Ir. Herwin Rubijono Hotel Ambhara 19 September Manajemen Proyek. Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim

Similar documents
After solving all the case studies, please forward your answers to for an extra credit.

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

Guten Tag. (good day)

Project Time Management

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2017

PMI Lexicon of Project Management Terms

Estimating Project Schedule-Time and Cost

International Association of Certified Practicing Engineers

PMP Exam Preparation Course Project Time Management

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Introduction to Project Management

6 PROJECT TIME MANAGEMENT

Information Technology Project Management, Seventh Edition

Sound Transit Internal Audit Report - No

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

Project Management Framework

Project Planning & Scheduling

Effective Project Coordination and Management

S O Seminar Objective

The PMP CRAM. The Guide to Pass the PMP

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Time Management PLANNING

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

IT Project Management. Essentials of IT project management 25 Sep 2017

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms

Content Break-up & Methodology for awarding Contact Hours / PDUs

Project Management Basics

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

Project Time Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

PMI-001 Questions & Answers

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

2.0 SCHEDULE DEVELOPMENT

Principles of Schedule Contingency Management

REQUIREMENTS DOCUMENTATION


1.Which of the items listed below is not one of the software engineering layers?

Resource Critical Path Approach to Project Schedule Management

Geog 469 GIS Workshop. Project Management

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PROJECT COORDINATION & MANAGEMENT

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.

PROJECT COORDINATION & MANAGEMENT

Project Management Glossary of Terms

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Compiled by Rajan Humagai

Project Management for Oil & Gas Professionals

EXHIBIT 2-2-C SCHEDULES

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

The Planning Process Group

From Russia With Love:

PMI EXAM PgMP Program Management Professional (PgMP)

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak

Global Project Management, LLC

THE PMP EXAM PREP COURSE

Planning & Scheduling

Schedule Compression

Project Management Concepts, Tools & Techniques

Schedule Module Exploration Systems Engineering, version 1.0

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

BCS THE CHARTERED INSTITUTE FOR IT. BCS HIGHER EDUCATION QUALIFICATIONS BCS Level 5 Diploma in IT IT PROJECT MANAGEMENT

Index. Symbols. 80/20 Rule, /15 Rule, 306

Glossary bglos.indd 10/28/2015 Page 1

Project Time Management

10/10/2013. Articles. Project Management

Just like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting. It is the Project Managers job to communicate:

Schedule Compression

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Successful Project Management

Project Management Academy

Project Execution Plan For

Synopsis 2017 of PS Project Management Course

Definition. Name of the tool or technique Project mission statement

Planning & Scheduling CSTM 102

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Management of Software Development Projects

PMP TRAINING COURSE CONTENT

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

Project Management. Time and Resources DPLE 157

Project Planning Tools

Scheduling 2 Day Structure

3.1 Edition APMP Syllabus APMP

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

PMI Scheduling Professional (PMI-SP)

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005

Chapter 3 Project Management

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional

PMP Q&As. Project Management Professional. Pass PMI PMP Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from:

Estimating and Scheduling

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE. CFS:BD 1 of 14 APPR:MB:JJG FHWA:APPR:

Easy Projects Glossary. Version 1.00

Software Project & Risk Management Courses Offered by The Westfall Team

Operations Management

ActualTests.CAPM.660Questions. Certified Associate in Project Management (CAPM)

Transcription:

Ir. Herwin Rubijono Hotel Ambhara 19 September 2016 Manajemen Proyek Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim

Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background : Education : S1 Teknik Komputer Port folio : - IT Consultant; - Project Management - SOP Working Experience : - PT Prosys Bangun Nusantara; - PT Alcatel Indonesia; - PT EB Connection; - PT HP Indonesia; - PT Multi Media Arto Sentosa (now) Projects: - Grand Indonesia; - Chevron Oil Company; - PT Telkom (SDP Project); - PT Telkom (Seat Management); - PT TGI; - PT PGN - Others Trainer/Instructor: - Prosys Bangun Nusantara - PLN - VICO - PT. Aneka Tambang - PT. Pakuwon Jati - PT. Adaro - ESDM - PT. Medco - PT. ANJ - PT. Pertamina - PT. Djarum - PII - Others

Subject : Project Time Management Project Cost Management Project Risk Management Project Claim Management

Project Time Management

Project Time Management The processes required to manage the timely completion of the project, as follows : Plan Schedule Management Define Activities Sequences Activities Estimate Activity Resources Estimate Activity Duration Develop Schedule Control Schedule Project Time Management

Define Activities, Milestone, Activity Sequence Activity List A comprehensive list of all schedule activities that are planned to be performed on the project. Helps project team members to understand what work is to be performed. Milestone A significant point or event in the project. An event that is possibly restraining future work or marking the completion of a major deliverable. A schedule milestone has zero duration. Sometimes called a milestone activity. Activity Sequence Conceptual and Methodologies-time Identifying and documenting dependencies among schedule activities. Precedence Diagram Method, is a technique used for constructing a schedule model in a which activities represented by node and linked by one or more logical relationship. Project Time Management

Conceptual and Methodologies-time Project Time Management

Conceptual and Methodologies-time Estimate Activity Resource Resource requirements: What resources (persons, equipment, or materials) What quantities of each resource will be used When each resource will be available to perform project activities

Conceptual and Methodologies-time Develop Schedule Identifies the scheduling method and tools used to create the schedule, and how the schedule is to be calculated. Critical Path Method (CPM) Precedence Diagram Baseline Project Schedule Actual Project Schedule Schedule Compression Scheduling Tools Project Time Management

