Outage Management Redesign Consultation Process (SE-109) September 4, 2013

Similar documents
SE-109: Outage Management Process Redesign Interim Process Training. Mark Gojmerac, IESO December 11, 2013

Outage Management Redesign Consultation Process (SE-109) Proposal for Process Redesign May 14, 2013

Outage Management Process Redesign (SE-109)

ADEQUACY REPORTING UPDATE

NPCC 2016 Ontario Interim Review Of Resource Adequacy

NPCC 2017 Ontario Interim Review of Resource Adequacy

Outage Management Process Redesign (SE-109)

Standard MH-TPL Transmission System Planning Performance Requirements

Outage Coordination Training MISO Training

Standard TPL Transmission System Planning Performance Requirements

OTHER REVENUES REGULATED HYDROELECTRIC

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations

Straw Proposal. Outage Management System Replacement. October 18, 2013

Roadmaps for Demand Response & Storage

Nova Scotia Power System Operator (NSPSO)

1.3 Planning Assumptions and Model Development

OTHER REVENUES REGULATED HYDROELECTRIC

TSOs, taking into account the following: Whereas

Market Rule Amendment Proposal

EIPC Scenarios for Analysis in 2014

PSE Attachment K Puget Sound Area Transmission Meeting

ENERGY MARKET PARTICIPATION

Standard Development Timeline

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

ERCOT in 2018: Challenges & Opportunities

Standard Development Timeline

Extended Short-Term Unit Commitment. Issue Paper/Straw Proposal

NPCC 2018 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2019 TO 2023 APPROVED BY THE RCC ON DECEMBER 4, 2018

Thunder Bay Sub-Region Local Advisory Committee Introductory Meeting. November 26, 2015

Resource Capability Testing

Standard Development Timeline

Outage Scheduling Manual

Regulation 101 Webinar. April 25, 2017

Ancillary Services Matrix

OUTAGE COORDINATION PROCESS

1. What level of consultation was undertaken to assess whether market rule amendments would be required to support this change in DR3 triggering?

Two Settlement PJM /06/2016

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Standard Development Timeline

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

SPP Emergency Operations: 2016 Summer Preparedness Workshop

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

A Transmission Planning Case Study for Wind Integration CREZ in ERCOT

Assessment of Load Shed Service for Import (LSSi) Product

Distributed Energy Resources (DER) Update Behind the Meter Generation (BtMG) Visibility

OUTAGE COORDINATION PROCESS

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

IESO Stakeholder Feedback for Demand Response Auction November Demand Response Auction Review/ Summary of October 20 Meeting

Power System Operation Procedure: Facility Outages

Expanding Capacity Eligibility

DESIGN NOTE FOR THE COORDINATION OF ASSETS: PART I - OUTAGE PLANNING

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

Standard TPL System Performance Following Extreme BES Events

NPCC 2015 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2016 TO 2020 DECEMBER 2015

Greater Ottawa Region Local Advisory Committee Meeting #5. June 21, 2016

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

JCM Drill Down Report. May 27, 2015

Storage as a Transmission Asset Stakeholder Comment Template

Storage as a Transmission Asset:

Pre-Scheduling Operations

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability

Energy Uplift (Operating Reserves)

Capacity Performance Training. March 16, 2015

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Renewable Integration: Market Schedule and CMSC, Communications for Variable Generation Dispatch, Market Participant Outreach

Post SAR July day Formal Comment Period with Parallel Ballot July 2013

Mapping Document for FAC-010-3

Scheduling Operations

Storage as a Transmission Asset Stakeholder Comment Template

Day-Ahead Energy Market

PJM Manual 10: Pre-Scheduling Operations Revision: 36 Effective Date: December 22, Prepared by Operations Planning Division

NORMES DE FIABILITÉ DE LA NERC - IRO (VERSION ANGLAISE)

FERC Order 841 Electric Storage Resource Compliance Straw Proposal Overview

Connection Study Requirements

MISO-PJM Joint and Common Market Drill Down Report

Standard TPL System Performance Under Normal Conditions

European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.

