HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

Similar documents
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

Building Excellence IV Capital Levy Projects Under Construction

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

Seattle Public Schools Building Excellence IV Projects Under Construction

Update on FCPS Construction/Renovation Projects. November 2015

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

Update on FCPS Construction/Renovation Projects. June 2016

NEW MIDDLE SCHOOL PROJECT

Schedule of Values Cruise Terminal 2 Expansion

Building Excellence IV Capital Levy Projects Under Construction

Update on FCPS Construction/Renovation Projects. December 2015

Project Manual Index of Specifications Shenandoah Schools Concession Building

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

City of Rohnert Park Building Department Inspection Descriptions

TABLE OF CONTENTS Public Safety Building

Update on FCPS Construction/Renovation Projects. July 2016

NEW MIDDLE SCHOOL PROJECT

Technical Assignment 2

FIELD COPY ATTACHMENT

APPLICATION AND CERTIFICATE FOR PAYMENT

ADDENDUM 2 - JULY 14, 2015

Building Excellence IV Capital Levy Projects Under Construction

Update on FCPS Construction/Renovation Projects. September 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

INSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process.

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS. Executive Summary.1. Detailed Project Schedule Site Layout Planning 4

Two complete sets of plans that are legible and drawn to conventional scale are required to be submitted with the Building Permit Application Form.

Update on FCPS Construction/Renovation Projects. August 2015

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS

Capital Projects Progress Report. January Presented by

Division 00 Procurement and Contracting Requirements

NEW MIDDLE SCHOOL PROJECT

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

4.1.3 Project Manual

The Homeowner s Building Application Checklist for Constructing a Residential Addition

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs

The Inspection Process. Waxhaw N.C.

Nassau County Building Department

NAAHB Workgroup Index General Ledger Account

Capital Projects Update

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

City Of Mendota Construction Procedures

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

City of Westerville Guide to Commercial Inspections

Section 4 - Design and Construction Overview

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

BuildingAdvisor.com Estimating Checklist

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio.

STATEMENT OF SPECIAL INSPECTION FORM

Building Systems and Design Elements included in SliDeRulE

BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT

KU West Campus LEEP II High Bay Facility Project # , A (c)

Safety Update Crossing study is in final review stages. Facilities Update Construction Progress

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

MITTERSILL WARMING HUT

Project Estimate Summary

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

Cost and Methods Analysis

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

PAULDING COLLEGE & CAREER ACADEMY

Office of Design & Construction State University Plaza Albany, New York

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

1 AND 2 FAMILY DWELLING REQUIREMENTS

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS

Fleet Elementary School

WORK AND PROJECT REQUIREMENTS

Residential Construction Minimum Required Inspections

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Building Architecture

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application)

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches

Boyden Library Board of Trustees Minutes of Monthly Meeting Monday, August 20, 2012

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

Transcription:

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update

PROGRESS UPDATE Rien Construction (General Contractor) Placed rebar, anchor bolts and concrete for footings and piers for areas A and D Graded, placed the stone base, vapor barrier and wire mesh for the slab on grade in area C and in the gym Placed subgrade insulation around perimeter walls at the connector and backfilled with stone Excavated and placed concrete footings and the elevator pit slab and sump pit Set door frames on the first and second floor of area B and at the gym and locker rooms Grouted under steel columns in area C Started demolition of the cafeteria vestibule and stone panels on the south side of the existing building Etzel Masonry (Masonry Subcontractor) Laid CMU backup for the mechanical room Continued laying split face block on areas B & C, the gym locker rooms, the mechanical room and the gym Sprayed air barrier on the block walls around the gym and area B Laid brick veneer on the gym and at the stairwells for areas B and C Laid CMU walls for the locker rooms, gym chases and elevator shaft Ferguson-Steel (Steel Erection Subcontractor) Installed columns, beams and roof joists for the first floor of area C Installed joists, bracing and acoustical decking for the gym Started installing beams and decking for the gym locker rooms and the rest of area D Emerick Masonry (Concrete Subcontractor) Placed and finished the concrete slab on grade for area C and the gym Grafton Construction (Interiors Subcontractor) Installed wall framing for the first and second floors of area B and started installing exterior wall framing for area C Installed sheathing, insulation and plywood for the exterior walls on area B and started installing sheathing on area C Installed wood blocking around the window openings on area B SRI Roofing (Roofing Subcontractor) Installed substrate boards, insulation, cover boards and EPDM roofing on area B, the gym and area C Boak & Sons (Spray Foam Insulation Subcontractor) Started spraying foam insulation for the exterior walls on the first floor of area B Merit Electrical Group (Electrical Contractor) Installed conduit, MC cable and boxes in the basement of area C and the first and second floors of area B Installed underground conduits in the mechanical room, gym and area C Worked with the masons to install conduit and junction boxes in masonry walls Installed temporary lighting on the first and second floors of area B and in the gym Vrabel Plumbing (Plumbing Contractor) Installed carriers, waste and vent piping for areas B and C and the gym locker rooms Installed domestic water lines for areas B and C Installed roof drains and rain water conductor piping for areas B and C Excavated and installed underground sanitary piping for the restrooms on the north side of the gym

