The tendered rates must include all the Contractor's costs associated with all on-site and off-site overheads and profit. BP 3

2 Payment Basis of Payment 1. Contract Works The tendered rates must include all the Contractor's costs associated with complying with the Section 1, excluding the costs associated with any Contract Management Review, refer Clause 1.1 below. 1.1 Contract Management Review Schedule Item 1.1 is a Provisional Item only. Payment will be made for each Contract Management Review undertaken in accordance with Section 1. The tendered rate must: a) allow for each review to take 2 days to complete b) fully compensate for completing each review and developing and implementing the Contract Improvement Plan as specified. 2. Contractor s Quality Plan 2.1 Preparation of CQP Payment of the lump sum (LS) will be made as follows: a) 100% when the CQP is agreed The tendered rate must fully compensate for preparing, accepting, reviewing and updating the CQP in accordance with Section 2. 2.2 Management of CQP Payment will be made as a lump sum for each month (when a monthly report is submitted) the CQP is implemented and managed in accordance with Section 2. This item does not include QA testing which is included in the unit rate. The tendered rate must: a) fully compensate for implementing and managing the CQP as specified b) not be less than nor greater than the values stated in the Schedule of Prices. 2.3 Quality Control Testing The tendered rates must include all the Contractor's costs associated with completing all sampling and testing in accordance with Section 2. BP 4

2 Payment Basis of Payment 3. General Requirements The tendered rates shall include all the Contractor's costs associated with complying with the Section 3. 4. Contractor's Programmes The tendered rates must include all the Contractor's costs associated with complying with the Section 4. 5. Contractor's Reports 5.1 Monthly Reports Payment will be made for each Monthly Report submitted in accordance with Section 5. The tendered unit rate must: a) fully compensate for preparing and submitting each Monthly Report as specified b) not be less than nor greater than the values stated in the Schedule of Prices. 5.2 Final and Maintenance Reports The tendered rates must include all the Contractor's costs associated with preparing and submitting the Final and Maintenance Reports in accordance with Section 5. 6. Traffic Management 6.1 Preparation of Traffic Management Plan (TMP) Payment of 100% of the lump sum will be made once the TMP has been agreed. The tendered rate must fully compensate for: a) preparing, reviewing, updating and acceptance by the Engineer of the TMP b) preparing site specific TMPs which may be required in accordance with Section 6. 6.2 Management of TMP The tendered rates shall include all the Contractor's costs associated with management and implementation of the TMP in compliance with the Section 6. Where existing TMPs have been approved (unless there are changes to the Code of Practice of Temporary Traffic Manangement (COPTTM) requirements), these approved TMPs may be BP 5

2 Payment Basis of Payment provided if appropriate for specific circumstances to all tenderers as the basis of pricing e.g. complex temporary traffic management situations. Any changes to the TMP shall be forwarded to the Engineer. All tendered rates must fully compensate for implementing and managing the TMP as specified, inclusive of the costs associated with implementation and management of the TMP during any consecutive or concurrent Separable Portions 6.3 Traffic Control The tendered rates must include all the Contractor's costs associated with providing all traffic control in accordance with Section 6. 6.4 Additional Traffic Control This is a Provisional Item and only applies to work completed as Unscheduled Works. Payment will be made for each day additional traffic control is provided in accordance with Project Specification Section 6. The tendered rate must fully compensate for providing all traffic control for each day as specified including the time for setup and disestablishment. 7. Environmental Management The tendered rates must include all the Contractor's costs associated with developing, implementing, managing and reviewing environmental management measures in accordance with Section 7. 8. Unscheduled Works Schedule Item 8 is a Provisional Item only. 8.1 Unscheduled Works In general, payment will be made on a lump sum basis for all Unscheduled Work completed in accordance with Section 8. The agreed lump sum: a) will be based on the rates tendered under the other Schedule Items b) must fully compensate for completing the unscheduled works as specified. BP 6

