City of Moss Landing, CA Sanitary Sewer Flow Monitoring SFE File #C Installation Report. Submitted To:

Similar documents
Wastewater Flow Monitoring Services

Rock River Water Reclamation District

MBARI Sanitary Sewer Analysis Report

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

Plaza Mexico Residences 3000 E Imperial Highway Lynwood, CA KPFF Job #

City of Elmhurst Comprehensive Flooding Plan December 5, 2011

Exhibit A. Scope of Services for Flow Monitoring Program 2015 Flow Monitoring City of Lawrence, Kansas

Section 7 Hydraulic Model Development and Evaluation Criteria

WEF Collection Systems Conference 2017

Basic Design of Replogle Flumes

PRELIMINARY WASTEWATER CAPACITY STUDY

OEPA CSO Overflow Reporting

Regional Hydraulic Model Plan

Appendix J Effluent Pump Station

MWRD Sewer Flow Metering Services

Request for Proposals. City of Elyria. Flow Monitoring and Infiltration/Inflow Field Testing Assistance

SPILL ESTIMATION. Not Just A Guess Anymore

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

Facilities Development Manual

Streamlining I/I Repairs in Berlin Charter Township

Rehabilitating a 105-inch Interceptor Innovations and Lessons Learned

Capacity Assurance in Charlotte s Central Business District

Hey and Associates, Inc.

SANITARY SEWER CHEMICAL GROUTING

Dynamic Hydraulic Modeling of a Wastewater Treatment Plant. City of Fort Worth Case Study

RESOURCE CONSENT CRC174931

City of Gardiner, Maine Wastewater Committee Meeting. CSO Storage Tank & Screening Evaluation

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

May 9, Honorable Jean Pace, Mayor City of Mammoth Springs P.O. Box 185 Mammoth Spring, AR Mammoth Springs WWTP (Fulton Co)

Sump Pumps Office procedures for the Drainage & Grading section

SANITARY SEWER CHEMICAL GROUTING

Agenda. Streamlining I/I Repairs in Berlin Charter Township.. Innovative Techniques

IPP Sampler Flow Pacing. Presented By Darrell Kuta Teledyne-Isco

Monthly Operating Report

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

MSDGC MODELING GUIDELINES AND STANDARDS VOLUME I SYSTEM WIDE MODEL

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Estimation of Parameters and Flow Characteristics for the Design of Sanitary Sewers in Malaysia

CONSTRUCTION PLAN CHECKLIST

Appendix F. Flow Duration Basin Design Guidance

Design and Construction of Local Public and Private Sewers and Ancillary Facilities

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

November 28, Dear Mr. Bechtold:

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Thornton Sewer Plant Operations Manual -DRAFT-

Turbidity-controlled suspended sediment sampling

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###)

Water Measurement Options in Low-Head Canals and Ditches

Infiltration and Inflow. Michael Sassaman Phone

Using Sanitary Sewer I/I Field Data to Calibrate a Storm Sewer Model

RETENTION BASIN EXAMPLE

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

Aqua-Swirl Stormwater Treatment System

Chapter 10. Conduit Outlet Structures Introduction General Layout Information

Preliminary Engineering Report. For the. Foxglove Trail. Prepared for: The City of Moore. Prepared By:

City of Elmhurst Comprehensive Flooding Plan Task Force Meeting

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS

SSO Response Standard Operating Procedures

WASTEWATER REVIEW CHECKLIST. Project Number: Reviewed By: Telephone:

Validation Studies and Beyond: Key Implementation Issues

Featherston Groundwater Infiltration Investigation

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

L3. Design Criteria of wastewater collection system

SSMP ELEMENT 6 Overflow Emergency Response Plan APPENDIX 6.7. Water Quality Monitoring Program

Section 8 System Evaluation and Capacity Assurance Plan (SECAP)

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

Fact-Based Model Validation

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Irrigation Structures 2. Dr. M. R. Kabir

Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel

Wilmette - Background

Measuring flow in open channels (weirs)

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

Inflow & Infiltration Micro Detection

Springfield, MO SSO Control Program: Using Big Data to Chart Progress

System Evaluation and Capacity Assurance Plan

appendix c Sewer area Study

Aqua-Swirl Stormwater Treatment System

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR

Municipal Sanitary Authority of the City of New Kensington

Sanitary Sewer. Infiltration & Inflow (I/I) Study. Presented by:

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:

September 23, Mr. Tony Bass Tri-City Utilities Wastewater Treatment Plant P.O. Box 84 Peach Orchard, AR RE: Compliance Inspection

If I can be of any assistance, please contact me at or (479) extension 16.

