Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams

Similar documents
Problems in Improvement Evaluation, QA and QC

Ground Modification Applications for Bio-Fuel Plants Raymond J. Franz, P.E. Roselle, IL

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting

Compaction and Jet Grouting

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING

TSAILE DAM MODIFICATION PROJECT Unearthing a Safer Dam

A Case Study: Foundation Design in Liquefiable Site

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

CE 6012 Ground Improvement Techniques Question Bank

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

A COLLABORATIVE SUCCESS CONSTRUCTION OF THE MORMON ISLAND AUXILIARY DAM KEY-BLOCK FOR SEISMIC REHABILITATION. Abstract

Ground improvement support using Confined aggregate piers in soft soil. Brian Metcalfe, P.E. Director of Engineering Geopier Foundation Company

Seismic Design & Retrofit of Bridges- Geotechnical Considerations

Application of Vibro Techniques for Infrastructure Projects in India

A COLLABORATIVE SUCCESS CONSTRUCTION OF THE MORMON ISLAND AUXILIARY DAM KEY-BLOCK FOR SEISMIC REHABILITATION. Abstract

Santa Clara Valley Water District Page 1 of 4

Scope of Discussion. Foundation Related Issues. Foundation Preparation and Treatment During Dam Construction 10/14/2014

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1

Successful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam

Liquefaction Mitigation in Silty Sands at Salmon Lake Dam Using Stone Columns and Wick Drains

Fly Ash Reservoir II Dam Initial Safety Factor Assessment. Cardinal Power Plant Brilliant, Ohio S&ME Project No A

Steel screw settlement reduction piles for a raft foundation on soft soil

Modules for Graduate Certificate in Geotechnical Engineering

LIMITED MOBILITY GROUTING -- PRACTICE IN NORTH AMERICA. Michael Byle, D.GE, F.ASCE,

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

GROUND ENGINEERING. Vibro Ground Improvement

A CASE HISTORY ON DESIGN, CONSTRUCTION, AND PERFORMANCE OF STONE COLUMN GROUND IMPROVEMENT BENEATH AN MSE EMBANKMENT

Expert Solution in BUILD ON US GEOTECHNICAL AND CIVIL ENGINEERING CONTRACTORS

Review and Feasibility Assessment of Offshore Ground Improvement Methods

Grouting Bilfinger Spezialtiefbau GmbH

ASCE Geo-institute (G-I) Soil Improvement Committee

Construction and Geotechnical Issues

Brochure 66-01E. Compaction Grouting

Ground Improvement Techniques

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

CHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS

Soil Densification Using Vibro-Stone Columns Supplemented with Wick Drains

Earth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola.

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

DAMS AND OTHER HYDRAULIC STRUCTURES

Ground Improvement Specialists

CONSIDERATIONS ON THE SEISMIC DESIGN OF HIGH CONCRETE FACE ROCKFILL DAMS (CFRDs) Bayardo Materón - Gabriel Fernandez

DAMS AND APPURTENANT HYDRAULIC STRUCTURES

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River

AMERICAN ELECTRIC POWER (SWEPCO)

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

geopier Lateral resistance

ASSESSMENT AND MITIGATION OF LIQUEFACTION RISK FOR EXISTING BUILDING FOUNDATION

NPTEL Course on Ground Improvement

Liquefaction Remediation by Compaction Grouting

Brochure E. Deep Vibro Techniques

Types of Inspections

A STUDY ON GROUND IMPROVEMENT USING STONE COLUMN TECHNIQUE

Prediction Method for Reservoir Collapse During Earthquakes

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park

Vibroflot Modular Product Range

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore

Chapter 19 GROUND IMPROVEMENT

In-ground cellular structure as a foundation system

TABLE OF CONTENTS. vii

Analysis of Seawall Concepts Using Yielding Soil Anchors

Conduits through Embankment Dams

SECTION TRENCHING

REHABILITATION OF EARTHQUAKE AFFECTED CHANG EARTHEN DAM

Lessons Learned from Dam Incidents and Failures Lessons Learned Identified

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

DTE Energy Monroe Power Plant

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

Introduction to Foundations on Fill and Backfilling

A POORLY GRADED SAND COMPACTION CASE STUDY

LACHEL FELICE & Associates. Advances in Finite Element Modeling Using PLAXIS SILVER REEF HOTEL/CASINO EXPANSION

