Ballard Phase I/Retrofit Supplemental Monitoring Plan

Similar documents
Modeling Green Infrastructure Compared with Large-Scale Monitoring at Kansas City, MO

Permeable Pavement Facilities and Surfaces

Water Resources Management Plan

LID PLANTER BOX MODELING

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

Stormwater Treatment Practice (STP) Calculator Instructions

4.8. Subsurface Infiltration

CENTRALIZED BMPS TYPICALLY PUBLICLY OWNED & MAINTAINED BMPS, TREATING A LARGE (>20 ACRES) URBAN DRAINAGE WITH MULTIPLE LAND

4.8. Subsurface Infiltration

Green Infrastructure Performance in NYC

Combined Sewer Overflow Reduction Program Briefing

Intended users: City and County public works Young engineers Developers Public officials and other non-engineers

Using WinSLAMM v10 to Predict Stormwater Pollutant Loads and Evaluate LID Management Approaches Overview

Design Example Residential Subdivision

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)

WQ-08 ENHANCED DRY SWALE

Hydrology for Drainage Design. Design Considerations Use appropriate design tools for the job at hand:

3.2 INFILTRATION TRENCH

Chapter 3 Previous Studies

4.12. Detention Basins

16.0 Water Quality Management Criteria for Developed Land

RETENTION BASIN EXAMPLE

Hydromodification Computer Modeling

BUREAU OF CLEAN WATER

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives

The SuDS Manual Frequently asked questions

the 2001 season. Allison brought high winds and street flooding to Houston, after

Permeable Pavement Hydrologic Modeling

Infiltration Guidelines

Hydrologic Modeling for Green Roofs, Rainwater Harvesting and LID Foundations

Conservation Design Approach for New Development

BMP Design Aids. w w w. t r a n s p o r t a t i o n. o h i o. g o v. Equations / Programs

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

Green Infrastructure Modeling Strategies

Using Sanitary Sewer I/I Field Data to Calibrate a Storm Sewer Model

WinSLAMM v Program Modifications Final, 3/16/19

Memorandum. MIDS Work Group Barr Engineering Company

Treatment Volume: Curve Numbers. Composite CN or Not? Treatment Volume: Curve Numbers. Treatment Volume: Calculation. Treatment Volume: Calculation

Will Your Green Infrastructure Program Help You Comply with Your Consent Order?

Planning Considerations for Stormwater Management in Alberta. R. D. (Rick) Carnduff, M. Eng., P. Eng. February 20, 2013.

WELCOME. Eastern Subwatersheds Stormwater Management Retrofit Study. Online Information Session

WinSLAMM v Program Modifications Final, 12/12/17

Post Construction BMP Monitoring: Critical to a Successful Green Infrastructure Program

Porous Pavement Flow Paths

Permeable Pavement. Pavements constructed with these units create joints that are filled with permeable

Progressive Solutions for a Historic Watershed

3.11 Sand Filter Basin

Refinement Task 19 Minne Lusa Basin Search for Hybrid Alternatives

Stormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC

Infiltration Trench Factsheet

Hydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated)

Assessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration

Evapotranspiration Calculations for Stormwater Quality Models

Evapotranspiration Calculations for Stormwater Quality Models

Matt Lundsted Principal Comprehensive Environmental Inc.

Effect of Land Surface on Runoff Generation

Hydromodification Management Measures

Hydromodification Management Measures

SFPUC Wastewater Enterprise URBAN WATERSHED MANAGEMENT PROGRAM

SFPUC Wastewater Enterprise URBAN WATERSHED MANAGEMENT PROGRAM

Modeling Sanitary Sewer Groundwater Inflow Rehabilitation Effectiveness in SWMM5 Using a Two Aquifer Approach

Stormwater Treatment Measure Sizing and Design Considerations SMCWPPP C.3 Workshop June 21, 2017

Site Design Checklist and LID Calculations Worksheet. Draft Revision December 2004

Computational Methods in Low Impact Development Stormwater Controls Part 1: Hydrology and Hydraulics Part 2: Case Studies and Models

and Green Infrastructure

EBL&S Development Station Park Green Preliminary Stormwater Quality Management Strategy REV 1

Public Notice U.S. Army Corps of Engineers, Norfolk District

Stormwater Bio-Infiltration Pilot Project Concept Proposal Submitted by

Sustainable Urban Stormwater Best Management Practices with InfoSWMM Sustain plus InfoSWMM 2D and SWMMLive

Real-time Control: The Next Generation of Smart Green Infrastructure Maine Stormwater Conference 2015

Stormwater Retention Pond Recovery Analysis

Design of Stormwater Wetlands

Western Washington Hydrology Model (WWHM) Software Introduction. Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington

n4.1 Site Assessment for Runoff Reduction Requirements

Clean Water Services Design and Construction Standards Update: Base Strategy and Methodology to Address Hydromodification Impacts

Clean Water Services Design and Construction Standards Update: Base Strategy and Methodology to Address Hydromodification Impacts

Phase 1 Part 2 CSO Control Plan Wellington Avenue CSO Facility. Hydraulic Modeling Software Selection

and Green Infrastructure

A detailed guide and sizing manual for the application of Silva Cells to meet the requirements of bioretention under paving.

