Philippines: Electricity Market and Transmission Development Project

Similar documents
Mongolia: Ulaanbaatar Heat Efficiency Project

ASIAN DEVELOPMENT BANK

Maldives: Employment Skills Training Project

Uzbekistan: Land Improvement Project

ASIAN DEVELOPMENT BANK

People s Republic of China: Capacity Building to Combat Land Degradation Project

ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS

Maldives: Employment Skills Training Project

Japanese ODA Loan. Ex-Ante Evaluation

GUIDELINES FOR THE VALIDATION OF PROJECT COMPLETION REPORTS AND EXTENDED ANNUAL REVIEW REPORTS

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

People s Republic of China: Hefei Xi an Railway Project

Principal Barriers/ Constraints to Successful Public-Private Partnerships

SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Performance, Problems, and Opportunities

PROJECT PREPARATORY TECHNICAL ASSISTANCE

Validation Report. Nepal: Crop Diversification Project. Independent Evaluation Department

Pakistan: Bahawalpur Rural Development Project

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: Proceed to appraisal

SECTOR ASSESSMENT (SUMMARY): ENERGY

(Financed by the Japan Fund for Poverty Reduction)

Independent Review of the System Operations of the National Grid Corporation of the Philippines (SO)

Completion Report. People s Republic of China: Hebei Zhanghewan Pumped Storage Project. Project Number: Loan Number: 1922 August 2014

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

Technical Assistance Report

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

Guidelines for the Validation of Project/Program Completion Reports*

SECTOR ASSESSMENT (SUMMARY): ENERGY

ECONOMIC ANALYSIS. 2. Economic rationale. The investment program economic rationale is as follows:

Ex-Ante Evaluation. Japanese ODA Loan

People s Republic of China: Songhua River Basin Water Pollution Control and Management Project

ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE PARTNERSHIP (PPP) PROJECTS IN THE APEC REGION

Republic of the Philippines: Implementing the Senior High School Support Program

People s Republic of Bangladesh: Supporting Education and Skills Development Investment Programs

ASIAN DEVELOPMENT BANK

Georgia: Development of Public Private Partnerships

Ex-Ante Evaluation (for Japanese ODA Loan)

SECTOR ASSESSMENT (SUMMARY): ENERGY

People s Republic of China: Acid Rain Control and Environmental Improvement Project

Bangladesh: Emergency Flood Damage Rehabilitation Project

Report and Recommendation of the President to the Board of Directors

Philippines: Southern Philippines Irrigation Sector Project

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

Philippines: Increasing Competitiveness for Inclusive Growth Program (Subprograms 1 and 2)

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

IND: Energy Efficiency Enhancement Project in Assam

Telecommunication Expansion Project (II)

Cambodia: Stung Chinit Irrigation and Rural Infrastructure Project

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Strategy Paper. December Review of the ADB Results Framework

Pakistan: National Drainage Sector Project

People s Republic of China: Research on Innovative Mechanism for Open Agricultural Investment

ASIAN DEVELOPMENT BANK

TERMS OF REFERENCE FOR TA CONSULTANTS

Mongolia: Reforms in Technical and Vocational Education and Training in Mongolia (Preparing the Skills for Employment Project)

ECONOMIC ANALYSIS. B. Calculation of Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis

Republic of the Union of Myanmar: Support for Public Private Partnership Framework Development

Mid-Term Review Report of Japanese ODA Loan Project for FY2012

An IDEV Project Cluster Evaluation. Spurring Local Socio-Economic Development Through Rural Electrification. Executive Summary

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT

Viet Nam: Central Region Livelihood Improvement Project

ADB and Renewable Energy

PUBLIC DISCLOSURE AUTHORISED

Asian Regional Public Debt Management Forums and Workshops

ADB Innovative Financing Instruments for Clean Energy

IN January 2018

AZERBAIJAN ECONOMY AND POWER SECTOR: CHALLENGES AND OPPORTUNITIES

The Study for Verification on Achievement and Progress of the Energy Sector Reform of the Philippines

Ex-Ante Evaluation (for Japanese ODA Loan)

