SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS Contractors General Conditions Site Works Setting out works: Rates

Similar documents
Transcription:

SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS 01000 Contractors General Conditions 02000 Site Works Setting out works: Rates shall include but not limited to all necessary equipments, tools, and workmanship needed to setout the new rooms in accordance to the bill of quantities and Engineer instructions 02010 02030 Provide all necessary tools, equipments and workmanship and setout the new facilities as per drawings. Lump Sum 1 Excavation for foundation and inside of building are classified in all kinds of soil from the actual surface of soil to the grades shown on drawing and net size required by the concrete dimension and Rates shall include but are not limited to the following Furnishing all material and installing, shoring and * bracing necessary to protect existing building, street,.walk ways, utilities and other Improvement and excavation against loss of ground or.caring embankment. Necessary dewatering. If required Excavation for the whole site and remove the top soil 15cm depth M3 72.6 02031 Excavation for isolated foundations as per structural drawings M.L 439.4 Backfilling : provide selected material approved by the engineer 50 cm depth in layers not exceeding 10 cm,compacted to a minimum of 95% Modified Proctor Test, as per 02040 drawings & specifications Provide all materials and backfill for foundation M3 369.354 02041 Provide all materials and backfill for floor leveling M3 291.5 03000 Concrete Works 03010 03011 Rates shall include but are not limited to the following furnishing concrete, all equipment necessary for transferring, depositing and discharging concrete, all types of forms as required to complete with all tests, structs,bracing scaffolding or staging and accessories, form oits tapes, reinforcing steel beams, tying wire, spacer, bolsters, joint sealants, water stops, curing compound and sleeves for embedded articles Provide all materials and lay in position plain concrete for Foundation M 3 17.576 Provide all materials and lay in position RC concrete for Floor areas (slab on grade) M3 52.47

03012 03013 03014 03015 03016 03017 03018 Provide all materials and lay in position concrete for Foundation 1:2:4 mix, with strength not less than 25 N/mm2 M3 71.305 Provide all materials and lay in position concrete for Short Columns 1:2:4 mix, with strength not less than 25 N/mm3 M3 13.65 Provide all materials and lay in position concrete for grade beams 1:2:4 mix, with strength not less than 25 N/mm2 M3 19.5122725 Provide all materials and lay in position concrete for Ground Floor Columns 1:2:4 mix, with strength not less than 25 N/mm3 M3 13.65 Provide all materials and lay in position concrete lintels for doors and windows M3 0.64 Provide all materials and lay in position concrete for Roof beams 1:2:4 mix, with strength not less than 25 N/mm2 M3 18.285225 Provide all materials and lay in position concrete for Ground Floor Slab 1:2:4 mix, with strength not less than 25 N/mm2. M2 83.012 Provide all materials and lay in position concrete for Staircase 03019 1:2:4 mix, with strength not less than 25 N/mm2. Job 0 04000 Masonry works 04010 04011 Rates shall include but not limited to all necessary formworks, equipments materials cutting around scarps, Provide all materials and build 1 brick wall with 1:6 C/S mortar around the building M2 101 Provide all materials and build 1 brick wall with 1:6 C/S mortar.for walls M2 376.90 Provide all materials and build 1 brick wall with 1:6 C/S mortar.for Parapet walls including coping detail as per drawings. M2 101 04012 Provide all materials and build Interlocking M2 265 04013 Provide all materials and build Curbstone M.L 113.75 05000 Metal works Rates shall include but not limited to providing all material,fabrications finishing painting and workmanship as directed by the Engineer 05010 provide and fix in position steel handrail as specified in the drawings for entrance steps M.L 10 05011 provide and fix in position metal grills for windows M.L 17.28 06000 Wood & Plastic Works 07000 Thermal & Moisture Protection Rates shall include but not limited to providing all material, finishing painting and workmanship as directed by the Engineer Provide all materials and install in position dam proofing course (3 coats of bituminous material) for kitchen and toilets M2 87.5