Water Resources Management Plan Appendix B

The proponent is responsible for meeting all approval requirements from relevant agencies.

Project Name: Add a unique name that appropriately identifies the submission

EVALUATION OF VOLUME IN TWO BIOSWALE. Judy Horwatich US Geological Survey

WSUD On-site Detention in xprafts 2013

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

Hydrologic Assessment of LID Honda Campus, Markham, ON

Stormwater Management Report Bachman Terrace Residential Development

1. Base Conditions: October 1, 2004, land use conditions with no BMPs applied.

Appendix E. Coordinating Erosion and Sediment Control With Low-Impact Development Planning

BMP #: Infiltration Basin

SUPPORTING DOCUMENT STORMWATER BEST MANAGEMENT PRACTICE (BMP) INFEASIBILITY WORKSHEET FOR ON-SITE STORMWATER MANAGEMENT

Precipitation Surface Cover Topography Soil Properties

Krista Reininga, PE Hydromodification and What it Means for the Design of Stormwater Facilities

Sizing Calculations and Design Considerations for LID Treatment Measures

Public Lands Low Impact Development Infrastructure Performance and Risk Assessment May 2016

CITY UTILITIES DESIGN STANDARDS MANUAL

Fact Sheet: How does stormwater biofiltration work?

Chapter 8. Inlets. 8.0 Introduction. 8.1 General

6.5 Extended Detention Basin

Transcription:

MEMORANDUM Ballard Phase I/Retrofit Supplemental Monitoring Plan PREPARED FOR: Seattle Public Utilities PREPARED BY: CH2M HILL DATE: August 17, 2012 Introduction This memo summarizes the plans for and benefits of post-construction monitoring of the Ballard Roadside Raingardens project, hereinafter referred to as the BRR1 project. Post-construction flow monitoring is essential to validate the performance of roadside raingardens as a cost-effective tool for reducing stormwater runoff within the right-of-way. Specifically, this monitoring will be used to confirm the conclusions of the project planning and modeling analysis, which have indicated that implementing roadside raingardens in the Ballard neighborhood is an effective approach for reducing combined sewer overflows. Background Ballard Roadside Raingardens Phase 1 and Retrofit The BRR1 project implemented in 2010 consisted of roadside raingardens constructed within portions of the right-of-way along 28th Avenue NW (from NW 65 th to NW 73 rd St), 30 th Avenue NW (from NW 80 th Street to Loyal Way NW) and 31 st Avenue NW (from NW 75 th to NW 77 th St). The raingardens are shallow depressions filled with bioretention soil, mulch, and native plants. These raingardens are designed to collect stormwater runoff from the surrounding pavement and allow it to filter through the soil (infiltration), which reduces the amount of stormwater flowing into the combined sewer system. Due to poor infiltration and community concerns, raingardens along 28 th Avenue NW were renovated to include underdrains with orifices in the summer of 2011. The revised design shifted the focus from relying on infiltration to increasing retention and delay of stormwater from entering the combined sewer system. The raingardens along 30 th Avenue NW showed adequate ability to drain and were not renovated. Elsewhere in Ballard, the raingardens were removed (filled) due to poor performance. The BRR1 project, including the renovation in 2011, were implemented as a pilot project to develop prototypes for roadside raingardens that could be used for controlling combined sewer overflows elsewhere in Seattle. This project is expected to improve assumptions about the effectiveness of these practices in reducing stormwater pollution from CSOs. SEA/BALLARD_MONITORING_TM_2012_0814_DBA 1