ECONOMIC ANALYSIS. B. Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis

The Philippine Energy Efficiency Project Lighting Up the Philippines in an Efficient Way

Evaluation Approach Paper Project Performance Evaluation Report: Investment 7224 and Loan 2214-INO Tangguh Liquefied Natural Gas Project April 2014

Report and Recommendation of the President to the Board of Directors

ASIAN DEVELOPMENT BANK PPA: IND 18181

ASIAN DEVELOPMENT BANK PPA: INO 22048

SECTOR ASSESSMENT (SUMMARY): ENERGY

ASSESSMENT OF THE ENERGY SECTOR

SUMMARY OF PROJECT PERFORMANCE

Japanese ODA Loan. Ex-Ante evaluation

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011.

Technical Assistance Report. People s Republic of Bangladesh: Support to Primary Education Development

Bangladesh: Chittagong Port Trade Facilitation Project

Ex-ante Evaluation - 1 -

Renewable Energy Market Transformation Initiative (REMTI): Support to the Philippines Renewable Market Development

WEST KALIMANTAN POWER GRID STRENGTHENING PROJECT Reducing Indonesia s Oil Dependency While Fostering Regional Cooperation

ECONOMIC ANALYSIS. A. Introduction

Socialist Republic of Viet Nam: Power Sector Reform Program

STRAGETIC RISK MANUAL

AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project

The World Bank Pernambuco Rural Economic Inclusion (P120139)

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR)

Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed by the Japan Fund for Poverty Reduction)

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Performance, Problems, and Opportunities

Long Beach City Auditor s Office

Kingdom of Thailand: Piloting Public Private Partnerships in the Social Sectors

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5150 Project Name. Indonesia Power Transmission Development Project Region

Philippines: Strengthening Public Private Partnerships in the Philippines

Transcription:

Validation Report Reference Number: PVR-310 Project Number: 36018 Loan Number: 1984 June 2014 Philippines: Electricity Market and Transmission Development Project Independent Evaluation Department

ABBREVIATIONS ADB Asian Development Bank EIRR economic internal rate of return ERC Energy Regulatory Commission FIRR financial internal rate of return IMO independent market operator MMS market management system NGCP National Grid Corporation of the Philippines PCR project completion report PEMC Philippine Electricity Market Corporation RRP report and recommendation of the President TA technical assistance TRANSCO National Transmission Corporation WESM wholesale electricity spot market NOTE In this report, $ refers to US dollars. Key Words asian development bank, energy sector, independent evaluation department, lessons, performance evaluation, philippines, power, project completion report, restructuring The guidelines formally adopted by the Independent Evaluation Department (IED) on avoiding conflict of interest in its independent evaluations were observed in the preparation of this report. To the knowledge of IED management, there were no conflicts of interest of the persons preparing, reviewing, or approving this report. In preparing any evaluation report, or by making any designation of or reference to a particular territory or geographic area in this document, IED does not intend to make any judgments as to the legal or other status of any territory or area.