MOD Data for Power System Modeling and Analysis

Putting Ontario s Long-Term Energy Plan Into Action

MOD-001-1a Available Transfer Capability Implementation Document

Reliability Coordinator Procedure

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

Extended Short-Term Unit Commitment. Draft Final Proposal

Business Process. BP_SO_12.1 Unit Testing

NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS

Canadian Wind Energy Association Operations and Maintenance Summit

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

DRAFT STUDY PLAN FOR 2018

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION

MOD Steady-State and Dynamic System Model Validation

Power System Operation Procedure Glossary Of Terms

MISO-PJM Joint and Common Market Drill Down Report

Data Viewer, Member Voting, Account Manager, DR Hub, Power Meter, and Data Miner Roadmaps

SPP at a Glance. Located in Little Rock. Approximately 600 employees

Transmission System Security and Planning Standards

Transcription:

Outage Management Redesign Consultation Process (SE-109) September 4, 2013

Agenda Stakeholder Feedback & IESO Response Final Process Redesign Proposal Suggestion for Software Capabilities Interim Process Redesign Proposal Criteria for Pre-Approvals Changes to the Interim Process Redesign Proposal Table-Top Session on Interim Process Redesign Discuss Interim Process Implementation Plan Next Steps 2

Feedback & Response: Final Process Redesign Proposed compensation mechanism for revocation of mid-term approvals approved by stakeholders At Risk declarations in the mid-term process may be confused with those used in the 18 Month Outlook process. 18 Month Outlook only provides At Risk declarations for outages starting within 9 months. The mid-term process will provide At Risk declarations for outage starting within 7 months. IESO will propose using either two distinct declarations or remove the declaration from the 18 Month Outlook process 3

Feedback & Response: Software Capabilities Broad range of recommendations received with major themes being: Greater transparency of outage information Automated communications & notifications Configuration capabilities (flexibility in creating, viewing and modifying outage requests) IESO will consider recommendations that contribute to the objectives of this process redesign initiative: Minimizing reliability risks to the power system Improving process efficiencies between the IESO and market participants. 4

Feedback & Response: Interim Process Redesign Manual tracking of final approvals may create confusion Similar risks exist for IESO assessments in real-time Existing software doesn t provide reliable means of tracking Efficiency gains of an implied final approval may be offset by the additional effort required to track eligible outages Deadline for approving pre-approved outages is impractical Alternatively, an end of business day deadline provides opportunity for mitigation in the event of a rejection Proposed submission & approval deadlines may not be suitable for commissioning activities Scheduling flexibility for lower impact commissioning activities will be provided under the pre-approval criteria 5

Feedback & Response: Criteria for Pre-Approval Broad range of suggestions received Approval by validation-only approach would significantly reduce eligible outages: Significant restrictions to participant scheduling flexibility Inclusion of an IESO reliability assessment expands preapproval eligibility Proposed criteria assumes criteria validation + reliability assessment being used (including the removal of implied final approval) Achieves greater scheduling flexibility while satisfying the principles of low system impact and minimal assessment effort 6

Feedback & Response: Proposed Pre-Approval Criteria Transmission & Distribution Outages, restrictions, de-ratings or changes in configuration of transmission facilities operated below 50 kv that: unload step-down transformers or individual windings of stepdown transformers; require paralleling or separation of low voltage buses via operation of the low voltage bus tie breaker; result in a load transfer of 20 MW or more from one step-down transformer station to another. Not included are those outages, restrictions, de-ratings or changes in configuration of transmission facilities operated below 50 kv that may adversely affect the operation of another market participant. tracking of these facilities requires further discussion 7

Feedback & Response: Proposed Pre-Approval Criteria (con t) Transmission & Distribution (con t) Power system auxiliaries that impose a loss of redundancy and have a recall 15 minutes; > 15 minutes if the loss of the redundant in-service auxiliary places no additional risk to the IESO controlled grid. Dispatchable Loads In addition to the criteria under transmission & distribution, those outages, restrictions, de-ratings or changes in system configuration that result in an atypical change of more than 20 MW. 8

Feedback & Response: Proposed Pre-Approval Criteria (con t) Generators Outages, restrictions, de-ratings or changes in the operation of a generator with a recall 15 minutes De-ratings to a level greater than a facilities forecasted energy production provided that: The facility cannot shift energy from one hour to another (wind, solar, run of the river hydro) The de-rating is limited in duration (to be determined) Segregated Mode of Operation (SMO) Power system auxiliaries that impose a loss of redundancy and have a recall 15 minutes; > 15 minute recall if the loss of the redundant inservice auxiliary places no additional risk to the IESO controlled grid. All generating facility plant auxiliaries with a recall of 15 minutes that affect more than a single generator or aggregate of generators where the loss of an additional element results in multiple unit/aggregate shutdowns. 9

