Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View

Similar documents
BUREAU OF INDIAN STANDARDS. Preliminary Draft Indian Standard

THE NEW PENSTOCK FOR THE HIGH-HEAD HYDROPOWER PLANT KAUNERTAL

AN INNOVATIVE PUMPED-STORAGE PROJECT IN AN UNDERGROUND MINE. Ernst Zeller November 2017

Qualification Procedure of Thermomechanical Steel ALFORM 700 for Pressure Shaft Lining of Reisseck II Pumped Storage HPP

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

MANUFACTURING TECHNOLOGY

THE MECHANICAL PROPERTIES OF STAINLESS STEEL

Fundamental Course in Mechanical Processing of Materials. Exercises

TMK HYDRA ART INSIDE SKIVED AND ROLLER BURNISHED COLD FINISHED SEAMLESS STEEL TUBES and PISTON RODS TUBES FOR HYDRAULIC CYLINDERS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

European Hydro Power Road Map. Herfried Harreiter (Verbund Hydro Power AG) Thomas Leitl (RWE Power AG)

Hot Forming. Kalpakjian

The Rio Grande project - Argentina

UNIT V PART A

Latest Trends in Fabrication of High Thickness Reactors

INVESTIGATION OF A PUMPED-STORAGE HYDRO PLANT IN THE ALPINE AREA SLOVENIAN TITLE

Residual Stresses and Distortion in Weldments

Contents. Introduction

Qualification Program for the Rehabilitation of Cleuson-Dixence: Requirements and Results

Design of Concrete Lining for Head Race Tunnel using STAAD

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Guidelines for the Construction of Pressure Vessel Type Tanks Intended for the Transportation of Anhydrous Ammonia at Ambient Temperatures

Oil tempered SiCr-alloyed valve spring wire Only manufactured in China

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes...

Oil tempered SiCrVNi-alloyed ultra-high tensile valve spring wire for surface nitriding

ITEM 442 METAL FOR STRUCTURES

Oil tempered SiCrVMo-alloyed ultra-high tensile valve spring wire for surface nitriding

True Stress and True Strain

High-strength and ultra-highstrength. rolled fine-grained steels. Technical terms of delivery for heavy plates

CAVERN STORAGE UNDER THE SEA BED - RENEWABLE ELECTRICITY STORAGE IN EUROPE 2025

Pump storage hydro power plant (PSKW) Reißeck

Relining Project in Turkey proves successful By Hans Juergen Koenig and Jens Kirste

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

LIST OF STANDARDS DEVELOPED IN CIVIL ENGINEERING STANDARDS

SCHNORR Product range

SECTION PRECAST CONCRETE SEGMENTAL TUNNEL LINING

9. VACUUM TANK 9. VACUUM TANK

ITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.

Construction and Dynamic Testing of Aluminium Nodes

NATURAL GAS COMPRESSOR STATION PIPELINE WELDING AND RELATED FACILITIES. Engr. Md. Saidur Rahman 1,*

TMR 4195 DESIGN OF OFFSHORE STRUCTURES. Problem 1. In the ULS control it is necessary to consider the load cases given in Table 1.

MACHINES DESIGN SSC-JE STAFF SELECTION COMMISSION MECHANICAL ENGINEERING STUDY MATERIAL MACHINES DESIGN

JUST THE FACTS CONCRETE PIPE VS. HDPE

Integrity Assessment of Headcovers and Headcover Fasteners

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

Specification Stainless spring steel

MANDATORY APPENDIX 2 RULES FOR BOLTED FLANGE CONNECTIONS WITH RING TYPE GASKETS

Increasing hydro-equipment value with field measurements. P. Weibel, J. Contreras, S. Lais, E. Parkinson. ANDRITZ HYDRO Switzerland

Experts in tunneling with Tunnel Boring Machines

Large Hydro ensuring Grid Stability with rapidly expanding Wind Generation

Need for Electricity storage

12/12/2017. Hydropower and Pumped Storage. The Benefits of Hydropower The Number One Renewable Energy

