Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

Similar documents
Transcription:

Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015

Arbor Heights Elementary School Elementary School North and South Building - Metal pan-decking and steel edgeform installation is ongoing. South Building - The eastern half of the second floor concrete slab-on-deck was poured. North Building - Remaining foundation walls formed and reinforced.

Arbor Heights Elementary School South Building - 2 nd Floor Pan Decking with Reinforcing Mesh August 21, 2015

Arbor Heights Elementary School South Building - 2 nd Floor Slab-on-Deck Concrete Pour August 21, 2015

Arbor Heights Elementary School South Building - 2 nd Floor Finishing Concrete August 21, 2015

Arbor Heights Elementary School North Building - 2 nd Floor Welding Edge Form August 21, 2015

Arbor Heights Elementary School Looking South through North Building August 14, 2015

Arbor Heights Elementary School View of Arbor Heights Elementary from North West Looking South East August 21, 2015

Genesee Hill Elementary School Site Plan 4

Genesee Hill Elementary School Area 1: Exterior wall framing and installation of sheathing at levels 1 and 2 on-going; mechanical ductwork install 95% complete; plumbing and electrical rough-in is ongoing; installation of roofing system nearing completion. Area 2: Concrete footing and stem wall foundations on-going, approximately 95% complete; structural steel erection is ongoing; continued roof trusses and bracing install; continued installing metal decking at level 2, mechanical mezzanine and roof. Area 3: Continued to install ductwork at mechanical mezzanine and started at stage; exterior metal framing continues; continued installing roofing system at high roof. Area 4: Installed framing and rigid insulation at skylights; began installing roofing system at roof. Site: Civil contractor began backfilling concrete retaining walls at access stairs to the lower parking lot; concrete slab encroachment removed from NE corner of site.

Genesee Hill Elementary School Aerial View

Genesee Hill Elementary School Area 1 - North Elevation

Genesee Hill Elementary School Area 1 Level 3 - Ongoing Installation of Exterior Framing

Genesee Hill Elementary School Area 2 - Ongoing Structural Steel Erection

Genesee Hill Elementary School Area 3 Roof Ongoing Installation of PVC Roofing System

Genesee Hill Elementary School Area 4 - Ongoing CMU Veneer Installation

Genesee Hill Elementary School Area 4 - Roof Framing of Skylight Curbs

Genesee Hill Elementary School Backfill at Access Stairs to Lower Parking Lot

Hazel Wolf K-8 at Pinehurst Site Plan

Hazel Wolf K-8 at Pinehurst Area A2 Classroom Building - Below grade masonry continued, capillary break placed for the building slab on grade. Metal deck installation ongoing on the 3 rd floor. Penthouse structural steel was completed this week. Area A1 - Foundations and stem walls are being damp proofed and on-site underground utilities are continuing. Area C Gym/Special Ed Areas - Concrete pours occurred for the large retaining walls along Pinehurst Way. Foundation and stem wall rebar and concrete work continues at the Kitchen/Music Room and Gym/ Commons areas. Below grade masonry continues at the Gym.

Hazel Wolf K-8 at Pinehurst Aerial View from the West

Hazel Wolf K-8 at Pinehurst Area A2 - Main Floor Corridor Looking South August 20, 2015

Hazel Wolf K-8 at Pinehurst Area A2 - Electrical Room Looking North East August 20, 2015

Hazel Wolf K-8 at Pinehurst Area A2 - Penthouse Steel Completed Looking North West August 20, 2015

Hazel Wolf K-8 at Pinehurst Area A1 - Damp Proofing Looking North August 21, 2015

Hazel Wolf K-8 at Pinehurst Area C - Excavation and Form Work Looking East August 21, 2015

Hazel Wolf K-8 at Pinehurst Area C - Geowell Cap Ends (Center Picture) Looking East August 21, 2015

Hazel Wolf K-8 at Pinehurst Area C - Stem Wall Rebar and Forming Looking North August 21, 2015

Hazel Wolf K-8 at Pinehurst Area C - Placement of Capillary Break August 21, 2015

New Thornton Creek Building Key Plan

New Thornton Creek Building Area A - Excavation of footings on-going. Concrete footing forming and placement of reinforcing steel in footings on-going. Installed underground plumbing in northeast portion of Building. Area B - Completed underground plumbing and electrical. Placing gravel capillary break, vapor barrier, steel mesh and rebar in preparation for concrete slab pour. Area C - Began erection of structural steel. Site - Completed sanitary sewer from property line to grease interceptor and from Area A north to grease interceptor. Completed grading and excavation of rain garden in southwest corner of site adjacent Area B. Began utility trenching for new electrical service and communication conduits. Off-Site - Completed street crossing and sanitary sewer connection under 40 th Ave NE.

New Thornton Creek Building Aerial Photo

New Thornton Creek Building Area A - Placing Forms for Footings

New Thornton Creek Building Area A - Placing Rebar in Footings

New Thornton Creek Building Area A - Conduits for Communication Running North

New Thornton Creek Building Area A - Rebar Installed in Elevator Pit

New Thornton Creek Building Area B - Vapor Barrier Installed Over Gravel Capillary Break

New Thornton Creek Building Area B - Steel Mesh and Rebar Installed

New Thornton Creek Building Area C - Steel Erection Begins

New Thornton Creek Building Area C - Steel Erection