07011 Provide all materials and install in position dam proofing course (3 coats of bituminous material) and application of khafji including down spouts as in the drawings M2 291.5 08000 Doors & Windows Rates shall include but not limited to providing all material,fabrications finishing painting and workmanship as directed by the Engineer 08010 Provide all materials and install in position heavy fire resistant doors Type D1 as per drawings and specs. M2 13.2 08011 Provide all materials and install in position heavy fire resistant doors Type D2 as per drawings and specs. M2 11 08012 Provide all materials and install in position heavy fire resistant doors Type D3as per drawings and specs. M2 9.6 08013 Provide all materials and install in position heavy duty aluminum widows type W1 M2 7.2 08014 Provide all materials and install in position heavy duty aluminum widows type W2 M2 2.88 08015 Provide all materials and install in position heavy duty aluminum widows type HLW1 M2 7.2 09000 Finishes Works Rates shall include but not limited to providing all material,fabrications finishing painting and workmanship as directed by the Engineer 09010 Provide all materials and lay in position min.2cm plaster layer for external walls with 1:8 C/S mortar M2 825.8068125 09011 Provide all materials and lay in position min.2cm plaster layer for narrow widths with 1:6 C/S mortar M.L 101 09012 Provide all materials and lay in position min.2cm plaster layer for roofs with 1:6 C/S mortar M2 178.5 09013 09014 09015 Provide all materials and lay in position 2 layers of under coat (Talia) and 3 finishing coats (one emulsion water based coats and two oil based coats) for internal walls finish M2 178.5 Provide all materials and lay in position 2 layers of under coat (Talia) and 2 finishing coats (emulsion water based coat) for external walls M2 825.8068125 Provide all materials and lay in position 2 layers of under coat (Talia) and 2 finishing coats (emulsion water based coat) for ROOF M2 178.5 09016 Provide all materials and lay in position \acoustical false ceiling. M2 204 Provide all materials and lay in position Ceramic Tiles 30*30 cm 09017 for floors M2 291.5 09018 Provide all materials and lay in position Ceramic Tiles 30*30 cm walls M3 70 09019 Provide all materials and lay in position Skirting of 10*30 cm Ceramic tiles M.L 124

10000 Specialties Rates shall include but not limited to providing all material,fabrications finishing painting and workmanship as directed by the Engineer 10010 Provide and install in position10000 Liter water tank No 0 10011 Provide and lay in position 5Kg CO2 Fire extinguishers No 0 11000 Equipments 12000 Furnishing 13000 Special Constructions 14000 Conveying Systems 15000 Mechanical Works Rates shall include but not limited to providing all material,fabrications finishing painting and workmanship as directed by the Engineer 15010 Provide all materials and build in position Discharge well as per drawings and directions of engineer (contractor to have sufficient information regarding the depth of water table and levels in the area prior Costing) Each 1 15011 15012 15013 15014 15015 Provide all materials and build in position 200*3500*2200 depth Septic Tank as per the Engineer directions Each 1 Provide all materials and lay in position 45*45 manholes as per the Engineer directions Each 4 Provide all materials and lay in position 30*30 cm gully traps as per the Engineer directions Each 3 Provide all materials and lay in position Hand washing basin with all accessories Each 4 Provide all materials and lay in position Western Type Toilet Seats with all accessories Each 6 15016 Provide and fix AC Split Unit 18000Btu, Mitsubishi, General or equivalent. Gas piping & Electric wiring in 500x500mm PVC trucking between indoor & outdoor units. A pair of Iron Brackets will also be provided for installation of outdoor Unit, with all accessories & fittings complete in all respects, The waste pipe shall have a slope of 150mm/m with the length to cover all as per drawings & specifications Each 9 15017 Provide all accessories and install Q1 inch PPR Water Supply Pipes M.L 60 15018 Provide all accessories and install Q2 inch PVC 6 Bars Water Drain Pipes M.L 45 15019 Provide all accessories and install Q4 inch PVC 6 Bars Water Drain Pipes M.L 30 16000 Electrical Works Rates shall include but not limited to supply of all materials,equipments tools, testing commissioning and the installation workmanship as per the drawings and specifications and directions of the Engineer

16010 16011 16012 Supply and install and operate Main Distribution Board English made or equivalent, complete installation, including for all connections, earthing, painting, testing and similar of One Three phase main panel board with connections from the mains including meter, cut off fuse, the capacitors measuring meters (Voltmeter and Ammeter) indicating lamps, the protection required for the measuring meters, various bus bars, terminal blocks and all accessories required One Electricity Meter The size of the board is suitable for all components and accessories with spare space of30%. Sample is to be provided for Engineer s approval. Each 1 Supply & install distribution panel.100a, including Erection, Testing & Commissioning, compartmentalized 18 way MCBDB Double door type, IP 42 powder coated comprising of "C" curve MCB's for LIGHTING / cum POWER DB. Including support clamps & angles frames as required. as per drawings & specifications Each 1 Provide all materials and lay in position 4 feats fluorescent lamps Each 62 16013 Provide all materials and lay in position ceiling lamps Each 30 16014 Provide all materials and lay in position 13 Amps Sockets Each 24 16015 Provide all materials and lay in position 150cm Ceiling Fan Each 12 16016 Provide all materials and lay in position 12 inches exhaust fan Each 8