FINAL DETERMINATION. To Grant a. Temporary Permit/Non-Attainment New Source Review Permit. For. Concord Steam Corporation.

Similar documents
ENGINEERING CALCULATION SHEET AIR RESOURCES DIVISION

PERMIT APPLICATION REVIEW SUMMARY

Michigan Department of Environmental Quality - Air Quality Division ADDITIONAL TECHNICAL INFORMATION FOR BOILERS

Naughton Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by

State of the Art (SOTA) Manual for Stationary Gas Turbines

Wyodak Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by

RULE Prevention of Significant Deterioration Adopted 9/24/84, Amended 11/18/85, 9/2/99, Amended 1/12/12 (Effective 2/8/13)

United States Environmental Protection Agency, Region 9. Air Division. Technical Support Document. for. EPA s Notice of Proposed Rulemaking.

Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware

State of New Hampshire Department of Environmental Services Air Resources Division. Temporary Permit

TITLE V OPERATING PERMIT STATEMENT OF BASIS

APPENDIX C SCAQMD PERMIT APPLICATION

AIR PERMITTING CASE STUDY: HARVARD S CHP EXPANSION

Arkansas Department of pollution Control and Ecology Division of Air Pollution Control. Summary Report Relative to Permit Application

RECOMMENDED CPCN CONDITIONS CASE NO CATOCTIN POWER, LLC

The State of New Hampshire Department of Environmental Services. Thomas S. Burack Commissioner

TECHNICAL FACT SHEET June 19, 2018

PERMIT APPLICATION REVIEW SUMMARY

[Including Revisions to Affected Portions of the Interstate Transport SIP for the hour Ozone and 1997 PM 2.5 NAAQS]

DTE Electric Company Belle River Combined Cycle Power Plant

PUBLIC PARTICIPATION DOCUMENTS For Holland Board of Public Works Holland, Michigan

Table of Contents. (a) APPLICABILITY... 1 (b) EXEMPTIONS... 1 (c) DEFINITIONS... 1 (d) STANDARDS... 2

BEST AVAILABLE CONTROL TECHNOLOGY & TOXIC BEST AVAILABLE CONTROL TECHNOLOGY DETERMINATION

09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural

A. The New Hampshire Code of Administrative Rules Env-A 100 et seq., New Hampshire Rules Governing the Control of Air Pollution; and

Table of Contents. (a) APPLICABILITY... 1 (b) EXEMPTIONS... 1 (c) DEFINITIONS... 1 (d) STANDARDS... 2

Notice of Intent Application

State of New Hampshire Department of Environmental Services Air Resources Division. Temporary Permit

PUBLIC PARTICIPATION DOCUMENTS For DCP Midstream, LP Hamilton Township, Michigan

CEE 452/652. Week 14, Lecture 1 NOx control. Dr. Dave DuBois Division of Atmospheric Sciences, Desert Research Institute

Update on ICI Boiler MACT

Atmospheric Emissions from Stationary Combustion Turbines

BOILER/HEATER > 5 MMBTU BACT Size: MINOR SOURCE BACT BOILER. BACT Determination Information

STATEMENT OF BASIS for NEWARK BAY COGENERATION PARTNERSHIP L.P.

"LIST AND CRITERIA" INDEX INTRODUCTION Section 1 - General Application Information... 5

PERMIT TO INSTALL. Table of Contents

BOILER/HEATER < 5 MMBTU BACT Size: Small Emitter BACT (PTE < 10 lb/day) BOILER. BACT Determination Information

A REVIEW OF THE EXPECTED AIR EMISSIONS FOR THE PROPOSED FIBROSHORE 40-MW POWER PLANT TO BE FUELED WITH POULTRY LITTER AND WOOD

TITLE V OPERATING PERMIT STATEMENT OF BASIS

Evaluation of Gas Turbine Air Quality Impacts from a Community Perspective

PERMIT APPLICATION REVIEW SUMMARY

PERMITTEE Seminole Electric Cooperative, Inc North Dale Mabry Highway Tampa, FL 33618

CHP, Waste Heat & District Energy

Draft Technical Support Document For Air Emission Permit No

Engineering Summary UNH Cogeneration Project Fall 2003, Durham, NH

BACT Determination Information

Meeting Multiple Challenges: Re-Rating W. A. Parish Unit 8

BACT Determination Information

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT DRAFT STAFF REPORT

Final Rulemaking: Additional RACT Requirements for Major Sources of NO x and VOCs. Citizens Advisory Council September 15, 2015

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. January 26, NEW SOURCE REVIEW PERMIT TO INSTALL No.

