ENGINEERING MANAGEMENT (GE

Similar documents
PROJECT TIME PLANNING. Process and Bar Chart Technique

Geog 469 GIS Workshop. Project Management

technology management & innovation introduction to project management (ii) project planning methods & tools

6 PROJECT TIME MANAGEMENT

Planning & Scheduling

Construction Planning and Scheduling

Project Time Management

Estimating Project Schedule-Time and Cost

Information Technology Project Management, Seventh Edition

Project Scheduling: Lagging, Crashing and Activity Networks

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Week 5 Project Work Plan

Project Time Management

PMP Exam Preparation Course Project Time Management

Business Decision Making

Project Time Management

PROJECT PLANNING AND SCHEDULING

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Construction Planning and Scheduling

Project Management in Practice Fifth Edition

Chapter 3 Managing Systems Projects

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Planning & scheduling

Managing Projects with MS Project 2010

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

East Central College

Chapter-7# Project Controlling and Scheduling

DAMELIN CORRESPONDENCE COLLEGE

Modern Systems Analysis and Design Seventh Edition

Planning & Scheduling CSTM 102

Time Management PLANNING

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005

Charting and Diagramming Techniques for Operations Analysis. How to Analyze the Chart or Diagram. Checklist of Questions - Example

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

Time has the least. amount of flexibility; Schedule issues are the main reason for

Microsoft Office Project 2010 Basic Course 01: Getting Started

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

Operations Management

Cambridge International AS & A Level Computer Science

PROJECT TIME MANAGEMENT

The Project Planning Process Group

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

Week 5 Project Work Plan

Microsoft Excel or Microsoft Project? Why Microsoft Office Project 2007 is Easier and More Effective for Managing Projects

Constructing Networks

Chapter 4 Project Management

Week 5 Project Work Plan

Welcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase

GE404 Engineering Management Topic1. INTRODUCTION

Week 5 Project Work Plan

FACTFILE: GCE DIGITAL TECHNOLOGY

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: )

SCH202: Manage Schedules

IST 302 : Project Time Management

Planning Tools and Techniques Part 2

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS

Project Planning & Scheduling

Chapter 24. Software Project Scheduling

Guten Tag. (good day)

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.

Lecture- 11. Project Scheduling. Dronacharya College of Engineering

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Microsoft Project study guide

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

THE PMP EXAM PREP COURSE

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

LECTURE 8: Planning & Control Functions & Tools (Part II) Project Management BACA

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras

Project Planning Tools

Scheduling Work at IPSC

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

Easy Projects Glossary. Version 1.00

Introduction to Project Management

International Association of Certified Practicing Engineers

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS]

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim

Small House Extension Project

Scheduling Resources and Costs

BA /14/2010. PSU Problem Solving Process. The Last Step 5. The Last Step 8. Project Management Questions PLAN IMPLEMENT EVALUATE

Mastering Microsoft Project 2010

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional

Community. Prepared. Supervised. Gaza,

FIGURE 8-8 Computer Printout of Sewer Line Activities Only (Sort of Activities List by Code Digit #I Equal to One).

The recommended guided learning hours for this unit are 30 hours.

10/10/2013. Articles. Project Management

Topic # 12. CIS Project Management: an overview

13 Project Graphics Introduction

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani

Scheduling. Adapted from John Musser

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Transcription:

بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 4 Scheduling and Bar Chart

Contents Objectives of the present lecture Planning and Scheduling Activity and Event Scheduling Techniques Bar Charts Critical Path and Critical Activities Problems Further reading 2

Objectives of the Present lecture To provide an overview of scheduling To discuss how to draw bar chart To discuss advantages and shortcomings of bar charts 3

Planning and Scheduling 4 Planning is the process of thinking systematically about the future in order to decide what our goals are, and how we are going to achieve them. Scheduling is the process showing relationship of activities and determining of the project duration time and the project activities starting and finishing timings.

Planning versus Scheduling 5 Planning Scheduling Planning can be thought of as determining what is going to be done, including how, where, and by whom. The majority of the work associated with defining how the project effort will proceed called planning In scheduling, this information is needed in order to determine when. Scheduling consists of determining the time needed for each of the planned tasks and the overall length of the project schedule.

Purpose of Scheduling Ensure that all activities are planned Their order of performance is accounted for The activity time estimates are recorded The overall project time is developed 6

What we consider in Scheduling How long the project is expected to take? When each activity should be started and ended? How resources can be used properly? What are the critical bottlenecks in the project? 7

Project Scheduling Principles Project scheduling is carried out before a project begins 8 It involves (1) identifying tasks, (2) estimating duration and (3) allocating resources Once the project is underway, the schedule may need to be revised based on initial progress The revision is done by creating milestones This ensures (1) cost estimates and (2) time constraints are maintained at a specific level of quality and scope

Activity and Event 9 Activity is a single work step (element) that has a recognizable beginning and end and requires time and resource for its accomplishment. An Event marks the point in time when an activity completes. Sequence of Activities for House construction project (Network diagram) Note: Activity is often used as an alternative term for task.

