Title: Protection and Management of Shallow Groundwater Sources for South Tarawa

Similar documents
COORDINATION OF THE WATER AND SANITATION SECTOR: BACKGROUND TO THE KIRIBATI NATIONAL WATER AND SANITATION COORDINATION COMMITTEE

Kiribati. Hot Spot Analysis. Report

EU Water Governance Programme. Kiribati Pilot Project

Water Governance Pacific Islands. Latu Sauluitoga Kupa Executive Director

Case Study A VULNERABILITY OF FRESHWATER LENS ON TARAWA THE ROLE OF HYDROLOGICAL MONITORING IN DETERMINING SUSTAINABLE YIELD

Hydrological Training Programme for Pacific Island Countries INTEGRATED WATER RESOURCES MANAGEMENT

HOT SPOT AND SENSITIVE AREAS FOR THE KINGDOM OF TONGA.

Implementation of Sustainable Development Goals Regional Seminar on Integrated Approaches for SDG Planning. Fiji

SECTOR ASSESSMENT: WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES. 1. Sector Performance, Problems, and Opportunities

24.LESOTHO Background Coverage

Country programme plan for Kiribati (June 2016 update)

Energy Footprint for Water Supplies in Pacific Islands

Logical Framework and Objectively Verifiable Impact Indicators

Hot Spot Analyses and Selection of focus for Demonstration Project for Tuvalu 1. Introduction and Summary

Pacific Island Nations REGIONAL ACTION PLAN

Maldives Country Paper

SECTOR ASSESSMENT: WATER AND SANITATION. 1. Sector Performance, Problems, and Opportunities

Effects of climate change on water resource of Maldives EMBASSY OF THE REPUBLIC OF MALDIVES TOKYO, JAPAN

NATIONAL WATER POLICY. (draft FINAL) Water is everybody s responsibility

Implementing Adaptation through LDCF and SCCF and the Climate Information Gap

5 th World Water Forum

Ministry of Public Utilities

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES

GEF PACIFIC IWRM PROJECT RESULTS NOTE

Groundwater Training Course SOPAC, April Island Groundwater Resources

NATIONAL PLAN REPUBLIC OF PALAU

National Water Policy for Palestine

Summary of the Pacific Community s 2015 work programme in. Kiribati. (November 2015 update)

Pacific Umbrella Initiative: Pacific Type II Partnership Initiative on Sustainable Water Management Proposed Partners

Call for EoI for assisting the Republic of Nauru to develop a National Water and Sanitation Policy Framework and Implementation Plan

KIRIBATI: NAPA PROJECT PROFILE

WASTEWATER POLICY STATEMENT

A NEW SONG FOR COASTAL FISHERIES PATHWAYS TO CHANGE & KIRIBATI CBEAFM

Sustainable Integrated Water Resources and Wastewater Management Project in Pacific Island Countries. National Stakeholder Consultation Process

UNDP-Spain MDG Achievement Fund. Terms of Reference for Thematic Window on Environment and Climate Change

SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES (WATER AND WASTEWATER)

II. Situation Analysis and Agriculture Sector Overview

SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES 1 Sector Road Map

SUSTAINABLE DEVELOPMENT OF WATER RESOURCES IN SMALL ISLAND NATIONS OF THE PACIFIC

Rashid Ali Khan, FAO (Ret.) Gurgaon, Haryana

Atoll Reclamation, an Option? Robert Smith, Geoscience Division PC

Integrated Catchment Modelling

Rainwater Harvesting for Domestic Water Supply and Stormwater Mitigation

Safe Water for People in Low, Small Island Pacific Nations: The rural urban dilemma

Chapter 4 Impact of Climate Change on Low Islands The Tarawa Atoll, Kiribati

SECTOR ASSESSMENT (SUMMARY): SANITATION

REGIONAL CONFERENCE on Sustainable Sanitation Solutions (3S) January 2019, Colombo, Sri Lanka

Ex-ante Evaluation - 1 -

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES 1

Strengthening Resilience of Water Supply and Sanitation to Climate Change in Coastal Towns of Bangladesh

LAW OF THE REPUBLIC OF INDONESIA NUMBER 7 OF 2004 REGARDING WATER RESOURCES

MANADO OCEAN DECLARATION (ADOPTED ON 14 MAY 2009, IN MANADO)

