Project Location. Agenda. Project Background Project Overview Project Challenges Lessons Learned

Similar documents
Terminal Particulars Questionnaire

PART 3 TERMINAL INFORMATION

Please find below some general information about COMVEX dry bulk terminal, according to Appendix no.1.2 of B.L.U. Code :

The Effect of Ultra Large Container Vessels on Cranes and Infrastructure

Pier 3 Upgrade Project

THE EFFECT OF ULTRA LARGE CONTAINER VESSELS ON CRANES AND INFRASTRUCTURE

1. Is it possible that each site will become divided into its own project contract? The projects will not be divided into separate contracts.

FALCONARA OIL TERMINALS INFORMATIONS = API REFINERY = S.P.M. abt 8 miles

The Port of Saldanha Bay Latitude S Longitude E

Energy East Pipeline. Project Overview. Kevin Maloney Manager, New Build Pipeline AB, NB, JV Irving and Cromer September, 2014

From Shore-to-ship to smart ports: Balancing demand and supply and optimizing capital expenditures

Trans Mountain Expansion Project Overview

a combined experience of nearly 200 years

Modifying Your Cranes to Serve Larger Ships

Walk Bridge Project. Norwalk Shellfish Commission. November 1,

INVESTMENT POTENTIAL INVEST IN PORT TERMINALS AT THE PORT OF WALVIS BAY NORTH PORT PROGRAM DATE: 29 AUGUST 2016 REVISION: 1

Mechanical support linkspans

The Port of Cape Town Latitude S Longitude E

Congo (D. R.) Ports description

2.1 Introduction. 2.2 Background and Project Overview. Chapter 2 Project Description Background Project Overview

Conversion of Kurnell refinery to a fuel import terminal

Effect of ULCVs on Cranes and Infrastructure

Port Capacity Analysis in Long Beach. Matt Plezia, POLB and Vaibhav Govil, AECOM TRB Irvine, CA June 29, 2010

Ports as Enablers for Growth Thought Leaders Breakfast : Three Ports, One City Nico Walters, General Manager Strategy, TNPA

Seaports and Marine Oil Terminals

Annex C. Port Zoning and Operational Opportunities and Constraints

Marine Terminal Information Booklet

Notice of Preparation

Inventory Management

Commonality of GoM Lightering Experience with GoM Shuttling

Growth In Container Volumes

LOADING OF BULK LIMESTONE AT MUSANDAM ANCHORAGE

Thames and Medway Physical Supply. Cockett Marine Oil Group web

Mozambique. Port description

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

JLTOC Update. October 7, 2016

CONSTRUCTING MODERN PORTS WITHOUT STEPPING ON WATER by

NAMPORT (NAMIBIAN PORTS AUTHORITY) N th ROAD PO Box 361 WALVIS BAY NAMIBIA

Dr. Konstantinos Galanis

Supporting the Supply Chain. Hinkley Point C

R/V ZERO-V A ZERO-EMISSION HYDROGEN FUEL CELL RESEARCH VESSEL 29 AUGUST 2018 UNOLS GREEN BOATS AND PORTS CONFERENCE 2018

Aryatech Marine & Offshore Services Pvt. Ltd. Aryatech Engineering Consultants FZE

TERAS SUNRISE Multi-Purpose Self Elevating Liftboat

Early Production in Deep Waters. Mats Rosengren, Frontier Drilling do Brasil Vitoria, Brazil

Oil Companies International Marine Forum MTIS Programme Terminal TPQ

APPENDIX E. Project Description Detailed Elements

CONTAINER PORT DEEPENING IN CARTAGENA

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

Brochure Cable transport. Engineering. Cable handling & storage. Equipment

The Future of the Ocean Economy - Offshore Wind

Brochure. Cable transport. Cable handling & storage. Deck Spread. Equipment

The VTTV Oil Storage Terminal Cyprus

WEB BASED OPERATIONAL SYSTEM FOR OPTIMIZING SHIP TRAFFIC IN DEPTH CONSTRAINED PORTS by

Energy Efficiency in Sustainable Port Development and Operations

YOUR PARTNER IN CUSTOMISED OFFSHORE VESSELS

OUR COMPANY YOUR MARITIME AND OFFSHORE PARTNER OUR MISSION AND VISION GROWTH AND COOPERATION MISSION SHE-Q SAFETY, HEALTH, ENVIRONMENT AND QUALITY

Gateway Infrastructure Development Programs in Urban Centers on the west coast of North America

Panama Canal Authority Toll Tariffs approved by Cabinet Council and published on the Official Gazzette Implementation: April 1, 2016

