Adapting Distribution Network Planning Practices and Design Standards to Accommodate Distributed Energy Resources

Similar documents
Facilitating Whole Electricity System Outcomes

ENABLING EMBEDDED GENERATION

Integration of Renewable Energy Sources in the Electricity System - Grid Issues -

How to incentivise utilities to adopt low carbon technologies

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

Low Carbon Networks Fund Review and Synthesis

Electricity System Operator Forward Plan 2018/19

WPD Innovation. Paul Jewell Policy Manager

UK Power Networks Innovation and future energy systems. Neil Madgwick & Giulia Privitera 3 March 2017

Dr Stuart Johnston. General Manager, Network Transformation. Energy Networks Australia. Submitted by to:

Bulk Power System Integration of Variable Generation - Program 173

Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective

Janusz Bialek DONG Energy Professor Durham Energy Institute

Distributed energy resource management - the way forward

Managing the Future National Transmission System A Smarter Way

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View

Microgrid impact on the development of electricity infrastructure

Smart Energy and Smart Grids Future challenges and smart solutions for the electricity system

Monitoring Demand-Side Flexibility

Community Energy Projects. Our guide to getting a connection

Open Networks Workstream 3: Product 2

Supporting Documentation A Changing Industry and Marketplace 0

Operational and technical challenges for D3: Lessons from FENIX

TasNetworks Transformation Roadmap 2025

ENGINEERING RECOMMENDATION P2/6 SECURITY OF SUPPLY JULY Energy Networks Association Engineering Directorate

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem

Consultation on the Electricity System Operator forward plan

RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018

RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018

UK Power Networks. Technology Watch (Smart) Networks Context & Innovation. 28 th April, 2015 David Boyer, Smart Networks Policy Lead

Export Limiting in Practice

MANGING THE FUTURE NETWORK IMPACT OF THE ELECTRIFICATION OF HEAT

IMPACT OF HIGH PENETRATIONS OF MICRO-GENERATION ON LOW VOLTAGE DISTRIBUTION NETWORKS

Realising the True Value of Energy Storage. Mick Barlow, Scott Osborne, S&C Electric Europe Ltd Nick Heyward, UKPN Alistair Steel.

Impact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc.

Bulk Power System Integration of Variable Generation - Program 173

Northumbria Research Link

10 th January SPEN DSO Vision Consultation Responses

September 2018 THOUGHT LEADERSHIP: INFRASTRUCTURE INVESTING IN A DISRUPTED WORLD Part 2: POWER SYSTEMS

Enabling Integration of Distributed Renewables - Program 174

Back to contents. Executive Summary. Flexibility Roadmap. FutureSmart. A smart grid for all: Our transition to Distribution System Operator

Supporting Document 03. Information to support our proposed base capital expenditure programme

Benefit Analyses of Irvine Smart Grid Projects N. KARALI, B. SHAFFER, K. CLAMPITT, A. ZHU, R. YINGER, C. MARNAY. Southern California Edison USA

REA response to DECC Consultation on Ensuring Regulation Encourages Innovation

Strategic Investment Options for Low Carbon Economy in the South Wales. 15th June 2016

National Infrastructure Assessment: Call for Evidence

Balancing performance with responsibility

Smart grids: flexibility from new sources needed to make renewable power work

ELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017

APGTF Workshop: Managing the Grid of the Future

Customer-Led Network Revolution Cost Benefit Analysis

GSR016: Small and Medium Embedded Generation Assumptions

The UCD community has made this article openly available. Please share how this access benefits you. Your story matters!