Pacific Cooperation Plan. Preliminary Sector Analysis for Water, Sanitation and Hygiene

MR. MELETI BAINIMARAMA PERMANENT SECRETARY FOR RURAL & MARITIME DEVELOPMENT, NATIONAL DISASTER MANAGEMENT & METEOROLOGICAL SERVICES

United Nations Environment Programme

Maldives National Adaptation to Climate Change / the Human Dimension of Global Climate Change

Conserve and sustainably use the oceans, seas and marine resources for sustainable development

KENYA WATER FOR HEALTH ORGANIZATION

Pacific Studies Series. Economic Costs of Inadequate Water and Sanitation SOUTH TARAWA, KIRIBATI

APPENDIX III LOGICAL FRAMEWORK ANALYSIS

Summary report on National Adaptation Plan Process in the Maldives

Presentation on community-based adaptation approaches in the Pacific Island Countries.

A. Achieving sustainable development in Asia and the Pacific

Multiple household water sources in Pacific Island Countries: adaptation to changes in seasonal precipitation

Transferring good practices, innovative approaches and lessons learned from ICM implementation in East Asia to other regions

An Overview of Integrated Water Resources Management in Pacific Island Countries: A National and Regional Assessment

EXECUTIVE SUMMARY solid waste, agricultural waste, manufacturing industrial waste potable generally more than adequate to satisfy the demands

SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES

ATTACHED TECHNICAL ASSISTANCE

Project for Strengthening Operation and Maintenance of

Ministry of Environment and Tourism

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES 1

FOR OFFICIAL USE ONLY

The Ocean Pathway. A Strategy for the Ocean into COP23 Towards an Ocean Inclusive UNFCCC Process

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE SERVICES 1

Community involvement in borehole siting and construction

High-Level International Conference on the International Decade for Action Water for Sustainable Development,

MDB joint statement for Rio+20

Plenary Session 1 Strategic Planning for Implementing the 2030 Agenda

Final Quarter 2015 Report to USAID

Muscat Declaration on Water adopted by the First Ministerial Forum on Water of the Group of 77 Muscat, Sultanate of Oman, February 2009

Andre Siohane Niue Water Supply Division-PWD Public Works Department

GEF PACIFIC RIDGE TO REEF PROGRAMME TONGA NATIONAL R2R PROGRAMME DOCUMENT

SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): 1 WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES

COMMUNITY PARTICIPATION IN DEVELOPMENT, OPERATION AND MAINTENANCE OF WATER SUPPLY AND SEWERAGE SERVICES

UN-GGIM: Europe Work Group A «Core Data» SDG related use cases

World Water Day Calendar

FP091: South Tarawa Water Supply Project. Kiribati ADB B.21/15

VISION 2030 JAMAICA NATIONAL DEVELOPMENT PLAN - A Strategic Framework for Balancing National Development and the Environment 7/19/2011 1

Support to Water Sector Development in Central Asia: The ADB Approach

SDG 6 (Water and Sanitation) in Republic of Korea

Environmental and Social Considerations in Detailed Planning Survey. (Technical Cooperation for Development Planning)

Water security in atolls through improved groundwater management

The RMI s Water & Sewer Utilities: RMI Water Summit March 22-23, 2011

Fisheries and Aquaculture in a Changing Climate

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

UNEP/AEO/ NEPAD Lead Indicators Change in incident of water borne diseases. UNSD suggestions. Population connected to public water supply

Open Working Group, February 2014: Australia, the Netherlands, United Kingdom Constituency Statement. Oceans and Seas, Forests and Biodiversity

Transcription:

Integrated Water Resources Management Demonstration Project Country: Republic of Kiribati Title: Protection and Management of Shallow Groundwater Sources for South Tarawa A. Executing Agency The Ministry of Public Works and Utilities in collaboration with the Public Utilities Board will be main executing agencies, working under guidance and assistance of the National Water and Sanitation Coordination Committee. B. Name and Post of Government Representative endorsing the activity Permanent Secretary Ministry of Public Works and Utilities P.O Box 498, Betio, Tarawa, Kiribati C. Cost of Project GEF Co-Funds Revisions to National Legislation, Policy & Plans $12,000 Training and support for Committee for the Management $8,000 $25,000 and Protection of Water Reserves Training and support for village water and sanitation $10,000 $30,000 committees in Buota and Bonriki Rain catchment and storage installation on community $80,000 $150,000 buildings Monitoring, analysis and reporting (health, environment, $70,000 $180,000 water) Installation of improved reticulation system and water $120,000 $400,000 meters Improved land management of reserves $80,000 $300,000 Community education campaign $30,000 $90,000 Installation of alternate sanitation system $90,000 $500,000 Total $500,000 $1,675,000 D. Linkage to National Priorities and Programs 1