2 Payment Basis of Payment 8.2 Cost Fluctuations The provisional sum allows for the payment of cost fluctuations. Payment will be made according to First Schedule, Clause 12.8.2. 9. Pre-surfacing Repairs 9.1 Surfacing 9.1.1. First Coat Sealing The tendered rates must include all costs incurred by the Contractor to complete the first coat seals. First coat seals include: a) single coat first coats and/or two coat first coats and/or premix surfacing b) temporary or sacrificial seal coats, if required. The Contractor will select the sealing technique to address traffic stresses and price accordingly. 9.1.2. Crack Sealing 9.1.2.1. Sealing 9.1.2.2. Additive Payment will be made for the total area of the crack sealing completed in accordance with Project Specification Section 9. The tendered unit rate must fully compensate for completely constructing the crack sealing and reinstating all pavement markings as specified. Payment for this Schedule Item will be in addition to Schedule Item 9. The tendered unit rate must: a) be based on the additive specified in the Operational Requirements b) fully compensate for completely supplying and blending the additive as specified. 9.1.3. Crack Filling Payment will be made for the total length of crack filled in accordance with Section 9. The tendered unit rate must fully compensate for completely filling each crack as specified. BP 7

2 Payment Basis of Payment 9.1.4. Scabbing and Stripping Payment will be made for the total area of scabbing and/or stripping repairs completed in accordance with Section 9. The tendered unit rate must fully compensate for completely constructing the scabbing and/or stripping repairs and reinstating all pavement markings as specified. 9.1.5. Flushing Payment will be made for the total area of flushing repairs completed in accordance with Project Specification Section 9. The tendered unit rate must fully compensate for completely constructing the flushing repairs and reinstating all pavement markings as specified. 9.1.6. High Pressure Water Treatment Payment will be made for the total area of high pressure water treatment (e.g. water blasting), completed in accordance with Maintenance Specification Section 9. The tendered unit rate must fully compensate for complete removal of detritus following high pressure water treatment, and reinstatement of any pavement markings removed within the treatment area. 9.1.7. Cold Milling Payment will be made for the total area of cold milling completed in accordance with Maintenance Specification Section 9. The tendered unit rate must fully compensate for completely constructing the cold milling repairs and reinstating all pavement markings as specified. 9.1.8. Lichen and Vegetation Removal Payment will be made for the total area of lichen and vegetation removal completed in accordance with Section 9. The tendered unit rate must fully compensate for the removal of the lichen and vegetation by the agreed method. 9.2 Digouts 9.2.1. Digout Repairs Payment will be made for the total area of digout repair completed in accordance with Project Specification Section 9. BP 8

2 Payment Basis of Payment The tendered unit rate must: a) include all costs associated with: reinstating and/or reconstructing the adjoining shoulder constructing the first coat seal, including premix surfacings if required, a temporary seal coat and reinstating all pavement markings b) fully compensate for completely constructing the digout repair as specified. 9.2.2. Stabilisation Repairs Payment will be made for the total area of stabilisation repair completed in accordance with Project Specification Section 9. The tendered unit rate must: a) include all costs associated with: reinstating and/or reconstructing the adjoining shoulder constructing the first coat seal, including premix surfacings if required, a temporary seal coat and reinstating all pavement markings b) fully compensate for completely constructing the stabilisation digout repair as specified. 9.2.3. Digouts in A/C Pavements This Item applies to completing digout repairs in A/C (asphaltic concrete) surfaced pavements only. The Item does not apply to constructing A/C surfaced digouts in chip sealed pavements. Payment will be made for the total area of digout repair completed in accordance with Project Specification Section 9. The tendered unit rate must fully compensate for completely constructing the digout repair as specified. 9.2.4. Miscellaneous 9.2.4.1. Positive Drainage Payment will be made for the total length of positive drainage constructed in accordance with Section 9. The tendered unit rate must fully compensate for completely constructing the positive drainage including reinstating and resurfacing of the trench as specified. 9.2.4.2. Geotextile BP 9

