IMPORTANT NOTICE. Kindly note that:

Similar documents
BACKGROUND INFORMATION DOCUMENT

(8 December 2014 to date) NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998

VLAKVARKFONTEIN COAL MINE

EWA ENVIRONMENTAL AFFAIRS

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

BACKGROUND INFORMATION DOCUMENT:

BACKGROUND INFORMATION DOCUMENT & INVITATION TO COMMENT JULY 2015

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.

NOVEMBER 2016 REVISION 0. Prepared by: JG AFRIKA (PTY) LTD

Figure 4. The proposed location of the Zalu Dam a) basin and b) wall.

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010

APPLICATION FORM FOR ENVIRONMENTAL AUTHORISATION

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: APPLICATION FOR THE MINING OF SAND AT BORROW PIT MR771/8.6/R/80, VAN WYKSVLEI, NORTHERN CAPE.

BACKGROUND INFORMATION DOCUMENT FOR A PROPOSED SEWER IN GROOT DRAKENSTEIN, WESTERN CAPE

BRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

BACK GROUND INFORMATION DOCUMENT

BASIC ENVIRONMENTAL IMPACT ASSESSMENT for the BEER PROPERTY MANAGEMENT FILLING STATION

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

BACKGROUND INFORMATION DOCUMENT SEPTEMBER 2014 MDEDET REF NUMBER: 17/2/3N-389

BACKGROUND INFORMATION DOCUMENT PROPOSED HAZARDOUS SUBSTANCE STORAGE FACILITIES AT THE SALDANHA BAY INDUSTRIAL DEVELOPMENT ZONE

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002

Cape Environmental Assessment Practitioners(Pty) Ltd

GP 30/5/1/3/2/10242 MP

APPLICATION FOR THE ESTABLISHMENT OF A BORROW PIT ON POGELA FARM NEAR HEATONVILLE, KWAZULU-NATAL DRAFT ENVIRONMENTAL MANAGMENT PROGRAMME

INTRODUCTION PROJECT DESCRIPTION

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL

Annexure E.3. Comment Response Report. Proposed Expansion of Ash Disposal Facility at the Kriel PowerStation, Mpumalanga: Scoping Report

RE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS

Reproduced by Sabinet Online in terms of Government Printer s Copyright Authority No dated 02 February 1998

Figure 1.1: Location of Majuba Power Station within the Pixley Ka Seme Local Municipality

Annex B2.3. Background Information Document

Proposed Establishment of the N.N. Metals (Pty) Ltd Waltloo Metal Reclamation Facility

SCOPING PHASE REPORT SOIL, LAND USE, LAND CAPABILITY AND AGRICULTURAL POTENTIAL SURVEY:

3 EIA PROCESS AND METHODOLOGY

BACK GROUND INFORMATION DOCUMENT

BACKGROUND INFORMATION DOCUMENT

SCOPING REPORT FOR AGGREGATE AND SAND MINING RIGHT APPLICATION BY CAROCODE (PTY) LTD.

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

1 INTRODUCTION. Figure 1.1: Steve Tshwete Local Municipality

ERM conducted the public participation process (PPP) as part of the EIA and EMPr Amendment for MP 30/5/1/2/2/133MR to include:

INTRODUCTION SECTION 24G PROCESS

REASSESSMENT OF THE FINANCIAL PROVISION FOR BLOEMHOF QUARRY, PARYS, FREE STATE PROVINCE

BASIC ASSESSMENT PROCESS

DEA Reference Number: To be announced

4 ADMINISTRATIVE FRAMEWORK 4.1 INTRODUCTION

BACKGROUND INFORMATION DOCUMENT (BID)

Mining in Sensitive Areas: Balancing Conservation & Development. Portfolio Committee for Environmental Affairs

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome

EXECUTIVE SUMMARY: SCOPING REPORT ENVIRONMENTAL IMPACT ASSESSMENT (EIA) PROCESS FOR VISSERSHOK NORTH LANDFILL WASTE MANAGEMENT LICENCE

