MONTHLY UPDATE PRIMROSE OIL SANDS FLOW TO SURFACE

Similar documents
MONTHLY UPDATE PRIMROSE OIL SANDS FLOW TO SURFACE

MONTHLY UPDATE PRIMROSE OIL SANDS FLOW TO SURFACE. January 10, 2014

MONTHLY UPDATE REPORT - PRIMROSE SOUTH W4M SEPTEMBER 22 TO OCTOBER 19, 2015

MONTHLY UPDATE REPORT - PRIMROSE SOUTH W4M AUGUST 19 TO SEPTEMBER 22, 2014

GROUSE GROUSE IN SITU OIL SANDS PROJECT. Proposed Development Plan. Plain Language Project Summary

MONTHLY UPDATE REPORT - PRIMROSE SOUTH W4M MAY 19 TO JUNE 22, 2015

Conservation and Reclamation INFORMATION LETTER. Environmental Protection Guidelines for Oil Production Sites - Revised January 2002

Cold Lake expansion project

Let s talk. About everything. Let s put it all on the table. Every sustainable solution, every safety practice, every infrastructure decision we want

Order. -AI1ta. Energy Regulator. MADE at the City of Fort McMurray, in the Province of Alberta, on

Water - policy and government regulation for heavy oil and oilsands development

Shell Canada Limited. Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No

Minimal Disturbance Brine Water and Oil Emulsion Spill Response in Northern Boreal Peatland Settings

Minimal Disturbance Brine Water and Oil Emulsion Spill Response in Northern Boreal Peatland Settings

Substation Developments Environmental Guidelines Checklist for Applicants

Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation

APPENDIX D 2017 PHOTO ESSAY

FORM 001-A Suspension and Abandonment Cost Estimate Report

atertech Banff, AB. April 29-May 1, 2009

Peatland Restoration. Environment and Sustainable Resource Development

Section 1 Project Introduction

Murphy Oil Operations in the PEACE RIVER AREA

IN THE MATTER of a CONTRAVENTION. of the OIL AND GAS ACTIVITIES ACT. [SBC 2008] Chapter 36. Before. The BC OIL & GAS COMMISSION. Case File

Groundwater Supply Development at Canadian Natural Resources Limited s In Situ Oil Sands Operations

Telephone Lake project

In-Situ Remediation of Brine Impacted Soils and Groundwater Using Hydraulic Fracturing, Desalinization and Recharge Wells

TABLE OF CONTENTS. Page

Preliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and

LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012

Effective June 17, 2013, the Energy Resources Conservation Board (ERCB) has been succeeded by the Alberta Energy Regulator (AER).

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES

Water Recycling Hydraulic Fracturing, Remote Surface Locations. Tyler Bittner

Meadow Creek West. Project overview:

SHELL ONSHORE OPERATING PRINCIPLES

Environmental Assessment, Reclamation and Exploration

Informational Letter IL 98-2

The Facts on Oil Sands Reclamation. By: Don Thompson July 31, 2008

Seal Main HCSS Pilot Subsurface Review

Code of Practice for Land Treatment of Soil Containing Hydrocarbons

50% $3 BILLION CAPTURE 3.5 TAILINGS MANAGEMENT OF TAILINGS FINE PARTICLES IN DEDICATED DISPOSAL AREAS BY 2015 INVESTMENT TO MANAGE TAILINGS

Integrated Surface Water and Groundwater Modelling for Oil Sands Reclamation

Incident Reporting Requirements

Jackfish 2 Project. Public Disclosure Document. August 2005

Alberta Transportation The City of Edmonton The City of Calgary

RISK MANAGEMENT OF A FORMER SALT STORAGE YARD

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

Presentation to the Oil Sands Multi-stakeholder Committee Bonnyville, September 13, 2006

Remediation Certificate Application for Upstream Oil and Gas Sites

Case Study: Remediation of Lead Impacted Soils Former Strathcona Shooting Range, Edmonton

In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project

Land Use Framework and Regional Planning Update

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION

JAPAN CANADA OIL SANDS HANGINGSTONE SAGD PROJECT

EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference. D. Glen Snarr, President & CFO September 21, 2006

Environment Canada Alberta Environment and Water March 2012

SECURE Energy Services Inc. Proposed Conklin Class II Landfill Portions of: NE W4, SE W4 and NW W4

Under Section 113 of the Environmental Protection and Enhancement Act

BEST OPERATING PRACTICES: Hydraulic Fracturing

Bill Richardson Governor. Highlights of the Pit Rule NMAC

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

Grizzly Oil Sands ULC

Environmental. Performance

Seal Main HCSS Pilot Approval Annual Performance Presentation

IN THE PROVINCIAL COURT OF ALBERTA CRIMINAL DIVISION HER MAJESTY THE QUEEN. -and- MCCOLMAN & SONS DEMOLITION LTD.