Modelo de regulação do setor elétrico na Inglaterra. Paul Whittaker Diretor de Regulação da National Grid

STRATEGIC INTERCONNECTED NETWORK TRANSITIONING

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Increase Power Grid Stability and Reliability with Enterprise Historians for Synchrophasor Data Management

Design and Implementation of Power Quality Relaying for Renewable (Inverter-Based) and Synchronous Generation Dominion Virginia Power

Adoption of Smart Grid Technologies: Results of a Survey of U.S. Electric Utilities. J. DEDRICK, Y. ZHENG Syracuse University USA

Open Networks Project

Modernization of the Power System

Upgrading Our Energy System. Smart Systems and Flexibility Plan

2012 Grid of the Future Symposium. Evolution of the US Power Grid and Market Operations through the next Decade

Non-BM Balancing Services Volumes and Expenditure

Operation of Power Systems with High Shares of Variable Renewables. Manuel Coxe. Progarmme Officer - Grid Integration

Regional Breakdown. Overview. Electricity July 30 th About the data. Modelling method (Active Demand)

Determination of Smart Inverter Control Settings to Improve Distribution System Performance

TC8 cooperates also with several organizations active in the field of electricity supply such as CIGRE, CIRED, IEEE, AFSEC, IEA.

Integrating Renewables and Distributed Energy Resources into California s Electricity Markets

Distributed Energy Resource Management System (DERMS)

Responses are given here with the section references from the consultation document.

Methodological Application to Integrate Renewable Energy Resource into Kuwait s Electrical Grid

Critical Load Serving Capability by Microgrid using 100% Renewable Energy

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

EWEA response on the ERGEG Position Paper on Smart Grids

Energy Networks Association Workstream 1 Product 8

CHAIRMAN S SUMMARY. Renewable Energy: a Route to Decarbonisation in Peril?

European Distribution System Operators for Smart Grids. Retail energy market: Supplementary response to the European Commission s public consultation

Click to edit Master title style. Click to edit Master title style Active Network Management Workshop

Understanding the Value of Uninterrupted Service. P CENTOLELLA Analysis Group, Inc., USA. M MCGRANAGHAN Electric Power Research Institute, USA

MCE Decision paper. 13 December A National Minimum Functionality for Smart Meters

Rate of Change of Frequency Distribution Code Modifications. Response to the Consultation

CBI Response to BEIS Call for Evidence

Introduction to local flexibility markets What are flexibility services and how can I get involved? Jodie Giles Senior Project Manager

Smarter Business processes resulting from Smart Data

Alternative Connection Application and Offer Process Proposal

2012 Grid of the Future Symposium. Trends for the Grid of the Future

The Voice of the Networks

Consolidating Operations, Planning and Protection Model Management Using a Network Model Manager Approach

ELECTRICITY NETWORK TRANSFORMATION ROADMAP: KEY CONCEPTS REPORT SUMMARY DECEMBER 2016

IMP/001/911 Code of Practice for the Economic Development of the LV System

Technical considerations for integration of distributed renewables on the grid

Targeted Deployment of Solar Generation using Advanced Inverters. J. VALENZUELA J. WOODARD J. SALSMAN National Grid USA

EDF and Integration of Distributed Energy Resources

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

Stakeholder Engagement Session on Long-Term Load and DER Forecasting July 14, 2017

UK Power Networks. Smart Grid Strategy

NIA Project Registration and PEA Document

Transcription:

21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Adapting Distribution Network Planning Practices and Design Standards to Accommodate Distributed Energy Resources S.L. HAY, C.E. HIGGINS TNEI Services Ltd United Kingdom SUMMARY The integration of Distributed Energy Resources (DER) on distribution networks has grown rapidly around the world throughout the past decade. DER encompasses not only generation and demand customers, but also elements of storage and other controllable network devices, enabling the transition towards decarbonised electricity systems. The long-established method of providing sufficient security of supply is conservative and deterministic whereby distribution networks are effectively over-designed to ensure enough capacity and redundancy is available to keep customers connected during contingency operation. DER can play a diverse and active role within distribution networks, enabling more efficient use of capacity and capital whilst not impacting network security. DER challenges the fundamental rules by which distribution networks have traditionally been planned and designed. The connection of many DER assets to date has been using relatively bespoke technical and commercial arrangements. More recently, penetrations of DER have risen to such levels, and growth is expected to continue, that there is increasingly a focus on adapting the core practices of electricity distribution i.e. planning, design, operation, control and management processes, to accommodate and embed DER into business as usual (BAU). Peak demand shifting and domestic generation management are two applications where DER can improve network capacity, reduce losses and network investment requirements. However, this requires a move to a more probabilistic approach to network planning and operation that considers the availability of various controllable loads and network assets. This is being actively explored by DNOs and in the current review of the UK distribution network security of supply standard. KEYWORDS Distribution Network Distributed Energy Resources Renewable Generation Standards Planning Stephanie.Hay@tnei.co.uk