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

ME -215 ENGINEERING MATERIALS AND PROCESES

Module 4 Design for Assembly

FABRICATION OF HEAVY WALL Cr-Mo / Cr-Mo-V REACTORS CHALLENGES AND TECHNOLOGY UPGRADATION AT LARSEN & TOUBRO LIMITED INDIA

BS EN :2004 EN :2004 (E)

Chakachamna Hydro. AEA Geothermal Conference

Energy Storage event. Pumped Hydro Storage. Karl Wimmer, Brussels, VERBUND AG,

ASTM Standards for Pipe & Fittings

Directive 97/23/EC Pressure Equipment

Sandvik SAF 2205 (Billets)

Figure (12.1) Foundation Grouting

4th International Engineering and Construction Conference - July 28, 2006

Requirements for Measuring and Pricing of Structural Concrete

PART I PERFORMANCE OF MATERIALS IN SERVICE. Materials and Process Selection for Engineering Design: Mahmoud Farag

For ASME Committee use only.

Independent certification of your products & services. 2.2 Relevant Standards 1. SCOPE

ASME B31.3 CUMULATIVE INDEX INTERPRETATIONS VOLS SUBJECT INDEX. Assembly and Erection Authorized Inspector (see Owner s Inspector)

under Buckling Behavior

Content. perform. Brief profile. Product information for high-strength thermomechanically hot-rolled strip and cut-to-length plate

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

Stress Relief and Material Properties Improvement Through Vibration VS. Common Thermal Method

Pumped hydro Storage Plants

Angle Cleat Base Connections

High-strength thermomechanically rolled fine-grain steels. Technical terms of delivery. voestalpine Grobblech GmbH

Structural modeling of casings in high temperature geothermal wells

The surface roughness of the polyurethane lining is 10 times lower than cement-lined pipes.

Sharing Experiences of the World s Largest Tidal Power Plant in Lake Sihwa, South Korea

Structural design criteria

Section 906. STRUCTURAL STEEL

Design and Model Test of Shaft Lining Compressible Connector in Deep Hydrophobic Alluvium*

Welding simulations: assessment of welding residual stresses and post weld heat treatment

Large-diameter bored piles and Large-hole drillings Applications

LABORATORY EXPERIMENTS FOR ASSESSING THE DETECTABILITY OF SPECIFIC DEFECTS BY ACOUSTIC EMISSION TESTING

The use of Heavy Plate in the fabrication of Urea Pool Reactor

1 INTERNATIONAL CONFERENCE ON HEAT TREATMENT AND SURFACE ENGINEERING OF TOOLS AND DIES IFHTSE 2005 Pula, Croatia, June, 2005

IN-SITU NONDESTRUCTIVE MEASUREMENTS OF KEY MECHANICAL PROPERTIES OF OIL AND GAS PIPELINES

Lecture 29 DESIGN OF WELDED JOINTS VII

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

STAAD.pro 2007 Design of Wind Turbine Foundations

IEEE 18-May Intake. Tunnel. Outlet

PERFORMANCE OF CYLINDRICAL LIQUID STORAGE TANKS IN SILAKHOR, IRAN EARTHQUAKE OF MARCH 31, 2006

Research on the Abrasion Erosion and Impact Resistance of Fiber Concrete

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS

CLASSIFICATION NOTES. Type Approval. Mechanical Joints. used in Piping

Item 442 Metal for Structures

Extension of Pumped Storage Plant Waldeck 2 in Northern Hesse / Germany

IMPACT AND PUNCTURING OF JARI TUNNEL AND ENLARGEMENT OF EXISTING TAPPINGS FOR ADDITIONAL WATER SUPPLY AND POWER GENERATION

Transcription:

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View J. Mayrhuber and P. Stering VERBUND Austrian Hydro Power AG, Am Hof 6a, A-1010 Wien, Austria Abstract Steel lined pressure shafts made from high strength steels are key elements for high head storage and pumped storage power plants. High strength steels plates from thermomechanical rolling with yield strength up to 500 MPa and from quenching and tempering with yield strength up to 950 MPa are commercial available. Whereas several projects apply such steels and can benefit from the high yield and tensile strength, in other projects these steels are have not been applied so far. The paper gives an overview of penstock design and construction principles applied for projects in Austria, where other factors besides yield strength affect the design of penstocks and the selection of steel grades and limit the application of steel grades above 690 MPa. With current and future high head power plant projects it is necessary to evaluate the design principles in combination with high strength steel grades to reach an technical and economic optimum for new projects. Introduction In Europe there is an increasing need for hydro power plants due to several reasons. The European commission has issued an ambitious program for EU-27 for increasing the production and use of energy from renewable sources to 20% of the total primary energy use by 2020 and aims for a share of 21% of electricity by 2010. Besides other renewable sources, this will lead to an increase of wind energy for electricity production. The projected growth of wind power of EU-27 is from 50 GW in 2006 to about 180 GW until 2020. The additional capacity of hydro power was assumed with + 20 GW by 2020 reaching a capacity of 120 GW [1]. The increase in wind power in the European electricity market requires compensation by control power. The control power or secondary control (ore minute reserve power) can be provided by pumped storage hydro power plants, which are able to compensate fluctuation wind power production and provide stable grid frequency either by additional production (to increase the grid frequency) or by negative control power for pumping purpose to increase power consumption and lower the grid frequency. Secondary control or reserve power has become an important topic for European power grid operators and has become a valuable product on the energy markets. One important source of control power can be pumped storage power plants (=psp), therefore most power plant operators are developing new projects. This paper focuses on projects for storage power plants and pumped storage power plants which use power conduits with steel lined pressure shafts, applying steel lining made from high strength steels fabricated by welding. Content Recent projects in Austria, especially for VERBUND, for steel lined pressure shafts use moderate design parameters, compared to recent international projects. This can be explained by several factors e.g. project specific topography, accepted design rules and acceptance by authorities, long term experience with approved construction technologies and long term operating performance and most important safety considerations. The aim of this paper is to outline the current situation for design and manufacturing of steel lined pressure shafts, the materials applied and the parameters, that affect the selection of the steel grades for pressure shaft linings. As an example a project under construction is presented and discussed. Potentials and limitations for application of higher strength steel grades are discussed and topics, that require more investigation for future projects are addressed. Current projects The country of Austria produces 2/3 of its electrical energy from hydro power with a peak capacity of 11,6 GW and an annual production of 66 TWh/year. Verbund owns and operates about 60% of this capacity. To increase the peak capacity and to provide the market with peak energy, potentials for high head power plants and for pumped storage power plants were investigated. The most economic projects use existing storage power plant reservoirs which can be connected with new power conduits to include new pumped storage capacity within the existing reservoir system. Two examples of this type are presented in Table 2 and 3 and Figures 1 and 2. 4-1

TABLE 1: EXISTING HYDRO POWER PLANTS OF VERBUND Number Capacity MW Output GWh Hydro power 108 7.113 21.134 plants = hpp High head hpp 21 2.850 4.318 Low head hpp 87 4.263 16.816 Figure 2: PSP Reißeck II project (2x215 MW in environmental assessment); with existing reservoirs: upper reservoir 7,8 Mio m³; lower reservoir 6,2 Mio m³ Figure 1: PSP Limberg II project scheme under construction (new power scheme 2x240 MW); with existing reservoirs; upper reservoir: 85 Mio. m³; lower reservoir 81 Mio. m³. These recent projects are located in alpine regions where tourism is an important factor. Also other environmental aspects play an important role, as the projects are located close to protected areas. Only underground systems for penstocks and powerhouse are acceptable. TABLE 2: HIGH HEAD PUMPED STORAGE POWER PLANT Type Under construction Applied for permission Other projects in planning (published) PROJECTS IN AUSTRIA Number Capacity Project MW 1 480 Verbund - Limberg 2 1 430 Verbund Reißeck 2 5 1.300 several TABLE 3: DATA OF VERBUND PSP PROJECTS Data Limberg 2 psp project Reißeck 2 psp project Nominal head 365 595 m Capacity MW 2 x ± 240 2 x ± 215 Status construction applied Start up 2011 2014 Penstock Ø 4,8 m 3,6 m 4-2

