HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update
PROGRESS UPDATE Rien Construction (General Contractor) Placed rebar, anchor bolts and concrete for footings and piers for areas A and D Graded, placed the stone base, vapor barrier and wire mesh for the slab on grade in area C and in the gym Placed subgrade insulation around perimeter walls at the connector and backfilled with stone Excavated and placed concrete footings and the elevator pit slab and sump pit Set door frames on the first and second floor of area B and at the gym and locker rooms Grouted under steel columns in area C Started demolition of the cafeteria vestibule and stone panels on the south side of the existing building Etzel Masonry (Masonry Subcontractor) Laid CMU backup for the mechanical room Continued laying split face block on areas B & C, the gym locker rooms, the mechanical room and the gym Sprayed air barrier on the block walls around the gym and area B Laid brick veneer on the gym and at the stairwells for areas B and C Laid CMU walls for the locker rooms, gym chases and elevator shaft Ferguson-Steel (Steel Erection Subcontractor) Installed columns, beams and roof joists for the first floor of area C Installed joists, bracing and acoustical decking for the gym Started installing beams and decking for the gym locker rooms and the rest of area D Emerick Masonry (Concrete Subcontractor) Placed and finished the concrete slab on grade for area C and the gym Grafton Construction (Interiors Subcontractor) Installed wall framing for the first and second floors of area B and started installing exterior wall framing for area C Installed sheathing, insulation and plywood for the exterior walls on area B and started installing sheathing on area C Installed wood blocking around the window openings on area B SRI Roofing (Roofing Subcontractor) Installed substrate boards, insulation, cover boards and EPDM roofing on area B, the gym and area C Boak & Sons (Spray Foam Insulation Subcontractor) Started spraying foam insulation for the exterior walls on the first floor of area B Merit Electrical Group (Electrical Contractor) Installed conduit, MC cable and boxes in the basement of area C and the first and second floors of area B Installed underground conduits in the mechanical room, gym and area C Worked with the masons to install conduit and junction boxes in masonry walls Installed temporary lighting on the first and second floors of area B and in the gym Vrabel Plumbing (Plumbing Contractor) Installed carriers, waste and vent piping for areas B and C and the gym locker rooms Installed domestic water lines for areas B and C Installed roof drains and rain water conductor piping for areas B and C Excavated and installed underground sanitary piping for the restrooms on the north side of the gym
Lugaila Mechanical (HVAC Contractor) Mobilized office trailer, storage trailers and stocked materials Installed hangers and hot water supply and return piping for terminal boxes in area B. Assisted Hranec with placing and leveling curbs for roof top units Hranec Sheet Metal (Sheet Metal Subcontractor) Continued hanging ductwork on the first and second floors of area B Installed curbs for roof top equipment on areas B and C and the gym Installed return air ductwork for the gym Contractor Rien Construction Co. Lugaila Mechanical PAYMENT APPLICATION SUMMARY Vrabel Plumbing Co. Merit Electrical Group William T. Spaeder Co. Commercial Appliance Contracts Northeast Interior Systems Canfield Development WorkSpace Solutions Construction Contract General Construction HVAC Construction Plumbing Construction Electrical Construction Fire Protection Construction Food Service Construction Architectural Casework Construction Asbestos Abatement Construction Maker Space Equipment All Contracts Total Billed $4,236,627.15 $341,617.50 $1,064,799.00 $509,247.54 $0.00 $241,668.00 $8,550.00 $14,400.00 $0.00 $6,416,909.19 Original Contract Sum $17,374,700.00 $3,752,700.00 $2,681,900.00 $4,555,070.00 $315,100.00 $459,833.00 $1,261,600.00 $247,777.00 $117,506.00 $30,766,186.00 Change Order 1 $0.00 $654.72 Change Order Total $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $654.72 $0.00 $654.72 Contract Sum to Date $17,374,700.00 $3,752,700.00 $2,681,900.00 $4,555,070.00 $315,100.00 $459,833.00 $1,261,600.00 $248,431.72 $117,506.00 $30,766,840.72 Balance to Finish $13,138,072.85 $3,411,082.50 $1,617,101.00 $4,045,822.46 $315,100.00 $218,165.00 $1,253,050.00 $234,031.72 $117,506.00 $24,349,276.81 Percent Complete 24.38% 9.10% 39.70% 11.18% 0.00% 52.56% 0.68% 5.81% 0.00% 20.86% May-18 $344,500.67 $29,925.00 $12,600.00 $387,025.67 Jun-18 $177,930.00 $76,410.00 $186,795.00 $109,309.50 $1,800.00 $552,244.50 Jul-18 $417,416.84 $232,933.00 $112,270.95 $4,551.30 $767,172.09 Aug-18 $784,227.83 $57,600.00 $151,556.00 $134,285.49 $213,232.50 $1,340,901.82 Sep-18 $589,834.35 $86,220.00 $93,627.00 $54,857.25 $12,023.10 $836,561.70 Oct-18 $1,922,717.46 $121,387.50 $369,963.00 $98,524.35 $11,861.10 $8,550.00 $2,533,003.41
PROGRESS PHOTOS: Concrete slab on grade for the gym locker rooms Steel and joist erection for area C
Underground electric installation under the main office area Mechanical equipment curbs on area B
Roof drain installation on area B Roofing installation on area B
Area D storage room concrete slab on grade Area C concrete slab on grade in the stairwells
Underground plumbing and the stone base was placed in area C Exterior wall studs started in area B
Block was placed for the elevator pit/shaft Vapor barrier and wire mesh were placed for the area C slab on grade
Roof joists and bracing were installed for the gym CMU was laid for the gym locker rooms
Plumbing carriers, waste and vent piping were installed in area B Underground sanitary piping was installed for the restrooms outside the gym
Ductwork installation continued in area B The concrete slab on grade was placed and finished for area C
Exterior wall framing and roofing started for area C Stone base was placed for the gym floor
Air barrier was applied to the gym walls and the brick fascia was laid Sheathing, insulation and plywood were installed on the exterior walls for area B
Split face block and brick was laid for the exterior gym walls Concrete slab on grade was placed and finished for the gym
Steel erection continued for area D CMU backup and split face block were laid for the mechanical room
Demo of the stone panels and vestibules on the south side of the existing building Roofing being installed on area C
View of area C Plumbing rough-ins in the gym locker rooms
Gym locker room showers Area C plumbing toilet room rough-ins
Area C stair structure installed Area B first floor progress
Spray foam insulation on the exterior walls in area B 1 st floor Area B second floor progress
Area C progress CMU installation for the elevator shaft
The connector for areas B and C Plywood and weather barrier installation on area B
The west side of area C The west side of area B
North and west sides of area B South side of area C and the west side of the gym and locker rooms