SAFETY BENEFITS 18. Tide-independence 18 Rapid ballasting 19 Integrated hydraulic Ro-Ro ramps 20 Safety features, the future and engineering 22

BS 6349:Part 1.1: 1: General Code of practice for planning and design for operations. David Veale

Notice of Preparation

Intermediate Transfer Ship Conversion. LT Mark Johnson, LT Cara LaPointe, LT Jip Mosman

Marine Facilities for LNG Carrier Transfer Alternatives

Angola. Ports description

Appendix A: Project Characteristics

Port Everglades Master/Vision Plan Update Stakeholder Meeting. January 28, 2010

SENSE - Self Erecting Nacelle and Service System Estimated Cost Savings

RoRo, Cruise and Naval Conversions

Notice of Tariff Change Effective January 1, 2014

Supplemental Pumps Pay Off During Low River Conditions

NOVEMBER Sean Strawbridge, Deputy Executive Director

SHIP TO SHORE PORT INTERFACE

Port Feeder Barge. Floating infrastructure for container ports.

Port Information for Studstrup Power Station

Memorandum. Ports and Harbors Advisory Committee and Planning Commission. Brad Ryan, Director of Public Facilities, Haines Borough

TERMINAL INFORMATION AVONMOUTH, BRISTOL

TRADOC Capability Manager-Transportation Army Watercraft Systems

TARIFF.

IBAU HAMBURG Self-Discharging Cement Carriers

Deepening/Dredging Impact on Navigational Efficiency in the Delaware River Main Channel

CITGO PETROLEUM CORPORATION CORPUS CHRISTI MARINE FACILITY REGULATIONS FOR VESSELS

TERMPOL 3.10 SITE PLANS AND TECHNICAL DATA

PLANNING, DESIGN, and REALIZATION OF AUTOMATED TERMINALS Ashebir Jacob P.E. Senior Port Engineer / Vice President

OFFSHORE TARIFF Valid as per June 1, 2018

Port of Los Angeles Presentation to the Los Angeles Investors Conference March 19, 2018

Dock Doctors. City of Burlington, Lake Champlain, VT Commercial Marina Floating Dock System EXPERIENCE

Ship to Ship Transfer POAC/ Superintendent Crude Oil, Chemicals and Petroleum Products (Bulk Liquids) 3 days

Wharf structures and Quay Deck landing areas, will be built in stages to accommodate the following transport fleet:

W.R. (BERT) ULBRICHT, P.E.

Pre-Fabricated Multi-Apron Steel Ramp

Final Environmental Impact Report

Accommodating Mega-Ships at Existing Wharves

NEWS C OMPANY LEADINGEDGE ENGINEERING

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempĂȘtes PIANC WG 101

Oil Companies International Marine Forum MTIS Programme Terminal TPQ

A Framework for Integrating Planning Activities in Container Terminals

APP 100 th Annual Conference, Redwood City, CA. Presented by Bill Partridge, Manson Construction Co. and Erik Soderberg, Liftech Consultants Inc.

Learn more at

FULL SERVICE PROVIDER IN ON- AND OFFSHORE LOGISTICS AT YOUR SERVICE CORPORATE INFO

CENEX-HARVEST STATES DOCK Superior, Wisconsin

Transcription:

Project Location Agenda Project Background Project Overview Project Challenges Lessons Learned

Project Location Pier T Berth T121

BP T121 Terminal Location

Terminal T121 Is Important to Region BP s No. 1 asset in this region Feeds oil to SOCAL refineries BP Conoco Valero T121 operates 24/7 to maintain refinery output

Project Background Initiated to reduce air emissions in support of the POLB Green Port program T121 terminal considered good candidate for cold ironing Alaska Class Tankers are diesel electric T121 electrical infrastructure already upgraded Cooperative agreement between Port of Long Beach & BP POLB landside improvements BP shipside improvements

Project Overview

Project Challenges Determine electrical design requirements Design cable management system (CMS) Integration of cold ironing into terminal operations Construction constraints Compliance with regulatory agency requirements

Determine Electrical Design Requirements Coordination meetings to identify, understand and resolve issues Project team coordination Port Of Long Beach Staff Consultant BP Local Staff Alaska Tanker Company Consultant Interface between ship and shore

Electrical Design Requirements Determine total required ship power Detailed study was required Breakdown ship electrical load 7.78 MW @.8 PF = 9.73 MVA Limit voltage drops LTC Transformer Bumpless power transfer Control cable Ship control of electrical supply Existing infrastructure Electrical service (SCE) meets cold ironing requirements

Cable Management Design Integrate with terminal operations Accommodate a range of ships Cold Ironed Non Cold Ironed Various methods to handle power & control cables Cable reel and crane on barge Cable reel on ship Cable reel on platform/crane on ship Cable reel and crane on platform

