Totaling approximately 617,000

Similar documents
Danielle Shetler - Structural option Courtyard by Marriott Lancaster, PA

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

Temecula Medical Center Temecula, CA

Erie on the Park. Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1

The building on 250 West Street is a 7-story multi-use that provides space for parking,

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

TECHNICAL REPORT II STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems

Technical Report #2. Matthew R Peyton

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

Crossroads at Westfields Building II

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal

Stephan Northrop Structural Option Dr. Linda Hanagan. North Shore Equitable Building Pittsburgh, PA Senior Thesis Proposal

Steel Expansion. Located along the Grand River in

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

William W. Wilkins Professional Building Columbus, Ohio

Drexel University Race Street Dormitory REVISED THESIS PROPOSAL Doug Tower Structural Advisor: Kevin Parfitt 2/7/07

OVERALL STRUCTURAL SYSTEM

CHAPTER 7 STRUCTURAL SYSTEMS

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

Hilton Baltimore Convention Center Hotel Western Podium

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Structural Breadth. Landmark Façade

Technical Report 1. Seneca Allegany Casino Hotel Addition. Salamanca, NY

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Spring Hill Suites Marriott

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2

Pro-Con Structural Study for Alternative Floor Systems October 27, 2004

Jonathan R. Torch Technical Report 2 Columbia University. Technical Report 2. Pro-Con Structural Study of Alternate Floor Systems

North Mountain IMS Medical Office Building

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

Caitlin Ferrell Structural Option Dr. Boothby, AE Faculty Consultant. Erie Convention Center and Sheraton Hotel

Hilton Baltimore Convention Center Hotel Western Podium

These systems are evaluated on the basis of serviceability issues such as:

Hilton Baltimore Convention Center Hotel Western Podium

Rutgers University Law School Building Addition and Renovation Camden, NJ

Expanding the Indiana Convention

Pre-schematic Considerations. Who. What. Where

Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania

Design Criteria. Analysis and Design of a High Rise Steel Braced Frame Core 22

Taking It to the Limit BY JOHN ROACH, PE, AND JOHN BOEKELMAN, SE, PE, RA CannonDesign

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

fifteen design for lateral loads Lateral Load Resistance Load Direction Lateral Load Resistance

Pro-Con Structural Study of Alternate Floor Systems

LEGAL. Lessons BY JEFF THOMPSON, P.E., AND ERIKA YARONI

OF THREE NEW BUILDINGS BEING CONSTRUCTED TO REPLACE THE EXISTING COMPLEX. THE FLOOR SYSTEM OF GEORGE READ HALL IS A HAMBRO COMPOSITE SYSTEM

Thesis Proposal. Executive Summary:

Technical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI

Traci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary

Simplified Building Schematic for Typical Floor (Levels 9 through 22):

fifteen design for lateral loads Lateral Load Resistance Load Direction Lateral Load Resistance

Structural Technical Report #2 By Robert Whitaker

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Revised Thesis Proposal

fifteen design for lateral loads Lateral Load Resistance Load Direction Lateral Load Resistance

SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series

By Thomas Taylor, PE, Datum Engineers Inc.

AISC Steel & Timber Research for High-Rise Residential Buildings

Structural Redesign Gravity System

Hyatt Place North Shore. Pittsburgh, PA T. Technical Assignment #1. Kyle Tennant. Kyle Tenn. Structural (IP) [Type the document subtitle]

STRUCTURAL TECHNICAL REPORT 1

THE PARKING STRUCTURE PROTOTYPE II

Structural Technical Report 1 Structural Concepts / Existing Conditions

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

Matthew Kutzler. Structural Option Spring Buildings C and D Campus Square, Lehigh University Bethlehem, PA

Boyds Bear Country Pigeon Forge, TN

David A. Walenga Technical Assignment #1

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report

Imaging Research Building

[TECHNICAL REPORT 3] Lateral System Analysis

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

Trump Taj Mahal Hotel

Hershey Research Park Building One. Technical Report 2. Jonathan Krepps Structural Option Advisor: Dr. Hanagan 10/12/12

Structural Technical Report 1 Structural Concepts/ Structural Existing Conditions Report

ON CHICAGO S NORTH SIDE, A. By Norman B. Golinkin, S.E.