Figure 3: Limberg II schematic overview Figure 4: Hydraulic scheme Limberg II Steel lined pressure shaft design The relevant parts of pressure shafts or penstocks can be the pressure tunnel with steel lining or open penstocks for high head power plants. For the current projects in mountainous regions it is preferred to build a pressure tunnel to avoid open penstocks, which can cause problems from an environmental point of view (public acceptance) and which have the risk of damage from external impacts. Underground evaluation by extensive drilling is done to gain information on geology and ground water to optimize the location of the power shaft. In addition the performance of tunnel boring machines (TBM) offer a high standard of construction progress, quality, accuracy and is an economic option for the time consuming tunnelling process. Open penstocks are used for bifurcations, manifolds and penstocks within power house and caverns. Design for internal pressure For steel lined pressure tunnels the experience of geotechnical engineering methods for rail or road tunnels is applied, which uses the surrounding rock for partial load bearing, a method which is widely applied in tunnelling in Europe. This method proposed by Seeber [3] has become a standard in Austria for the design of steel lined pressure shafts. It includes several elements e.g. use of the surrounding rock mass as load bearing component, which has to be maintained with additional measures (pressure injection or local support elements) to achieve a bearing ring structure; measurements of mechanical properties of rock at different positions. This leads to a local design, where the load by internal penstock hydrostatic pressure is transferred via elastic deformation /(expansion) partially to the steel membrane expansion and partially to compression of the surrounding rock. Depending on the local parameters as rock working curve (pressure vs. deformation;) local gap between steel and rock and deformation of steel lining an equilibrium is reached between expansion due to internal hydrostatic pressure and membrane stress in the steel lining and compressive stress in the surrounding rock. By this method it is possible to transfer a significant part of the internal pressure load to the surrounding rock, which can bear up to 50% of the total load or even more at optimum conditions. Design even without steel lining is possible under certain conditions. Design for external pressure Two factors lead to external pressure load on the steel lining: The design method requires concrete injection to avoid gaps and to activate the rock load bearing, so the external injection pressure is relevant. Whereas during construction the tunnel is dewatered by a drainage pipe, this pipe is also injected with concrete after completion, so that an external ground water level and pressure builds up. This can lead to high external pressures as high as the rock and soil covering above the penstock. The design must consider stability against external pressure, which can lead to buckling problems of the lining. For stability like resistance against buckling the geometry (wall thickness of lining and roundness of the lining) and elasticity-modulus of the steel are essential, the higher yield strength has an minor effect with increasing values [4]. High strength steels lose some of their advantage under these conditions. For improvements of buckling resistance the wall thickness can be increased or external circular stiffener rings can be applied. Project planning for the location (depth, geological structure, ground water level) of the power shaft requires an optimization between high rock cover (allows high load transfer to the surrounding rock reducing steel lining thickness) and ground water levels (resulting in external pressure requiring increased steel lining or external stiffeners). For an optimum penstock location only the internal pressure should be design relevant. The design relevant situation for Limberg 2 project 4-3