The project.s main objective is inline with government policy statement of enhancing and ensuring the equitable distribution of development benefits to the people of Kiribati in accordance with principles of good governance. The project will concentrate its efforts in addressing key policy issues of helping poorer people who are under strain with unacceptable levels of inequity using Integrated Water Resources Management (IWRM) concepts. The project will work in close partnership with people living in the vicinity of the two main water reserve areas for the urban capital South Tarawa, Bonriki and Buota, to ensure safe water supply for 43.5% of the nation s population and logistic support for 80% of national developments. The project is linked to the Kiribati Adaptation Program Phase II Water Resources and Awareness Components and will serve as a demonstration for developing and protecting groundwater source areas in other atolls and islands in Kiribati, especially in designated growth centres. The linkage between the KAPII project and the IWRM project is that KAPII will concentrate on institutional and policy levels and resource assessment, while the IWRM project will work on practical aspects of water resources management. This project is consistent with the goal of the draft National Water Resources Policy Water for Healthy Communities, Environments and Sustainable Development which is: To ensure that communities have affordable access to sustainable water supply systems providing water of suitable quality and appropriate quantities and to appropriate sanitation to meet all reasonable health, environmental, and development needs It addresses most of the specific draft policy objectives within the draft National Policy to: 1. Improve the safety of freshwater supplied from groundwater and rainwater systems. 2. Protect fresh groundwater resources from adverse human impacts. 3. Sustainably manage all aspects of the use and conservation of freshwater. 4. Improve knowledge of the quality and quantity of the nation s freshwater resources and demand for them. 5. Improve knowledge and management of water resources under climatic extremes, variability and change. 6. Improve outer island water supplies. 7. Increase community awareness and understanding of water resource and sanitation issues. 8. Increase community participation in water resource and sanitation management. 9. Increase the use of rainwater harvesting. 2

10. Develop instruments to help manage demand and allocation of water. 11. Review and revise, where necessary, all legislation, regulations and organisational responsibilities relevant to water and sanitation. 12. Ensure that people working in the water and sanitation sector have appropriate knowledge and skills. 13. Ensure an adequate supply of trained personnel for the water and sanitation sector. 14. Ensure cost effective planning, operation and maintenance of water supply and sanitation systems. This demonstration project also addresses water-related goals in the Kiribati National Development Strategy 2003-2007: 1. Raise the quality of life by improving supply and quality of water. 2. Ensure sustainable use of water resources, 3. Promote community participation for better use of water resources, 4. Provide sound infrastructure and services at reasonable costs, 5. Rehabilitate and expand existing water supply systems, 6. Improve collection, storage, treatment and distribution of water, 7. Rehabilitate the sewerage and sanitation system and improve its operation, 8. Improve maintenance standards for government assets, and 9. Ensure that all future construction projects comply with the Environment Act This demonstration project also addressed strategies raised during extensive consultations throughout the Gilbert Group conducted for the National Adaptation Program of Action, Kiribati Adaptation Project (KAP) Phase I (2003) which identified 10 water and sanitation -related priority strategies in the top 25: 1. Water pumps/pipes to get water from good source to settlement areas and homes 2. Protect water wells 3. Assess and locate available water on the islands 4. Water conservation at home (including awareness raising) 5. Improve sanitation, construct toilets 6. Water conservation in piping systems 7. Install rainwater tanks 8. Install desalination plant 3