2 Payment Basis of Payment Payment will be made for the total area of geotextile placed in accordance with Project Specification Section 9. The tendered unit rate must: a) be based on the geotextile specified in the Operational Requirements b) fully compensate for completely supplying and placing the geotextile as specified. 9.2.4.3. Surface Water Channels This Item: 9.2.4.4. Other a) applies to drainage maintenance associated with completing a task or group of tasks b) does not provide for completing dedicated drainage maintenance works. Payment will be made for the total length of surface water channel constructed in accordance with Section 9. The tendered unit rate must fully compensate for completely constructing the surface water channel, and tying the new surface water channel into the existing drainage facilities, as specified. Payment will be made for the total area or length of repair completed in accordance with Project Specification Section 9. The tendered unit rate must fully compensate for completely constructing the repair as specified. 9.3 Depressions 9.3.1. Rip and Remake Payment will be made for the total area of rip and remake completed in accordance with Project Specification Section 9. The tendered unit rate must: a) include all costs associated with constructing the first coat seal, including premix surfacings, and, if required, a temporary seal coat and reinstating all pavement markings b) fully compensate for completely constructing the rip and remake repair as specified. 9.3.2. Premix Reshaping Payment will be made for the total area of premix reshaping completed in accordance with Project Specification Section 9. BP 10

2 Payment Basis of Payment The tendered unit rate must: a) include all costs associated with constructing the first coat seal, if required, and reinstating all pavement markings b) include all costs associated with cold milling prior to constructing the premix infill c) fully compensate for completely constructing the premix shaping repair as specified. 9.4 Edge Break Payment will be made for the total length of edge break repair completed in accordance with Section 9. The tendered unit rate must: a) include constructing the first coat seal and reinstating all pavement markings b) fully compensate for completely constructing the edge break repair as specified. 9.5 Service Covers for Pre-Reseal Repairs Payment will be made for each service cover adjusted in accordance with Section 9. The tendered unit rate must fully compensate for completely adjusting each service cover including constructing the surfacing and reinstating all pavement markings as specified. 10. Pre-surfacing Treatments 10.1 Texturising Payment will be made for the total area of texturising seal completed at each site in accordance with Section 10. The tendered rate must fully compensate for completely constructing the texturising seal and reinstating all pavement markings and cleaning all raised pavement markers as specified. 10.2 Minor Levelling Payment will be made for the total quantity of minor levelling constructed in accordance with Section 10. The tendered rate must fully compensate for completely constructing the minor levelling and reinstating all pavement markings as specified. BP 11

2 Payment Basis of Payment 10.3 Cold Milling 10.3.1. Cold Milling Payment will be made for the total area of cold milling completed in accordance with Project Specification Section 10. The tendered rate must: a) be based on the depth specified in the Operational Requirements b) fully compensate for completely cold milling each area as specified. 10.3.2. Asphalt Concrete Inlay Payment will be made on the total area of pavement milled (see Basis of Payment, Clause 10.3.1) in accordance with Section 10. The tendered rate must fully compensate for supplying and completely constructing the asphaltic concrete and reinstating all pavement markings as specified. 10.4 Membrane Seal 10.4.1. Membrane Seal Payment will be made for the total area of membrane seal completed in accordance with Project Specification Section 10. The tendered rate must: a) be based on the residual application rate and grade of chip specified in the Operational Requirements b) fully compensate for completely constructing the membrane seal as specified. 10.4.2. Modified Membrane Seal Payment will be made for the total area of modified membrane seal constructed in accordance with Section 10. The tendered rate must: a) be based on the additive, residual application rate and grade of chip specified in the Operational Requirements b) fully compensate for completely constructing the modified membrane seal as specified. BP 12