PROJECT BASIC DATA Project Number: 36018 PCR Circulation Date: Jan 2012 Loan Number: 1984 PCR Validation Date: Jun 2014 Project Name: Electricity Market and Transmission Development Project Country: Philippines Approved ($ million) Actual ($ million) Sector: Energy Total Project Costs: 106.0 90.3 ADB Financing: ($ million) ADF: 0.0 Loan: 40.0 35.6 Borrower: 26.0 23.4 OCR: 40.0 Beneficiaries: 0.0 0.0 Others: 0.0 0.0 Cofinancier: JBIC Total Cofinancing: 40.0 31.3 Approval Date: 19 Dec 2002 Effectiveness Date: 15 Mar 2004 9 Mar 2004 Signing Date: 16 Dec 2003 Closing Date: 30 Jun 2009 3 Aug 2009 Project Officer: Location: ADB headquarters Peer Reviewer: From To Dec 2002 Dec 2009 K. Hewitt, Evaluation Specialist, IED2 Y. Zhai Validators: P. Choynowski, Consultant F. D. De Guzman, Evaluation Officer, IED2 Quality Reviewer: B. Nguyen, Senior Director: B. Finlayson, IED2 Evaluation Specialist, IED2 ADB = Asian Development Bank; ADF = Asian Development Fund; IED2 = Independent Evaluation Department, Division 2; JBIC = Japan Bank for International Cooperation; OCR = ordinary capital resources; PCR = project completion report. A. Rationale I. PROJECT DESCRIPTION 1. The East Asian financial crisis, transmission bottlenecks, and high power system losses brought about severe power shortages in the early 1990s, followed by surplus generating capacity in the late 1990s because of reduced demand. This led the Government of the Philippines in the late 1990s to initiate the restructuring of the power sector to address these problems and ensure accessible, high quality, affordable, and a sustainable supply of electricity. Restructuring was to involve (i) disaggregating the industry into generation, transmission, distribution; (ii) introducing competition in generation; (iii) introducing a wholesale electricity spot market (WESM); (iv) privatizing generation and operation of transmission by a concessionaire; (v) introducing open access to distribution networks; and (vi) having an independent agency regulate the industry. To support restructuring and create a competitive wholesale market, the transmission network would need sufficient capacity to transport power between load centers and generators competing for dispatch. In particular, the transmission system s capacity in Mindanao needed to be augmented to meet the government s objective of electrifying all villages by 2006.

2 2. The Asian Development Bank (ADB) has long been involved in the energy sector in the Philippines. ADB has supported the government's plans to restructure and privatize the electric power industry and create a competitive electricity market. Restructuring was consistent with ADB's country operational strategy for the Philippines and ADB's Energy Policy, 1 and was seen as a way to help overcome many problems in the sector. To create a competitive electricity market, a market management system (MMS) needed to be established to undertake initial market operations and train market participants. Three critical components from an earlier proposed transmission interconnection and reinforcement project were included in the project design to prevent disruptions in the transmission system. B. Expected Impact 3. According to the project framework in the report and recommendation of the President (RRP), 2 the expected impacts were improved well-being of people in the Philippines, and reduced poverty through improvements in the national economy. Improvements in well-being and poverty reduction was to be measured by the (i) increase in gross national product per capita, (ii) reduction in national debt, and (iii) lower unemployment rates. C. Objectives or Expected Outcome 4. The objective of the project, according to the project framework in the RRP, was to assist the government in improving the accessibility, quality, affordability, and sustainability of the national electricity supply. This objective was to be achieved by (i) reducing, in real terms, the average retail electricity price within 5 years, (ii) improving grid reliability to levels higher than the Energy Regulatory Commission (ERC) targets, and (iii) minimizing grid losses below the ERC s system loss cap. Other outcome indicators were improved accessibility and 100% village electrification by 2006 with about 5,000 households benefiting from the Mindanao project, and the improved and sustainable financial performance of the industry, measured at a national level. D. Outputs 5. The project outputs were as follows: (i) a competitive wholesale electricity market achieved by developing a market management system for the wholesale electricity spot market, and appointing an independent market operator (IMO); (ii) a 220-kilovolt (kv) doublecircuit transmission line between San Manuel and Mexico; and (iii) six transmission substations in Mindanao. E. Provision of Inputs 6. The total cost of the project, plus physical and price contingencies, and interest during construction, was estimated at $106.0 million equivalent. This amount included a foreign exchange cost of $85.5 million and a local currency cost of $20.5 million equivalent. The $40.0 million loan from ADB had a 20-year term including a grace period of 6 years; an interest rate determined in accordance with ADB s London interbank offered rate-based lending facility; a commitment charge of 0.75% per annum; and a front-end fee of 1.0%. The Japan Bank for International Cooperation was to cofinance the foreign exchange cost of the project through an 1 ADB. 2000. Energy 2000: Review of the Energy Policy of the Asian Development Bank. Manila. 2 ADB. 2002. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the National Power Corporation and Technical Assistance Grant to the Republic of the Philippines for Electricity Market and Transmission Development Project. Manila.