6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, October 2012

SOIL IMPROVEMENT WITH JET-GROUT COLUMNS: A CASE STUDY FROM THE 1999 KOCAELI EARTHQUAKE

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

Mr. Paul Dunlap, California Department of Water Resources

aggregate piers / vscs

Mechanical and Hydraulic Behavior of Cut off-core Connecting Systems in Earth Dams

VERIFICATION OF GEOTECHNICAL GROUTING- STRATEGIES AND PLANNING. Michael J. Byle, D.GE, F. ASCE

Material properties of Tailings from Swedish mines

COST- BENEFIT STUDY OF REMEDIATING WEST SACRAMENTO LEVEES FOR SEISMIC HAZARD. West Sacramento Study Area

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

Water Control Structures Selected Design Guidelines Alberta Environment Page 14-1

Earthwork and Ground Technology. Site Improvement

Chapter 3: Summaries of Case Histories

Modified Centreline Construction of Tailings Embankn1ents

2018 Annual Dam and Dike Inspection Report

McElroy s Run Impoundment Structural Stability Assessment Report

Soil Mechanics Prof. B.V.S. Viswanathan Department of Civil Engineering Indian Institute of Technology, Bombay Lecture 16 Compaction of Soils VI

Ponds: planning, design, and construction

CASE STUDY ON DIFFERENT GROUND IMPROVEMENT TECHNIQUES FOR A PROPOSED BUILDING ABSTRACT

EARTHQUAKE SAFETY OF EXISTING DAMS

Seismic Considerations and Design Methodology for Lightweight Cellular Concrete Embankments and Backfill

Remedial Foundation Solutions for Existing Tanks

Ground Improvement. A Discussion on Dynamic Compaction. Chris Woods, P.E., D.GE., LEED AP BD+C Vice-President

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update

AMERICAN ELECTRIC POWER (SWEPCO)

Transcription:

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams by James K. Mitchell, Sc.D., P.E., Dist. M.ASCE University of Alberta, Edmonton, Alberta October 6, 2010 1

SCOPE OF THE LECTURE Types of distress and failure of existing embankment dams and their causes Why so many existing embankment dams require fixing Available ground improvement methods and basis for selecting among them Illustrative case histories Recent trends in design and ground improvement method applications Some major unresolved problems 2

TYPES OF DISTRESS AND FAILURE OF EXISTING EMBANKMENT DAMS AND THEIR CAUSES Excessive Settlement Liquefaction of embankment and foundation materials Large Deformations Cracking and opening of seepage paths Damage to control structures 3

Loss of freeboard and overtopping as a result of: Crest settlement from compression of the embankment and foundation Crest settlement from loss of embankment stability and lateral displacement Crest settlement from liquefaction in the embankment and/or foundation and lateral spreading 4

Almost all embankment dams undergo some settlement as a result of an earthquake (Modified and redrawn from Swaisgood, 1998) 5

Fort Peck Dam Failure in 1933 static liquefaction of a loose sand embankment fill (not caused by an earthquake) 6

Failure of Fort Peck Dam static liquefaction of a loose sand embankment fill 7

Lower San Fernando Dam Failure, 1971 Earthquake-induced liquefaction 8

1971 Slide Lower San Fernando Dam Photo taken during reservoir emptying after the earthquake to protect the large population at risk downstream 9

Seepage and Piping (initiated by cracking and differential movements): Within and through the embankment as a result of cracking of the core and inadequate protective filters Seepage and piping through the foundation as a result of cracking of cutoff walls and seepage control blankets Piping along conduits as a result of differential ground movements 10

Settlement and cracking at Hebgen Dam, MT in 1959 EQ 11

12 Transverse crack in a long, low dam near Anchorage caused by the Great Alaska EQ of 1964 (from Sherard, 1973)

Loss of Reservoir Control can result from: Loss of spillway Damage to spillway gates Damage to inlet and outlet works 13

WHY DO SO MANY DAMS NEED REMEDIATION? Many were built on sedimentary deposits now known to be susceptible to liquefaction Many dams were built using methods now known to yield embankments that have poor stability; e.g. hydraulic filling Aging dam inventory and the deteriorating effects of time on the condition of the dam and appurtenant structures Much more is known about how dams can be adversely impacted by seismic shaking Escalation of estimated seismic risk Larger populations in the downstream floodplain now and in the future Higher standards for dams built today stricter regulatory requirements 14