INTRODUCTION Distribution networks have been, and for the most part are still, designed conservatively to comply with security of supply standards and ensure adequate redundancy such that peak demand can be met, even in contingency conditions (typically N-1 above low voltage). This practice has led to networks, especially at higher voltages e.g. 33 kv, only utilising up to half of the installed capacity of their assets in anticipation of mostly infrequent faults or planned maintenance. While security of supply remains paramount to distribution networks, the substantial increase in DER is driving the evolution of the associated standards to include provision for active (controllable) generation and demand customers in network planning activities, replacing the traditional passive philosophy of planning and operation. The benefits of incorporating DER into planning and design standards are numerous. By allowing active network components to contribute to security of supply, existing network infrastructure and assets can be utilised more efficiently, reducing system losses and, in many instances, deferring capacity reinforcements. Such reinforcements are time-consuming, often very expensive and can also result in stranded assets if load growth is not realised. If reinforcements can be deferred or avoided through the use of DER then not only are network issues resolved more promptly, but significant cost savings can be made and passed onto customers and increased volumes of low carbon generation and demand can connect. Greater visibility of networks through more monitoring and control devices is another advantage. Embedding the consideration of DER into planning and design standards would also make it easier for future customers to connect due to greater clarity of technical and commercial arrangements. This paper considers the adequacy of existing distribution network planning and design standards and examines how the integration of high volumes of DER is driving changes, recognising that fundamental change is ultimately what is required. Ongoing innovation work in the area by distribution network operators (DNO) supports the case. Recommendations on how standards and practices could be revised to accommodate more flexible operation of distribution networks are also explored through case studies which illustrate some of the features of DER and how they challenge existing practices. Whilst this is focused on the UK where we are actively supporting DNOs in better understanding and responding to the influence of DER on network design, it has many parallels for other countries where DER connection is increasing. EXISTING PLANNING & DESIGN STANDARDS FOR DISTRIBUTION Relevant Planning Standards There are a number of planning and design standards that new connections to UK distribution networks e.g. DER, must comply with. The G59 Engineering Recommendation for the Connection of Generating Plant to the Distribution Systems of Licensed Distribution Network Operators [1] provides guidance on all of the requirements throughout the connection process. The document contains a list of planning and design standards which provide rules, limits and guidance for such aspects as security of supply (ER P2) [2], voltage fluctuations (ER P28) [3] and unbalance (ER P29) [4], power quality (ER G5) [5] and earthing (TS 41-24) [6]. The G59 (and the standards listed within) are applicable in the UK however there are equivalent standards and guidance in most countries with a developed electrical grid. Security of Supply Perhaps the most important standard to review in the context of connecting increasing levels of DER is Engineering Recommendation P2 Security of Supply. The current version of the distribution network security of supply standard in the UK is Engineering Recommendation (ER) P2/6. It was published in 2006 and is a revision of P2/5 which was published in 1978. The revision does not revisit the analyses performed for P2/5, rather it was updated to account for a more diverse range of distributed generation (DG) types including landfill gas, CHP, waste to energy, wind and hydro. As such, the standard has 1