Biomass Emissions Permitting in Pennsylvania

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. March 17, 2004 NEW SOURCE REVIEW PERMIT TO INSTALL

BEST AVAILABLE CONTROL TECHNOLOGY DETERMINATION

ASA Bloomingburg, LLC. Air permit-to-install (PTI) number Public Hearing Date April 18, 2006 Comment Period End Date April 25, 2006

AIR REGULATION IN SOUTH CAROLINA 3 JUNE 2016

Power-Cost Alternative De-NOx Solutions for Coal-Fired Power Plants

Woodbridge Energy Center

GASP comments regarding Air Quality Plan Approval C - Tenaska Pennsylvania Partners, LLC Westmoreland Generating Station

Biomass Combustion Technology

Technology Advancement and Standards for Biomass Fuel to Energy Conversion. Topics Covered

Oklahoma Gas & Electric

4.0 Emissions Inventory

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION AIR QUALITY PROGRAM PLAN APPROVAL

New Source Review Staff Presentation Community Advisory Council

Application for Prevention of Significant Deterioration Preconstruction Permit

GOVERNMENT of PUERTO RICO OFFICE OF THE GOVERNOR ENVIRONMENTAL QUALITY BOARD

Update on Michigan Air Pollution Control Rules and Policies. MMEA Fall Conference October 4, 2017

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY

COMAR Amendments and Regulation.12 Standards for Biomass Fuel-Burning Equipment Equal to or Greater Than 350,000 Btu/hr

RULE Federally Enforceable Limits on Potential to Emit - Adopted 1/25/96, Amended 1/12/12 (Effective 3/8/12)

Air Permi>ng: A Major Piece of the Puzzle or Trying to Keep All of

PERMIT APPLICATION REVIEW SUMMARY

TECHNICAL FACT SHEET September 24, 2018

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. November 15, 2013 PERMIT TO INSTALL

Guide to Low-Emission Boiler and Combustion Equipment Selection

Progress Report Study Approach and Assumptions

Biomass Boiler Emission Abatement Technologies. Simon Wakefield

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT DRAFT STAFF REPORT

The Role of Combined Heat and Power (CHP) in Virginia s Energy Future

New Nominal 44 MW CoGen Project Massachusetts Institute of Technology Prevention of Significant Deterioration Application (40 CFR 52.

Biomass use will be higher than has been represented... 10

Stakeholder Meeting Installed Capacity Demand Curves

STATEMENT OF BASIS. For the issuance of Draft Air Permit # 1987-AOP-R4 AFIN:

SUNY Westchester Community College Air Emissions Permit Program Latest Revision Date January 2, 2016 Previous Revision Date June 12, 2015.

TruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time>

POTENTIAL TO EMIT LIMITATIONS FOR PART 70 SOURCES. (Adopted 6/15/1995, revised 1/18/2001 and 1/20/2011)

NOx CONTROL FOR IGCC FACILITIES STEAM vs. NITROGEN

Emissions Control Project

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. February 3, NEW SOURCE REVIEW PERMIT TO INSTALL No.

42 USC 7511a. NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

Application for Temporary Air Permit University of New Hampshire Turnkey Landfill Gas to Energy Project

PROPOSED ADOPTION OF RULE 3.25, FEDERAL NEW SOURCE REVIEW FOR NEW AND MODIFIED MAJOR PM2.5 SOURCES FINAL STAFF REPORT

Oklahoma Department of Environmental Quality Air Quality Division

Control Technologies Applicable to Municipal Waste Combustion

RULE Federally Enforceable Limits on Potential to Emit - Adopted 1/25/96

Output-Based Regulations: Best Practices Option for CHP. Neeharika Naik-Dhungel Program Manager, US EPA CHP Partnership July 13, 2011

SACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT EXPEDITED BARCT IMPLEMENTATION SCHEDULE FOR ASSEMBLY BILL 617.

New Source Review Reform: What Lies Ahead

Transcription:

FINAL DETERMINATION To Grant a Temporary Permit/Non-Attainment New Source Review Permit For Concord Steam Corporation To Construct a 305 MMBtu/hr Biomass Boiler (Wood & Natural Gas), 2 Auxiliary Boilers (76.8 MMBtu/hr each unit, firing Natural Gas only), and 2 Emergency Generators (Rated at 6,000 kw and 1,250 kw) At Concord Steam Corporation located at 291 S. Main St. in Concord, NH Prepared by the New Hampshire Department of Environmental Services Air Resources Division February 27, 2009

TABLE OF CONTENTS I. Applicant s Name and Address:... 3 II. Physical Address of the Facility:... 3 III. Background:... 3 IV. Project Description:... 4 V. Summary of LAER Emission Limitations:... 5 VI. Air Quality Impact Analysis:... 6 VII. Conclusion:... 7