Note 10 Predecessor activities mean coming before Successor activities mean coming after The duration of an activity is the time that will be consumed in completing a task Overlap the activities to reduce the project time

Activity Duration 11 One of the following tools and techniques can be used for estimating the activity duration: Expert judgment Quantitative calculations Duration of activity (D) = Quantity of work / [Production rate of a crew or equipment No. of crews] Where production rate = Quantity produced in unit of time Duration of activity (D) = Quantity of work Unit rate productivity of a crew or equipment Where unit rate productivity = Time needs to produce one unit of output Time unit (days, weeks etc.) is employed to specify activity duration.

Scheduling Techniques Bar Charts and Linked Bar Charts Network Model (Analysis) Activity on arrow (AOA) Activity on node (AON) Precedence Diagram Line of Balance Time-location Diagram 12

Bar Charts Henry Gantt developed a method of relating a list of activities to a timescale in a very effective manner, by drawing bar charts. Activities are presented as bars on the chart, while across the top or bottom of the chart is a time line. For each activity, a bar is drawn from the activity s starting time until its ending time. Its primary advantage is that its simple graphic representation allows one to grasp schedule information quickly and easily. Bar charts are the most commonly employed and readily recognized scheduling models in use today. 13 Bar chart showing General Construction Work Tasks The activity sequencing is for an apartment, and one can easily see when each activity is to begin and when is to be completed.

Bar Charts (Contd.) 14 This simple example shows at a glance how the different activities relate to each other. Note that the activities are time scaled and have been superimposed over a calendar. With the timescale presentation, a bar chart shows operations and the time consumed by each operation. Bar chart showing General Construction Work Tasks

Use of Bar Chart in showing Scheduled versus Actual Progress Bar Chart can also show the scheduled versus actual progress. The heavy-dashed vertical line represents the current date, and the shaded portions of the activities indicate the amount of work that has been completed by the current date. It is obvious that the project is slightly behind schedule. The progress on the framing activity has not met expectations. It is evident that the project can be completed on time by accelerating the work effort on framing, finishing interiors, or both. This information is easy to grasp from this bar chart, and there is little chance of misinterpretation. Bar chart showing scheduled versus actual performance Adjustments to the schedule may be warranted if the delay in project completion(about 1 week) is not acceptable. 15

Uses of Bar Chart 16 Showing the order of the different activities Showing when operations should start and finish Checking what labor or equipment are needed and when Checking out delivery dates for materials Explaining to everyone concerned what and when is due to happen Forecasting cash flow During execution, the chart can be used to control the work

Advantages of Bar Chart A major strength of bar charts is the ability to clearly and quickly present the status of a project No extensive training is required to learn how to extract information from them 17

Shortcoming of Bar Charts 18 Very cumbersome as the number of activities, increases Difficult to use for forecasting the effects of changes No indication where management attention should be focused Ineffective for project shortening

Critical Path Critical Path and Critical Activity Longest sequence of activities which must be completed on time for the project to complete on due date Critical Activity A critical activity is any activity that is on the critical path. If there is a delay in any of these activities then the whole project will be delayed Note: An activity on the critical path cannot be started until its predecessor activity is complete; if it is delayed for a day the entire project will be delayed for a day unless the activity following the delayed activity is completed a day earlier. 19

How to identify critical path in a bar chart 20 Start with the last activity Draw a vertical line from the i th node of the last activity i j The activities whose j nodes touch the vertical line, are potential critical activity Proceed in this manner until you reach time 0

Bar Chart for Building a Bridge 21

Bar Chart 22

Problem-1 23 Draw Gantt bar chart for a small Engineering project listed below and find (a) Total duration of the project (b) Critical activities Activity Depends on Time (Weeks) A None 4 B A 6 C B 7 D C 3 E None 3 F A, E 4 GE 201: Dr. N. A. Siddiqui 9/21/2018

Solution 24 Activity Durati on (Wks) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 A 4 B 6 C 7 D 3 E 3 F 4 Project Duration = 20 weeks Critical Activities = A, B, C, and D. Ans. Ans.

Problem-2 25 For the following project draw Gantt bar chart if the project starts on Monday 15/6/2015. Identify the critical activities and find the total duration of the project in terms of number of (i) working days; and (ii) Calendar days. Consider that workdays are six days a week (Saturday Thursday). Activity Depends on Time (days) A None 2 B A 3 C None 3 D B,C 2 E C 1 F E,B 3 GE 201: Dr. N. A. Siddiqui 9/21/2018

Solution 26 Act. Dur. SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI A 2 B 3 C 3 D 2 E 1 F 3 Project Duration: Calendar days = 9 Working days = 8 Critical Activities: A, B and F. Ans. Ans. Ans.

Software generated bar charts 27

Further Reading Read more about the scheduling and bar charts from 28 Jimmie W. Hinze. Construction Planning and Management, Fourth Edition, 2012, Pearson.

Thank You 29