16. Design of Pipeline Structures.

CLAY STREET BRIDGE REPLACEMENT

1. Overview 2 2. Definitions 2 3. Laboratory Testing Criteria 2. A. Laboratory Qualifications 2. B. Analysis of TSS Samples 2. C.

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

Temporary Watercourse Crossing: Culverts

Transcription:

City of Moss Landing, CA Sanitary Sewer Flow Monitoring SFE File #C91-01 Installation Report Submitted To: MBARI Attention: Mr. Keith Raybould 7700 Sandholdt Rd Moss Landing, CA 95039-9644 Submitted By: SFE Global NW 4141 Northgate Blvd., Suite 3 Sacramento, California 95834 (866) 332-9876

City of Moss Landing, CA Sanitary Sewer MBARI Installation Report Flow Monitoring 1.0 INTRODUCTION This report provides details of the sanitary sewer flow-monitoring project conducted by SFE Global for the City of Moss Landing, under the direction of Mr. Keith Raybould. Enclosed are the details of the installation of one site under the Temporary Flow Monitoring Study. This site was commissioned and commenced data logging for reporting to MBARI as of November 20 th, 2007. The anticipated duration of this project is two months. Mr. Paul Loving, as Project Manager represents SFE Global during this project. Site # Location Meter and Primary Device Used C91-01-01 Sandholdt Rd SFE Custom Compound Weir w/ ISCO Meter 2.0 MONITORING PROGRAM Prior to installing the flow monitoring station, SFE performed a detailed site assessment of the potential site to determine the most appropriate flow monitoring device in achieving optimal results. Factors such as pipe size, channel condition, site location, and site hydraulics were all considered and documented while performing the site assessment. See Appendix #2 of this report for site assessment details. SFE installed the flow monitoring station in accordance with the approved site assessment documentation. The meter had been calibrated and set to log data at a 5-minute interval. To ensure proper operation of the station, a regular maintenance schedule will be adhered to for the duration of the project. During each site maintenance inspection conducted by SFE, corresponding meter and field readings were obtained and recorded on the field maintenance sheet. These readings provide an indication of the accuracy and operation of the meter. See Appendix #2 of this report for the field report sheets detailing site inspection information, calibrations, and depth verifications. Confined space entry procedures and general site/traffic safety was adhered to during site installation and site maintenance. SFE utilizes the DBI SALA rescue system, a 2800 CFM air induction device and TMX 412 air quality monitors. All of our staff members are thoroughly trained and certified in confined space entry procedures. Certificates are available upon request. A thorough traffic control plan was established and used by SFE Global crews where required. 2.1 SANITARY METER INSTALLATION LOCATIONS Site C91-01-01 Sandholdt Rd: SFE installed a Custom Compound Weir and an ISCO Meter at a depth of 68.5 inches within the manhole to monitor flow from the 350mm pipe. 3.0 FLOW MONITORING RESULT See Appendix #3 for the flow monitoring results from November 21 st to December 20 th, 2007. Flow monitoring will resume for the anticipated two-month project duration.. Report End January 2008 SFE Global C91-01