Final Determination Page 3 I. Applicant s Name and Address: II. Concord Steam Corporation P.O. Box 250 Concord, NH 03301-0250 Physical Address of the Facility: Concord Steam Corporation 291 South Main Street Concord, NH 03301 County: Merrimack UTM Coordinates: Easting: 274452 m Northing: 4784830 m III. Background: On March 17, 2008, Concord Steam Corporation (CSC) submitted an application for a Non-Attainment New Source Review (NSR) Permit in accordance with the New Hampshire Code of Administrative Rules Part Env-A 618, Additional Requirements in Non-Attainment Areas and the New Hampshire Portion of the Northeast Ozone Transport Region, and Part Env-A 607, Temporary Permits, respectively. CSC submitted supplemental information on April 9, 2008 in support of its original application submittal. In addition, CSC submitted a change in plans for Boilers 1, 2, and 3 on September 12, 2008. CSC proposes to construct a 19.5 MW biomass fired power plant with auxiliary equipment. The permit application also included information concerning the pollution control equipment and raw material receiving, storage, and transfer equipment for Boiler 1, as well as the auxiliary combustion devices that are related to this project. The CSC facility is a major stationary source under the NSR program, as emissions of nitrogen oxides (NOx), a non-attainment pollutant, will be in excess of the major source threshold of 50 tons per year 1. As a result, the proposed project is subject to the non-attainment New Source Review (NSR) and Temporary Permit permitting requirements contained in Env-A 618 and Env-A 607, respectively. On January 16, 2009, DES issued a Statement of Basis (Preliminary Determination) recommending that a Temporary Permit/NSR Permit be issued to CSC. The Preliminary Determination detailed DES technical and regulatory review and contained a Draft Temporary Permit/NSR Permit containing conditions for the proposed operation. Public notices were published in the Union Leader and Concord Monitor newspapers on January 16, 2009, respectively, notifying the public of the Preliminary Determination, NOx offsets required, the emissions resulting from the installation of the proposed facility, the determination of Lowest Achievable Emission Rate (LAER) for NOx, including the type of equipment and the prescribed LAER emission limits, and that an ambient air dispersion modeling analysis was performed, determining that the facility will not cause a significant impact on air quality and does not violate any state or federal air quality standards. Requests for a public hearing and/or written comments filed with the Director in accordance with Env-A 1 The NSR major source threshold for NOx is 50 tons per year in Merrimack, Hillsborough, Strafford, and Rockingham counties and 100 tons per year for the remaining portion of New Hampshire. 3

Final Determination Page 4 621.06 and received no later than February 16, 2009, were considered by the Director in making a final decision. No comments were received from the general public, Federal Land Manager, or USEPA Region I during the comment period. As no comments were received regarding this permit application, DES did not make any changes (to the conclusions reached in the Preliminary Determination) in this Final Determination. IV. Project Description: CSC proposes to build a wood-fired power plant on approximately 25 acres of land along and south of Langdon Street in the southern part of Concord, New Hampshire. The facility will generate electricity for sale to the grid and steam for the district heating system in the city of Concord. This facility will replace the former Concord Steam Plant located on Pleasant Street in Concord. The plant is a combined heat power (CHP) type operation with energy efficiency of approximately 39%. Some of this efficiency is due to the use of a Riley Power Boiler and its integrally efficient combustion design. The Riley Stoker is an approved combustor by the Massachusetts Division of Energy Resources (MADOER) and qualifies for Massachusetts Renewable Energy Credits (RECs). Boiler 1 has a multi-clone followed by a dry electrostatic precipitator (ESP) for removal of particulate matter. A cold selective catalytic reduction (C-SCR) system follows the ESP for NOx removal at temperatures around 450 degrees Fahrenheit. Aqueous ammonia solution at 19% ammonia, by weight, is injected into the SCR inlet, and is designed to chemically react with the NOx and convert it to nitrogen and water, with unreacted ammonia emissions, referred to as the ammonia slip stream emissions, to be less than 20 ppm by dry volume at 6% oxygen. Waste heat from the flue gas leaving the SCR is extracted using a condensing heat exchanger (CHX). The condensed water from the flue gas is reused. The Boiler 1 feedwater is preheated by the CHX. This new design allows more steam to drive the steam-driven turbine, instead of heating feed water, hence, producing more electricity. The condenser also removes certain salts and organic condensible matter, which have a high boiling point. Only virgin wood chips and non-contaminated wood products such as pallet wood chips or untreated wood product chips will be used as fuel for Boiler 1. Natural gas will be used to initially start up and warm up Boiler 1. Fuels derived from construction and demolition wood waste are specifically prohibited from being used as fuel for Boiler 1. Auxiliary equipment includes a spray cooling pond that will be used for cooling water from Boiler 1. In addition, there are two boilers, Boiler 2 and Boiler 3, which are both rated at 76.8 MMBtu/hr gross heat input rate and will be capable of burning natural gas only. These two boilers will be restricted to less than 700 hours of operation per consecutive 12-month period and will be used when Boiler 1 is out of service to provide steam to the district heating system in the City of Concord. In addition, the facility will have two diesel-fired emergency generators (EG1 and EG2) rated at 600 kw and 1,250 kw, respectively, for emergency lighting and start up of Boiler 1, in the event of a power outage at the facility. The two emergency generators will be 4

