CMPDI. 4.6 Mine Closure Plan

Similar documents
Terms of Reference (ToR) for EIA BUILDING STONE QUARRY OWNED BY LINEJ T.P

Overburden dumps are stacked separately as per the guidelines and the same will be used for backfilling in mined out area.

2) A copy of the document in support of the fact that the Proponent is the rightful lessee of the mine should be given.

Environment Management Plan

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

RECLAMATION OF COAL MINE VOID

STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDELINES FOR PREPARATION OF MINE CLOSURE PLAN

PROPOSED TERMS OF REFERENCE

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS

Proposed Terms of Reference for EIA studies

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE

PROPOSED TERMS OF REFERENCE (TOR) FOR

ENVIRONMENTAL MANAGEMENT PLAN

SANDCRETE ENGINEERING NIG. LTD. Background Information Document (BID)

ENVIRONMENT MANAGEMENT PLAN. For Excavation of Brick Earth (Total Mining Area Ha.) (for Manufacturing of Bricks)

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING

EIS TABLE OF CONTENTS

Environmental Policy Statement:

TERMS OF REFERENCE. Notes for NEPA for Generic Terms of Reference

Appendix 4. Soil Management Plan

ENVIRONMENT MANAGEMENT PLAN

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Terms of Reference. As Required by the Environment Act For Preparation of an Environmental Assessment Report

ENVIRONMENTAL MANAGEMENT PLAN

Granite (Building Stone) Quarry owned by Biju. V.T at Aryanad Village, Nedumangad Taluk, Thiruvananthapuram District, Kerala

8 Geology, Hydrology & Hydrogeology

Notes for NEPA for Generic Terms of Reference

Piplyakamil Murrum Quarry located at Khasra No 90/2, near Village Piplyakamil, Tehsil- Dharampuri, District Dhar M.P

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Granite (Building Stone) Quarry owned by Kunhi Muhammed at Melmuri Village, Eranad Taluk, Malappuram District, Kerala

ENVIRONMENTAL MANAGEMENT PLAN

2. PRE-FEASIBILITY REPORT

V: PROJECT SCOPING & METHODOLOGY

1. PRE-FEASIBILITY REPORT

MINING REGULATIONS IN FOREST AND ECO-FRAGILE AREAS A PRESENTATION BY RAJEEVA, IFS, ADDITIONAL PRINCIPAL CHIEF CONSERVATOR OF FORESTS.

PRE FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT

EMP ENVIRONMENTAL MANAGEMENT PLAN FOR BUILDING STONE QUARRY M/S. SIDDARTHA STONE CRUSHING INDUSTRIES Sy.No. 1118/4, Bangaramakki Bengre II Village, Bh

DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF MINING AND RECLAMATION. Coal Refuse Disposal - Site Selection

Preliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and

Environmental Impact Statement. Avoca Tank Project

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

Chapter 4. Airport Authority Governance, Statutes and Policies

Reclamation after Mine Closure Procedure Considering Biodiversity Offset and Ecological Restoration: A need of the hour.

Base Metal and Iron Ore Mining

TABLE OF CONTENTS. Atlas-Campaspe Mineral Sands Project Environmental Impact Statement

Deccan Cements Limited, Bhavanipuram Lime stone Mine -2, Mahankaligudam Palakeedu, Suryapet(Dist). Telangana MoEF No: J-11015/497/2007-IA II

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT

SLAUGHTERHOUSES AND ABATTOIRS

ENVIRONMENTAL IMPACT ASSESSMENT

Highway 11 Realignment

KYNSHI-I HEP (270 MW), MEGHALAYA

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha)

LEBANON WATER SUPPLY AUGMENTATION PROJECT ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

City of Mississauga Environmental Impact Studies Terms of Reference 2002

STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE

Environmental Impact Assessment (EIA)

E1184 v1. 6. Environmental Management Plan (EMP)

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

Annex F Scoping Checklist

Verification of controlled wood supply according to FSC-STD (V2-1) EN Annex 3 and FSC-STD Item 5.

Factor Potential Effects Mitigation Measures

CHAPTER SURFACE MINING AND RECLAMATION PLAN REGULATIONS

AGENDA ITEM NO Particulars of Forests: (iv) Name of Forest Division and Forest area involved. Jhunjhunu Forest Division 95.

Operating and Reclamation Plan

No.J-11015/307/2006-IA.II(M) Goverment of India Minister of Enviroment,Forest and Climate Change Impact Assessment Division ***

STATE EXPERT APPRAISAL COMMITTEE GOVERNMENT OF PUNJAB (Office of the Secretary) Vatavaran Bhawan, Nabha Road, Patiala

Environmental Checklist: 26. Forestry Projects(1) Confirmation of Environmental and Social Considerations. Environmental Item.

Mining of Minerals MINING LEASE of BAUXITE Mining Project for CARBORUNDUM UNIVERSAL LTD. S.No. 146/147 PAIKI

NEWNES JUNCTION SAND AND KAOLIN EXTRACTION PROJECT

Mining of Minerals MINING LEASE of LIME STONE Mining Project for GAYTRI MINERALS.