2 Payment Basis of Payment 11. Resealing 11.1 Preparation of Surface 11.2 Binder Payment will be made for the total area of pavement resealed in accordance with Project Specification Section 11. The tendered rate must fully compensate for completely preparing the surface for resealing as specified. 11.2.1. Conventional Binder (All Grades) Payment will be made according to TNZ P/4, Clause 26.2.2. The tendered rate must fully compensate the supply and completely constructing the conventional binder as specified. 11.2.2. Lighting Kerosene Payment will be made according to TNZ P/4, Clause 26.2.3. The tendered rate must fully compensate for supplying and completely blending the lighting kerosene as specified. 11.2.3. Automotive Gas Oil Payment will be made according to TNZ P/4, Clause 26.2.4. The tendered rate must fully compensate for supplying and completely blending the automotive gas oil as specified. 11.2.4. Adhesion Agent Payment will be made according to TNZ P/4, Clause 26.2.5. The tendered rate must fully compensate for supplying and completely blending the adhesion agent as specified. 11.2.5. Modified Binder Payment will be made for the total volume of modified bituminous binder approved for payment according to Basis of Payment, Clause 11.2.1. BP 13

2 Payment Basis of Payment The tendered rate must: a) be based on the additive nominated in the Operational Requirements b) fully compensate for supplying and completely constructing the modified binder as specified. 11.3 Emulsions 11.3.1. Conventional Emulsion Payment will be made according to TNZ P/4, Clause 26.3. The tendered rate must fully compensate for supplying and completely constructing the emulsified binder as specified. 11.3.2. Modified Emulsion Payment will be made according to Basis of Payment, Clause 11.3.1. The tendered rate must: a) be based on the additive nominated in the Operational Requirements b) fully compensate for supplying and completely constructing the modified emulsified binder as specified. 11.4 Sealing Chip 11.4.1. Sealing Chip Payment will be made for the total area of sealing chip constructed in accordance with Project Specification Section 11. The tendered rate must fully compensate for supplying and completely constructing the sealing chip as specified. 11.4.2. Pre-coated Sealing Chip Payment will be made for the total area of pre-coated sealing chip constructed in accordance with Section 11. The tendered rate must fully compensate for supplying and completely pre-coating and constructing the pre-coated sealing chip as specified. BP 14

2 Payment Basis of Payment 11.4.3. Dry Lock Payment will be made for the total area of reseal dry locked in accordance with Project Specification Section 11. The tendered rate must fully compensate for supplying and completely constructing the dry lock as specified. 11.4.4. Supply of Higher Polished Stone Value (PSV) Aggregate 11.4.4.1. PSV 51 58 The supply o PSV 51-58 aggregate is deemed to be included in the tendered rates. 11.4.4.2. PSV 59 61 (Over-rate to Schedule) The over-rate shall only be paid on the total area of sealcoat constructed using PSV 59-61 aggregate where this higher PSV chip is required. 11.4.4.3. PSV > 61 (Over-rate to Schedule) The over-rate shall only be paid on the total area of sealcoat constructed using PSV > 61 aggregate and where this higher PSV chip is required. 12. Thin Asphaltic Surfacings 12.1 Asphalt Concrete 12.1.1. Preparation of Surface Payment will be made for the total area of pavement resurfaced in accordance with Project Specification Section 12. The tendered rate must fully compensate for completely preparing the surface for resurfacing (but excluding any pre-surfacing treatment, including milling the existing pavement) as specified. 12.1.2. Asphalt Concrete Payment will be made for the total area of asphaltic concrete constructed in accordance with Section 12. The tendered rate must fully compensate for completely constructing the asphaltic concrete overlay as specified, including tack coat or membrane seal, and all preparation work, as specified. BP 15

