Design and Implementation of Power Quality Relaying for Renewable (Inverter-Based) and Synchronous Generation Dominion Virginia Power

Similar documents
Determination of Smart Inverter Control Settings to Improve Distribution System Performance

Impacts of the Decentralized Wind Energy Resources on the Grid

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE

Critical Load Serving Capability by Microgrid using 100% Renewable Energy

Increase Power Grid Stability and Reliability with Enterprise Historians for Synchrophasor Data Management

Feasibility Study Report

ISO New England Net Load Analysis with High Penetration Distributed PV. J. BLACK ISO New England USA

ELECTRIC SYSTEMS PROCEDURE: ES DISTRIBUTED ENERGY RESOURCES (DER)

Requirements for the Connection of Facilities to The Dayton Power & Light Co. Transmission System

Targeted Deployment of Solar Generation using Advanced Inverters. J. VALENZUELA J. WOODARD J. SALSMAN National Grid USA

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring

FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0

Investigating Power System Primary and Secondary Reserve Interaction under High Wind Power Penetration Using Frequency Response Model

APPROACH TO IMPLEMENT VARIABLE TRANSFER LIMITS IN ENERGY IMBALANCE MARKETS R. RAMANATHAN(*) Maxisys Inc., USA

POTOMAC ELECTRIC POWER COMPANY

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA

TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. Policy Bulletin No Appendix A SAFETY & INTERCONNECTION REQUIREMENTS FOR ALTERNATE ENERGY PRODUCTION

Mitigating Extraordinary Events using Wide Area Monitoring Applications

NERC Lessons Learned and Industry Recommendation

Facility Interconnection Requirements

ALSTOM Transmission & Distribution, Protection & Contrôle

Adapting Distribution Network Planning Practices and Design Standards to Accommodate Distributed Energy Resources

Phasor measurement units gain credibility through improved test and calibration standards

Contribution of PV Power Plants to Flicker Severity in Power Distribution Grids

MATL Requirements Facility Interconnection Requirements

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

Duquesne Light Company FACILITY INTERCONNECTION REQUIREMENTS (FAC 001) GENERATION FACILITIES TRANSMISSION FACILITIES END USER FACILITIES 12/30/2015

The Relationship of Primary, Secondary, and Tertiary Regulation / Dispatch under High Wind Penetration

CUSTOMER GUIDE FOR THE INTERCONNECTION DISTRIBUTED RESOURCES TO THE PUBLIC SERVICE COMPANY OF OKLAHOMA DISTRIBUTION SYSTEM

Automated Fault Location. T. LAUGHNER Tennessee Valley Authority USA

Operations and Maintenance Considerations for Underfrequency Relaying Design

Solar Integration into the PJM Grid

Modeling, Monitoring and Mitigating Geomagnetically Induced Currents

CUSTOMER GUIDE FOR THE INTERCONNECTION DISTRIBUTED RESOURCES TO THE AMERICAN ELECTRIC POWER DISTRIBUTION SYSTEM

CUSTOMER GUIDE FOR THE INTERCONNECTION DISTRIBUTED RESOURCES TO THE AMERICAN ELECTRIC POWER DISTRIBUTION SYSTEM

NERC Reliability Initiatives and Smart Grid

2012 Grid of the Future Symposium. Trends for the Grid of the Future

ISSN Vol.07,Issue.16, November-2015, Pages:

Large-scale Integration of Distributed Energy Resources within Electric Power Systems. Danish Cell Controller Project Brief

Technical Requirements for Distributed Generation Connection

2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications

Bulk Power System Integration of Variable Generation - Program 173

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO

IMPACT OF SMALL PRODUCERS ON POWER QUALITY IN DISTRIBUTION GRIDS BASED ON ELEKTRILEVI OÜ GRID

Grid Interconnection Standards for Distributed Resources and Microgrids

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

CALCULATING VARIABLE TRANSFER LIMITS FOR DYNAMIC TRANSFERS

Consolidating Operations, Planning and Protection Model Management Using a Network Model Manager Approach

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Smart Virtual Power Plants for the Future Electric Grid Realization and Benefits

AORC Technical meeting 2014

AEP Guidelines for Transmission Owner Identified Needs

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Connection Study Requirements

2014 Grid of the Future Symposium

Public Utility District Number 1 of Snohomish County

Integration of Distributed Renewables - Program 174

DISTRIBUTED GENERATION INTERCONNECTION PROCEDURES. June 21, 2011

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

An Oracle White Paper June Microgrids: An Oracle Approach

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Security Guideline for the Electricity Sector: Identifying Critical Assets

2012 Grid of the Future Symposium. Evolution of the US Power Grid and Market Operations through the next Decade

Electric Sector Coupling: Promise and Pitfalls

The Nanogrid Collective: a Means of Integrating Thousands of Individual Customers Into System Operations and Markets. P.J. PALERMO PJP Consulting USA

