Structural Breadth Study

Similar documents
The building on 250 West Street is a 7-story multi-use that provides space for parking,

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS

Pro-Con Structural Study of Alternate Floor Systems

Metal Fabricators. Phone DAKA (3252) Fax Serving the Construction Industry and Manufacturers Since 1977

DIVISION 5 - STRUCTURAL STEEL AND IRON WORK

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Abington Memorial Hospital

SECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing.

COURTYARD INFILL STRUCTURE DESIGN

MINIMIZATION OF EXPANSION ANCHORS FOR DESIGN SIMPLICITY AND CONSTRUCTABILITY

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.

JONES AIRWAY, LLC CLEVELAND REGIONAL JETPORT SECTION STRUCTURAL STEEL

Temecula Medical Center Temecula, CA

DIVISION 5 METALS SECTION STRUCTURAL STEEL

ANALYSIS 2 PREFABRICATED FAÇADE

1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.

LIGHT-GAUGE PANELIZED WALL SYSTEMS. Michael Waggoner Mark Schroeder

Analysis 2 Pre-fabricated Metal Stud Crete Panels-Structural Breadth

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider

DIVISION 5 METALS COLD FORMED METAL FRAMING Structural Metal Stud Framing

STEEL STRUCTURAL SYSTEMS

HOW TO. ESTIMATE the COST CONTENTS O F S T R U C T U R A L S T E E L ROBERT R. BONENFANT, JR. - JULY RATIOS AND ANALYSIS Main CSI Division

Installing metal decking, curtain walls, window walls, siding systems, miscellaneous metals, ornamental iron, and similar materials; and

Guide for Inspecting Metal Building Systems. First Edition

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

ITEM 442 METALS FOR STRUCTURES

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

1.02 SYSTEM DESCRIPTION

Case Study of Mercy Health Partners St. Vincent Regional Heart Center. Copyright. Step 1: Design Team Formation

SECTION STRUCTURAL STEEL FRAMING

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING

Research Facility Core and Shell (RFCS) Presented by Tim Maffett on April 8 th, 2013

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1

1.02 SYSTEM DESCRIPTION

SECTION COMPOSITE METAL DECKING

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2

DIVISION 5 METALS BUSHEY FEIGHT MORIN ARCHITECTS INC. 473 NORTH POTOMAC STREET HAGERSTOWN, MARYLAND FAX:

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E.

TECH REPORT 3 SANTA ROSA JUNIOR COLLEGE STUDENT CENTER. Alternative Methods Analysis. Dan Vallimont 2009 SENIOR THESIS

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

Thesis Proposal December 5, 2003

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

Steel Expansion. Located along the Grand River in

Thesis Proposal. Matthew R Peyton

Abington Memorial Hospital Abington, PA. Project Description

Structural Breadth. Landmark Façade

East Central College

SECTION STRUCTURAL STEEL

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM):

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Mansfield University Dormitories Mansfield, Pennsylvania

Project Address: Name of Person Completing Form:

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS

Structural Steel: An Industry Overview

2941 Fairview Park Fairview Park. Eric Sobel. Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE # 5A Metal and Structural Steel 09/01/11

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

Penn State Health and Human Development Building State College, PA

POINT. Making the. The highlights of High Point University s newest academic building are comprised of open volumes, and steel makes them happen.

Analysis and Design of a High Rise Steel Braced Frame Core 60

SE APPRENTICE. Today s Speakers. Lateral Load Systems. Lateral Loads

Concrete weighs about 150 pounds per cubic foot

UC Denver Guidelines and Design Standards SECTION STRUCTURAL METAL FRAMING

MULTI-RESIDENTIAL BUILDING SOLUTIONS

SECTION ALUMINUM WALKWAY COVERS. A. The requirements of Division 1 specifications shall apply to work specified in the section.

STATEMENT OF SPECIAL INSPECTION FORM

SPECIFICATIONS Section Cantilevered Walkway Cover

Best Buy Corporate Building D (4) Richfield, MN

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

Statement of Special Inspections 2013 CBC

SECTION COLD-FORMED METAL FRAMING

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

Home Depot Page 1 of 5 HDPB Humacao, PR 10/19/09

Thesis Proposal. Office Building. Sayre, PA. Faculty Advisor: Dr. Thomas E. Boothby Revised: January 9, 2013

DIVISION 5 METALS SECTION METAL DECKING

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

Thesis Proposal. Office Building. Sayre, PA. Faculty Advisor: Dr. Thomas E. Boothby Revised: April 1, 2013

SECTION PRE-ENGINEERED METAL BUILDING

Item 442 Metal for Structures

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014

Connection Design Assistance Manual

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

Potential Solutions- Background: Current Designs. Potential Solutions. Goals for Design What are we concerned about?

Introduction to Cambering

TECHNICAL ASSIGNMENT THREE

SECTION MISCELLANEOUS METALS

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

LAPEYRE STAIR PRODUCT LINE

Special Inspection Requirements for Occupancy Permits

INSTRUCTIONS AND GUIDELINES

. SECTION HANGERS AND SUPPORTS

A-BEAM W Erection Manual 2

SECTION NON-STRUCTURAL METAL FRAMING

A-BEAM S Erection Manual 2

Chuck Brooks, P.E., P.Eng. C&S Engineers

Special Delivery. A California healthcare complex takes structural engineering collaborative design and integrated project delivery to new heights.