BACKGROUND INFORMATION DOCUMENT

1 INTRODUCTION 1.1 PROJECT BACKGROUND

Mangaung Gariep Water Augmentation Project (MGWAP)

Basic Assessment and Environmental Management Programme Helam Mining Page 1

Proposed Expansion of the existing Natal Solvent Recovery facility on ERF 7590, Pinetown (10 Clubhouse Place, Westmead) REF: 12/9/11/L44704/4

BOLAND ENVIRONMENTAL CONSULTANTS CC

DRAFT BASIC ASSESSMENT REPORT QUATUM OF CLOSURE REPORT ESTABLISHMENT OF A BORROW PIT ON POGELA FARM LOCATED NEAR HEATONVILLE, KWAZULU-NATAL

PROPOSED CONSTRUCTION OF A SEWAGE TREATMENT PLANT AT CAPE POINT, TABLE MOUNTAIN NATIONAL PARK

SCOPING PHASE REPORT SOIL, LAND USE, LAND CAPABILITY AND AGRICULTURAL POTENTIAL SURVEY:

APPENDIX 5 ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED REVERSE OSMOSIS PLANT AT HENDRINA POWER STATION, MPUMALANGA EXECUTIVE SUMMARY: FINAL BASIC ASSESSMENT REPORT

The PPP has been designed to achieve the following objectives: To ensure that stakeholders are well informed about the proposed development;

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

BACKGROUND INFORMATION DOCUMENT

Environmental Management Plan (EMP)

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE

ethekwini Environment al Health Department.

ENVIRONMENTAL SCOPING REPORT

Proposed establishment of a quarry in the Ngquza Hill Local Municipality, Eastern Cape

Environmental Guidelines for Preparation of an Environmental Management Plan

Fact Sheet: Anglesea Power Station and Mine Rehabilitation Overview

13 July

BASIC ASSESSMENT REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME REPORT

NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008

EnviroLeg cc NATIONAL WATER Reg p 1

BACKGROUND INFORMATION DOCUMENT AND INVITATION TO COMMENT

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

CHINA AFRICAN PRECIOUS METALS ORKNEY GOLD MINE CLOSURE LIABILITY UPDATE

Proposed Windhoek - Gocheganas Road upgrade. Environmental Assessment Scoping Risk Report

INSTALLATION OF A SOLAR PHOTOVOLTAIC POWER PLANT AT ESKOM S DUVHA POWER STATION: ENVIRONMENTAL IMPACT ASSESSMENT

DOORNVALLEI EXT 5 & 6

Basic Assessment Process

Eskom Holdings SOC Ltd. Report Prepared for. Report Number Report Prepared by

4 PROJECT ALTERNATIVES

Appendix A: Details of EAP

BACKGROUND INFORMATION DOCUMENT

Town of Whitby Public Works Department

3 PROJECT ALTERNATIVES

DRAFT BASIC ASSESSMENT REPORT

Lodestone Namibia (Pty) Ltd. Magnetite Mining Prospect near Dordabis: EPL 3112 PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT CONTENTS

Appendix G. Financial Provision Report

COMMENT AND RESPONSE REPORT (CRR) VERSION 2

ENVIRONMENTAL RISK ASSESSMENT: PROPOSED INSTALLATION OF VODACOM OPTIC FIBRE CABLE BETWEEN NELSPRUIT, KABOKWENI AND WHITE RIVER, MPUMALANGA PROVINCE

Proposed Magdalena Colliery Discard Dump Extension. Draft Environmental Impact Assessment Report

Annexure: Need & Desirability

A. OWENS 1 and J. BURKE 2

EXTERNAL AUDIT REPORT IN FULFILMENT OF THE ENVIRONMENTAL AUTHORISATION FOR THE REHABILITATION OF THE VAAL WASTE DUMP SITE ARCELORMITTAL SOUTH AFRICA