Section 1 - Introduction

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Assessment of Environmental Liabilities of Historically Reclaimed Sites

Reclamation: Legislative / Regulatory Requirements

Brownfield Re-use + Sustainable Remediation = Sustainable Development

Alberta Regulations: Wellbore Integrity Issues Driving Regulatory Change

October Published by. Energy Resources Conservation Board Avenue SW Calgary, Alberta T2P 3G4

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

Manitoba s Submission Guidelines for Peatland Management Plans

Manitoba s Submission Guidelines for Peatland Recovery Plans

Liberia REMEDIATION AND DISPOSAL OF SULPHUR CONTAMINATED SOLID WASTES. May 1996 GUIDELINES FOR THE ENVIRONMENT

NOTICE OF A PROPOSED CHANGE TO AN APPROVED DEVELOPMENT

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED HORIZON NORTH PIT EXTENSION PROJECT

Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation

Page 1 of 6 Permit No: MN R J. Mineral Mining and Dressing

PROTOCOL FOR THE MONITORING OF DRILLING-WASTE DISPOSAL SUMPS Inuvialuit Settlement Region Northwest Territories

MULTIPHASE APPROACH TO REMEDIATION USING SUBSURFACE FRACTURING, SURFACE EXTRACTION AND MODIFIED FENTON CHEMISTRY

ENVIRONMENTAL SCREENING REPORT

NORTHWEST TERRITORIES WATER BOARD

The last update was March 4, 2016.

Port Granby Project Fall 2017

Site C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017

Canadian Natural Upgrading Limited

APPENDIX E HORIZONTAL DIRECTIONAL DRILL EXECUTION PLAN

Aggregate, Landscapes and Watersheds: A Brief Overview

Options Evaluation for Remediation of the Gunnar Site Using a Decision-Tree Approach. T.L. Yankovich and A. Klyashtorin

PERFORMANCE OF AN ENGINEERED COVER SYSTEM FOR A URANIUM MINE WASTE ROCK PILE IN NORTHERN SASKATCHEWAN AFTER SIX YEARS

Environment and Sustainable Resource Development. Supplement Instructions Enhanced Approval Process (EAP)

Recovery Process - Cold Heavy Oil

Stage 4 Geotechnical Investigations Information Sheet

Appendix 9 Consultation

Kearl Kearl Oil Sands Project Project Description November 2003

Draft. Scope of Work. Task 1 RCRA Facility Investigation and Corrective Measures Study

Details of the Proposed Action

SHALE FACTS. Production cycle. Ensuring safe and responsible operations

Transcription:

1 Introduction MONTHLY UPDATE PRIMROSE OIL SANDS FLOW TO SURFACE March 3, 2014 Primrose/Wolf Lake Oil Sands Project (PAW) is a thermal in situ operation located approximately 65 km north of Bonnyville and about 350 km northeast of Edmonton, primarily inside the Cold Lake Air Weapons Range. The approved project area covers 288 sections or 73,728 hectares. Bitumen production from this project employs cyclic steam stimulation (CSS) technology whereby steam is injected into the oil sands formation (at approx. 500 metres depth) through wells to reduce the viscosity of the bitumen. After steaming, bitumen then flows through the same wells and is processed at project facilities. In May and June of 2013, Canadian Natural discovered four sites in the Primrose project area where bitumen emulsion had flowed to surface (FTS). Measures were immediately taken to address the incidents in order to clean up, investigate, remediate and address the causes of the events. The legal descriptions of the four FTS sites are: 02-22-067-03 W4M (2-22) 10-01-067-03 W4M (10-1) 10-02-067-03 W4M (10-2) 09-21-067-04 W4M (9-21) The prompt and thorough management of environmental impacts is of the highest priority for Canadian Natural. In the Primrose/Wolf Lake Oil Sands Project flow to surface incident, the most immediate concern was the containment and clean-up of the bitumen emulsion from the terrestrial and aquatic environments. Also of urgent concern was managing the impacts to wildlife, soil, water quality, and vegetation. The land disturbances associated with the Primrose flow to surface incident will be reclaimed and restored. This includes the surrounding areas and any disturbances associated with the investigation of the incident (roads, well sites, equipment storage, etc.). All aspects of environmental response and management are the responsibility of Canadian Natural and subject to the oversight and regulation of provincial and federal authorities. Canadian Natural is working with the Alberta Energy Regulator (AER) and Alberta Environment and Sustainable Resource Development (AESRD) to investigate and remediate the affected locations and investigate the root cause of the bitumen emulsion seepage to surface. We appreciate AER and ESRD s ongoing support as we continue to manage these events. In the fall of 2013, Canadian Natural evaluated the best technical approach to access the fissure below the shallow water body at the 9-21 site. In consultation with AESRD, multiple options were considered. Canadian Natural decided the best option was to move the water from its original position and temporarily store it in two near-by locations, allowing access to the underlying fissure. 1