Modeling Efforts to Date As part of the Seattle Public Utilities plan for controlling CSOs, called the long-term control plan, areas of the city under SPU s jurisdiction were analyzed with USEPA s Stormwater Management Model Engine version 5.0.021 (SWMM5). This analysis resulted in a computer simulation of potential stormwater runoff flows and CSOs under several scenarios, including the use of the BRR1 project s roadside raingardens. These practices were entered into the initial model assuming a similar configuration as the BRR1 projects, which rely on infiltration into the native soils, by entering parameters for the ponding, soil and storage layers. The results of this analysis were used to evaluate the potential effectiveness of using raingardens in the Ballard neighborhood currently affected by CSOs. These results indicated that the roadside raingardens could be an effective tool for reducing the frequency and volume of CSOs in Ballard (CH2M HILL and B&C, 2011). The same modeling analysis was used to evaluate and recommend specific modifications to the raingardens along 28th Avenue NW in the summer of 2011 (CH2M HILL, July 2011). The updated model provided preliminary recommendations for several design elements (e.g., size, depth), recommended modifications to maximize available storage in the raingardens, and estimated the amount of CSO reduction the renovated raingardens could provide. Existing Monitoring Programs SPU conducts on-going flow monitoring of each outfall in the combined sewer system that is regulated by the state-issued NPDES permit. In addition, to support the model analysis discussed above, SPU collected flow data from a micro-meter installed in a maintenance hole downstream of the constructed rain gardens along 30th Avenue NW from October 1, 2009 through May 31, 2010. The meter and location were selected because they could provide the information needed to evaluate the effectiveness of the BRR1 pilot projects at reducing flows to the combined sewer system, based on a common stormwater monitoring rule. This rule selects a monitoring location where at least 10 percent of the area that produces stormwater runoff (typically impervious surfaces such as roads, driveways, sidewalks and roofs) drainsto raingardens or other green stormwater infrastructure. Proposed Monitoring Program The goals of pilot projects such as the BRR1 project are to confirm the performance of green stormwater infrastructure and its effectiveness at reducing CSO volumes, and to determine the most cost-effective approaches to use within the right-of-way. Currently, the presumed performance of green stormwater infrastructure as a CSO control approach is largely based on prior monitoring of green infrastructure installed in other areas, literature from around the country, and model simulations such as that described above for the BRR1 project. Inthe-ground, post-construction monitoring is essential to support the conclusions of the modeling analysis and the project design. Controlled Flow Tests The BRR1 project s Quality Assurance Project Plan (QAPP), completed by SPU in 2011, describes in detail the procedures for conducting post-construction monitoring controlled flow tests to evaluate the performance of the constructed raingardens (SPU, 2011). These SEA/BALLARD_MONITORING_TM_2012_0814_DBA 2

controlled flow tests are designed to provide field verification of the model simulation s predictions, and eliminate uncertainty regarding the upstream drainage area and the seasonal variability in infiltration. As written in the project s 2011 QAPP, the specific objectives of the controlled flow tests are: Adequately and accurately characterize the hydrologic performance of the roadside raingardens by replicating the storm flow used in the model simulation with water from a hydrant and collecting continuous water level and flow velocity in the downstream combined sewer pipe during the simulated storm. Continuous water level measurements will be collected using piezometers within shallow wells or stormwater structures. Capture both baseline and post-construction data for each of the simulated storm events. The baseline data would be captured by running the simulated storm (flows from the hydrant) down the street and bypassing the raingardens to simulate the runoff without the interception by the raingardens. The post-construction data would be captured by running the simulated storm down the street and allowing it to enter the raingardens. Successive controlled flow tests would be run during a range of pre-storm moisture conditions. The controlled flow tests would occur during the dry summer months when the base flows in the CSS are low, which will allow for more accurate detection of the flows from the simulated storms. The initial tests will simulate dry conditions and successive tests will represent more common winter periods where storm events are preceded by periods of prolonged rainfall. Determine the rates of stormwater infiltration in the raingardens during the times when the soil is already saturated. This will be done at the end of the post-construction tests. See Table 1 for a summary of which parameters may be calibrated using the data from the controlled flow tests. TABLE 1 Bio-Retention Cell Model Parameter Calibration via Controlled Flow Test Parameter Source/Description Method for Verification Surface: Storage Depth Per Plans Field measurement Soil: Thickness Soil: Porosity Soil: Field Capacity Soil: Wilting Point per Ballard Plans, see note on storage Per Green-Ampt Parameters based on Brakensiek and Rawls data. Per Rawls (1992) for Loamy Sand texture Per Green-Ampt Parameters based on Brakensiek and Rawls data. Field Measurement via hand hole Calibrated from Controlled Flow Test, calculated based on stored volume assuming field capacity at beginning of test. No calibration proposed. Potentially could conduct moisture tests on antecedent soils 3 days after rainfall. Not critical for CSO design. No methods identified. Potentially could conduct moisture tests upon visual observation of plant wilting. Not critical for CSO design. Soil Conductivity Per RainWise Sizing Calibrated from Controlled Flow Test, based on surface storage relative to perched water on native SEA/BALLARD_MONITORING_TM_2012_0814_DBA 3