3 untied loan of $45.5 million; and the executing agency was to provide $20.5 million to finance the local currency cost. About 48 person-months of international consulting services and 24 person-months of domestic consulting services were allocated for the supervision of developing the MMS. The National Transmission Corporation (TRANSCO) 3 was to supervise construction and engineering design for the transmission and substation component. 7. The project included advisory technical assistance (TA) to support the transition to a competitive electricity market. The TA was designed to (i) review bid documents for the MMS and help evaluate bids; (ii) provide independent advice to the Department of Energy and the government prior to and during the initial operation of the WESM; (iii) develop an implementation plan for selecting the IMO; (iv) conduct industry consultations; and (v) prepare tender documents and assist in selecting the independent market operator. Funds were allocated for 16 person-months of international and 4 person-months of domestic consulting services. The total TA cost was estimated at $1.15 million, which consisted of a foreign exchange cost of $700,000 and local currency costs of $450,000 equivalent. ADB was to provide an $800,000 grant, and the government was to supply $350,000 counterpart funding in local currency. F. Implementation Arrangements 8. The National Power Corporation (NPC) was the designated borrower of ADB s loan with the Government of the Philippines as guarantor, and TRANSCO as the executing agency for the project. TRANSCO appointed a project director to coordinate the work and implement all project components. The Department of Energy was the executing agency for the advisory TA, with TRANSCO closely coordinating implementation. During the WESM s initial operations, TRANSCO provided administrative and financial support to the autonomous group market operator. 9. For the loan-financed transmission and substation components, TRANSCO appointed for each region a project manager to handle implementation in the field, with assistance from site managers. Although this arrangement complied with ADB requirements, the project completion report (PCR) noted that the project director did not have sufficient authority to ensure timely implementation of the project, and procurement problems and right-of-way issues were beyond his control. 4 Despite this constraint, the PCR noted that the project had complied with ADB environmental requirements and government environmental regulations, and had little adverse environmental impact. From the social perspective, the PCR noted about 700 project-affected people, of which some were relocated and all were financially compensated. 10. It was necessary to modify the scope of the project because the Japan Bank for International Cooperation s board of directors approved only $40.0 million compared to the original proposed amount of $45.5 million. At completion, the MMS component s actual cost was $10.7 million compared with the estimated $25.0 million at appraisal, thus incurring a savings of $14.3 million. This savings covered the shortfall in the estimated foreign currency requirement, resulting in only slight modifications in the project design. An additional $3.7 million was spent on WESM training and metering equipment. 3 Appendix 8 of the project completion report indicated 10 procurement packages. 4 ADB. 2012. Completion Report: Electricity Market and Transmission Development Project in the Philippines. Manila.

4 11. The San Manuel Concepcion Mexico transmission line and its associated substation expansions were commissioned on schedule on 15 April 2009. Substation expansions in Mindanao were completed on 13 November 2011, almost 3 years after the appraisal schedule. In general, the NPC and TRANSCO complied with the loan covenants in the project and loan agreements. TRANSCO s project implementation conformed to sound administrative, financial, engineering, environmental, and public utility practices. However, WESM assets have yet to be transferred from TRANSCO to the market operator. 12. The TA completion report prepared in May 2009 rated the project successful although the government deferred one of the expected outputs the appointment of the IMO and instead established the Philippine Electricity Market Corporation (PEMC) to operate the WESM. 5 The PEMC is composed of 15 representatives from various sectors of the electric power industry as well as independent members. 6 A transition mechanism was set up to transfer the market management function from the PEMC which was still the autonomous group market operator 5 years since WESM operations began in Luzon in 2006 to the planned IMO. The asset and liabilities function is expected to be transferred to the IMO under a competitive bidding process in 2014. The PCR for the loan was prepared in January 2012; it rated the project successful. II. EVALUATION OF PERFORMANCE AND RATINGS A. Relevance of Design and Formulation 13. The TA completion report assessed the TA relevant in design and effective in achieving its objective. The PCR for the loan rated the project relevant because it was consistent with ADB s country operational strategy for the Philippines 7 and continued to be relevant through its support for economic growth an ADB priority area for assistance to the Philippines. The strategy recommended that, among other things, ADB assistance focus on rural development; more balanced regional development, especially in the southern Philippines; and policies and programs particularly on greater private sector participation and institutional capacity building to improve the country s infrastructure. Moreover, ADB signed a poverty partnership agreement with the government in October 2001, reiterating ADB s support for the government s privatization program and sector policy reforms to foster private sector development. 14. ADB s 1995 Energy Policy 8 was built on four key pillars: (i) poverty reduction, (ii) promoting private sector participation, (iii) regional and environmental impacts, and (iv) regional cooperation. The project was consistent with ADB s review of the 1995 Energy Policy in 2000, 9 specifically with the recommendation that ADB focus more on private sector participation such as unbundling, restructuring, and privatization with improved corporate governance. The transmission and substation components were consistent with the recommendation that ADB invest in enhancing the efficiency of production, transportation, and end use of energy. 5 ADB. 2009. Technical Assistance Completion Report: Transition to Competitive Electricity Market in the Philippines (TA No. 4073). Manila. 6 The deferment was considered a necessary transition arrangement to ensure that all operational issues during the initial years of WESM operation were fully mitigated before handing over WESM administration to an independent operator. 7 ADB. 1998. Country Operational Strategy Study: Philippines. Manila. 8 ADB. 1995. The Bank s Policy Initiatives for the Energy Sector. Manila. 9 ADB. 2000. Energy 2000: Review of the Energy Policy of the Asian Development Bank. Manila.