Lugaila Mechanical (HVAC Contractor) Mobilized office trailer, storage trailers and stocked materials Installed hangers and hot water supply and return piping for terminal boxes in area B. Assisted Hranec with placing and leveling curbs for roof top units Hranec Sheet Metal (Sheet Metal Subcontractor) Continued hanging ductwork on the first and second floors of area B Installed curbs for roof top equipment on areas B and C and the gym Installed return air ductwork for the gym Contractor Rien Construction Co. Lugaila Mechanical PAYMENT APPLICATION SUMMARY Vrabel Plumbing Co. Merit Electrical Group William T. Spaeder Co. Commercial Appliance Contracts Northeast Interior Systems Canfield Development WorkSpace Solutions Construction Contract General Construction HVAC Construction Plumbing Construction Electrical Construction Fire Protection Construction Food Service Construction Architectural Casework Construction Asbestos Abatement Construction Maker Space Equipment All Contracts Total Billed $4,236,627.15 $341,617.50 $1,064,799.00 $509,247.54 $0.00 $241,668.00 $8,550.00 $14,400.00 $0.00 $6,416,909.19 Original Contract Sum $17,374,700.00 $3,752,700.00 $2,681,900.00 $4,555,070.00 $315,100.00 $459,833.00 $1,261,600.00 $247,777.00 $117,506.00 $30,766,186.00 Change Order 1 $0.00 $654.72 Change Order Total $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $654.72 $0.00 $654.72 Contract Sum to Date $17,374,700.00 $3,752,700.00 $2,681,900.00 $4,555,070.00 $315,100.00 $459,833.00 $1,261,600.00 $248,431.72 $117,506.00 $30,766,840.72 Balance to Finish $13,138,072.85 $3,411,082.50 $1,617,101.00 $4,045,822.46 $315,100.00 $218,165.00 $1,253,050.00 $234,031.72 $117,506.00 $24,349,276.81 Percent Complete 24.38% 9.10% 39.70% 11.18% 0.00% 52.56% 0.68% 5.81% 0.00% 20.86% May-18 $344,500.67 $29,925.00 $12,600.00 $387,025.67 Jun-18 $177,930.00 $76,410.00 $186,795.00 $109,309.50 $1,800.00 $552,244.50 Jul-18 $417,416.84 $232,933.00 $112,270.95 $4,551.30 $767,172.09 Aug-18 $784,227.83 $57,600.00 $151,556.00 $134,285.49 $213,232.50 $1,340,901.82 Sep-18 $589,834.35 $86,220.00 $93,627.00 $54,857.25 $12,023.10 $836,561.70 Oct-18 $1,922,717.46 $121,387.50 $369,963.00 $98,524.35 $11,861.10 $8,550.00 $2,533,003.41

PROGRESS PHOTOS: Concrete slab on grade for the gym locker rooms Steel and joist erection for area C

Underground electric installation under the main office area Mechanical equipment curbs on area B

Roof drain installation on area B Roofing installation on area B

Area D storage room concrete slab on grade Area C concrete slab on grade in the stairwells

Underground plumbing and the stone base was placed in area C Exterior wall studs started in area B

Block was placed for the elevator pit/shaft Vapor barrier and wire mesh were placed for the area C slab on grade

Roof joists and bracing were installed for the gym CMU was laid for the gym locker rooms

Plumbing carriers, waste and vent piping were installed in area B Underground sanitary piping was installed for the restrooms outside the gym

Ductwork installation continued in area B The concrete slab on grade was placed and finished for area C

Exterior wall framing and roofing started for area C Stone base was placed for the gym floor

Air barrier was applied to the gym walls and the brick fascia was laid Sheathing, insulation and plywood were installed on the exterior walls for area B

Split face block and brick was laid for the exterior gym walls Concrete slab on grade was placed and finished for the gym

Steel erection continued for area D CMU backup and split face block were laid for the mechanical room

Demo of the stone panels and vestibules on the south side of the existing building Roofing being installed on area C

View of area C Plumbing rough-ins in the gym locker rooms

Gym locker room showers Area C plumbing toilet room rough-ins

Area C stair structure installed Area B first floor progress

Spray foam insulation on the exterior walls in area B 1 st floor Area B second floor progress

Area C progress CMU installation for the elevator shaft

The connector for areas B and C Plywood and weather barrier installation on area B

The west side of area C The west side of area B

North and west sides of area B South side of area C and the west side of the gym and locker rooms