BACKGROUND INFORMATION DOCUMENT: EXPANSION OF SINGITA SWENI LODGE

SCOPING REPORT FOR THE PROPOSED WEST WITS MINING PROJECT

Kendal /Kusile to Zeus Environmental Monitoring Report

Transcription:

1 APPLICATION FORM FOR ENVIRONMENTAL AUTHORISATIONS IN TERMS OF THE NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 AND THE NATIONAL ENVIRONMENTAL MANAGEMENT WASTE ACT, 2008 IN RESPECT OF LISTED ACTIVITIES THAT HAVE BEEN TRIGGERED BY APPLICATIONS IN TERMS OF THE MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT, 2002 (MPRDA) (AS AMENDED). Kindly note that: IMPORTANT NOTICE 1. As from 8 December 2014, this document serves as the application form, and incorporates the requisite documents that are to be submitted together with the application for the necessary environmental authorisations in terms of the said Acts. 2. This application form is applicable while the Mineral and Petroleum Resources Development Amendment Act of 2008 is in effect, as the form may require amendment should the Act be further amended. 3. Applicants are required to apply for the necessary water use licence and any other authorisations nor licences to the relevant competent authorities as required by the relevant legislation. Upon acceptance of an application for a right or permit in terms of the MPRDA, applicants will be required to provide evidence to the Regional Manager that a water use licence has been applied for. 4. The Regional Manager will respond to the application and provide the reference and correspondence details of the Competent Authority, and in the event that the application for a right or permit is accepted, together with the date by which the relevant environmental reports must be submitted. Notwithstanding anything that may appear to be stated to the contrary in the acceptance letter, the timeframes are in fact aligned and the prescribed timeframes for the submission of documents as regulated by the NEMA regulations must be strictly adhered to. 5. The application must be typed within the spaces provided in the form. The sizes of the spaces provided are not necessarily indicative of the amount of information to be provided. Spaces are provided in tabular format and will extend automatically when each space is filled with typing. 6. The failure to submit complete information as required in this application form may result in the refusal of the application for an environmental authorisation and consequently of the right or permit applied for. 7. This application must be submitted through the SAMRAD online application system of the Department of Mineral Resources under Other documents to upload. 8. Unless protected by law, all information filled in on this application form will become public information on receipt by the competent authority. Any interested and affected party should and shall be provided with the information contained in this application on request, during any stage of the application process. 9. Please note that an application fee is payable in terms of the National Environmental Management Act and the National Waste Management Act, which fees must be paid upon lodgement of the application. Should the said application fees not be paid as prescribed the application for a right or permit in terms of the Mineral and Petroleum Resources Development Act cannot be considered to have been made in the prescribed manner and the said application for a right or permit will have to be rejected. In this regard the type of applications must be identified in the table below.