Appendix 1 Technical Information C91-01 - Installation Report Appx.doc

SFE Global Custom Compound Weirs - A Technical Discussion SFE s Custom Compound Weir Technology was first developed in 1983. This system consists of the following two components: A customized primary device (Custom Compound Weir or CCW), which provides a predictable relationship of "head" versus "flow". A water level sensor and data logger Testing & Awards The relationship between "head" and "flow" for the primary device was initially established in a hydraulics lab in conjunction with the Canadian Centre for Inland Waterways (CCIW) and published in a report prepared for a local utility. In subsequent years the monitoring techniques were further refined and additional laboratory work was carried out for the primary device. In 1988 the Association of Consulting Engineers in their annual national engineering awards program recognized the work with an Award of Merit. Any level sensing device may be used reliably measure flows including ultrasonic level indicators, pressure transducers and floats. The system was designed to make it economically feasible for even small utilities to be able to operate a network of stations for a long duration - the low operating costs & high accuracy/reliability prevailing over other measurement systems. Self-Cleaning The primary device has a rectangular notch, which then flares out into a "V" section and then a rectangular upper portion. The notch and "V" section have chamfered 38 mm thick "lips" which make them self-cleaning and result in a very high weir flow coefficient. The self-cleaning properties of these weirs have been amply field proven over the past 18 years at approximately 2200 such stations. Each of our Custom Compound Weirs is custom designed by an open channel hydraulics specialist for the manhole, chamber or channel configuration it is to be used in. SFE Global: A field Service Engineering Company

Low Flow Accuracy For sewers up to 534 mm diameter the notch is typically 100 mm wide and 140 mm deep. This results in a flow rate of roughly 1.0 l/s for a head of 25 mm. Since a 2.5 psi pressure transducer or narrow beam ultrasonic indicator is usually capable of measuring water levels within +/- ¼, flow rates down to 1.0 l/s can readily be measured (a special unit has previously been designed to measure pre-treated wastewater flow rates down to 0.001 l/s). No Sewer Backups The lower notch magnifies the variation of the water level with small changes in flow rate (e.g. for the base flow regime). The overall primary device or "weir" normally has an opening greater than the pipe cross sectional area and capacities greater than that of the sewer in which they are placed. Any Size, Any Shape SFE has installed custom compound weirs in sewers from 0.15 m to 3.6 m as well as in varying sizes of pond outlets, creeks, WWTP s, etc. Custom designing the primary device for the manhole or channel in which it will be placed means that you have considerable control over the final flow regime. This has allowed many difficult hydraulic situations to be handled including bends, junctions, slopes over 10%, drop connections, and drops in the main pipe invert. Velocity Measurements Not Required One of the major advantages of SFE s Custom Compound Weir is that it only requires a depth sensor and logger; a velocity sensor is not used. Many of the problems associated with sewer flow monitoring are related to the velocity sensor and the need to measure average velocity. Velocity sensors are prone to fouling with subsequent "drifting" of the signal whereas pressure sensors will still accurately register variations in water level even if they have debris on them. No In the flow Probes The use of SFE s Custom Compound Weir further improves the performance of pressure sensors since they no longer represent an effective obstruction in the flow (they are installed behind the weir). They will always have a reasonable "head" on them as the weir lip elevation maintains a minimum depth of 100 mm behind the weir. As pressure transducers are much less accurate when depths approach zero; this situation becomes a problem for Area-Velocity (AV)) type meters in small pipes where base flow rates are low. SFE Global: A field Service Engineering Company

Less Expensive Level only monitors such as those used with our Custom Compound Weir are less expensive than AV meters and need less power to operate. Flow profiling is needed for conventional AV meters to ensure that the velocity sensed at a point or across a band of flow is properly transformed into average velocity across the pipe section. Since the Custom Compound Weir does not use velocity, profiling becomes redundant. High Accuracy Dye dilution and full-scale lab comparisons have been conducted and the results have been excellent. In most cases +/- 5% is readily achievable without special attention. Temporary or Permanent The Custom Compound Weir s are normally located in the manhole chamber about 300 mm from the downstream end. Material Life Expectancy Uses Lumber/Lexan 1 week to several years Short Term (E.g. I/I Study) Plywood Up to 2 years Temporary Pressure Treated Lumber 5 to 8 years Semi-Permanent Lexan and 3/16 Stainless 50 Years Permanent No Surcharges Is there a possibility of sewer surcharges causing basement flooding because of the use of such primary devices or weirs? The question has been raised many times over the past 18 years and was addressed on a project when the Custom Compound Weir was first designed in 1984. The purpose of that first project was to determine the cause of persistent sewer related basement flooding. The client was very concerned that the study procedures did not create more flooding since two Custom Compound Weir stations were just downstream of the area receiving the flooding. The design and placement of the Custom Compound Weirs addressed this as follows: Each CCW was located in a manhole and not in the pipe, approximately 300 mm from the downstream end so that if the weir were to ever get blocked it could simply overflow safely. (This event has never occurred). For manholes with a chamber larger than the pipe (i.e. 450 mm pipe in standard 1065 mm manhole), the weir opening is greater than the pipe area. The flow over the weir is also at critical depth and therefore at a higher velocity than normally occurs in the pipe itself. As a result, the weir capacity is much greater than the pipe capacity in most installations. SFE Global: A field Service Engineering Company