2 Payment Basis of Payment 12.2 Open Graded Porous Asphalt 12.2.1. Preparation of Surface Payment will be made for the total area of pavement resurfaced in accordance with Project Specification Section 12. The tendered rate must fully compensate for completely preparing the surface for resurfacing (but excluding any pre-surfacing treatment including milling the existing pavement) as specified. 12.2.2. Porous Asphalt Payment will be made for the total area of porous asphalt constructed in accordance with Project Specification Section 12. The tendered rate must fully compensate for completely constructing the open graded porous asphalt as specified, including a tack coat if required. 12.2.3. Polymer Modified Porous Asphalt Payment will be made according to Basis of Payment, Clause 12.2.2 for the total area of polymer modified porous asphalt in accordance with Section 12. The tendered rate must: a) be based on the additive nominated in the Operational Requirements b) fully compensate for completely constructing the polymer modified porous asphalt as specified. 12.2.4. Asphalt Concrete Ramps Payment will be made according to Basis of Payment, Clause 12.1 for the total area of asphalt concrete ramps constructed according to Section 12. The tendered rate must fully compensate for completely constructing the asphaltic concrete ramps as specified. 12.3 Other Surfacings Payment will be made for the total area resurfaced in accordance with Section 12. The tendered rate must: a) be based on the other surfacing nominated in the Operational Requirements b) fully compensate for completely constructing the other surfacing as specified. BP 16

2 Payment Basis of Payment 12.4 Service Covers Payment will be made for each service cover adjusted in accordance with Section 12. The tendered unit rate must fully compensate for completely adjusting each service cover including constructing the surfacing and reinstating all pavement markings as specified. 13. Traffic Services 13.1 Traffic Services Payment will be made for reinstating all Traffic Services at the tendered rates as detailed in Section 5 Schedule of Prices, Traffic Services Schedule. The tendered rate must fully compensate for completely reinstating all traffic services as specified if the: a) actual quantity of work exceeds the quantity stated in the Schedule of Traffic Services, the rate for Schedule Item 13 will be adjusted by multiplying the actual quantity for each sub-item by the tendered rate and recalculating the rate for Schedule Item 13. b) traffic services are not reinstated within the specified response times (see Section 13) payment for this Item will be reduced by 5% for each day between the date the work is due for completion and the date the traffic services are reinstated. BP 17

Contents 1. Contract Works 1 1.1 Scope 1 1.2 Contract Works' Description 1 1.3 Obligations 2 1.4 Road Classes 3 1.5 Performance Monitoring 3 1.6 Contract Completion 6 1.7 Defects Liability Period 6 2. Contractor's Quality Plan 7 2.1 Scope 7 2.2 Response Times 7 2.3 Contract Quality Plan 7 2.4 Document Procedures 8 2.5 Standards and Materials 10 3. General Requirements 11 3.1 Scope 11 3.2 Response Times 11 3.3 Network Information 11 3.4 Working Hours 11 3.5 Communications 12 3.6 Inspections 13 3.7 Location of Work 14 3.8 Existing Services 14 3.9 Repair of Damage 14 3.10 Reinstatement of Traffic Control Devices 14 3.11 Plant and Equipment 15 3.12 Other Contractors 16 3.13 Publications and Standards 16 3.14 Stockpile and Disposal Areas 17 3.15 Land Entry Agreements 17 3.16 Removal and/or Recycling of Damaged Components 18 3.17 Definitions 18 4. Contractor s Programmes 29 4.1 Scope 29 4.2 Response Times 29 4.3 Review of Programme 29 4.4 Preparation of Programmes 29 4.5 Management and Implementation of Programme 31 5. Contractor s Reports 33 5.1 Scope 33 5.2 Response Times 33 5.3 Reports 33 5.4 Monthly Report 33 5.5 Final Report 35

Contents 5.6 Maintenance Report 35 5.7 Daily Report 35 5.8 Work Site Crash/Accident Reports 36 6. Traffic Management 37 6.1 Scope 37 6.2 Response Times 37 6.3 Traffic Management Plan 37 7. Environmental Management 39 7.1 Scope 39 7.2 Response Times 39 7.3 Key Considerations 39 7.4 Resource Consents 40 8. Unscheduled Works 41 8.1 Scope 41 8.2 Response Times 41 8.3 Priced Proposals 41 8.4 Completion 41 9. Pre-surfacing Repairs 42 9.1 Scope 42 9.2 Definitions 42 9.3 Response Times 42 9.4 Specific Requirements 43 9.5 Digouts 46 9.6 Materials 47 9.7 Depressions 47 9.8 Edge Break Repairs 48 9.9 Service Covers 49 9.10 Shoulder Maintenance 49 9.11 Performance Criteria 50 10. Pre-surfacing Treatments 52 10.1 Scope 52 10.2 Definitions 52 10.3 Response Times 52 10.4 Specific Requirements 52 10.5 Performance Criteria 54 11. Resealing 55 11.1 Scope 55 11.2 Definitions 55 11.3 Response Times 55 11.4 Specific Requirements 56 11.5 Performance Criteria 57 12. Thin Asphaltic Surfacings 58