Feedback & Response: Proposed Pre-Approval Criteria (con t) Tests All system tests as described in Market Manual 7.3, Section 1.3.11 provided they have a recall of 15 minutes and are not considered Power System Tests as per Market Rules Chapter 5, Section 6.6. Testing of generation units with a recall of 15 minutes, including: in-service or commissioning tests testing of de-rated units at levels above the de-rated levels; testing of units currently on outage; and tests of facilities providing ancillary services 10

Interim Process Proposal: Market Rule Changes Re-instate the requirement to request final approval and provide actual start and end times for pre-approved outages Change the submission deadline time for all submissions from 23:59 EST to 16:00 EST 11

Interim Process Proposal T-21 Calendar Days T-14 Calendar Days T-5 Business Days T-3 Business Days T-2 Business Days T-1 Business Days T=0 (Outage Starts) Process is mandatory for all planned outages Submissions due at 16:00 EST, T-5 Business Days, Approvals due at 16:00 EST, T-3 Business Days 14 Day Advance Approval process remains unchanged from today Submissions due at 16:00 EST, T-21 Calendar Days, Approvals due on the last business day at 16:00 EST, that is at least T-14 Calendar Days in advance Pre-approved outages can be requested up to 16:00 EST, T-2 business days Manual confirmation (like 14 day process) required (auto-processing unavailable) Must meet pre-approved criteria (to be developed within SE-109) Still subject to IESO advance approval / rejection by 16:00 EST, T-1 business days (validation of criteria and a reliability; auto-validation unavailable) Advance approval implies final approval and no need to report actual start or end times (as long as scope remains unchanged) Forced outages are incorporated up to real-time (T=0) Timestamp retention rules for rejection/revocation/recall Must be rescheduled within 5 business days Retention available only once for rejections 12

Table Top Session: Interim Process Proposal 13

Table Top Session: Submissions & Assessments Any planned outage submitted prior to the submission deadline for 3 day advance approval (16:00 EST on Sept 4) will be assessed by the end of the 3 day advance approval assessment period (16:00 EST on Sept 6) This includes any outage eligible for pre-approval Outages eligible for pre-approval can be requested for pre-approval up to 2 business days in advance of the date the outage is scheduled to start (16:00 EST on Sept 9) and will be assessed by the end of 1 business day in advance (16:00 EST on Sept 10) For pre-approvals, IESO will first validate whether the outage meets the submission criteria; then perform a reliability assessment. 14

Pre-Approval Examples: Submission Generator A protection outage scheduled to start Sept 11 and submitted to the IESO on Sept 6 (after the deadline for requesting 3-day advance approval) MP does not confirm to the IESO that the outage is submitted for preapproval by 16:00 EST on Sept 9 Without a confirmation, IESO rejects the outage as the MP failed to meet the submission requirements. 15

Pre-Approval Examples: Validation Transmission Line A protection outage with a recall of 60 minutes scheduled to start Sept 11 and submitted to the IESO on Sept 6 (after the deadline for requesting 3-day advance approval) MP confirms with the IESO that the outage is submitted for pre-approval by 16:00 EST on Sept 9 IESO validates that the outage meets the pre-approval criteria and proceeds with a reliability assessment The outage passed validation because it was a loss of redundancy and a recall of > 15 minutes is acceptable since the loss of the B protection would not pose an additional risk to the IESO controlled grid. 16

Pre-Approval Examples: Assessment Load transformer ABC (yellow) outage scheduled to start Sept 11 and submitted to the IESO on Sept 6 (after the deadline for requesting 3-day advance approval) MP confirms with the IESO that the outage is submitted for pre-approval by 16:00 EST on Sept 9 Outage passes IESO validation but still requires a reliability assessment Since transformer ABC outage requires load to be transferred to an alternate supply, the IESO determines the load transfer creates a thermal violation due to another transmission outage (blue) already in-progress and rejects the transformer ABC outage for security reasons. 17

Pre-Approval Examples: Stakeholder Scenarios 18

Discussion: Interim Process Implementation Implementation proposed for Feb 2014 Ahead of spring maintenance season Allows for sufficient feedback on documentation & software changes Documentation Market Rules, Market Manuals Online Outage Form Guideline Software Changes IESO Software Online Outage Form Application Programming Interface Training Format & Materials 19

Next Steps Sept 5 3 week comment period on Interim Process rule changes closes Sept 13 Stakeholder feedback on Pre-Approval criteria and proposed Interim Process changes due Sept 17 Next Technical Panel Meeting Opportunity for Interim Process rule changes to be voted on for IESO Board approval Sept 27 IESO response to stakeholder feedback due Early Oct Next Stakeholder Meeting (Pre-Approval Criteria & Market Manual Changes) 20

Thank You Questions/Comments? 21