concerning the rock cover situation, the internal and external pressure is shown in Figure 5. Figure 5: schematic load situation - pressure shaft Limberg II As mentioned above both loads internal and external pressure - must be considered for design and depending on the relevant load case, the adequate material for the steel lining can be chosen. For the Limberg example the design regime switches: internal pressure in the upper penstock section an intermediate section where external pressure by ground water and buckling stability is relevant - and the lower section, where again the internal pressure becomes dominant. Figure 6: Circumferential load situation and pressure fluctuations (fatigue load) For higher yield strength steels using the present compound design the local fatigue situation at the grouting sockets should be investigated more closely and optimized for a high fatigue life of all welded details. Design for fatigue The main design load is the static load by internal hydrostatic pressure. During filling of the penstock and operation additional dynamic pressure fluctuations occur, which result from plant start and stop, from load changes or from reversing the flow from turbine to pumping mode. The hydrostatic pressure fluctuations can reach considerable levels compared to the nominal design stress (Figure 5). For the Limberg 2 project penstock the additional dynamic pressure fluctuations can reach 37% for the lining close to the surge chamber and 17 % for the manifold. For fatigue life calculation a lifetime of 75 years with expected operation profile is assumed. An examination for the steel lining especially for the welds (longitudinal and circumferential welds) was done and gives sufficient fatigue life. For local construction elements (e.g. grouting sockets) the fatigue situation is more complex and the calculated fatigue life is determined by local design and weld details. Here the reserve in fatigue life is much lower and the situation is aggravated with higher design stress levels. For such elements the application of high strength steel loses some advantage. With the present design using materials up to S 690 the fatigue limitations became visible but could be solved. Figure 7: Penstock material for Limberg II: S 460 ML (TM-steel) e.g. upper surge chamber S 500 ML, S 550 ML (TM-steel) intermediate pressure S 690 QL for high pressure parts Steel grades used for lining The steel grades applied for the Limberg 2 project are shown in Figure 7. The internal diameter of the penstock lining is 4,8 m. The shaft diameter produced by the TBM is about 5,8 m. The steel lining is designed for both internal and external pressure and depending on the local situation the steel grade is chosen. The actual situation is listed in Table 4. The amount of steel lining for the pressure shaft (length of about 585 m) is about 2.700 tons, the length of weldments (longitudinal and circumferential) was calculated with 4.600 m with a total weld deposit of about 8.000 kg. Also other parts of the pressure water conduit are steel lined with similar or even lower steel grades and an additional amount of 2.800 tons. So the total amount for steel lining for the project adds to about 5.500 tons of steel plates. The total amount of steel can serve as a basis for evaluation of the potential weight reduction by applying higher strength steel 4-4

grades. TABLE 4: STEEL GRADES FOR LIMBERG 2 PENSTOCK Section Steel grade Plate thickness Section 1 S 550 ML 30 mm Section 2 S 460 ML 32 34 mm Section 3 S 500 ML 34 mm Section 4 S 550 ML 34 mm Section 5 S 690 QL 33-34 mm Higher strength steel linings, gives lower wall thickness, reduces welding volume and time and also reduce the necessity for post weld heat treatment (=pwht). A stress relief heat treatment is sometimes required for wall thickness > 30 mm or for applying ASME-Standards > 36 mm. So application of hss will reduce the necessity of pwht and gives an advantage for construction time and costs. Penstock construction Pipe fabrication For penstock construction the steel lining is prefabricated on the construction site in the upper valve chamber where pipes are rolled and welded submerged arc welding (=sma) from plates: two semishells are connected by longitudinal welds to 3 m pieces. Three pieces are then connected by circumferential welds to 9 m pipes which are then tested and inspected. After welding of the grouting holes and sockets the 9 m pipes are transferred to the tunnel. An extensive quality assurance program for materials and the welding process and non destructive testing (=ndt) program was developed with renowned experts and is applied to avoid any risk of welding defects. with 4 automated welding heads. One operator per head monitors and optimizes the welding conditions. The final ndt testing (manual) is carried out after 48 h to avoid undetected cold cracks. The method was successfully applied in earlier projects [5]. Figure 9: Pressure shaft welding in the inclined tunnel Grouting and injection After welding the gap between rock and steel lining is filled with concrete (Figure 10) and the next pipe is added. After completion of welding of the steel lining a 2 step injection program is started: The first step aims to fill the gap between steel and concrete and concrete and rock, which results from shrinkage of concrete and compensates for the relative temperature shrinkage of the lining (t = -10 C). This is done by injection using the prefabricated grouting sockets. The injection pressure must be below the critical pressure for buckling of the lining. After hardening of the first injection, the grouting sockets are used for rock drillings (up to 3 m and more) for deep injections to improve the load bearing capacities of the surrounding rock. For the second injection step even higher pressures are applied. Figure 8: Fabrication process of penstock steel lining Pipe welding For the circumferential welds in the tunnel a steel backing plate is used and the welding is done by automated tungsten hot wire method from the inside by simultaneous weldling Figure 10: Gap between steel lining and concrete - cross section of steel lined pressure shaft 4-5