Integration issues and simulation challenges of high penetration PV

Level 1 - Public Information

Analysis of Wind Power Integration for Power System Transient Stability

(D2-01_28) ROLE OF ICT in Power System

Transmission Interconnection Requirements. Table of Contents

International ejournals

Transmission Cost Allocation in the Midwest

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

NORDAC 2014 Topic and no NORDAC 2014 http :// 3.1

Statistical Path Analysis Performance Evaluation Of ElectroFlow For Majan Electricity Distribution

LOAD SERVING ENTITIES PJM REGION

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

Impact of PV Energy Resources on the Quality of power of the Electrical Power System

JOURNAL OF APPLIED SCIENCES RESEARCH

Transmission Planning Procedures and Planning Criteria TDOG108

Statistical Path Analysis Performance Evaluation Of ElectroFlow For Skippy

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018

Grid Interconnection Issues for Wind Generation

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

Extended Microgrid Using (DER) Distributed Energy Resources

Analysis of DG Influences on System Losses in Distribution Network

Session 1 DER Integration and Grid control

An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference

NSPI BULK POWER FACILITIES CONNECTION GUIDE Report number NSPI-TPR-002-2

City of Pasadena Water and Power Department Power Division DISTRIBUTED GENERATION FACILITIES INTERCONNECTION REQUIREMENTS REGULATION 23

Benefit Analyses of Irvine Smart Grid Projects N. KARALI, B. SHAFFER, K. CLAMPITT, A. ZHU, R. YINGER, C. MARNAY. Southern California Edison USA

World Scientific Research Journal (WSRJ) ISSN: Research on Intelligent Microgrid and its Reliable Grid Connection

Primary Frequency Response Stakeholder Education Part 1 of 2

Bulk Power System Integration of Variable Generation - Program 173

Interconnection Application

Wind Power Harmonic Emission versus Active-Power Production

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

Transcription:

21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Design and Implementation of Power Quality Relaying for Renewable (Inverter-Based) and Synchronous Generation at Dominion Virginia Power C.G. MERTZ Dominion Virginia Power USA P.J. HAWKS Dominion Virginia Power USA SUMMARY This paper outlines Dominion Virginia Power s approach to power quality relaying design and implementation based on IEEE Std. 519-2014: IEEE Recommended Practice and Requirements for Harmonic Control in Electric Power Systems, IEEE Std. 1453-2015: IEEE Recommended Practice for the Analysis of Fluctuating Installations on Power Systems, and IEEE Std. 1159-2009: IEEE Recommended practice for Monitoring Electric Power Quality. The Dominion Virginia Power service territory has numerous generation interconnection requests for various types of renewable generation with a majority being solar. KEYWORDS Power Quality, Relaying, Inverter-Based Generation christopher.g.mertz@dom.com

1. INTRODUCTION The motivation for this work stems from the magnitude of interconnection requests within both the PJM interconnection queue, and the Virginia and North Carolina state jurisdictional queues. Historically, traditional synchronous generation interconnection requests have had a much lower fruition rate than renewable or distributed generation resources through each of the feasibility, system impact, and facilities study phases. PJM received 42 solar generation interconnection requests from December 1 st, 2015 to May 29 th, 2016. These 42 solar facilities combine for over 1000 megawatts capacity, and 2000 megawatt hours of total energy. The paper will discuss aspects of relay logic design, communications and data architecture, and where we are today with one transmission level solar interconnect at Dominion Virginia Power. 2. DESIGN AND DEVELOPMENT OF THE DVP POWER QUALITY RELAY Dominion Virginia Power s power quality relay design includes elements monitoring overfrequency, under-frequency, over-voltage, under-voltage, power factor, imbalance, harmonics (THD and TDD), and flicker. Dominion Virginia Power is utilizing the SEL-735 to perform these functions. The SEL-735 has built in Four-Quadrant VAR Metering that we can use to take action, when necessary, for over-frequency, under-frequency, over-voltage, and undervoltage conditions. Figure 1: Four-Quadrant Control [1] 2