15

Construction of a Hydraulic Fill Dam in the Early 1900 s 16

Hydraulic Filling Operations 17

Hydraulic Fill Dam Completed in 1915 Placement method results in loose, potentially liquefiable embankment shell and soft clay core 18

Steps in the Evaluation of Dam Safety 1. Review project history site conditions, construction records, as-built conditions, maintenance records, etc. 2. Assess current conditions of the foundation, embankment and appurtenant structures 3. Determine site seismicity and estimate the ground motions 4. Determine hydraulic demands; e.g., PMF, Reservoir levels 5. Develop best estimate site characterization models for the dam and its foundation 6. Do simple/approximate analyses for estimation of possible liquefaction, deformations, and cracking 7. Do the results indicate the possibility of failure or nearfailure by any conceivable failure mode? 8. If so, then more refined analyses and a risk assessment are necessary. 9. If the risk is greater than acceptable limits, then begin development of protective and remedial strategies 19

Methods and Problems in Characterization of the Site and Existing Dam Conditions Accurate definition of the foundation rock and soil strata types, geometry and properties Definition of the embankment internal geometry and material properties design, construction records and photographs, field explorations In-situ tests types, applications and limitations Laboratory tests types, applications and limitations Geophysical methods types, applications and limitations (Data from different sources do not always provide a clear, consistent indication of liquefaction potential or residual strength) 20

SAN PABLO DAM, CALIFORNIA 21

San Pablo Dam - A Case of Misidentified materials 170-ft high, 125-ft wide, 1200-ft long hydraulic fill dam completed in 1921 Founded on alluvial sediments; some zones susceptible to liquefaction Embankment of hydraulic fill material that consisted of weathered sandstone and shale Evaluations in 1960 s and again in 1970 s assumed a liquefiable embankment, evidently because it was a hydraulic fill, and included tests on sandy embankment samples - resulted in a small DS buttress in 1967 and large US buttress to bedrock in 1979 Reevaluation in 2004 assumed liquefiable embankment and indicated excessive slumping and overtopping in M7.25 EQ on Hayward Fault Considered completely rebuilding the dam- would require draining the reservoir Chose an in-place alternative instead, with Cement Deep Soil Mixing (CDSM) in the foundation and a large DS buttress fill. Extensive field (mostly CPT) and lab testing programs revealed that the embankment material was fine-grained and not susceptible to liquefaction. As a result a considerably smaller zone of CDSM and reduced buttress was used. 22

Obtaining hydraulic fill for San Pablo Dam 23

Buttress constructed in 1967 Buttress constructed in 1979 Construction of third retrofit of San Pablo Dam began in Fall 2008 (see Civil Engineering, October 2008) now complete (2010) 24

25 SAN PABLO DAM: Remediated (2009) using Cement Deep Soil Mix Block and Downstream Berm

Ground Improvement Methods Used for Strengthening Dams and Their Foundations 26

Ground Improvement Methods for Mitigation of Seismic Risk to Existing Embankment Dams and Their Foundations 27

Roller compaction at Mt. St. Helens Sediment Retention Dam, WA Embankments constructed using modern equipment and methods would not be expected to be vulnerable to damage under seismic loadings but this has not always been the case. 28

An experimental program of compaction by dropping a heavy concrete block was done by the U.S. Army Corps of Engineers in the mid-1930 s during construction of 29 the Franklin Falls Dam in New Hampshire.

Deep Dynamic Compaction Courtesy of DGI-Menard 30

Variation of improvement with depth after DDC is consistent with the strain distribution beneath the weight impact point. Upper limit for densification by DDC is about 31 35 feet.

Effectiveness of DDC in Different Soils 32 From Hayward Baker

Vibrocompaction Nicholson Construction, Vibrofoundations, Inc. 33 Slide Courtesy Russell A. Green

Vibroreplacement Stone Columns Developed based on German (1930 s) vibroflotation technology, introduced to North America in 1940 s Wet and dry methods to depths of 100 ft Top and bottom feed Column installation can provide densification of matrix soil (if fines content not excessive) Columns can enhance drainage and provide some reinforcement Rapid, but difficult to penetrate stiff cohesive soils 34

Compaction pile construction at Tablachaca Dam in Peru 35

Typical Patterns used to Treat Large Areas S Tributary Area = 0.87S 2 S Tributary Area = S 2 Triangular Pattern Compaction Point Square Pattern 36