Critical Path and Float Identification Conceptual and Methodologies-time Backward calculation 4 5 A20 7 8 8 A30 8 1 2 3 days 1 day 7 9 13 A10 3 5 6 6 A60 2 days 1 2 2 3 6 7 A40 A50 8 8 5 days 9 13 Forward calculation 4 days 3 6 2 days 7 8 9 Project Time Management

Critical Path and Float Identification Conceptual and Methodologies-time Backward calculation 4 5 A20 7 8 8 A30 8 1 2 3 days 1 day 7 9 13 A10 3 5 6 6 A60 2 days 1 2 2 3 6 7 A40 A50 8 8 5 days 9 13 Forward calculation 4 days 3 6 2 days 9 7 8 critical path Project Time Management

Project Time Management

Conceptual and Methodologies-time Time Scheduling Gantt Chart Project Time Management

Conceptual and Methodologies-time Critical Path Critical Path Generally - not always - the sequence of schedule activities that determines the duration of the project. Generally, it is the longest path through the project. Critical Path Method Used to determine the amount of scheduling flexibility (the amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project duration. Project Time Management

Conceptual and Methodologies-time CPM (Critical Path Method) Project Time Management

Project Cost Management

Conceptual and Methodologies-cost Cost Management Cost Estimating : Developing an estimate (approximation) of the costs of the resources needed to complete project activities. Cost Budgeting : Allocating the overall cost estimates to the individual work items in order to establish a cost baseline for measuring project performance. Project Cost Management

Cost Management Conceptual and Methodologies-cost

Conceptual and Methodologies-cost Cost Baseline, Expenditures, and Funding Requirements Project Cost Management 19

Earned Value, Planned Value, and Actual Costs Conceptual and Methodologies-cost Earned Value Management (EVM) is a methodology that combines scope schedule, and resource measurement to assess project performance and progress. Planned Value (PV) Earned Value (EV) Actual Cost (AC) Variance from the approval baseline will also be monitored : Schedule Variance (SV) = EV PV Cost Variance (CV) = EV AC Schedule performance index (SPI) = EV/PV; SPI <1 : behind schedule; SPI=1 : on schedule SPI>1 : Ahead Schedule Cost Performance index (CPI)=EV/AC CPI <1 : over planned cost; CPI=1 : on planned cost; CPI > 1 : Under Planned cost Project Cost Management

Conceptual and Methodologies-cost Earned Value, Planned Value, and Actual Costs EV Project Cost Management

Project Risk Management

A1 Project Risk Management Risk Management in the projects involves: Identify risk Assessing and analyzing the likelihood and impacts of risks Conceptual and Methodologies-risk Project Risk is an uncertain event or condition that, if it occurs, has an effect on at least one project objective. Trying to reduce the uncertainties (by gathering more information or making different decisions) Trying to lessen the impacts of risks Developing contingency plans for critical risks Monitoring risks as the project progresses Project Risk Management

Slide 23 A1 Author, 9/15/2016

Conceptual and Methodologies-risk Origin of Project Risk Project risk has its origins in the uncertainty present in all projects: Known risks are those that have been identified and analyzed, making it possible to plan responses for those risks. Known risks that cannot be managed proactively, should be assigned a contingency reserve. Unknown risks cannot be managed proactively and therefore may be assigned a management reserve. A negative project risk that has occurred is considered an issue. Project Risk Management

Conceptual and Methodologies-risk Type of Risk : Risk Avoidance: changing the project plan to eliminate the risk or condition or to protect the project objectives from its impact. Risk Acceptance: accepting the consequences should a risk occur. Plan for dealing with it when it occurs, but do nothing to lessen its probability or impact. Risk Transfer or Deflection: assign the risk to a 3 rd party. (e.g. Insurance, Outsourcing) Risk Mitigation: reducing the impact of a risk event by reducing the probability of its occurrence. (e.g. contract experts) Project Risk Management

Conceptual and Methodologies-risk PROBABILITY Threshold of Risk Levels 5. Almost Certain Low Med High High High 4. Likely Low Med Med High High 3. Possible Low Low Med Med High 2. Unlikely Low Low Low Med Med 1. Rare Low Low Low Low Med IMPACT 1.Insignificant 2. Minor 3. Mode- 4. Major 5. Catasrate trophic Project Risk Management

Conceptual and Methodologies-claim Project Claim Management Project Claim Management

Conceptual and Methodologies-claim Claims management describes the processes required to prevent project claim, to mitigate the effect of those that do occur, and to handle claims quickly and effectively. Claims could be come from project owner or project contractor Claim processes : - Negotiation - Mediator - Arbitration board - Legal judgment Project Claim Management

Project Claim Management covered : o Claim Identification; o Claim Quantification; o Claim Prevention; o Claim Resolution

1. Claim Identification Identifying from scope knowledge and contract term/condition changes of some activity. Determine claim extra work Determine extra time 2. Claim quantification Determine statement of claim Determine of claim activity 3. Claim prevention Create project plan and term/condition of contract & risk management plan 4. Claim Resolution Contribution on statement of work and claim quantification definition; Contribution on contract preparation

Claim Causes : o Changes in subsurface conditions; o Discrepancies and ambiguities in plans and specifications; o Neglect or delay; o Sending other contractors onto the site; o Delays and Changes in the work

End of Slide Q & A