Utilizing four-quadrant control gives the protection scheme added security so action is not taken that would negatively impact the transmission system. For example, if the Dominion Virginia Power system were to experience a FIDVR (Fault Induced Delayed Voltage Recovery) event that diminished the voltage significantly below nominal, and a nearby solar generation facility were operating in quadrant I (delivering real and reactive power), tripping the generation offline would only exacerbate the condition of the transmission system. Power Quality Function Pseudo-Relay Logic Under-voltage (UV) UV and (QIII or QIV) = ACTION Over-voltage (OV) OV and (QII or QI) = ACTION Under-frequency (UF) UF and (QII or QIII) = ACTION Over-frequency (OF) OF and (QI or QIV) = ACTION Table 1: Actionable Conditions for Under/Over-Voltage and Under/Over-Frequency We can generalize by saying, adverse condition and adverse operating points for said condition requires action. Action can be substituted for anything: tripping, changing the generator set-point, or triggering an event record. At this time, Dominion Virginia Power is opting to trigger an event record. In the future, tripping after some delay may be suitable if the generation is consistently the source of adverse operating conditions. The expectation for all renewable generation facilities is to generate between 0.95 power factor leading or lagging. The voltage and current imbalance is measured at the interconnect location. IEEE Recommended Practice for Monitoring Electric Power Quality, IEEE Std. 1159-2009, dictates voltage and current imbalance must be between 0.5%-2% and 1.0-30% respectively [2]. Dominion Virginia Power has experienced significant current imbalance on various voltage levels and is considering 2% voltage imbalance and 20% current imbalance as adverse operating points requiring examination. Dominion Virginia Power has implemented the statistical based approach from the IEEE Recommended Practice and Requirements for Harmonic Control in Electric Power Systems, IEEE Std. 519-2014, in the SEL-735 [3]. The 10 minute THD values are readily available from the relay, and TDD values are implemented by taking the ratio of facility output divided by the facility contractual output multiplied by the THD. Each of the 10 minute THD or TDD values are compared with the applicable limits outlined in IEEE Std. 519-2014 Table 1 through Table 4 and a counter increments if the value of the 10 minute calculation period exceeds the limit. If the generation facility s weekly voltage THD and current TDD count exceeds 50 then the generation facility has violated the weekly 95 th percentile short time (10 min) value in IEEE Std. 519-2014. Similarly to the harmonic statistical approach, the flicker statistical based approach also considers 10 minute aggregates (called P st for short-term) where criteria is outlined in Table 2 of IEEE Recommended Practice for the Analysis of Fluctuating Installations on Power Systems, IEEE Std. 1453-2015 [4]. While Dominion Virginia Power acknowledges the 99 th percentile values for both harmonic content and for flicker, during the initial assessment period we will only look towards a more relaxed relaying criteria. 3

3. COMMUNICATION AND DATA CONSIDERATIONS The purpose of the power quality relay in the first phase of development is to acquire data to help us better understand the behaviour of individual facilities and how these facilities interact with Dominion s electric transmission system during normal operation and abnormal events. Data is presently stored locally on the relay in what the SEL-735 calls load profiles. Each of the six load profiles is set up to store sets of average operational data (current, voltage, power, and frequency) in 5 minute intervals for 366 days, average total harmonic distortion data (current THD, and voltage THD) in 60 minute intervals for 366 days, average individual phase harmonic data (harmonics 1-5, 7, 9, and 11) in 60 minute intervals for 366 days, end-ofinterval flicker data (PLT, and PST) in 10 minute intervals for 366 days, and maximum and minimum operational data in 5 minute intervals for the previous 5 days. The two primary limitations of this system are availability of storage space on the relay and accessibility of the data. When the new power quality relaying design is put into service (Fall 2016), we will begin streaming power quality data back to our OSIsoft PI System database. We plan to put additional flags or triggers in place to notify a select few engineers when criteria is approaching or has breached a limit specified in section 2 of this paper. This data is also readily available to all Dominion Virginia Power engineers who may want to perform their own statistical analysis, visualize and trend data, set up personal calculations, or be notified if data exceeds a certain bound. Operational data (current, voltage, real power, reactive power, apparent power, frequency, and power factor), individual phase voltage THD and calculated current TDD, individual phase harmonic data (3 second aggregate, instantaneous magnitude, and instantaneous angle), voltage and current imbalance, and counter register information for statistical approach of IEEE-519-2014 and IEEE-1453-2015 implementation will be streamed to the PI System database via DNP protocol. 4. WHERE WE ARE TODAY: SOLAR FACILITY #1 HARMONIC CONTENT Solar Facility #1 was the first facility interconnected to Dominion Virginia Power s 230 kv electric transmission system. Solar Facility #1 is an 80 MW solar photovoltaic facility connected in the eastern portion of Dominion Virginia Power. The figures below show real power output, percent current THD, and flicker from Solar Facility #1 on a cloudy day with intermittent output (5/6/2016) versus a relatively consistent day (5/9/2016). 4

Figure 2: Solar Facility #1 Real Power, THD, and Flicker From both graphs we can determine operation of the solar photovoltaic facility at very low output levels causes significant current THD, but current THD is misleading. We can take the same two graphs, apply the formula for TDD from section 2, and we see different results. Figure 3: Solar Facility #1 TDD Calculation 5

On May 6 th, 2016 we had TDD averages slightly over 5% during two periods, 10:00:00 and 14:00:00. On May 9 th, 2016 we had TDD averages well over 5% around 8:00:00. IEEE-519-2014 calls for TDD limits on systems greater than 161 kv to be less than 1.5%; both days have steady-state averages exceeding this value. While this data was gathered and plotted manually, our future goal is to utilize OSIsoft PI System to continue to make associations in steady-state generation performance and facility transient response to system disturbances. Our plan is to set up an automated power quality report on performance of inverter based generation, power electronic FACTs devices, and conventional synchronous generation as a baseline to predict and mitigate power quality issues in the future and associate power quality violations with performance and longevity of electric transmission assets. BIBLIOGRAPHY [1] Schweitzer Engineering Laboratories, SEL-735, 2015. [2] IEEE Recommended practice for Monitoring Electric Power Quality, IEEE Std. 1159-2009. [3] IEEE Recommended Practice and Requirements for Harmonic Control in Electric Power Systems, IEEE Std. 519-2014. [4] IEEE Recommended Practice for the Analysis of Fluctuating Installations on Power Systems, IEEE Std. 1453-2015. 6