A rating curve was provided for a demo weir that has the standard opening used in pipes up to 450 mm. Table 1 below shows the flow capacity of this weir configuration at selected heads versus the full flow capacity of selected pipe sizes up to 450 mm at a 0.25 % grade. The comparison illustrates that the CCW capacity can be much greater than the pipe capacity. Flow Capacity of Standard Small Pipe Configuration at Selected Heads Full Flow Capacity of Selected Pipes @ 0.25 % Grade Head (mm.) Flow (l/s) Pipe Diameter (mm.) Capacity (l/s) 25 1 200 16 140 12 250 30 200 22 300 48 318 63 380 88 508 145 450 143 610 230 Laboratory Tested Hydraulic model testing conducted at the Canada Centre for Inland Waters, provided the opportunity of observing the pipe / weir / manhole performance as the flow rates in the system were increased to the point that it surcharged. As the system started to surcharge, the control shifted from the weir to the downstream pipe and there was essentially no drop in the water surface across the weir (i.e. under surcharge, the weir was not influencing the water levels upstream). Custom Designs Every Custom Compound Weir is custom designed with a rectangular low flow notch and chamfered lips to give it a high weir flow coefficient. This means that it passes a greater flow for a given head than normal sharp crested weirs. Custom designed means specific concerns are addressed at specific sites. SFE Global: A field Service Engineering Company

Appendix 2 Site Information Including Photos & Field Reports C91-01 - Installation Report Appx.doc

Site Assessment CLIENT FLOW MONITORING #: 1 SFE PROJECT #: NAME: MBARI SFE SITE #: Date / Time: 11/20/07 8:46 AM C91-01 C91-01-01 Project Specific Information Client Name: MBARI End User Name: MBARI Project Name: Sanitary Sewer Flow Monitoring Client Contact: Keith Raybould (831) 775-1828 Field Contact: Art Frolli (831) 755-4950 SFE PM Contact: Paul Loving (604) 992-6792 Site Equipment Install / Remove Date: 11/20/07 Meter Make & Model: ISCO 2150 Level Type: Pressure Velocity Type: Average Primary Device: Weir Wireless: No Redundancy: No Logging Rate: 5 Min Site Location Information Site Profile Client Manhole #: Address (Location): Sandholdt Rd Pipe #1 Size: 4 Inches City, State: Moss Landing, CA Pipe #2 Size: 6 Inches GPS (North - West ): N 36 47.970 W 121 47.223 Pipe #3 Size: 8 Inches Landmarks: Just East of Bridge Pipe #4 Size: N/A Inches Additional Information: Manhole Depth: 68.5 Inches Map of Area Laterals / Rungs: Additional Information: No No Manhole Layout 1 2 3 Traffic Control Requirements Provider: County Date & Time: Condition Local Depth: Frequency: Install / Maintenance / Removal Velocity: Speed Limit: 25 MPH Turbulent: # of Lanes Effected: 2 Surcharge: Lane Configuration: Road Silting: Additional Information: In middle of Road Solids: Notes Notes 1 Set up secondary level/flow logging rate. If Level is greater than 4" to log every 30 seconds. 2 3 Site Hydraulics 11/20/07 8:46 AM 0.25 Inches 0.5 FPS Yes No No No Down Stream of Lift Station. Very high levels of H2S inside Manhole. N Revision 3.1

Site Pictures CLIENT FLOW MONITORING #: 1 SFE PROJECT #: NAME: MBARI SFE SITE #: Date / Time: 11/20/07 8:46 AM C91-01 C91-01-01 Picture 1 Picture 2 Picture 3 Picture 4 Notes 1 2 3 Revision 3.1