2 PLEASE STATE TYPE OF AUTHORISATIONS BEING APPLIED FOR. APPLICATION TYPE APPLICABLE FEE Mark with an X where applicable NEMA S&EIR application on its own R10 000.00 NEMA BAR application on its own R 2 000.00 NEMWA S&EIR application on its own R10 000.00 NEMWA BAR application on its own R 2 000.00 NEMA S&EIR application combined with NEMWA S&EIR application R 15 000.00 NEMA BAR application combined with NEMWA BAR application R 3 000.00 NEMA S&EIR application combined with NEMWA BAR application R 11 000.00 1. CONSULTATION BASIC ASSESSMENT AND/ OR SCOPING REPORT 2. DETAILS OF THE APPLICANT Project applicant: Krosa (Pty) Ltd Registration no (if any): 1994/000739/07 Trading name (if any): N/A Responsible Person, (e.g. Hendrik Jansen van Rensburg Director, CEO, etc).: Contact person: Hendrik Jansen van Rensburg Physical address: Portion 96 of the Farm De Wagendrift 417 JR Postal address: P.O. Box 17230, Pretoria North Postal code: 0116 Cell: 078 964 0058 Telephone: 012 548 4531 Fax: 012 548 6927 E-mail: Krosa.debbie@gmail.com 3. ENVIRONMENTAL ASSESSMENT PRACTITIONER (EAP) INFORMATION EAP: EcoPartners (Pty) Ltd Professional 2005/028736/07 affiliation/registration: Contact person (if different Jansie Cornelius from EAP): Company: EcoPartners (Pty) Ltd Physical address: 177 Weltevreden Road, Berario Postal address: PO Box 73513, Fairland Postal code: 3020 Cell: 072 3914679 Telephone: 011 431 5521 Fax: 086 664 2908 E-mail: jansie@ecopartners.co.za If an EAP has not been appointed please ensure that an independent EAP is appointed as stipulated by the NEMA Regulations, prior to the commencement of the process. The declaration of independence and the Curriculum Vitae (indicating the experience with environmental impact assessment and relevant application processes) of the EAP must also be attached as Appendix 1.

3 4. PROJECT DESCRIPTION Farm Name: Portion 96 of the Farm De Wagendrift 417 JR Application area (Ha) Magisterial district: Distance and direction from nearest town 21 digit Surveyor General Code for each farm portion 4.58 ha Cullinan The property is located within the Tshwane Metropolitan Municipality, 8km to the south west of the settlement Moloto and 20km to the north east of the town of Cullinan. De Wagendrift 417 JR, portion 96 T0JR00000000041700096 Locality map Attach a locality map at a scale not smaller than 1:250000 and attach as Appendix 2 Description of the overall activity. (Indicate Mining Right, Mining Permit, Prospecting right, Bulk Sampling, Production Right, Exploration Right, Reconnaissance permit, Technical co-operation permit, Additional listed activity) If the mining permit is granted, mining will commence in the following way: 1. Removal of the top 0.3m 0.5m of soil with bulldozers. 2. Stockpiling of the topsoil in soil berms. 3. Establishment of plant growth on topsoil berms to protect the soil (if vegetation establishment does not occur naturally). 4. Mining process will continue using mechanised moving equipment such as bulldozers and front end loaders to mine building sand, the product will be stored on site and sold to the relevant clients. Sand will be stockpiled according to their different properties. 5. The topography will be altered, no deep voids is expected. Ramps will be removed by earth moving equipment and the damming up of water will be prevented 6. 1 ha will be mined per financial quarter 7. Total area disturbed will be 5 ha 8. Concurrent rehabilitation

4 5. ACTIVITIES TO BE AUTHORISED (Please provide copies of Environmental Authorisations obtained for the same property as Appendix 3). (For an application for authorisation that involves more than one listed activity that, together, make up one development proposal, all the listed activities pertaining to this application must be indicated. Please note that any authorisation that may result from this application will only cover activities specifically applied for).(attach a proposed site plan, drawn to a scale acceptable to the competent Authority, showing the location of all the activities to be applied for, as Appendix 4) NAME OF ACTIVITY (E.g. For prospecting - drill site, site camp, ablution facility, accommodation, equipment storage, sample storage, site office, access route etc etc etc E.g. for mining,- excavations, blasting, stockpiles, discard dumps or dams, Loading, hauling and transport, Water supply dams and boreholes, accommodation, offices, ablution, stores, workshops, processing plant, storm water control, berms, roads, pipelines, power lines, conveyors, etc etc etc.) Mining site (Application for mining permit) Mining Site (Clearance of vegetation for Mine excavation & Soil stockpile 0.50ha) Aerial extent of the Activity Ha or m² LISTED ACTIVITY (Mark with an X where applicable or affected). APPLICABLE LISTING NOTICE (GNR 983, GNR 984 or GNR 985) 4.58 ha GN 983 Activity 21 5ha GN 983 Activity 27 WASTE MANAGEMENT AUTHORISATION (Indicate whether an authorisation is required in terms of the Waste Management Act). (Mark with an X ) N/A N/A