ENVIRONMENT MANAGMENT PLAN

(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)

The Standard Criteria, current as of November 2013, as defined in Schedule 4 of the EP Act are as follows:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

Performance Standard 6

S e c t i o n B i o d i ve r s i t y

NOTE COVER PAGE GENERAL

NOTICE OF A PROPOSED CHANGE TO AN APPROVED DEVELOPMENT

1 Name of the Project Gonua Iron & Mn. Mine of Sri Pawan Kumar Ahluwalia

JW/docDM AEE for Non-Minimum Impact Activities

DRAFT CH 10 & CH 11 October 7, 2015 From: SLDCProposedAmendmentsBCCPacket part3-1Nsm

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES

8 Geology, Hydrology, Hydrogeology

WETLAND RESTORATION PROGRAMS IN THE PRUT RIVER BASIN

ENVIRONMENT MANAGEMENT PLAN

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB MINISTRY OF ENVIRONMENT AND FORESTS, GOVERNMENT OF INDIA

Sustaining Terrestrial Biodiversity: Saving Ecosystems and Ecosystem Services

Environmental Planning and Assessment Act 1979

Performance Standard 6 V2

ENVIRONMENT DIVISION COAL INDIA LTD HEADQUARTERS

February Reference Section in Supplemental. Reference Section in Consultants Reports. Reference Section in Application. TOR No.

Transcription:

4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2. Social Aspects 3. Financial Aspects Technical Aspects: The following technical aspects would be reviewed in the final mine closure planning. Details can be worked in closure plans envisaged to be prepared. Safety hazards including management of fire and subsidence: In the mine closure plan, action for control of likely fire areas of the mines will be discussed. Action will also be suggested to cover all the safety aspects. Management of Pit Slopes: The final quarry slopes shall be so designed and then subsequently developed that after the closure of the mine, there is no likelihood of any slope failure. The final slope of the quarry has been designed with above consideration. However, strict compliance with the proposed final slope of quarry would be made as given in Quarry & Surface Layout Plan and subsequent slope stability studies. Management of hydrology and hydro-geology: In the mine closure plan, the surface flow pattern of precipitation and mine water would be clearly developed and water channel suitably laid down so that it does not disturb the general hydrology of the area. 188

Details of decommissioning of the infrastructures: The decommissioning of the various infrastructures developed for the mine like office complex, roads, pipelines and transmission line etc. shall be planned in details so that the land occupied by these infrastructures are released. However, before such decommissioning, the possibility of re-use of these infrastructures for the neighbouring mines shall be explored. Closure of entry to the open-cast mine : All entries to the mine must be planned to be effectively closed so that illegal mining from these openings and safety hazards by way of entry of fire and water etc. will be prevented in the abandoned mines. Environmental Aspects: This would include the following Management of final voids: In the mine closure plan, voids due to mining are to be dealt and the final land use plan will include filling of the voids for land reclamation where possible and for hydro reclamation where feasible. The study on slope study will be made by some scientific agency and in final closure plan their suggestions will be incorporated. Reclamation of forests/vegetation: It is to be ensured that in the final land use plan, all vacant land acquired for the project is afforested Channelisation of available water: If the mine is having sufficient water and if on closure, the mine water flows into the surface water courses, channelising this water for surrounding community for their irrigational/domestic uses may be taken up. This can be planned by providing structures involving one time costing Management of Recharge Areas: The pre-mining and post mining scenario on the hydrogeological recharge system would be included in the closure plan. 189

Acceptable Surface and Ground Water Flows: In the final closure plan of the mine, wherever the mine water is likely to flow out to surface and meet the surface water sources; the quality of water from such mines would be assessed and flow pattern designed in the final plan. Land Use During Mining Pre-mining vs. Post-mining land use Post mining Land Use (Conceptual) Particulars Area Particulars Area (ha) (ha) 1. Area to be 80.0 1. Area to be excavated 80.0 excavated 2. Mine 15.0 2. Mine Pheriphery & safety 15.0 Pheriphery & safety zone zone 3. Approach 10.0 3. Approach road 10.0 road 4. Coal storage 10.0 4. Coal storage & 10.0 & handling/office/ Workshop/Store/ power supply arrangements/e TP (including haul/service roads ) handling/office/workshop/stor e/power supply arrangements/etp (including haul/service roads ) External dumps5.e 120.0 External dumps5.external 120.0 dumps TOTAL 235.0 TOTAL 235.0 Alternative use of land: For internal OB dump, vegetation and afforestation has been planned as a final land use. However, for areas other than OB dumps and voids, the alternative land use would be deliberated in the closure plan. While agriculture is the best land use if it is supported by some irrigation facilities, vegetation will be second utility of the land which can be planned. A comparative statement showing the post-mining vis-à-vis during-mining land use of the additional area to be acquired for the project is tabulated above. 190