Contents 12.1 Scope 58 12.2 Definitions` 58 12.3 Response Times 58 12.4 Specific Requirements 59 12.5 Performance Criteria 62 13. Traffic Services 63 13.1 Scope 63 13.2 Definitions 63 13.3 Response Times 63 13.4 Specific Requirements 64 13.5 Performance Criteria 64

1 Contract Works 1. Contract Works 1.1 Scope This Section describes the extent and location of the Contract Works, the Contractor's and Engineer's obligations and describes performance reviews. 1.2 Contract Works' Description 1.2.1. Extent This Contract is for the resurfacing sections of highway within a network and may include, if provided for in the Contract Documents, determining the most cost effective treatment and/or repair and completing pre-surfacing repairs following possession of site for that year. The Operational Requirements details the specific requirements that apply to this Contract. All work required by this resurfacing work including treatment selection and design will be completed under the Engineer's direction. This contract requires a high degree of co-operation between the Contractor and the Engineer. The detailed investigations carried out by the Contractor to facilitate the design of the works may necessitate review of the outputs of the treatment selection process. In some cases technical reviews may be necessary to resolve the most effective treatment and such reviews may involve the utilisation of external resources. The treatment selection and design processes, and roles and responsibilities relating to these, are described in Transit's State Highway Asset Management Manual. The Contract Works (see General Conditions, Clause 1.2) are described in this Project Specification, summarised in the Schedule of Prices and include: a) implementing a CQP to enable the completion of the Contract Works (see Section 2) b) providing all labour, plant and materials required to complete the Contract Works. The Contract Works excludes planned maintenance except as provided in the Contract Documents 1.2.2. Location The Contract Works are located within the network described in Operational Requirements, Clause 2. The network includes: a) all carriageways, bridges and other structures, stormwater structures, roadside furniture and road safety barrier systems, and encompasses the road reserve bound by existing fences or road reserve boundaries b) all established rest areas and roads, bridges and stormwater structures within these areas. c) If a local road intersects the state highway at grade, the Contractor must maintain the state highway for a distance of 10 metres from the limit line position or to the end of seal, whichever is the lesser. This maintenance includes: Pavement maintenance PS 1

1 Contract Works Maintenance of regulatory signs associated with the intersection Maintenance of raised traffic islands Other areas associated with the intersection as outlined in the Operational Requirements. 1.3 Obligations 1.3.1. Contractor's Obligations The Contractor must: a) construct nominated surfacing b) maintain the surfacing for the period specified (see First Schedule, Clause 11.1.1) c) provide the Site and Surfacing Reports d) ensure that sufficient resources are maintained to source the needs of the contract, both for programmed and scheduled works and for unscheduled works. e) programme and complete the works according to the Contract Documents f) the Contractor will review the weather forecast and ensure that work is completed when the required result can be achieved. 1.3.1.1. Maintenance on State Highway Benchmark and Calibration Sections State highway benchmark and calibration sections are listed in the Operational Requirements. The maintenance requirements for these sections are tabulated below: Table 1.1: Maintenance on State Highway Benchmark and Calibration Sections Section Type Benchmark Section (excluding any calibration length) Calibration Section (Sterilised) Calibration Section (Non-Sterilised) Obtain Approval Prior to Maintenance work (Yes / No) No Yes Yes Maintain to Contract Specification (Yes / No) Yes No (Hazard Removal Only) Yes Maintenance records provision Details entered into RAMM database Details entered into RAMM and LTPP Site Maintenance Databases Details entered into RAMM and LTPP Site Maintenance Databases Note: The completed LTPP site maintenance database for each financial year shall be submitted to the Asset Management Team, NZTA National Office, Wellington annually by the end of July. PS 2