Daytona Beach Pier Building Renovation Jun 2010

Transcription:

Structural Breadth Study Connection Redesign

Structural Breadth Study Connection Redesign Existing EIFS Connection The expansion project is a steel frame structure with concrete slab on deck. There is a total of 2200 tons of steel to be erected on the building over a scheduled duration of 22 weeks. A tower crane was placed in the center of the building, inside the main atrium. This was the most logical location for the crane, as it is mostly open space. The budgeted amount for the steel contract is $6.03 million. One important aspect that had to be considered by the designer was how the Exterior Insulation Finish System (EIFS) was going to be attached to the structure of the building. EIFS is used for most of the exterior finish of the hospital. The majority of the EIFS panels are being installed in 27 or 28 sections. The panels are attached to 6 steel studs with mechanical fasteners. Figure 5 below shows a detail of the attachment of the EIFS panels to the structure of the building. The existing detail contains two sets of double channels connected to two 5/16 plates. These plates are bolted to the double channels with a total of six bolts and welded to the W14 beam and the tube steel. The entire assembly was created onsite by the steel erectors. Figure 5: Existing Connection Design There are several disadvantages to constructing this detail. The two sets of double channels are excessive and more difficult to install; two pieces take longer to erect than one. The two 5/16 plates must be welded on the top and the bottom of the channels, which takes a lot of time. The connection is located below the 25 of 97

concrete floor and must be accessed from the floor underneath. This would require ladders or lifts, which are inconvenient for the erectors and welders. This connection is inefficient in terms of erection time and labor costs. The connection typically occurs every 27 around the perimeter of the building on several floors. There are 200 occurrences of this detail. The steel erection of the building took 22 weeks to complete, per contract. However, an additional 16 weeks of work was required to complete miscellaneous steel bolt up, welding, and bracing. Proposed EIFS Connection In order to improve the efficiency of the steel erection process, an alternative to this detail will be examined. The proposed design aims to reduce erection time by reducing the number of pieces and the amount of welding. A detail of the proposed connection design is shown in figure 6. The main difference between the existing detail and the proposed detail is the number of pieces in the connection. While the existing included 6 pieces to be installed between the W shape and the tube steel, the proposed design only requires 4. This makes a significant difference in terms of erection time, given that there are 200 of these connections. Another significant difference between the designs is the connections of the pieces. The proposed detail requires less welding than the original and fewer field installed bolts. Normally, fastening bolts takes less time than welding these pieces together. Figure 6: Proposed Connection Design In addition to reducing the number of members, the proposed design will have Angle A, Angle B, and the 5/16 plate prefabricated in the shop prior to delivery. Prefabricating these pieces will significantly reduce the erection time of this process. It will also save money in labor costs for welders and steel erectors. There will be an additional cost for prefabrication and delivery, as they will be more difficult to deliver prefabricated pieces than the individual pieces. 26 of 97

The alternative design allows for the same amount of adjustment available in the original. In fact, the connection would be easier to adjust, as there are fewer pieces and fewer connections. The dimensions of the pieces do not change from one design to the other; the only aspect that has changed is the shapes of the pieces. There is no reduction in the structural integrity of the connection. The design calls for ASTM A 325 bolts. The bolts are to be used to hold the pieces in place and to allow for any adjustments to be made. Once the prefabricated pieces are in place, the pieces would be welded in their final position. Below is a comparison of the connections. Full images of the connection can be found in Appendix D. Analysis Results Figure 7: Existing and Proposed Steel Connection A cost analysis was performed to determine the advantages of the proposed design. The majority of the cost savings are in labor, as the proposed design takes much less time to erect. A total of $566 was saved off the budget, along with 6 days on the duration of this activity. The results of the analysis are in figure 8, below. A more detailed analysis can be found in Appendices E and F. 27 of 97

Cost Labor + Material + Delivery + Prefab Existing: $5,130 + $8,558 + $389 + N/A = $14,077 Proposed: $1,710 + $7,591 + $1,035 + $3,174 = $13,511 Schedule Cost Savings: $566 Existing: Proposed: 9 days 3 days Schedule Savings: Figure 8: Summary of Proposed Design Savings 6 days The proposed change does not yield significant cost savings. While the erection labor cost was reduced, the added prefabrication costs negate any cost savings. The cost for material was cheaper in the proposed design because fewer pieces of steel were used. The delivery cost of the alternative design was greater than the existing condition, as the pieces would have to be shipped prefabricated, reducing the amount of steel each truck could hold. A value of $75/ton was used to calculate the delivery cost, as opposed to the existing $25/ton. The main benefit of this change is the reduction in the schedule by 6 days. The prefabrication of the pieces reduced the required labor time in the original design. The prefabrication time should not affect the erection time, as they are performed independently. Another example of saved time occurs during the physical installation. The original design would require a considerable amount of layout and coordination, as there are more pieces to be installed. The prefabricated unit would be easier to install and requires less preparatory work. Connection Redesign Conclusion The analysis of the alternative design shows a slight cost savings and a reduction of 6 days from the steel erection schedule. Given the design s restraints, it would be beneficial for the contractor to install this design as opposed to the original design. Assuming the prefabricator can deliver the pieces when needed, it would be beneficial for both the management team and the steel erector. 28 of 97