TABLE 1 Bio-Retention Cell Model Parameter Calibration via Controlled Flow Test Parameter Source/Description Method for Verification soil surface. 1 Soil: Conductivity Slope Per user s manual, average between sand and silt loam. No calibration proposed. Soil: Suction Head Assumed, Loamy Sand. No calibration proposed. Storage: Height Storage: Void Ratio Storage: Conductivity No effective storage assumed, however, 0 is not an allowable value Equivalent to 0.4 porosity used for soil Min. assumed for till. No calibration proposed. No calibration proposed. Calibrated from Controlled Flow Test based on saturated drawdown of ponding. Storage: Clogging Factor Not used. Not used. Underdrain: Drain Coefficient Underdrain: Drain Exponent Standard orifice coefficient = 0.62 Per orifice equation = 0.5 Calibrated from Controlled Flow Test 2 Calibrated from Controlled Flow Test 2 Underdrain: Drain Offset Height Per plan Per plan. 1. May be difficult to measure without subsurface piezometers to isolate ponding due to soil media vs. underlying native soil. 2. If conducted along 28 th Avenue. Additional Recommended Monitoring Objectives While the controlled flow tests currently proposed will help to confirm and refine the project s model simulation, additional post-construction monitoring methods are needed to test the raingardens performance and address other concerns related to the project; in particular, groundwater impacts. The following sections describe the objectives of the additional monitoring under the following categories: short term performance, design refinements, long-term performance, and groundwater impacts. Then Table 2 identifies the monitoring techniques recommended for each of these monitoring categories, as well as the controlled flow tests and continuous flow monitoring described above. Short-term Performance Monitoring S1: Calibrate model simulation of rain garden performance As noted above, the controlled field test will help verify some parameters within the rain garden models, however, other parameters may be difficult to test and refine to develop a more reasonable simulation of rain gardens. Design Refinements Monitoring SEA/BALLARD_MONITORING_TM_2012_0814_DBA 4

D1: Effectiveness of intermediate orifice flow restrictors. The 28 th Avenue NW rain garden design incorporates intermediate orifices to maximize soil storage within rain garden cells along the moderately sloped roadway. Water level measurements from piezometers installed within upstream of the raingarden could help determine the effectiveness of these elements, and identify potential modifications. D2: Impacts of shallow ponding on surface infiltration The 28 th Avenue NW rain garden design essentially eliminates surface ponding. Water level measurements from piezometers installed downstream of the raingarden could help determine if the amount of stormwater flowing into the raingarden exceeds the surface infiltration capacity of the soils and bypasses the facility. Long-term Performance Monitoring L1: Seasonal variability of infiltration rates Infiltration rates within and beneath the rain gardens may vary depending on antecedent moisture levels and groundwater flows. Continuous flow monitoring in the combined sewer pipe system, combined with water level measurements from piezometers installed within the raingarden itself, could define the infiltration rates in the raingarden in different seasons. The proposed controlled flow tests will be conducted during the summer months to eliminate these impacts. L2: Changes to infiltration rates due to clogging Infiltration rates in the bioretention soils and underlying native soils may change over time and due to sediment accumulation and compaction. Water level measurements from piezometers installed upstream of and within the raingarden could define how infiltration rates may change in response to clogging. L3: Net volume reduction due to GSI in real-time operations The controlled flow tests described earlier will provide an indirect estimate of the total CSO volume reduction by improving the accuracy of green stormwater infrastructure model simulations. However, additional continuous monitoring over a full year could provide a more direct measurement of the net volume reduction due to the constructed roadside rain gardens. Controlled flow tests alone cannot account for the seasonal variation through a year, account for recapture of infiltrated stormwater back into the combined sewer system or the total effective impervious area captured by the rain gardens. L4: Peak flow reduction due to GSI in real-time operations As discussed under L3 above, by themselves the controlled flow tests are limited in their ability to inform estimations of the total net flow reduction in the combined sewer system over a full year. Continuous flow monitoring over a full year could provide a more direct estimate of peak flow reductions, in addition to net volume reductions, due to the raingardens. Water level measurements from piezometers SEA/BALLARD_MONITORING_TM_2012_0814_DBA 5