5 6. PUBLIC PARTICIPATION (Provide details of the public participation process proposed for the application as required by Regulation. Details of the Public Participation process to be followed. 6.1.1. IDENTIFICATION OF INTERESTED AND AFFECTED PARTIES TO BE CONSULTED IDENTIFICATION CRITERIA Will the landowner be specifically consulted? Will the lawful occupier on the property other than the Landowner be consulted? Will a tribal authority or host community that may be affected be consulted? Will recipients of land claims in respect of the area be consulted? Will the landowners or lawful occupiers of neighbouring properties been identified? Will the local municipality be consulted? Will the Authority responsible for power lines within 100 metres of the area be consulted? Will Authorities responsible for public roads or railway lines within 100 metres of the area applied for be consulted? Will authorities responsible for any other infrastructure within 100 metres of the area applied for be consulted? (Specify) Will the Provincial Department responsible for the environment be consulted? Will all of the parties identified above be provided with a description of the proposed mining /prospecting operation as referred above? Will all the parties identified above be requested in writing to provide information as to how their interests (whether it be socio-economic, cultural, Mark with an X where applicable YES NO heritage or environmental) will be affected by the proposed mining project? Other, Specify Please note that the applicant is the landowner. 6.1.2. DETAILS OF THE ENGAGEMENT PROCESS TO BE FOLLOWED Steps to be taken to notify PROVIDE DESCRIPTION HERE interested and affected The first phase of the PPP includes the identification of I&APs. parties(describe the process to be Initial identification of I&APS and stakeholders will take place at the beginning undertaken to consult of the Mining Permit Application; they will include, adjacent landowners, local interested and affected parties including public municipality as well as (State Departments and/or Organs of State) which have meetings and one on jurisdiction in the area. one consultations. NB the affected parties must be specifically consulted It is important to note that the identification and notification of potential regardless of whether or stakeholders will be an on-going process throughout the PPP, as more not they attended public meetings. Photographs information is gathered and contact with people is established. of notice boards, and copies of advertisements Once the project reference number has been obtained from DMR, written and notices notifying potentially interested and notices will be send to all identified I&APs and stakeholders, along with a Krosa affected parties of the Mining Information Document (KMID) inviting them to register as an I&AP for proposed application

6 must be attached as Appendix) the project. A legal notification regarding the Mining Permit Application will be placed in a local newspaper and site notices will be placed on the proposed mining site inviting the public to register as an I&AP. The Basic Assessment Report for Consultation will be compiled and will be made available for comment to all registered I&APs for a period of 30 days. One consultation meeting with registered I&APs and land owners is planned. All registered I&APS will also be afforded the opportunity to comment on the Final BAR once it is submitted to DMR (90 days after the application is submitted). Information to be provided to Interested and Affected Parties. Information to be required from Interested and Affected Parties. (Please note that no evidence of PPP can be attached to this application as the PPP will only commence once the project reference number has been received from DMR) Compulsory The site plan. List of activities to be authorised Scale and extent of activities to be authorised Typical impacts of activities to be authorised ( e.g. surface disturbance, dust, noise, drainage, fly rock etc.) The duration of the activity. Sufficient detail of the intended operation to enable them to assess what impact the activities will have on them or on the use of their land) Other, specify: All the above will be provided to Interested & Affected Parties Compulsory To provide information on how they consider that the proposed activities will impact on them or their socio-economic conditions To provide written responses stating their suggestions to mitigate the anticipated impacts of each activity To provide information on current land uses and their location within the area under consideration To provide information on the location of environmental features on site to make proposals as to how and to what standard the impacts on site can be remedied. requested to make written proposals To mitigate the potential impacts on their socio economic conditions to make proposals as to how the potential impacts on their infrastructure can be managed, avoided or remedied). Other, Specify: Registered Interested & Affected Parties will be requested to comment on Draft and Final Reports and all issues above will be described in the reports.