Social Aspects: The social aspects of land use planning relating to mine closure would include the following: Re-deployment of Workforce: The company employees will be gainfully engaged in the neighbouring projects after cessation of mining activities. Management of Community Facilities: In view of the short life of the project no new community facility will be created. However, the existing facilities of adjoining areas will be strengthened. CLOSURE ACTION PLAN Closure planning is a life-of-mine exercise that begins with the commencement of mining operations and continues till post closure. The dynamic nature of closure planning requires regular and critical review to reflect changing circumstances as a result of any operational change, new regulation, new technology and remain flexible enough to cope with unexpected events. Following steps have to be undertaken in relation to Mine Closure Planning: (a) Dense forest consists the leasehold area of the project, so the ecological aspects of mine closure should be duly taken care of. Study with regards to impact on Flora & Fauna due to mining activity shall be taken up. (b) In order to identify potential impact necessary hydrogeological studies into postmining groundwater recharge has to be done. The void of the mine can be proposed as a water resource to be utilized for aquaculture. (c) As a detailed component of the Closure Plan, a Decommissioning Plan is to be developed towards the final stages preferably 5 years prior to tentative closure of mine. Once established, it may be updated annually. Closure Cost The cost of implementing the closure plan to eliminate or reduce the impact identified above has to be estimated. Although no statutory guidelines exist on financial 191

provisioning for mine closure activities as yet, financial provisions of Rs. 2.50/t for closure cost are proposed to be provided from revenue expenditure in order to undertake mine closure activities. This closure cost may be reviewed under the changing circumstances and new legislative requirements. 4.7 Impact on Flora and Fauna and Conservation Plan The direct impacts of mining disturbances to land surfaces are usually significant, with the likelihood of destruction of biodiversity within natural ecosystems through the removal of natural soils, plants and animals. However, mining is a temporary land use because the mineral deposit is finite and eventually gets exhausted. The social and legislative context of mining in many parts of the world today means that some form of rehabilitation goals will have to be set for the post closure situation, and nowadays these are often determined prior to the granting of planning and operating permission for a new mine. In this context, ecological rehabilitation of mined land represents one of, if not the best approach to promote both sustainability and the safeguarding of biodiversity. From the Flora-Fauna survey, it can be seen that, the core zone (PA) of the proposed Lekhapani OCP does not have any endangered species of Flora or Fauna. Overall status of Flora & Fauna of the study area is normal and satisfactory. Major Features in the Study Area (Core Zone) Feature National Park / Sanctuary Biosphere Reserve /Tiger Reserve/ Elephant Reserve /any other Reserve Habitat for migratory birds Corridor for animals of Schedule I & II of the Wildlife (Protection) Act, 1972 Name/ Status Nil Nil Nil Nil 192

Flora & Fauna in the Core Zone It has been observed in the flora & fauna study that no rare, endangered species of flora and fauna is found in this area. Conservation Measures Ecological restoration is about a broad set of activities (enhancing, repairing, or reconstructing degraded ecosystems and optimizing biodiversity returns). In essence, the restoration of mined land is based around ecosystem reconstruction. It is usually a question of the re-establishment of the capability of the land to capture and retain fundamental resources (energy, water, nutrients and species). With this in view, it is proposed to plant the trees and undertake development of green belt in the project area at all possible places. As a trend, the faunal population is on decreasing trend in general. Arrangement of adequate funds has been made for enhancing, repairing, or reconstructing degraded ecosystems and optimizing biodiversity returns. Development of Habitat Technical Reclamation Because of the opencast mining, the topography of disturbed land will be suitably reclaimed by physical methods such as: Easing of steep slopes Terracing Land leveling Bunding Contour trenching Gulley plugging etc. 193

Reclamation of Back-filled Area The back-filled area will be biologically reclaimed by suitable means. Green Belt around the Mine There is need for creating green belt (approximately 30m wide) in the safety area to provide an effective dust, noise and sight curtain in the periphery of mining area. The trees to be planted in the green belt area shall act as buffers and shock absorber against dusts, noise and stone flying. Trees in the green belt will be tall, wind firm, broad leaved and evergreen. Species for Plantation and Green Belt Development The species selected for plantation on the internal dump and also in the other areas will be of mixed type having a combination of fast and slow growing species with an ultimate aim to have triple storey plantation i.e. a combination of species of tall, intermediate and short height. A list of the species suggested for afforestation has already been indicated earlier in this chapter. However, in any case monoculture will not be adopted, because ecologically these are more unstable communities. The schedule and break-up of location for plantation is given earlier in this chapter. Post-mining Land use Plan of Core Zone has been enclosed as Plate No. XIII. Water Treatment & Water Quality Water will be discharged only after suitable treatment. As such, mine discharge from the project is not likely to have any impact on the faunal species diversity within the terrestrial and aquatic habitats of downstream water course. 4.8 Effects of Traffic Movement Suitable mitigation measures shall be taken to minimize the ambient air pollution on both sides of the road, noise nuisance, formation of ruts & potholes on the surface of the road. 194

4.9 Visual/Aesthetic Effects Suitable mitigation measures are envisaged for this project to eliminate spots of eyesore due to excavation of coal and OB as well as transportation, water logging by provision of proper drainage, land reclamation (both technical and biological) and afforestation. 195