Each DDC impact influences a much greater volume of ground than the zone of influence of a probe during vibro-compaction. Much larger spacing (several meters) can be used between DDC impact points than the spacing for vibrocompaction probe points. 37

Expected Vibro-Compaction, Vibroreplacement and Rammed Aggregate Results Relative Effectiveness Ground Type Densification Reinforcement Drainage* Sands Excellent Very Good Good Silty Sands Very Good Very Good Very Good Non-plastic Silts Good Excellent Very Good Clays Marginal Excellent Excellent Mine Spoils Depends on gradation Good Dumped Fill Good Good Depends on gradations Depends on gradations *Assumes no fines mixed into columns 38

Effect of fines on SPT resistance 39

Closely-spaced Prefabricated Vertical Drains Installed Prior to Treatment by Vibratory or Impact Methods Can be Effective for Improvement of Higher Fines Content Soils: Salmon Lake Dam, Washington is an example (Luehring, et al 2001) 60-ft thick deposit of silty foundation material Fines content to > 60% Prefabricated vertical (wick) drains on 3 or 6-ft centers to depth of 58-61 ft between dry, bottom-feed stone column located on 6-ft centers Column diameters of 3.0 or 3.75 ft; replacement ratios of 22 or 35 % 40

Explosive Compaction Can be useful for densification at large depths (>30 m) and where there is a high content of gravel, cobbles, and boulders 41

Seymour Falls Dam prior to Seismic Upgrade (Siu et al., 13th World Conference on Earthquake Engineering, Vancouver, 2004) 42

Foundation Densification by Explosive Compaction and Deep Dynamic Compaction at Seymour Falls Dam prior to Construction of New Embankment (Siu et al., 13th World Conference on Earthquake Engineering, Vancouver, 2004) 43

Densification of a high gravel and cobble content layer at Seymour Falls Dam, BC note gas and water ejecting from blast holes (from Elliott, et al) 44

Deep Dynamic Compaction at Seymour Falls Dam Most drops were 25 tonnes from 25 meters Ave. energy was 550 tonne-m/sq m. (from Murray, et al, 2005) 45

Seymour Falls Dam after Remediation New earthfill dam and gravity wall extension, with the original earthfill dam showing as a grassy ridge along the top; the concrete slab and buttress dam is at right.(canadian Consulting Engineer, October 2007) 46

Comparative Costs Actual cost depends on project size, location, depth of treatment, mobilization, local conditions, availability of contractors, etc. A relative cost of 1 may be of the order of $(3-4)/m 3 of improved ground. Comparative Costs of Vibro-Densification Methods: Treatment Method Relative Cost (per unit volume) Deep Dynamic Compaction 0.5-2 Vibro-Replacement 3-10 Vibro-Compaction 2-10 Vibratory Probe ~3 Blasting (EC) 0.25-1 47

Deep soil mixing at Jackson Lake Dam (First large-scale use of DSM in the U.S.) 48

49

50

51

52

53

54

Schematic of Jet Grouting 55

56 Cement Deep Soil Mix and Jet Grout Columns at a Recent (2006) Dam Downstream Test Section

Jet Grout and CDSM Columns at a Recent (2006) Dam Test Section 57

Selection of most appropriate method(s) depends on many factors, including: Soil type and suitable methods for improving it Level of improvement needed Magnitude of improvement attainable by a method Required depth and thickness of treatment Areal extent of treatment Accessibility of the site Environmental considerations Time and cost considerations Local experience Confidence in method effectiveness (QA/QC) Construction risks Long-term monitoring and performance requirements 58

METHODS FOR EVALUATION OF IMPROVED GROUND Surface settlement and heave Backfill quantities Sampling of admixture treated soil Penetration tests: SPT, CPT, BPT, DMT Shear wave velocity Undisturbed samples Hydraulic conductivity (in-situ) Construction data records (power, energy input, pressures, quantities, rates, etc.) Can see a lot just by watching 59

QA/QC requirements for improved ground During construction, observations should be made and recorded at each improvement location, including: Ground surface movements Volume of backfill material used Grout take Amount of energy or pressure expended Consistency, unit weight, viscosity of mixed in-situ materials and spoils returned to the ground surface After construction, in-situ methods such as SPT, CPT and/or shear wave velocity testing can be performed to verify that the level of improvement is achieved. Laboratory testing can also be used to verify some types of improvement 60