9. Collect water from further away in the bush 10. Proper use of land At the regional level, the demonstration project is aimed at key issues, concerns and constraints identified in the Pacific Regional Consultation Meeting on Water in Small Island Countries at Sigatoka, Fiji Islands, 29 July 3 August 2002 which were: 1. Freshwater availability 2. Increasing demands for water. 3. Water quality degradation in surface and groundwater catchments, with consequent down gradient impacts on human health and the environment. 4. Insufficient knowledge of island freshwater resources. 5. Insufficient education, training and capacity in water resources. 6. Inappropriate technology and methods, in relation to rural water supplies. 7. Catchment and groundwater reserve management issues. 8. Vulnerability of water resources to natural hazards, climate variability and change; 9. Insufficient community education, awareness and participation; 10. Water leakage and other losses including wastage in distribution systems; 11. Legislation, policy, planning and administrative issues. The proposed project also follows strategies identified in the Pacific Regional Action Plan on Sustainable Water Management under its six themes: 1. Water resources 2. Island Vulnerability 3. Awareness 4. Technology 5. Institutional Arrangements 6. Finance E. Linkage to IWRM and GEF Project Priority Demonstration This Demonstration Project is eligible under the OP9 strategies: 1. Protection of water supplies 4

2. Land and marine-based sources of pollution 3. Vulnerability to climate change It also tackles regional priority concerns identified in the Strategic Action Program for the GEF Pacific International Waters Program, which identified Integrated Coastal and Watershed Management as a contributing solution to: 1. Pollution of marine and freshwater from land-based activities 2. Unsustainable exploitation of living and non-living resources. F. Context and Background Bonriki and Buota water reserves are the only current sources of reticulated safe drinking water for South Tarawa, the capital of Kiribati. These islands supply 43.5% of the nation s population and support the livelihood of more than 80% of local communities. The reserves support more than 80% of national development and are a very high Government priority, with extremely high potential for degradation originated from both human and natural causes. Safe, fresh water supplies in South Tarawa, the densely populated capital of Kiribati, are at the limit of sustainability. Groundwater source areas in these low lying coral atoll islands are extremely vulnerable. They are under significant threats from rising sea levels resulting from global climate change and variability, from storm surges and from encroachment, pollution and overuse. Less than 30L/person/day of treated water is currently available in the capital. There is no information on actual freshwater use since many households use domestic wells of dubious quality and rainwater to supplement supplies. New sources of affordable, safe freshwater are urgently required. South Tarawa has 43.5% of the country s population, which has grown at an exponential rate of 4% since 1963 due to natural increase and major inward migration. Between 2000 and 2005, the growth rate was 6%. Infant mortality due to water-borne disease in Kiribati is amongst the highest in the Pacific. Diarrhea disease rates in South Tarawa are even higher than the national average. The population density in some areas exceeds 15,000 people/km 2. but only about 23% of households in the capital are serviced by the saltwater-flush sewage system. Treated, reticulated freshwater for South Tarawa is sourced from shallow, freshwater lenses in Bonriki and Buota islands at the southeastern corner of Tarawa atoll. To protect groundwater sources, regulations under the 1977 Public Utilities Board Act permitted the declaration of water reserves in South Tarawa. The lands overlying freshwater lenses in Buota, Bonriki, and Teaoraereke were declared Water Reserves. These regulations prohibit settlement and allow eviction of existing dwellers and land owners from the Reserves. Despite the regulations, Teaoraereke was abandoned as a freshwater source in 1992 because of the unrelenting encroachment by settlers which polluted the groundwater. The extremely limited land area in South Tarawa and the population growth rate 5

mean that encroachment is a continuing threat to the remaining water reserves and to the safety of the public water supply. Land ownership is essential for subsistence survival, even in urban areas, as it involves traditional resource rights. The declaration of Water Reserves and the pumping of groundwater from private lands for public reticulation were extremely unpopular with landowners and resulted in vandalism of infrastructure. The government now pays an annual lease to landowners but they do not participate in the management or care of the water reserve. Removing settlers from the reserves and the prevention of gravel mining there are politically sensitive issues for the government. G. Goal Objectives Outputs and Activities i) Goal To ensure long-term sustainability of the Bonriki and Buota water reserves to meet the growing water demand for urban population and to serve as an exemplary model for small islands states with similar geological settings. ii) Objectives The objectives of the project are to demonstrate the technical, social, economic, legal and environmental systems necessary to protect and properly manage groundwater sources and to demonstrate the health, environmental, social and economic benefits that flow from improved integrated management. iii) Outputs and Activities 1. Establishment of Project Management Office Project Coordinator/Manager and staffs appointed on contract basis. Project office established adjacent to project site. Project Steering Committee established and meeting held on monthly basis. 2. Reformation and strengthening of Community-Government Committee for Management and Protection of Water Reserves in South Tarawa. Obtain approval from the National Water and Sanitation Coordinating Committee for the reestablishment of the committee. Meeting convened with Buota and Bonriki villages to select members Approval of selected members by the NWSCC. TOR for the committee approved. 3. Construction of Water Reticulation System for Buota Village 6