FAIRFIELD INN & SUITES, MARRIOT PITTSBURGH, PA

This report investigates alternative floor systems for the building. A brief summary of each system is as follows:

Trump Taj Mahal Hotel

Campus Square Buildings C & D Lehigh University, Bethlehem, PA

Thesis Proposal. Matthew R Peyton

John Jay College Expansion Project

Final Report. Seneca Allegany Casino Hotel Addition. Salamanca, NY

Structural Concepts and Existing Conditions Report

Date: 'Comments' b Steel Quantity Takeoff. 'Quantities' b Design Loads and Parameters

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

THE FORENSIC MEDICAL CENTER

1000 CONTINENTAL SQUARE

FINAL REPORT. Structural Redesign of Hershey Medical Center Children s Hospital. Penn State Hershey Medical Center Children s Hospital

Jackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna

Technical Report #1. Indiana Regional Medical Center Indiana, PA. Cody A. Scheller. Structural Concepts & Existing Conditions Report

Point Pleasant Apartments Point Pleasant, NJ Ryan P. Flynn Structural Option Faculty Consultant: Dr. Hanagan

Transcription:

Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street area. The combination hotel-retail-cinema complex was conceived in 1996 as a way to attract people to Battery Park City, located near the southern tip of Manhattan, during the evenings and on weekends, when it is largely empty. Opened to the public in June 2000, the L-shaped hotel is situated on a site measuring 62,500 sq. ft and has two wings connected by a 9,200 sq. ft east-west atrium with skylights and glass walls on its west. The development, which represents an $80 million dollar investment on behave of its developer Forest City Rantner, showcases a 463-room hotel, a 16-screen movie theater, a sizable retail complex and a 13-storyhigh, glass-walled public atrium forming a centerpiece offering sweeping views of the Hudson River. Staggered Truss System Proves Economical For Hotels By Aine Brazil, P.E. Complex Requirements The functional needs of the project s components could not have been more diverse. Movie theaters require long clear spans of up to 60, with high floor-to-floor heights, typically 32. In contrast, hotels generally need short spans for 13 to 5 wide rooms and low floor-to-floor heights, normally in the range of 8 8 to 10. Retail spaces offer somewhat more flexibility: they benefit from longer open spaces, however spans of 30 to 40 are generally acceptable. Space usage also dictated the types of ceilings that had to be used in the project. As large-volume, high-occupancy spaces, movie theaters need a ceiling plenum for air and service distribution, as well as acoustic enhancement. Where as, hotel rooms are small, private spaces served by individual HVAC units. With bathrooms stacked vertically,

Transferring alternate columns under the hotel footprint to provide column spacing of up to 30 in order to accommodate the hotel s public spaces and retail at the base. However, it soon became clear that if the project was to survive the Thornton-Tomasetti engineers were going to need to throw a few traditions out the window. Basic Staggered Truss System includes: Story high trusses span building width Vierendeel panel permits central corridor. Trusses Alternate column lines on each floor piping is distributed inside the walls, while the bedroom ceiling is usually the soffit of the floor slab above with a directly applied surface finish. Retail spaces will frequently use a ceiling plenum for service distribution and the installation of special features. Interior is typically column-free Floor system alternately supported on the top and bottom chords of trusses. Trusses resist both gravity and lateral loads. Flouting Tradition Certain pieces of conventional wisdom are generally applied when choosing structural systems for a project, most of them dependent on the project s location and uses. For a New York mixed-use project like Embassy Suites, such wisdom would point to a concrete flat-slab system for the hotel and a steel-framed structure for the movie theaters. Design Dilemma During the initial stages of concept development, the project s budget estimate showed a very tight proforma. Unless the construction cost per square foot (psf) could be reduced, the project would not be financially feasible. The conceptual cost estimate, based on construction costs for similar projects built in the New York City market, called for a cast-in-place concrete system. The design team was charged with the task of finding significant cost savings and fresh ideas were needed. Thornton-Tomasetti Engineers proposed the use of a staggered truss system for the hotel combined with a conventional steel frame and composite slab-on-metal deck for the theater and retail components. Cost estimates by Bovis Lend Lease confirmed the value of the cost savings to be in excess of $2 million. The team had found a viable and economic solution, the next was to satisfy the client of the ability of the system to meet the program requirements while still providing the estimated cost savings. Hotels: Concrete vs. Steel Why is concrete flat slab so often the system of choice for hotel buildings? Flat-slab construction provides several important benefits: Shallow uniform thickness of the structure facilitates lower floor-tofloor heights, reducing the cost of the structure and the area of the exterior wall. Flat concrete slab soffit avoids the need for hung ceilings.