Final Determination Page 5 limited to less than 500 hours of operation per consecutive 12-month period. EG1 will be relocated from the Pleasant Street facility to the new site at 291 South Main Street. In summary, the pollutant emitting equipment which require permitting include: One Wood & Natural Gas fired boiler, rated at 305 MMBtu/hr gross heat input rate; A Spray Cooling Pond for the Wood & Natural Gas fired boiler; Two Auxiliary Boilers firing Natural Gas only, each rated at 76.8 MMBtu/hr gross heat input rate; and Two Emergency Generators, rated at 600 kw and 1,250 kw. Table 1 below summarizes the net emissions increases from the proposed project. Table 1 Net Emissions Increases Pollutant Program Projected Project Emissions tons per year (tpy) Major Source Threshold (tpy) Is Proposed Project Major? (Yes/No) NOx NSR 95.93 50 Yes NOx PSD 95.93 250 No CO PSD 246.51 250 No PM PSD 41.65 250 No SO 2 PSD 34.15 250 No VOC NSR 12.48 50 No Lead PSD 0.00022 0.6 No V. Summary of LAER Emission Limitations: In accordance with non-attainment New Source Review regulations, the proposed facility is subject to a lowest achievable emission rate (LAER) for emissions of NOx. LAER is defined as that rate of emissions which reflects (a) the most stringent emission limitation which is contained in the implementation plan of any State for such class or category of source, unless the owner or operator of the proposed source demonstrates that such limitations are not achievable; or (b) the most stringent emission limitation which is achieved in practice by such class or category of source, whichever is more stringent. On January 16, 2009, DES issued a Preliminary Determination and Draft Temporary Permit/NSR Permit for the proposed project. The Preliminary Determination explained DES review of the permit application and included a detailed discussion on the non-applicability of 5

Final Determination Page 6 the PSD program and applicability of the NSR program and the requirement to apply LAER limits for NOx. The Preliminary Determination contained proposed LAER limits for all applicable NSR pollutants and the rationale used in establishing those limits. Table 2 lists all applicable LAER limits contained in the Temporary Permit/NSR Permit. Table 2 Summary of LAER Emissions Limitations (All NOx Emissions Limitations Based on 3-hour Averaging Period Unless Otherwise Specified) Pollutant NOx limit (Basis) Wood & Natural Gas fired Boiler (Boiler 1) 0.065 lb/mmbtu (30-day rolling average) (LAER) Auxiliary Boilers 2 and 3 (Each Device) 0.049 lb/mmbtu (Natural Gas) (LAER) Emergency Generators 1 and 2 (Each Device) 1.98 lb/mmbtu (Diesel Fuel) (LAER) NOx Control Technology Selective Catalytic Reduction Low NOx Burners, Flue Gas Recirculation, and < 500 hours operation per consecutive 12 month period < 700 hours operation per consecutive 12 month period An internal comment was made concerning the 30-day averaging period for Boiler 1, i.e., if a facility could use down days as a zero in calculating the average. As a result of that comment, DES has added qualifying language to the 0.065 lb NOx/MMBtu emission limit based on a 30-day rolling average, indicating that it is to only include successive calendar operating days when the plant operated for a continuous 18 hour period during the calendar day. VI. Air Quality Impact Analysis: Section IX of the Preliminary Determination presented a detailed overview of the ambient air impact analyses that were conducted as part of the permit application review. The analyses demonstrated that the emission increases from the proposed facility will remain below all applicable state/federal ambient air quality standards, including PSD Class I and Class II increment levels, Ambient Air Limits (for applicable regulated air toxic pollutants) and National Ambient Air Quality Standards. As no comments were received regarding these analyses, no further discussion is contained in this Final Determination. 6

Final Determination Page 7 VII. Conclusion: It is the Final Determination of DES that a Temporary Permit/NSR Permit be granted to CSC. This determination is based upon the review of the application submitted by CSC and is supported by the findings outlined in the Preliminary Determination and this Final Determination. 7