7 7. DESCRIPTION OF THE ASSESSMENT PROCESS TO BE UNDERTAKEN ITEM Environmental attributes. Describe how the Environmental attributes associated with the development footprint will be determined. Identification of impacts and risks. (Describe the process that will be used to identify impacts and risks. Consideration of alternatives. Describe how alternatives, and in particular the alternatives to the proposed site layout and possible alternative methods or technology to be applied will be determined. Process to assess and rank impacts. Describe the process to be undertaken to identify, assess and rank the impacts and risks each individual activity. DESCRIPTION In order to assess the potential impacts of the mining activities on the receiving environment, the baseline conditions of the study area need to be established. A desktop study will be used to determine the environmental attributes of the proposed site by making use of online data bases, government databases and government tools Using the Status Quo, the likely impacts can be determined that will originate from the specific activity on the receiving environment. The criteria for the description and assessment of environmental impacts were drawn from the Guidelines for EIA Regulations and in terms of the Environmental Conservation Act, 1989 (Act No 73 of 1989) [ECA]. Although the ECA EIA Regulations have been repealed, the Guideline Document still provides good guidance for conducting impact assessments. Activities to be undertaken as part of the proposed prospecting application and its respective operation and decommissioning phases, give rise to certain impacts. For the purpose of assessing these impacts, the project has been divided into two phases from which impacting activities can be identified, namely: Operational phase: All activities involving the operation and maintenance Decommissioning phase: Closure and Rehabilitation: All activities relating to the closure & rehabilitation Site location alternatives were considered, but provided fatal flaws. To the west of the property runs a river, the application area is 500m away from the river. To the north lies a drug and alcohol rehabilitation facility. The application area is owned by the applicant and hence this is the best locality. The mining area will consist out of the active mining site and the product stockpile area to the east of the mining pit. In order to determine the significance of an activity each activity will be rated. The following parameters were used: Significance will be determined by means of the following calculation: Extent of Impact x Duration of Impact x Intensity of Impact x Probability of Occurrence of Impact = SIGNIFICANCE The following tables will be used to provide a value to each of the factors in the calculation: Extent of Impact Site Specific 1 Regional 2 National 3

8 International 4 Duration of Impact Short term 1 Medium term 2 Discontinuous 3 Long term 4 Permanent 5 Intensity of Impact Low 1 Medium 2 High 3 Probability of Occurrence of Impact Improbably (low likelihood) 1 Probable (Distinct possibility) 2 Highly probable (Most likely) 3 Definite 4 Contribution of specialist reports Describe how specialist reports, if required, will be taken into consideration and inform the impact identification, assessment and remediation process. Determination of impact management objectives and outcomes. Describe how impact management objectives will be determined for each activity to address the potential impact at source, and how the impact management outcomes will be aligned with standards. Significance High 161-240 Medium 81-160 Low 1-80 There are no foreseen specialist studies required at this time. If specialist studies are required, the specialist reports will form part of the Basic Assessment Report and the risk identified will be ranked appropriately in order to quantify the scale of possible impacts. Impact management will be done through proposed mitigation measures that will be developed for each impact identified. This mitigation measure may minimise the impact or minimise the extent of the impact, the duration of the impact, the intensity of the impact and/or the probability of the impact. Mitigation measures for all significant impacts will be included in the Environmental Management Plan. The objective of the mitigation measures will be to be compliant to applicable standards.