The water is scheduled to be returned from its temporary storage locations to its original position in the spring of 2014. This technical option was chosen as it would be the least environmentally impactful and provide the best approach to contain the entire fissure. You can find weekly photographs documenting this process on our corporate website, at www.cnrl.com. The best regulatory option to do this work in a timely manner was through an Environmental Protection Order (EPO-2013-33/NR), which we requested and then received on September 24, 2013. The requirement to conduct this work prior to freeze-up was also an essential component of pursuing this regulatory option. Monthly progress reports can be on our corporate website, at www.cnrl.com. Our efforts to date focused on ensuring each surface location is secured, and that recovery and reclamation activities progress. In August 2013, we began applying for approvals to advance our investigation and requested an Enforcement Order. On October 21, 2013 we received the Enforcement Order (EO-2013/05-NR) that allows us to continue mitigation and investigation activities. Canadian Natural s plan consists of eight separate plans requiring AESRD and AER approval prior to any earthworks or drilling activity, as described below. Investigative drilling is ongoing and will continue throughout the winter season. 2 Summary of Activities to Date 2.1. Surface Site Containment, Delineation and Remediation Plan This plan covers site containment, delineation and remediation plans for each site. The bitumen surface releases at all sites are fully contained within clay berms. Clean-up is complete on 3 terrestrial sites and 92 per cent complete at 9-21. Bitumen emulsion recovered to date: 1,177m3 as of February 17, 2014. Current seepage rate: less than 1m3/month from all sites. Status at each site: 2.1.1 2-22 (Terrestrial Site) Discovered June 8, 2013. Clean up is complete and 7,396 tonnes of impacted material have been removed for disposal at the Tervita Class II landfill in Bonnyville, Alberta. Bitumen emulsion impacted area is 0.31 hectares. Under the Enforcement Order we have been approved to conduct investigative activities in a 26 hectare area. We may not use the entire area, and as of March 4, 2014 we have developed on 9.8 hectares. 99m3 of bitumen emulsion has been recovered as February 17, 2014. Bitumen emulsion seepage from the fissure has slowed to an almost imperceptible rate and is contained within clay berms. Construction of the investigative areas began early January and is ongoing. Construction of the fissure containment structure and drilling pad is complete. Reclamation will be initiated on a portion of the 2-22 site this winter. 2

2.1.2 10-1 (Terrestrial Site) Discovered May 20, 2013. Clean up is complete and 25,394 tonnes of impacted material have been removed for disposal at the Tervita Class II landfill in Bonnyville, Alberta. Bitumen emulsion impacted area is 0.55 hectares. Under the Enforcement Order we have been approved to conduct investigative activities in an 8 hectare area. We may not use the entire area, and as of March 4, 2014, we have developed on 4.1 hectares. 350 m3 of bitumen emulsion has been recovered as of February 17, 2014. Bitumen emulsion seepage from the fissure has slowed to an almost imperceptible rate and is contained within clay berms. Construction of the fissure containment structure and drilling pad is complete. 2.1.3 10-2 (Terrestrial Site) Discovered May 20, 2013. Clean-up is complete and 17,410 tonnes of impacted material were removed for disposal at the Tervita Class II landfill in Bonnyville, Alberta. Bitumen emulsion impacted area is 0.57 hectares. Under the Enforcement Order we have been approved to conduct investigative activities in a 37 hectares area. We may not use the entire area, and as of March 4, 2014 we have developed on 12.5 hectares. 559 m3 of bitumen emulsion has been recovered as of February 17, 2014. The rate of bitumen flow has slowed to an almost imperceptible rate and the fissures are contained within clay berms. Construction of the fissure containment structure and drilling pad is complete. 2.1.4 9-21 (Water Body Site) Discovered June 24, 2013. The impacted area has been reduced from 20 hectares to less than 6 hectares and cleanup is 92% completed as of February 17, 2014. Under the Enforcement Order we have been approved to conduct investigative activities in a 28 hectare area. We may not use the entire area, and as of March 4, 2014 we have developed on 5.8 hectares. Bitumen emulsion seepage from the fissure has slowed to an almost imperceptible rate and is contained within clay berms. 170 m3 of bitumen emulsion has been recovered as of February 17, 2013. On September 24, 2013 we received an Environmental Protection Order for the 9-21 site to allow us to isolate, excavate and contain the fissure below the water body. To facilitate this work, the water from the area was removed and stored in two near-by, temporary storage areas. Work is currently underway to remove impacted soil from beneath the water body. The flow to surface will be contained within berms and a retaining wall. The retaining wall plan was approved by AESRD late January and construction of the retaining wall is underway. The water will be returned to the water body in spring of 2014 as per Alberta Environment and Sustainable Resource Development s requirements. Fencing and berms around the 9-21 site are being inspected weekly 3