5 15. The project was a central component in the government s program of restructuring and privatizing the electric power industry to ensure accessible, high quality, affordable, and sustainable electricity supply, and creating a competitive electricity market. The project addressed the key constraints to the economic development of the Philippines: operational efficiency and capacity shortages. In the early 1990s, Luzon experienced severe power shortages, which prolonged blackouts and caused adverse economic impacts. Subsequently, the East Asian financial crisis in 1997 suppressed economic growth and reduced electricity demand, resulting in surplus power-generating capacity and causing debt service burdens of power purchasers to spiral upward. Transmission bottlenecks raised electricity prices and made grid power inaccessible to some businesses and households. 16. In general, the project was appropriately designed to address the main issues affecting the sector. This validation rates the project relevant. B. Effectiveness in Achieving Project Outcome 17. The PCR considered the project effective in supporting the ongoing development and restructuring of the power sector in the Philippines. However, the PCR did not indicate the number of new households connected to the grid because of the project, or the number of people affected by the market reform measures such as real price reductions against the baseline. In implementation, the transmission line was completed on time, although three of the six substations in Mindanao were installed 3 years later. The MMS was commissioned and the WESM operation increased the number of more private power generators, resulting in competitive electricity pricing and dampening the rising trend in electricity prices. Reliability surpassed the ERC s targets in 2009 and 2010, and the PEMC produced regular and timely dispatch schedules, calculated market prices, and prepared settlement statements. Commercial WESM operation in Luzon started on 26 June 2006 after a trial period of market operation. However, 5 years since then, the PEMC has remained as market operator. Guidelines in selecting the IMO s Board of Directors are being finalized and targeted for completion in 2014. 18. Because of the project, grid losses were lower than the caps set by the ERC. 10 Transmission system losses in Luzon were 2.87% in 2009 and 2.47% in 2010, and substantially reduced in Mindanao from 4.69% in 2009 to 3.81% in 2010. By 2009, 100% electrification in barangays was achieved in Mindanao. The completed transmission component successfully reduced congestion in Luzon and Mindanao, resulting in more reliable and dependable delivery of power and expanded electrification coverage in rural Mindanao. The large social welfare gains from the electrification and the substantial resource cost savings from reduced losses are reasons to conclude that the project was effective. This validation rates the project effective, similar to the PCR s rating. C. Efficiency of Resource Use in Achieving Outcome and Outputs 19. The PCR rated efficiency satisfactory. The PCR noted that the project opened the electricity market in the Philippines to independent power producers, and WESM operation was successful because it helped reverse the rising trend of electricity rates in the Luzon and Visayas grids. Completion of the transmission line and substation components in Luzon increased transmission and transformation capacities of the Luzon grid, enabling full dispatch 10 Caps set by the Energy Regulatory Commission were 2.98% for Luzon and 4.35% for Mindanao.