9 8. OTHER AUTHORISATIONS REQUIRED LEGISLATION SEMAs National Environmental Management: Air Quality Act National Environmental Management: Biodiversity Act National Environmental Management: Integrated Coastal Management Act National Environmental Management: Protected Areas Act National Environmental Management: Waste Act National legislation Mineral Petroleum Development Resources Act National Water Act National Heritage Resources Act Mark with an X where applicable AUTHORISATION REQUIRED APPLICATION SUBMITTED YES NO YES NO This application Others: Please specify Please provide proof of submission of applications in Appendix 5. In the event that an authorization in terms of the National Environmental Waste Management Act is required for any of the activities applied for please state so clearly in order for such an authorisation to be considered as part of this application. 9. DRAFT EMPr For consultation purposes, provide a high level approach to the management of the potential environmental impacts of each of the activities applied for. ACTIVITIES (E.g. For prospecting - drill site, site camp, ablution facility, accommodation, equipment storage, sample storage, site office, access route etc etc etc E.g. for mining,- excavations, blasting, stockpiles, discard dumps or dams, Loading, hauling and transport, Water supply dams and boreholes, accommodation, offices, ablution, stores, workshops, processing plant, storm water control, berms, roads, pipelines, power lines, conveyors, etc etc etc.) Mining excavation PHASE (of operation in which activity will take place). State; Planning and design, Pre-Construction Construction, Operational, Rehabilitation, Closure, Post closure. SIZE AND SCALE (of Disturbance) (volumes, tonnages and hectares or m²) TYPICAL MITIGATION MEASURES (Eg, storm water control, dust control, noise control, access control, rehabilitation etc., etc.,) Operational 4.58 ha Storm water control Dust control Access control Waste management Land capability Noise monitoring Topsoil storage COMPLIANCE WITH STANDARDS (A description of how each of the recommendations herein will comply with any prescribed environmental management standards or practices that have been identified by Competent Authorities) GN 702 South African guidelines (SANS 1929:2005) Dust Regulations SANS Noise Standards

10 ACTIVITIES (E.g. For prospecting - drill site, site camp, ablution facility, accommodation, equipment storage, sample storage, site office, access route etc etc etc E.g. for mining,- excavations, blasting, stockpiles, discard dumps or dams, Loading, hauling and transport, Water supply dams and boreholes, accommodation, offices, ablution, stores, workshops, processing plant, storm water control, berms, roads, pipelines, power lines, conveyors, etc etc etc.) Storage of product stockpile Mining Site (Mine excavation & product stockpile area) PHASE (of operation in which activity will take place). State; Planning and design, Pre-Construction Construction, Operational, Rehabilitation, Closure, Post closure. SIZE AND SCALE (of Disturbance) (volumes, tonnages and hectares or m²) TYPICAL MITIGATION MEASURES (Eg, storm water control, dust control, noise control, access control, rehabilitation etc., etc.,) Spillage control Operational 0.50 ha Dust Control Erosion Control Decommissioning & Closure 5.08 ha Rehabilitation COMPLIANCE WITH STANDARDS (A description of how each of the recommendations herein will comply with any prescribed environmental management standards or practices that have been identified by Competent Authorities) Dust Regulations 10. CLOSURE PLAN In the space provided under each heading below, please provide a high level description of the plan for closure and the information that will be provided in the draft EMPr accompanying draft basic assessment report or environmental impact reports going forward. Baseline environment Describe how the baseline environment will be determined with the input of interested and affected parties and due cognizance of the current land uses and or existing biophysical environment The baseline environment will be described in the BAR documents. All registered I&APs will be afforded the opportunity to comment on the BAR. Comments related to the baseline environment will be included in the final BAR. Closure objectives Describe the closure objectives and the extent to which they will be aligned to the baseline environment The overall goal for closure of the mining site is to re-instate the predetermined land-use by the land owners, neighbours and community, ensuring that the land is stable and safe in the long-term. The closure objectives apply to the mining area in its final closed state and not whilst the site is in transformation towards this state. They nevertheless provide guidance during the operational phase. Closure objectives relate to the following:

11 Physical stability: Ensure the topography does not present dangers and ensure water will not dam up. Environmental quality: To ensure that local environmental quality is not adversely affected by possible physical effects and chemical contaminants arising from the mining site after completion of mining activities. Health and safety: To limit the possible health and safety threats to humans and animals using the rehabilitated mining area after completion of mining activities. Land capability/land-use: To ensure continuation or to the re-instate a suitable land capability over as large as possible area affected during mining. Aesthetic quality: To leave behind a rehabilitated mining site that is neat and tidy, giving an acceptable overall aesthetic appearance. Biodiversity: To encourage the re-establishment of indigenous and/ or appropriate vegetation on the rehabilitated mining site such that the biodiversity is largely re-instated over time, as well as protect the undisturbed areas to maintain/enhance the biodiversity of these areas. Rehabilitation Plan Describe the scale and aerial extent of the prospecting or mining listed activities to be authorised, including the anticipated prospecting or mining area at the time of closure, and confirm that a site rehabilitation plan drawn to a suitable scale will be provided in the draft EMPr to be submitted together with the draft EIR or Basic Assessment Report as the case may be. The applicant will implement concurrent rehabilitation of the 4.58 ha mining site. Mining will take place in sections of 1.15 ha, the sections will gradually be rehabilitated as the mining continues to the next section. Rehabilitation will involve placing topsoil over disturbed area and ensuring plant growth establishes and include profiling of the ramps to remove any open voids. Roads will remain post mining, to be used by the landowner. No residue stockpile will remain on site. Rehabilitation Cost Describe how the rehabilitation cost will be determined and provide a preliminary estimate thereof The success of rehabilitation and vegetation establishment will monitored on a 6 monthly basis (early winter and after the first rains) by conducting of rehabilitation audits. Where required repair to side slopes, erosion gullies and vegetation will be managed. Krosa recognises the need for the determination of appropriate and accurate mine closure costs and that the financial provision made, based on these costs, is a key business requirement. Aligned to this commitment, the following key considerations are given to the determination of the closure costs:

APPENDIX 1 13

APPENDIX 2 14

15 APPENDIX 4 DECLARATION OF THE EAP I, Jansie Cornelius, declare that General declaration: I act as the independent environmental practitioner in this application I will perform the work relating to the application in an objective manner, even if this results in views and findings that are not favourable to the applicant I declare that there are no circumstances that may compromise my objectivity in performing such work; I have expertise in conducting environmental impact assessments, including knowledge of the Act, Regulations and any guidelines that have relevance to the proposed activity; I will comply with the Act, Regulations and all other applicable legislation; I will take into account, to the extent possible, the matters listed in regulation 8 of the Regulations when preparing the application and any report relating to the application; I have no, and will not engage in, conflicting interests in the undertaking of the activity; I undertake to disclose to the applicant and the competent authority all material information in my possession that reasonably has or may have the potential of influencing - any decision to be taken with respect to the application by the competent authority; and - the objectivity of any report, plan or document to be prepared by myself for submission to the competent authority; I will ensure that information containing all relevant facts in respect of the application is distributed or made available to interested and affected parties and the public and that participation by interested and affected parties is facilitated in such a manner that all interested and affected parties will be provided with a reasonable opportunity to participate and to provide comments on documents that are produced to support the application; I will ensure that the comments of all interested and affected parties are considered and recorded in reports that are submitted to the competent authority in respect of the application, provided that comments that are made by interested and affected parties in respect of a final report that will be submitted to the competent authority may be attached to the report without further amendment to the report; I will keep a register of all interested and affected parties that participated in a public participation process; and I will provide the competent authority with access to all information at my disposal regarding the application, whether such information is favourable to the applicant or not all the particulars furnished by me in this form are true and correct; will perform all other obligations as expected from an environmental assessment practitioner in terms of the Regulations; and I realise that a false declaration is an offence in terms of regulation 71 of the Regulations and is punishable in terms of section 24F of the Act.