1 Contract Works 1.3.2. Engineer's Obligations The Engineer will: a) determine the treatment for each site b) complete each treatment design, except the mix design for thin asphaltic surfacings c) supervise the Contractor's operation and complete CQP reviews to: assess the Contractor's progress and performance assess the content and appropriateness of all the work included in the Contractor's Programmes verify the Contractor's reports certify the Contractor's claims for payment according to the Contract Documents. e) complete performance appraisals. f) updating of the inventories including measures adopted to ensure the accuracy, validity and completeness of the data presented for updating the Client's databases. 1.4 Road Classes Table 1.2 Road Classes shows the classification of each highway road within the network. Class M U R1 R2 R3 R4 Table 1.2: Road Classes Type/Volume Motorways and Expressways Urban State Highways Greater than or equal to 10,000 vpd 4,000 to 9,999 vpd, Heavy Vehicle and Tourist Routes 1,000 to 3,999 vpd 0 to 999 vpd 1.5 Performance Monitoring Systems shall be implemented to monitor and report on the performance of the Contract in respect to achievement of performance indicators and compliance with the specified outcomes defined in this contract. 1.5.1. Monitoring by the Engineer The Principal requires the Engineer to: a) provide monthly contract progress reports b) complete performance evaluations. Performance evaluations will be completed to: PS 3

1 Contract Works i) assess the Contractor's overall performance ii) monitor the performance indicators (see Clause 1.5.3) iii) assess the culture of the contracted parties and the Engineer's performance iv) determine the Contractor's overall track record score for the Contract. All parties will meet with an independent party, if required, and complete each appraisal. v) If provided for in the Contract Documents, the resulting overall performance appraisal score will be used to determine if the Contract will be extended, see First Schedule, Clause 1.2. vi) Where provided for in the Contract Documents, any performance appraisal to determine if the Contract shall be extended to the following Separable Portion shall be undertaken by the Engineer 6 months prior to the specified Separable Portion date. vii) The Engineer shall advise both the Contractor and Principal, in writing, the resulting overall performance appraisal score. viii) Each evaluation will be completed using the Performance Evaluation Form (PACE), see Appendix 1.2 ix) The evaluation frequency for this contract is to be determined by the Engineer following contract award. General guidelines indicate that evaluation frequencies are set at monthly intervals throughout the contract period, but shall not be at more than 6 monthly intervals throughout the period of the contract. c) complete a final contract report and determine the Contractors overall track record score. The performance evaluations will be considered in determining the overall track record score. 1.5.2. Contract Management Review The purpose of the contract management review (CMR) is to assess the compliance and effectiveness of contract management activities, and the ability of the Contract to achieve specified contract outcomes. The Principal: a) has developed procedures for the CMR. The CMR will be completed over a two-day period in the Contractor's offices b) may complete the CMR at least once during the contract period and more frequently if problems are encountered c) will give 2 weeks notice of the CMR. The Contractor: i) must provide a working space and make available contract personnel and records to complete the review PS 4