directly into reduced seismic load. Since the 14-story building s lateral systems were governed by seismic design, the reduced lateral design forces resulted in significantly lower cost. In addition, the mixed-use nature of the project strengthened the case for an all-steel-framed structure. Composite steel framing with slab on metal deck was a logical, cost-effective choice for the theater clear spans of 40 to 60. For retail uses, steel framing provides maximum flexibility, permitting easy modification when tenants change. The steel weight averaged 7 psf for the hotel and 15 psf for the theaters, which when combined came to a total steel tonnage on the project of 3500 tons. In a concrete structure, transfer girders would have been necessary to achieve the longer, more open spans needed at the lower public spaces. Concrete slab satisfies the required fire rating for floor construction. Concrete slab provides good sound insulation and minimal floor vibration. The staggered-truss system used for the Embassy Suites Hotel had many of the same advantages: The Filigree precast plank floor is 8 thick spanning to the staggered trusses, which are encapsulated in the partition walls between hotel suites and do not affect floor-tofloor heights. The soffit of the planks can be finished in the same way as the concrete slabs, without hung ceilings. The Filigree precast plank satisfies fire rating of the floor system. The detail at the ends of each plank provides system continuity, resulting in a stiff floor structure. The decision to use the staggered truss system was, in the end, a financial judgment. For the specific project and site under evaluation, the steel system offered significant advantages: The weight of the steel and plank structure is 15% less than that of an equivalent concrete frame. Since the project site is located on land that was filled/reclaimed in the 1960s, deep end-bearing-pile foundations were required to support the structure. With depth-torock averaging 80, the reduction in structural weight resulted in approximately 15% fewer piles and smaller pile caps. Reduced dead load translates Independent Structures or Combined? The project footprint is organized with the theater in a trapezoidal block measuring 135 to 170 eastwest and approximately 200 northsouth, located in the northeast corner of the site with retail beneath. The hotel occupies two wings in an L shape: the west wing is 65 170, while the south wing is 45 265. The 13-story atrium separates the theaters and west wing from the south wing. The only connections are a 40 wide bay of rooms at the east end of the atrium and a 10 wide bridge at each hotel floor at the west end of the atrium. This slot isolates the structural systems and tends to favor a solution using two independent buildings. However, separating the building into two structures would have led to the use of undesirable expansion joints. To avoid the use of expansion joints, the building was designed as a single unit. This presented an interesting challenge that was solved by tying the north and south sections together with horizontal K-bracing at the west end of the atrium at floors