In consulation with the Committeee for the N=Management and Protection of Water Reserves: Construction of two elevated tanks (22 kl capacities) Laying of 100 mm and 50 mm distribution lines Laying of transmission main pipe from Bonriki water treatment plant to the two new elevated tanks Connection of individual households using a standard connection design. 4. Construction of Water Reticulation System for New Bonriki Village Construction of one elevated tank (22 Kl capacity) Laying of distribution main Laying of transmission main to feed the elevated tank. Connecting individual households using the standard connection design. 5. Trial introduction of a three-tiered water tariff and water metering and Improvement of reserves and diversity of water sources Ensure that all household water connections have water meter installed. Develop a model for the formation and operation of village level water and sanitation committees Improved procedures for monitoring, analysis and reporting of groundwater condition, water production, water quality, and environmental impacts of water production from reserves and from domestic water wells. Cleanup of water reserves including infilling of old babwai and gravel pits and cutting down deep rooted trees to minimize evapo-transpiration. Improved health through better protection of groundwater, improved supply of treated water, safe rainwater and well water. Improved understanding of the biodiversity of water reserves in South Tarawa. Increased use of domestic and communal rainwater harvesting. Improved procedures for measuring water use from the reticulation system, domestic wells and rain tanks. Increased water production from water reserves. 6. Improve Health, Welfare and Adaptation for Bonriki and Buota residents 7

Increased social amenity, recreational facilities and employment opportunity for communities around reserves Improved sanitation systems for groundwater source areas Increased community awareness of strategies and procedures to conserve and protect safe fresh water sources. Improved adaptation strategies for managing water reserves under threats from global change. Replication: This integrated approach to the protection of groundwater sources will be replicated firstly in designated additional freshwater source areas in North Tarawa, then in designated outer island development centres and priority outer islands, then in other outer islands. It is also of direct relevance to other low-lying small island nations in the Pacific and Indian oceans. Potential Execution: Through the National Water and Sanitation Coordination Committee, convened by the Ministry of Public Works and Utilities (MPWU) with direct contributions from MPWU, the Public Utilities Board, the Environment, Lands and Agricultural Development, Health and Medical Services, Finance and Economic Development, Line and Phoenix Islands Development, Internal and Social Affairs, Fisheries & Marine Resources Development, Education Youth & Sport Development and the Meteorology Office. Predicted cost: Activity GEF Co-Funds Establishment of Project Management Office 50,000 200,000 2. Reformation and strengthening of Community-Government 55,000 85,000 Committee Management and Protection of Water Reserves 3. Construction of Water Reticulation System for Buota Village 105,000 300,000 4. Construction of Water Reticulation System for New Bonriki Village 50,000 200,000 Trial introduction of a three-tiered water tariff 80,000 250,000 6. Improve Health, Welfare and Adaptation for Bonriki and Buota residents 160,000 600,000 8

500,000 1,675,000 H. Potential Co-funding: Co-funding components of this project will come from projects and current expenditures from the Government of Kiribati and the Public Utilities Board annual budgets. Projects identified as possible cofinancing sources are listed below: Title of Project Water Supply Extension and Sewerage Improvement Executing Organisation Ministry of Public Works & Utilities and Public Utilities Board Funding Source EU Value of Project AUD$1,630,000 Project Timeframe 2008-2009 Project Focus The project is drawn to complete works that are left incomplete by the Asian Development Bank loan funded project in which was implemented from 2003-2005. Brief description of Improve individual house connection using an agreed different types of key standard design activities and expected Construction of two 22 kl capacity elevated tank at outcomes strategic locations in the Temaiku area. Acquisition of jetting machine to clean sewerage manholes and sewer mains. Key Project Contacts Expected outcome is an improved water supply and sewerage services to 43.5% of the total population of Kiribati Mr. Taboia Metutera Chief Executive Officer Public Utilities Board Betio, Tarawa 9

Kiribati Phone: +686 26292/26056 Areas of overlap or complement with the GEF IWRM project Email: ceo.pub@tskl.net.ki Installation of improved reticulation system and water meters. Improve management of water reserves. Community education campaign. GEF Requested Revisions 10