1 Contract Works ii) will be provided with a report and, if appropriate, a contract improvement plan. This plan will be used to address areas of non-compliance and to monitor the Contractor's progress and performance. The results of the review will be included in the Contractors PACE evaluation as well as being included in the assessment of quality (see Clause 1.5.3.3). Evaluations will take into consideration the number and type of non-compliances identified, and the Contractor's ability to meet agreed completion dates in respect to corrective action required in response to the review findings. 1.5.3. Monitoring by the Contractor The Contractor must monitor their own performance and in particular the following performance indicators. The updated Performance Indicators must be included in the Monthly Report (see Section 5). 1.5.3.1. Financial Performance The following financial performance indicators will be measured: a) Accrued Value of Work versus Budget and Updated Forecast b) Value of Monthly Programmes versus Budget, Forecast and the value certified for payment c) Value of Outstanding Work and Work In Progress. The financial performance indicators will be measured for each payment item and the Contract Works (see Sections 4 and 5). 1.5.3.2. Achievement 1.5.3.3. Quality The following achievement indicators will be measured: a) the number of tasks completed each month compared to the number of tasks programmed b) the number of faults the Engineer identifies that were not rectified within the specified response times c) the number of outstanding tasks each month compared to the number of tasks programmed. The following quality indicators will be measured: a) the number of non-complying tasks compared to the number of tasks programmed. The term 'non-complying tasks' is defined as including; repairs outside specification, failure of repair, and complaints; including those identified both internally and externally (e.g. by the Engineer or Public) b) samples of the Contractor's records, including minutes of meetings etc., that demonstrates the Contractor's procedures for handling quality issues c) CQP compliance (see Section 2) PS 5

1 Contract Works d) the number and/or type of Non-Compliances identified in internal contract systems compliance audits, reviews and/or audits by the Engineer (see Clause 1.5.1) and (where appropriate) contract management reviews (see Clause 1.5.2) e) any other indicators developed during the contract period. 1.5.3.4. Safety (including Traffic Management) The following safety indicators will be measured: a) the number of near misses identified b) the numbers of work site crash/accidents, observed crashes, and/or crash evidence c) TMP compliance (see Section 6) d) samples of the Contractor's records, including minutes of meetings etc., that demonstrate the Contractor's procedures for handling safety issues e) any other agreed indicators developed during the contract period. 1.6 Contract Completion Within 7 days of completing each Separable Portion and/or the Contract Works (see First Schedule, Clause 10.2.1), the Contractor must: a) write advising the Engineer that all works are complete and comply with the Contract Documents b) request the Certificate of Practical Completion for each Separable Portion and/or the Contract Works. 1.7 Defects Liability Period A minimum of two weeks before the defects liability period is complete, (see First Schedule, Clause 11.1.1) the Contractor must request the Defects Liability Certificate for each Separable Portion and/or the Contract Works. The Defects Liability Certificate will not be issued until the Contractor has demonstrated the Contract Works comply with the Contract Documents. PS 6

2 Contractor's Quality Plan 2. Contractor's Quality Plan 2.1 Scope This Section sets out the minimum requirements for the quality assurance of the Contract Works quality assurance. The work required must be completed in accordance with Section 1, TNZ Q/1 (Q1) and Q/2 (Q2) and the following requirements. 2.2 Response Times Table 2.1 states the response times for preparing, submitting, reviewing, updating and accepting the CQP. Activity Draft CQP Final CQP Pre-commencement Review Surveillance Review Annual CQP Review Table 2.1: Contract Quality Plan Assessment Within 2 weeks of the Date of Acceptance of Tender Within 1 week of the Engineer s review of the draft CQP and before the date of possession of site A minimum of 72 hours following the Engineer s notification of the review A minimum of 24 hours following the Engineer s notification of the review Within 3 weeks of the anniversary of Acceptance of Tender 2.3 Contract Quality Plan The Contractor must develop the Contract Quality Plan (CQP), and the contract works must be undertaken in accordance with the CQP. The CQP must be based on the Contractor's quality, health and safety and environmental management systems. Nothing in the CQP will take precedence over the requirements of the Contract Documents. In particular, nothing in the CQP will relieve the Contractor from the performance of the Contractor's obligations under the Contract Documents even though the CQP has been approved by the Principal or the Principal's Agent. The expectation is that the Contractor will take full ownership of all quality assurance aspects so that the Principal can be assured that the acceptability of the end result will not be attributed to a quality issue. 2.3.1. CQP Implementation and Management The CQP must be implemented and managed so: a) the Contract Works are identified, programmed and completed within the response times specified b) the Contract Works are completed according to the Contract Documents PS 7