effectively changed very little in almost four decades, yet distribution networks have evolved significantly in the last decade alone. The table below summarises the level of redundancy required for distribution networks based on Group Demand (estimated maximum demand at a grid supply point). Table 1: UK Requirements for Network Redundancy [2] Group Demand Required Redundancy Up to 1 MW N-0 No requirement 1 MW up to 60 MW N-1 At least one additional circuit to supply demand for First Circuit Outage Over 60 MW N-2 At least two additional circuits to supply demand for First and Second Circuit Outages P2/6, with support from Engineering Technical Report (ETR) 130 [7], makes allowances for intermittent and non-intermittent generation (wind, small hydro only) by assigning reliability values (F Factors) to DG based on size or persistence. The reliability of non-intermittent generation is dependent on the number of units in a generating station while intermittent generation reliability is based on how long the generating station is required to be available and is irrespective of the number of units. A combination of: 1. the requirements for system redundancy in the form of additional capacity; and 2. the conservative view of DG contribution to meeting demand, has resulted in distribution circuits and transformers sized around twice the peak demand capacity requirement, where peak demand occurs, in some cases, for less than 1 hour per year; while locally available generation is not being accounted for and so capacity must be provided for generation sourced outside the local network area. Additionally, any demand growth beyond network capacity triggers material upgrades in asset ratings to ensure that this level of security of supply is maintained. Figure 1 below illustrates the requirements for redundancy in the security of supply standards which are based on worst case (N-1) conditions. Figure 1: Comparison of Worst Case (N-1) vs. Typical Operating Conditions for Distribution Network Design The current security of supply methodology is deterministic and based on peak demand rather than the demand profile. A capacity assessment will then identify any areas where reinforcement is required 2

based on forecasted peak demand. Implementing a more probabilistic methodology has the potential to utilise existing capacity more effectively through better understanding of how different types of DG and DER could contribute to meeting demand. This prospect has been examined extensively in the ongoing review of the ER P2 standard [8] where the benefits and challenges of implementing more probabilistic methodologies are measured. DER CHALLENGES AND OPPORTUNITIES In the context of short- and long-term network planning and design, the main challenges and opportunities for distribution networks presented by the connection of DER include: Responsive generation and demand which may alter peak load, removing the predictability of demand profiles in the planning processes but adding flexibility; Decentralised network controllable devices e.g. energy storage, actively managing network parameters in real-time and utilising network assets more efficiently; and Intermittent and distributed generation that is not always visible to the network operator in the control centre which makes daily operational management and control more challenging; Each type of DER is potentially operating and responding to varied commercial triggers and instructions. The capabilities of DER, in the context of their real-time operation and control, are starkly different to the long-term planning approach taken by distribution network/system operators. Capacity and redundancy are ensured well in advance and according to peak loading forecasts. However, by embracing the capabilities of DER, networks can be planned, designed and ultimately operated much more efficiently. Case Studies The following case studies are examples of how different applications of DER challenge existing standards. Early outcomes of ongoing work by UK DNOs including a review of the current P2 standard [8] are presented where relevant alongside the case studies. 1. Peak Demand Shifting Peak demand shifting can be achieved in a number of ways; through responsive demand, the use of storage or the implementation of small-scale or domestic generation. As described in the previous section, peak demand is the main indicator used to assess capacity (and redundancy) requirements of networks according to ER P2/6, and demand growth will trigger upgrades once network capacity is reached. As such, if peak demand can be reduced locally through: Shifting using smart meters or appliances to schedule consumption at off-peak times; Levelling using storage to produce/consume energy to keep demand level; or Displacement using domestic or local generation to serve demand. Conversely, smart control of demand can be exploited to absorb solar and wind generation at times of peak production (if storage is unavailable). Peak Demand Shifting can not only defer capacity upgrades but could also create opportunity for more DER customers to connect in the same network area. UK Power Networks (UKPN) Low Carbon London (LCL) project is a good example of how flexible demand can be used to defer reinforcement [9]. The project also looked at how DG can contribute to security of supply [10] which is discussed later in the paper. LCL carried out various trials using industrial and commercial demand response both as a short-term operational tool and as a longer-term alternative to network reinforcement. 3