CCW Installation Form CLIENT FLOW MONITORING #: 1 SFE PROJECT #: C91-01 NAME: MBARI SFE SITE #: C91-01-01 Date / Time: 11/20/07 11:45 AM Technician 1: Technician 2: Matt Smith John Garcia Meter Depth vs.. Field Depth Calibration / Verification Reading Date Time Field Meas Number (in.) Initial 11/20/2007 12:05 0.250 1 2 11/20/2007 11/20/2007 12:06 12:08 0.250 0.250 3 11/20/2007 12:12 0.250 Meter Depth (in) 11.820 0.230 0.220 0.190 Comments Pre Adjust (Zero Meter Level before Installation) Average 0.250 0.210 * Three Continuous Measurements Within 0.5 Inches * Average Meter vs (WL1 and WL2) Within 5% Manhole Depth (in) (D2+D3) 68.500 56.500 D1+ D2 = CNST 39.875 D2 Pipe Diameters (in) Pipe 1 4 Pipe 2 6 Pipe 3 8 Pipe 4 N/A Weir Size 350mm D4=Invert to Weir Lip (D3-D1) 28.625 D3 16.625 D1 12 Obvert to Weir Lip N/A 12.000 D4 Revision 3.1

Appendix 3 Site Summary Including Hydrograph C91-01 - Installation Report Appx 3.doc

City of Moss Landind, CA C91-01-01 SFE CCW w/isco Meter Sandholdt Rd November 21 to December 20, 2007 Flow 90.00 80.00 70.00 60.00 Flow (gpm) 50.00 40.00 30.00 20.00 10.00 0.00 20-Nov-07 25-Nov-07 30-Nov-07 05-Dec-07 10-Dec-07 15-Dec-07 20-Dec-07

City of Moss Landing C91-01-01 SFE CCW w/isco Meter Sandholdt Rd November 21 to December 20, 2007 Level 3.50 3.00 2.50 Level (in) 2.00 1.50 1.00 0.50 0.00 20-Nov-07 25-Nov-07 30-Nov-07 05-Dec-07 10-Dec-07 15-Dec-07 20-Dec-07

City of Moss Landing, CA C91-01-01 SFE CCW w/isco Meter Sandholdt Rd November 21 to December 20, 2007 Date Avg Flow Min Flow Max Flow Total Flow (gpm) (gpm) (gpm) (mgd) 21-Nov-07 15.43 1.03 72.03 0.022 22-Nov-07 8.90 1.26 75.86 0.013 23-Nov-07 14.49 1.19 74.76 0.021 24-Nov-07 15.45 1.19 72.57 0.022 25-Nov-07 12.47 1.29 73.35 0.018 26-Nov-07 14.28 1.48 72.92 0.021 27-Nov-07 14.96 1.52 74.75 0.022 28-Nov-07 21.55 1.86 76.16 0.031 29-Nov-07 25.94 2.49 79.98 0.037 30-Nov-07 21.33 2.01 82.10 0.031 01-Dec-07 15.64 0.21 74.80 0.023 02-Dec-07 12.93 1.51 72.85 0.019 03-Dec-07 13.31 1.17 69.65 0.019 04-Dec-07 14.22 1.12 69.89 0.020 05-Dec-07 16.60 0.85 71.04 0.024 06-Dec-07 18.61 1.91 74.75 0.027 07-Dec-07 18.44 2.13 77.22 0.027 08-Dec-07 21.60 2.65 78.58 0.031 09-Dec-07 16.50 2.81 77.54 0.024 10-Dec-07 16.68 2.92 75.69 0.024 11-Dec-07 18.06 2.97 77.99 0.026 12-Dec-07 18.59 3.06 76.77 0.027 13-Dec-07 19.45 2.41 76.29 0.028 14-Dec-07 20.47 2.56 75.66 0.029 15-Dec-07 17.84 2.71 74.20 0.026 16-Dec-07 15.04 3.00 73.65 0.022 17-Dec-07 22.20 2.85 75.03 0.032 18-Dec-07 23.42 2.80 73.82 0.034 19-Dec-07 19.45 2.96 75.02 0.028 20-Dec-07 18.77 3.02 75.67 0.027 Statistics Total Flow Min Flow Max Flow (mg) (gpm) (gpm) 0.753 0.210 82.100