6 of the generating plants in northern and southern Luzon. In Mindanao, the additional transformers ensured reliable power supply to nearby areas as well as sufficient capacity for rural electrification. 20. The economic analysis in the PCR assessed the economic viability of the project s MMS component based on fulfillment of the Philippines legal requirements. The PCR noted that the actual MMS cost was about 43% of the initial estimate because it was purchased as software modules off the shelf rather than custom-made. The actual cost was $10.7 million, compared with $25 million at appraisal. The economic analysis of the MMS within a 5-year life (as was implemented) should have identified the least cost among other options. 21. The PCR did not present the economic internal rates of return (EIRRs) and least-cost analysis of unit costs for the transmission and substation components. It should have calculated and presented these figures to compare with the figures in the RRP. 22. Given that project implementation occurred largely as outlined in the RRP, and some cost savings offset delays in some substation components, this validation rates the project efficient. D. Preliminary Assessment of Sustainability 23. The PCR rated the project likely to be sustainable. The PCR estimated the financial internal rates of return (FIRRs) for the MMS component at 65% and the transmission and substation components at 9.94%. For the MMS component, the PCR noted that the market operator obtained its revenue from fees from market participants, and that the MMS hardware and software were still operational. The PCR noted that the system infrastructure is 5 years old, nearing obsolescence, and will need to be replaced in the near future. The PCR should have assessed the WESM s financial sustainability as an institution and its capacity to both finance and upgrade the MMS. 24. For the transmission and substation component, the PCR assessed sustainability based on revenues being assured through performance-based regulation and good maintenance of the facilities, and strict compliance with safety and operational procedures. In this validation s view, this assessment is insufficient. A financial assessment of the National Grid Corporation of the Philippines (NGCP) would have better determined whether project assets will be maintained in the future. The PCR should have also assessed the institutional capacity of the WESM and the NGCP. 25. Nevertheless, the WESM and the NGCP are viable power institutions, providing effective oversight on the wholesale power market and the transmission grid, respectively. 11 Therefore, this validation rates the project likely to be sustainable. 11 Although the WESM is market-driven, many players provide oversight. For instance, the Energy Regulatory Commission was tasked to enforce the rules and regulations governing the operations of the electricity spot market, while the Department of Energy was responsible for energy policy and planning. The National Grid Corporation of the Philippines was granted the franchise to operate, manage, and expand the Philippine electric transmission grid for 25 years (from 2008), renewable for another 25 years. Ownership of the transmission assets (lines, substations, land, and structures) remain, however, with the Government of the Philippines through the National Transmission Corporation (TRANSCO).

7 E. Impact 26. The RRP indicated that impact would be measured in terms of increase in gross national product per capita, reduction in national debt, and decrease in unemployment. Unfortunately, it is not possible to make any inferences on these indicators due to problems of attribution. The PCR evaluated impact by concluding that the project has contributed to the reliability, quality, and affordability of power supply in the Luzon and Mindanao grids. This conclusion seems correct based on the outcomes of the project. 27. The PCR did not rate impact. In this validation s view, the project s impact on poverty, institutional development, economic growth, environment, and social outcomes is significant. III. OTHER PERFORMANCE ASSESSMENTS A. Performance of the Borrower and Executing Agency 28. The PCR noted that after March 2009, TRANSCO had difficulties submitting quarterly progress reports and completion reports because project records and personnel were moved to the PEMC and the NGCP. The PCR also noted TRANSCO s delayed procurement process because of its cumbersome procedures for bid evaluations and approval of contract award. 29. TRANSCO complied with ADB s guidelines and national laws for procurement, land acquisition, and resettlement. The valuation and compensation procedure involved information campaigns, data gathering, stakeholder consultations, verification of documentary requirements, cost valuation, negotiations, and processing of payments. Expropriation cases for failed negotiations were filed in courts. However, TRANSCO was unable to complete the land acquisition and resettlement plan within the appraised implementation schedule. The PCR rated the performance of the NPC as borrower and TRANSCO as executing agency partly satisfactory. This validation agrees with the PCR s rating. B. Performance of the Asian Development Bank 30. The PCR stated that ADB s performance did not contribute to implementation delays. ADB assisted TRANSCO in resolving issues brought to its attention during procurement and project implementation. However, ADB s closer monitoring of the procurement process and the social engineering parts of the project would have helped minimize implementation delays. ADB s project administration was rated satisfactory. This validation holds a similar view on ADB s performance. IV. OVERALL ASSESSMENT, LESSONS, AND RECOMMENDATIONS A. Overall Assessment and Ratings 31. The PCR rated the project successful. This validation gives a similar rating. The project was relevant, effective, efficient, and likely to be sustainable. Therefore, this validation s overall project rating is successful.