With the inclusion of DER, and specifically peak demand shifting, there needs to be more visibility of what the demand profile consists of i.e. demand, DG, storage, electric vehicles, in order to better understand and forecast power flows at lower voltages. Potential adaptations to existing standards to incorporate flexible demand could include a revised methodology for calculating and forecasting capacity requirements at different substation levels i.e. primary, secondary substations. 2. Domestic Generation Management Increasingly, households and businesses are deploying distributed generation behind the meter whereby any generation not consumed in the household/business is exported back to the grid. Since the low voltage network was not designed for reverse power flows exporting to the grid, novel methods of maximising self-consumption and reducing overall export were researched and trialled in the Northern Powergrid Customer Led Network Revolution (CLNR) innovation project. The solar PV trials monitored 93 domestic customers with either: No intervention; Automatic load balancing which diverts excess PV generation to hot water storage; or An In-House Display (IHD) which notified customers of generation exceeding their consumption to encourage them to manually increase it. The aim was to benchmark and assess whether automatic or manual intervention is more suitable to manage excess generation export at LV [11]. The approaches used in this trial indicated that there was no visible additional benefit to automatic intervention however, the sample size was relatively small. Early work in the review of ER P2 has identified some limitations of the standard relevant, including no explicit consideration of prosumers i.e. domestic customers who produce and consume electricity. Also, demand is only considered in >1 MW groups. Potential adaptations could include more detailed identification of demand groups and include provisions for domestic generators to encourage the more active role of consumers in generation management across the network. Big Data As a result of increased monitoring requirements for more flexible loads and controllable devices on the grid, Big Data will be an important aspect of future distribution networks in the context of operation. However it can also be exploited to improve various aspects of network planning and design. More accurate monitoring of generation and demand will improve understanding of network behaviour and load forecasting. It will also enable a more probabilistic methodology to be employed to security of supply capacity assessments as well as improved selection of solutions when capacity is reached. EVOLUTION OF DISTRIBUTION STANDARDS A number of UK DNOs, as part of their innovation projects, have already carried out exploratory work on how DER (distributed generation, storage, electric vehicles, demand response etc) could contribute to and improve existing security of supply standards. UKPN s LCL project looked both at how DG and responsive demand could be addressed in the context of security of supply [9], [10]. Northern Powergrid, as part of their Customer Led Network Revolution (CLNR) project have conducted a review of P2/6 and ETR130 with a view to advise on updated F Factors for different types of generation and the methodology for assessing DG contribution to security of supply [12]. Recognising that the UK security of supply standard is based on deterministic load behaviour, and is no longer fit for purpose, a fundamental review of the Engineering Recommendation P2 is in progress, commissioned by the Energy Networks Association. Early outcomes of this review have been published in [8] and a number of reform options have been presented: 4