Cable Management Design Selected Option Cable reel on platform crane on ship

CMS Platform Design CMS Platform Positioning Position within reach of ships crane Mooring lines, berthing and fendering Circulation and gangways CMS Interface Considerations Vertical requirements based on: Tidal fluctuations Deep to light draft range of ship Shipside cable tray Vessel Movement Passing vessel Currents Winds

CMS Platform Design - Mooring COMPREHENSIVE TANKER DATA BASE DISPLACEMENT MOULDED DRAUGHT FREEBOARD Manifold Nr. Vessel DWT See Note LOA LBP BEAM DEPTH * TPC from Name * LADEN BALLAST * * * LADEN LADEN Bow (TONS) (TONS) (TONS) m m m m m m m 2398 Nan Hai Xi Wang 174,015 204,026 30,011 293.24 275.00 46.00 24.00 18.60 105.00 5.40 136.86 2399 Enalios Ethra 151,973 179,078 27,105 290.69 275.01 46.00 24.01 16.80 117.35 7.21 2400 Nan Hai Fa Xian 254,642 294,382 39,740 348.91 330.71 51.82 25.58 20.00 157.60 5.58 173.74 2401 Agip Marche 254,650 294,390 39,740 285.79 267.34 51.80 25.60 20.00 157.80 5.60 173.74 2402 Arco Spirit 266,586 307,667 41,081 335.26 323.07 54.31 26.20 20.47 167.30 5.73 160.93 2403 Arco Independence 266,586 307,667 41,081 335.26 323.07 54.31 26.20 20.47 164.70 5.73 160.93 2404 Agios Nikolaos 263,394 304,119 40,725 343.51 330.71 51.88 26.22 20.48 158.03 5.74 170.69 2405 Chevron Edinburgh 268,334 309,610 41,276 338.63 320.00 53.60 26.41 20.56 157.48 5.85 161.54 2406 Alamoot 317,825 364,424 46,599 351.45 336.00 55.40 26.47 20.44 138.78 6.03 159.40 2407 Tonbridge 267,911 309,140 41,229 339.15 324.00 53.50 26.60 20.73 157.50 5.87 168.86 2408 Acquila Trader 260,849 301,289 40,440 338.10 319.99 51.87 26.70 20.90 200.00 5.80 2409 Saudi Splendour 280,579 323,204 42,625 340.79 324.03 54.46 26.99 21.07 162.00 5.92 2410 Myrtos Bay 257,099 297,116 40,017 337.06 320.00 54.50 27.00 19.93 160.10 7.07 153.01 2411 World Champion 273,150 314,959 41,809 337.01 320.00 54.56 27.00 20.02 161.20 6.98 2412 Africa 274,479 316,435 41,956 348.77 330.56 51.82 27.33 21.39 159.00 5.94 165.20 2413 Lyria 277,553 319,847 42,294 343.01 330.72 51.87 27.34 21.36 160.00 5.98 171.25 2414 Mare Discovery 515,700 580,816 65,116 354.55 353.30 56.44 28.42 22.30 172.00 6.12 181.66 2415 Bridgeton 407,823 463,323 55,500 365.99 351.15 70.00 29.10 22.60 228.00 6.50 180.42 2416 Acropolis 554,999 623,381 68,382 381.92 368.80 63.25 35.00 23.41 228.80 11.59 181.36

CMS Platform Design - Mooring

CMS Platform Design - Berthing

CMS Platform - Circulation

CMS Platform - Circulation

CMS Platform - Circulation

CMS Platform Design - Final Layout

Construction Constraints Limited site access & stringent safety requirements Site constraint & safety solutions Specified access requirements based on BP s shipping schedule Specified safety requirements for hazardous area Split project into two construction contracts Provided offsite construction area fabricate and assemble: piles platform, access trestle, catwalk

Construction Constraints Site constraint & safety solutions (continued) Identified anticipated work windows Specified Multiple Mobs & Demobs Enhanced geotechnical investigation Investigated previous studies Performed additional boring program Side scan sonar Diving survey

Regulatory Agency Compliance Unique type of project Several Agencies Involved CA State Lands Commission Compliance with MOTEMS City of Long Beach Planning & Building Codes Requirements USACOE Eel grass, Cleurpa Taxifolia USCG Emergency action plan Ship Classification Agencies Ship side modifications

Lessons Learned Unique challenges of cold ironing on liquid bulk terminals Safety in a hazardous environment Single berth limits construction access Ship control of shore side equipment Additional deep water structures Cable must be lifted to ship Intensive coordination required