four, eight and twelve. The bracing and open atrium space create an impressive visual effect that highlights both architectural and engineering design. The combined structure lacks the normal symmetry found in a typical staggered truss building. With floorto-floor heights varying significantly from the hotel to the theater (8 9 vs. 32 ), floor diaphragms aligned only at the lower retail floors. Careful attention was paid to the transfer of diaphragm forces throughout the footprint and between the different floor elevations. Precast plank diaphragm forces were transferred through a fully grouted joint over each truss chord with interlocking rebar. This detail also helped provide continuity to increase the floor stiffness and thus reduce vibrations. Structural Components Advantages of Staggered Truss System include: Improved layout flexibility due to elimination of interior columns & two-bay open space in longitudinal direction; Large open spaces at base of building; Faster erection due to fewer pieces; All-dry system speeds winter construction; Efficient lateral system due to inherent stiffness; and Reduced structure weight compared to concrete construction. Hotel Tower Story-deep staggered trusses span transversely across the narrow dimension of each hotel wing. The truss spacing matches the suite partition locations, typically varying from 26 to 30 on center. Staggering occurs on alternate lines from one floor to the next. The 8 deep precast Filigree planks span from the top chord of one truss to the bottom chord of the adjacent truss. Since the trusses are completely encapsulated by the partition walls of the hotel, minimal width truss members are desirable. HSS rectangular sections were determined to be the most efficient. Top and bottom chords vary from TS 4 6 ½ to TS 4 16 ½. Both diagonals and verticals are typically 4 4 ½, except at the vierendeel bays. The trusses frame into the weak axis of the steel columns with seated connections. Lateral resistance in the transverse direction is provided by the extremely stiff trusses, which provide adequate lateral resistance for free when sized for gravity loads. For this project, lateral loading (either wind or seismic) did not control the design of any truss members. In the longitudinal direction, conventional Chevron bracing was provided in stairwells for lateral resistance. The tube steel is A500 Grade B. Movie Theaters The floor construction consists of composite floor framing construction. Beams were designed using LRFD design approach. The grade of steel for the floor beams, columns and bracing was ASTM A572 Grade 50. Cambering of the beams permitted the use of W18 beams for the 40 spans and W27 beams for the 60 spans. Floor slabs varied from 2 metal deck plus 2½ normal weight concrete to 3 metal deck plus 4½ normal weight concrete where required for acoustic separation. Roof framing over the theater area consisted of open web joists with 1 ½ roof deck. Provision was made within the footprint of each theater for the tenant fit-out of a full stadium seating theater. Partial mezzanine levels were provided, framed in structural steel, approximately 19 above the floor, to house projection booths and provide secondary means of egress. The stadium seating was supported on light gage steel joists and stud walls sitting on top of the theater slabs. This solution permitted the design and construction of the theater fit-out to lag behind the base building construction and provided an economical framing method for the stadium-seating component. Foundation System The depth-to-rock and thickness of the fill layer mandated a deep foundation system. Steel pipe piles filled with concrete were chosen. Load tests indicated that a capacity of 200 tons could be achieved with a

12 ¾ -diameter pipe with wall thickness of ½, filled with 8000 psi concrete. Pile pipe steel was ASTM A252 Grade 3. They were 12 and 3/4 by 3/8 piles. Though conventional wisdom often leads engineers in the right direction in making design decisions, at times we must not be afraid to take risks. Meeting the objectives of a client whether they be related to time, cost or function is the primary goal of every project. In the case of the Embassy Suites Hotel development, the client s cost requirements would determine whether or not the project got built at all. In this restrictive circumstance, engineers decided to ignore everything that was known about typical residential construction in New York City in favor of the staggered steel-truss system. In a demonstration of the rule that some risks simply must be taken, the result they found was exactly what they and their client were looking for. Aine Brazil, P.E. is a structural engineer with Thornton-Tomasetti Engineers in New York City, NY. Embassy Suites Hotel Battery Park City Location: New York City Owner/Developer: Forest City Ratner Companies, New York City Structural Engineer: Thornton- Tomasetti Engineers, New York City Architect: Perkins Eastman Architects P.C., New York City Construction Manager: Bovis Lend Lease, New York City Steel Fabricator: Helmark Steel (AISC member), Wilmington, DE Steel Erector: Helmark Steel (AISC member), Wilmington, DE Steel Detailer: Helmark Steel (AISC member), Wilmington, DE