8 Overall Ratings Criteria PCR IED Review Reason for Disagreement and/or Comments Relevance: Relevant Relevant Effectiveness in Effective Effective Achieving Outcome: Efficiency in Achieving Satisfactory Efficient Outcome and Outputs: (Efficient) Preliminary Assessment of Sustainability: Likely to be sustainable Likely to be sustainable Overall Assessment: Successful Successful Borrower and executing agency: Partly satisfactory Less than satisfactory Performance of ADB: Satisfactory Satisfactory Impact: Not rated Significant Quality of PCR: Less than satisfactory Shortcomings in efficiency, sustainability, and impact assessments (para. 36) ADB = Asian Development Bank, IED = Independent Evaluation Department, PCR = project completion report. Note: From May 2012, IED views the PCR's rating terminology of "partly" or "less" as equivalent to "less than" and uses this terminology for its own rating categories to improve clarity. Source: Independent Evaluation Department. B. Lessons 32. The PCR identified several lessons. First, it highlighted the need to train all market participants to ensure their readiness. On the transmission and substation component, the PCR suggested that ADB and TRANSCO should have closely collaborated to prevent implementation delays; implementation would have proceeded quicker had TRANSCO appointed full-time staff for bid evaluation. A single procurement of the substation equipment and resolution of right-of-way issues before project commencement would have hastened implementation. 33. The PCR noted that compensation and resettlement issues would have been resolved more quickly had the project made affected people better aware of the property valuation process and the impact of the project upon them, and established a mechanism for resolving disputes. Local government institutions would also have helped resolve disputes. The project should have activated the external monitoring group earlier to prepare it for the task of assisting affected people. This validation agrees with these lessons. C. Recommendations for Follow-Up 34. This validation concurs with the PCR s recommendations. This validation suggests that the PCR should have added a recommendation on establishing a monitoring and evaluation system as part of the project design, which would have helped assess outcomes and outputs. V. OTHER CONSIDERATIONS AND FOLLOW-UP A. Monitoring and Evaluation Design, Implementation, and Utilization 35. The RRP stated that TRANSCO will compile and analyze data to facilitate project performance monitoring and evaluation. It will forward this information to ADB in accordance

9 with the agreed schedule of performance measurement indicators to assess the macroeconomic impact and achievement of sector development goals of the Project. The loan covenants did not require a monitoring and evaluation system to be established. The PCR did not discuss monitoring and evaluation. The absence of a monitoring and evaluation system was likely the main reason why the PCR did not calculate EIRRs or assess project impact. B. Comments on Project Completion Report Quality 36. The PCR s major shortcoming was insufficient analysis and assessment of the project s efficiency, sustainability, and impact. The PCR did not calculate the EIRR for the transmission and substation components, and it erroneously used the FIRR as an efficiency rating rather than a sustainability measure. The PCR neither calculated the FIRR according to ADB guidelines nor did it provide a financial assessment of the implementing agencies to support its sustainability rating. The PCR should have provided more evidence of project impact in Luzon and Mindanao. Overall, the PCR s quality is less than satisfactory. C. Data Sources for Validation 37. Data sources included the RRP, the PCR, and back-to-office reports of ADB review missions. D. Recommendation for Independent Evaluation Department Follow-Up 38. The PCR recommended that a project performance evaluation report be prepared in the last quarter of 2012. Since this date has passed, this validation recommends an evaluation to be undertaken at the earliest opportunity to verify the effectiveness, efficiency, sustainability, and impact of the project.