Retaining P2/6 without revision; Retaining deterministic planning standard but includes improvements to account for nonnetwork solutions i.e. DER; Implementing a non-deterministic planning standard; Implementing a non-deterministic planning standard but retaining some deterministic elements for minimum reliability; and Abolition of the planning standard if other regulatory framework is in place. Incorporating DER solutions into the standard could improve productive efficiency however it is recognised that it is difficult to pre-determine DER contributions when assessing reliability, work is ongoing. In Europe, ENTSO-E (European Network of Transmission System Operators for Electricity) has published a portfolio of network codes which are currently going through the process of becoming legally binding [13]. These network codes aim to facilitate harmonisation, integration and efficiency of the European electricity market. Although these codes are focused on the transmission network, the connection of large industrial loads and distribution networks is considered in the Demand Connection Code [14] which considers Demand Side Response from these entities and allows the TSO to place requirements on this to maintain network security. The Electric Power Research Institute (EPRI) is very active in the area of DER research and they have a wide portfolio of research findings. They have carried out various research, developments and trials in the area to gain a better understanding of the challenges associated with integration of DER. For example, in association with Con Edison, they conducted an investigation into whether DER could help achieve improved reliability on a network [15]. Their Smart Grid demonstration initiative has also studied DER in relation to its interoperability and integration with a view to standardising them as part of BAU [16]. IEEE 2030 Guide for Smart Grid Interoperability of Energy Technology and Information Technology Operation with the Electric Power System, and End-Use Applications and Loads [17] was published in 2011 and provides guidelines on the integration of smart grid technology and associated IT with the power system. Further guidance was published in 2015 on the connection of energy storage systems (2030.2) and there is work ongoing relating to the connection of electric-sourced transportation (e.g. electric vehicles) (2030.1). CONCLUSIONS It is evident that for distribution networks to evolve and integrate DER effectively, the associated technical standards must also evolve. This has been recognised by stakeholders and a variety of work is being carried out to determine the changes required to maximise the opportunities that DER offers for more efficient network planning and design. Peak demand shifting and domestic generation management are two applications where DER can improve network capacity, reduce losses and network investment requirements. The existing focus in the UK on a single annual peak demand value and N-1, at high voltage, does not consider the benefits that can be provided by an increasing volume of controllable customer loads and network assets on the network. Also, there is increasingly domestic and small-scale generation that is available to provide local supply albeit with consideration of probabilistic characteristics and/or manage generation export during low demand times. Focused analysis of the large volumes of data that are becoming available across all voltage levels will provide further evidence and justification for future adaptation of network planning standards to better incorporate DER. 5

BIBLIOGRAPHY [1] Engineering Recommendation G59, Issue 3 Amendment 1, August 2014, Recommendations for the Connection of Generating Plant to the Distribution Systems of Licensed Distribution Network Operators. [2] Engineering Recommendation P2/6, July 2006, Security of Supply. [3] Engineering Recommendation P28, September 1989, Planning Limits for Voltage Fluctuations Caused by Industrial, Commercial and Domestic Equipment in the United Kingdom. [4] Engineering Recommendation P29, October 1996, Planning Limits for Voltage Unbalance in the United Kingdom. [5] Engineering Recommendation G5/4-1, October 2005, Planning Levels for Harmonic Voltage Distortion and the Connection of Non-Linear Equipment to Transmission Systems and Distribution Networks in the United Kingdom. [6] Technical Specification 41/24, Issue 1, 1992, Guidelines for the Design, Installation, Testing and Maintenance of Main Earthing Systems in Substations. [7] Engineering Technical Report 130, 2006, Application Guide for Assessing the Capacity of Networks Containing Distributed Generation. [8] NERA Economic Consulting, Imperial College London, DNV.GL, 20 November 2015, Engineering Recommendation P2 Review Workstream 2.7: Alignment of Security of Supply Standard in Distribution Networks with Other Codes and Schemes. [9] UKPN, September 2014, Industrial and Commercial Demand Response for Outage Management and as an Alternative to Network Reinforcement. [10] UKPN, September 2014, Distributed Generation Addressing Security of Supply and Network Reinforcement Requirements. [11] Element Energy for Customer Led Network Revolution, February 2015, CLNR Insight Report: Domestic Solar PV Customers with Automatic Balancing. [12] EA Technology, Durham University and Newcastle University for Customer Led Network Revolution, October 2014, Review of the Distribution Network Planning and Design Standards for the Future Low Carbon Electricity System. [13] ENTSO-E Website, Network Code Overview, https://www.entsoe.eu/majorprojects/network-code-development/pages/default.aspx, Sourced July 2016. [14] ENTSO-E Website, Demand Connection Code, https://www.entsoe.eu/majorprojects/network-code-development/demand-connection/pages/default.aspx, Sourced July 2016. [15] EPRI, Con Edison, October 2012, Case Study on Assessment of Achieving Increased Reliability with Distributed Energy Resources: Consolidated Edison. Report not publicly available. [16] EPRI, March 2010, Distributed Energy Resources and Management of Future Distribution. [17] IEEE Standards Association Website, http://grouper.ieee.org/groups/scc21/2030/2030_index.html, Sourced July 2016. 6