Both injection steps are carried out after completion of the welding process and require the use of drilling and injection equipment (Figure 11). Drainage systems which are used during first grouting are also filled and injected. These steps consume extra construction time but are essential to activate the load bearing of the surrounding rock and complete the compound system. The compound system has a long tradition in Austria and is described in detail [5]. Figure 11: Steel lined pressure shaft grouting and injection system with cross section of grouting socket Penstock safety considerations The application of a compound-system steel lining / prestressed concrete gives an high inherent safety, resulting from safety factors from both components. For the steel lining usually 60% of yield strength is applied for design value for normal design load (and 90% of yield strength for extreme load) conditions. In addition the design stress for rock load is limited to proven (and tested) levels and the load bearing of rock is assured by the 2-step cement injection process. Even in case of failure of one of the two components, the load bearing capacity of the other should prevent a catastrophic failure of the penstock. Conclusion Steel lined pressure shafts are major elements of new storage and pumped storage power plants. More than 10 projects are under construction in Europe, which will use steel linings for pressure shaft. For the design of steel lined penstocks different design rules can be applied, depending on accepted rules by the local authorities and on planners and operators experience. For the projects of Verbund, steel lined penstocks are designed with partial load transfer to the surrounding rock and are constructed with injection to close the gap between lining and rock under external pressure. This design leads to reduced membrane stress in the steel lining so that the required wall thickness or yield strength can be reduced. The design rules involving activated rock to reduce membrane stresses have their limits in cases where the penstock is exposed to stability problems by external pressure. As shown for the Limberg 2 project the dimensions of the steel lining can locally be determined by external pressure, leading to increase in plate thickness with reduced yield strength for stability reasons. Intermittent operation, frequent starts/stops and load changes lead to dynamic pressure fluctuation and oscillations in the penstocks resulting in pulsation load and fatigue stress in the steel lining. The level of pulsation can reach significant levels (locally up to % of static load) and if the plant lifetime is considered, the damage accumulation must be analyzed and considered for design. Here again the specific design, which requires injection flanges welded into the membrane, can lead to local notches, to residual stresses and peak stresses which can affect the fatigue life. The advantage of high strength steel grades is reduced by such structural imperfections thus again. High strength steels grades of yield strength 690 MPa and higher could be an economic alternative to the presently applied steel grades, however the accepted design rules for the projects described, present some limitations: The accepted design rules compound concept - with its well proven inherent safety would have to be modified. In the specific construction process with potential stability load cases by external pressure, the high strength grades lose their advantage. Fatigue stresses at welded parts (e.g. grouting sockets) can also limit the advantage of hss grades. In addition the availability of hss materials and the quality assurance of the fabrication and welding process has to be proven. However there are several arguments for higher grades that include: Economic aspects: reduced material costs and welding time, less need for pwht, therefore reduced construction time and ecological benefits due to reduced materials and energy consumption and reduced transport and manipulation. References [1] The EREC Renewable Energy Technology Roadmap 20% by 2020; 14 November 2008: at: www.erec.org/ [2] M. J. Barnes: Hydropower in Europe: Current Status, Future Opportunities, HRW-Jurnal, July 2009 p. 24 [3] Seeber, G.: Neue Entwicklungen für Druckstollen und Druckschächte. In: Österreichische Ingenieur-Zeitschrift 18 (1975), Heft 5, S. 37-48 [4] Jacobsen, S., Buckling of circular rings and cylindrical tubes under external pressure, Water Power, December 1974 [5] P. Stering, E. Wagner, P. Widauer, "Reconstruction of the Power Conduit for Kaprun Main Scheme" Paper presented at the Conference High Strength Steel for Hydropower Plants, Graz 07 2005 4-6