installed within the raingarden itself would also inform these peak flow reduction estimates. L5: Raingarden overflow frequency, inundation periods, storm event size, and prestorm conditions Continuous tracking of water levels within the raingardens would provide better information for assessing general raingarden performance, evaluating effects on plants, confirming sizing factors, identifying potential performance issues, and characterizing what storms and conditions lead to rain garden overflows. Groundwater Impacts Monitoring G1: Effects of underdrains on lowering local perched groundwater. G2: Changes to dry weather flow in the combined sewer system due to underdrains intercepting shallow groundwater. Continuous flow monitoring in the combined sewer pipe downstream of the raingarden could provide information for determining the effects of the installed underdrains on dry weather flows and shallow groundwater. Additional Monitoring Methods Continuous monitoring in the combined sewer, along with measurement of water levels with observation wells (called piezometers), are expected to achieve these additional monitoring objectives. Continuous Monitoring in Combined Sewer The flow monitor in the maintenance hole downstream of the constructed rain gardens along 30th Avenue NW (discussed above under Existing Monitoring Programs) will be reestablished not just for the controlled flow tests but for a period of at least one year to compare post-construction performance to the baseline period prior to construction. Flow data from this baseline period was not used in the initial model; however, the data may be used to refine the model and obtain a more accurate prediction of stormwater flows to the raingarden along 30th Avenue NW, which would allow SPU to more accurately estimate its performance. Piezometers Piezometers are small observation wells that measure groundwater level, or head. The locations of the 3 piezometers described below are shown on Figures 2 and 3. Piezometer within the raingarden ( 1 in Monitoring Location Plan figures) A small piezometer will be placed in the raingarden within the last orifice before flows discharge to the combined sewer system to record water levels within the raingarden soils and surface ponding areas. Where installed in conjunction with an underdrained rain garden, the monitoring of water levels upstream of the orifice control provides a basis for estimating the amount of discharge back to the combined sewer system prior to overflow. In addition, monitoring of the water levels will confirm drawdown times (the time it takes for groundwater levels to return to dry weather levels) and variability over the year. Piezometer downstream of the raingarden ( 2 in Monitoring Location Plan figures) SEA/BALLARD_MONITORING_TM_2012_0814_DBA 6

A small piezometer will be placed within the sewer system downstream of the raingarden (at the intersection) to measure and record when levels indicate overflow from the raingarden. Piezometer upstream of the raingarden ( 3 in Monitoring Location Plan figures) A small piezometer will be placed within a maintenance hole upstream of the raingarden to measure and record the difference in water levels between the upstream sewer system and the raingarden, in order to evaluate if the intermediate orifices in the raingarden are maximizing available storage and that water is able to infiltrate the surface soils despite minimal ponding depth. References CH2M HILL and B&C, 2011 CH2M HILL, July 2011 Seattle Public Utilities (SPU). 2011. SEA/BALLARD_MONITORING_TM_2012_0814_DBA 7

Table 2. Anticipated Objectives Met by Monitoring Methods Code in Attachments A1 and A2 Number of Meters Recommended on 28th Number of Meters Recommended on 30th S1 RG Model Calibration D1 Intermediate Orifices D2 Impacts of Shallow Ponding L1 Seasonal Variability in Infiltration L2 Effects of clogging L3 Net Volume Reduction L4 Net Peak Flow Reduction L5 Rain garden OF Freq. & Event Char. G1 Underdrain effects on GW G2 Effects on DWF Controlled Flow Tests O 1 O X X Continuous Monitoring in Combined Sewer X X X X O X Piezometers within raingarden cell or outlet structure 1 1 1 X O 2 X X X O 2 O Piezometers within downstream catch basin 2 1 X X X Piezometers within upstream raingarden cells 3 1 X X X X: Should meet objective O: Partially meets objective 1. As noted in text, controlled flow tests with surface observations alone may not provide sufficient data to fully confirm the raingarden model simulation, particularly the amount of area draining to the raingarden. 2. The piezometer will be installed to measure both surface ponding as well as water level within the soils; otherwise it will not be able to indicate which overflows are due to limited surface infiltration. SEA/BALLARD_MONITORING_TM_2012_0814_DBA 8

Calibrate tributary impervious area to match rise in ponded depth due to Calibrate to match periods of max ponding and/or observed discharge downstream Calibrate Saturated infiltration rate of native soils (+ Orifice discharge where underdrains ) to match Surface Ponding Drawdown Rate after end of rainfall Where ponding is observed prior to saturation of subsoil Indication that bioretention soil are limiting Calibrate Drainable porosity of bioretention soil to match Change in Drawdown Rate after ponding is drained FIGURE 1. EXAMPLE USE OF MONITORING DATA TO CALIBRATE RAIN GARDEN PARAMETERS SEA/BALLARD_MONITORING_TM_2012_0814_DBA 9