2.2. Geology and Regional Ground Water Delineation, Monitoring and Remediation Plan This plan covers ground water delineation, monitoring and remediation in and around the FTS sites. The plan was approved by AESRD December 9, 2013. A multi stage groundwater drilling investigation is planned for all 4 sites. Construction of the fissure containment structures and drilling pads on the 3 terrestrial sites is complete. Canadian Natural received approval from AESRD for additional area required at 9-21 to accommodate the drilling/installation of additional down gradient monitoring wells. As of February 14, one borehole and one hydro monitoring well have been drilled at the 2-22 FTS. As the containment structures and drilling pads are now prepared, several monitoring wells will be installed in February/March in accordance with the Ground Water investigation Plan. 2.3. Source/Flow Pathways Investigation Plan This plan outlines the investigation activities that will be undertaken at and around the four FTS sites and may be adapted depending on the outcome of the investigation activities. The objectives of the plan are to locate and delineate the FTS flow path from its source in the Clearwater, and identifying the root cause(s) of FTS. The plan was approved by AESRD December 9, 2013. 14 Cretaceous investigation wells were drilled between January 15 - February 14. We have performed remedial operations on 6 abandoned wellbores in the area. Currently we have have four drilling rigs drilling cretaceous investigation wells. Construction of the fissure containment structures and drilling pads on the terrestrial sites is complete. Site preparation at the 9-21 site is ongoing. 2.4. Surface Water Management and Monitoring Plan This plan covers site surface water management and monitoring plans for the FTS sites. In general, surface water was managed and monitored at the FTS sites through the following measures: Precipitation between January 25 and February 17, 2014 was in the form of snow rather than rain; therefore, no surface water quality sampling was undertaken. Water management in terms of surface water diversion and collection during excavation at the 10-1, 10-2 and 2-22 sites did not occur during the February reporting period. This was mainly due to the presence of fissure containment structures and drilling pads that have filled the previously open excavations. Between January 25 and February 17, 2014, 22 m3 of water was collected in small depression areas at the 9-21 site and removed by vacuum truck for disposal. Once thawing begins and water is again encountered, it will be tested and hauled away for disposal or pumped into the borrow pit adjacent to the 9-21 water body. 2.5. Wildlife Management Plan This plan addresses wildlife deterrents, capture and treatment of impacted wildlife and rehabilitation/release options. 4

Wildlife deterrents have been removed from the terrestrial sites as the containment structures and drilling pads are complete. Wildlife activity in the vicinity of the FTS sites continues to be minimal due to the freezing conditions and snow. Additionally, frozen conditions at each location have helped to minimize the risk of wildlife exposure to possible contamination. Canadian Natural will comply with all federal and provincial legislation that apply to the conservation and management of wildlife. Winter tracking surveys have been completed at all 4 FTS sites and there is no indication of Caribou in the areas. Spring wildlife deterrents for use at the 9-21 site will be installed in March, 2014. 2.6. Waste Management Plan This plan outlines the waste management activities that will be undertaken by Canadian Natural at the 4 FTS sites. The Waste Management activities may be adapted as the needs of the investigation and clean-up change, which will be shared with AESRD and AER. It is Canadian Natural s goal to manage the waste resulting from this bitumen release in a manner that will mitigate environmental impact, minimize waste volumes and utilize recycling opportunities where possible. Drilling waste from investigation drilling is being managed using remote sumps in accordance with Directive 50. 2.7. Reclamation Plan While the final reclamation plan will not be submitted to AESRD/AER until June 2014 (in accordance with Enforcement Order EO-2013/05-NR), the initial plan covers Pre-Disturbance Assessments (PDA) and Conservation and Reclamation plan. The purpose of the PDA and C & R plan is to identify: Annual reclamation procedures and progress reporting will begin November 1, 2014 and continue annually until advised otherwise by AESRD. No update for this reporting period. 2.8. Communications Plan This plan summarizes our planned weekly and monthly communication with stakeholders, regulators, Government officials and the general public. Canadian Natural s website will be updated on a regular basis. We will continue to address government, media and public inquiries. We will provide written summaries and meet with stakeholders as needed to provide updates. 5

3 Summary Significant progress on the surface clean-up has been made at all four sites. While the surface clean-up can mitigate the environmental impact of these events, there are also issues that need to be investigated in the subsurface. Canadian Natural s efforts to investigate and mitigate these events in the subsurface require access to suitable surface locations. To minimize the environmental impact associated with the investigation, Canadian Natural intends to complete activities on existing leases and previously disturbed lands wherever possible. 6