The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations

Similar documents
Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

Tohoku Pacific Earthquake and the seismic damage to the NPSs

Tohoku Pacific Earthquake and the seismic damage to the NPSs

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

The Fukushima Daiichi Nuclear Power Station Accident

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident

Information on Status of Nuclear Power Plants in Fukushima

Nuclear Power Stations' Response to the Off the Pacific Coast of Tohoku Earthquake

Great East Japan Earthquake and the seismic damage to the NPSs

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

Fukushima Daiichi Disaster. Facts and lessons learned. July Takashi Shoji Programme Director of WANO

Great East Japan Earthquake and the seismic damage to the NPSs

Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami

Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011.

Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants

Nuclear energy - four months after Fukushima

Overview of Fukushima accident. Nov. 9, 2011 Orland, Florida

Nuclear Accident at Fukushima #1Nuclear Power Station

Fukushima Dai-ichi. Short overview of 11 March 2011 accidents and considerations. 3 rd EMUG Meeting ENEA Bologna April 2011

Deconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery?

Seismic Damage Information (the 164th Release) (As of 15:30 June 9, 2011)

Spent Fuel and Spent Fuel Storage Facilities at Fukushima Daiichi

Contents of Summary. 1. Introduction

Copyright 2016 ThinkReliability. How a Reactor Works

Conditions of Fukushima Dai-ichi Nuclear Power Station Unit 1 (As of 18:00 March 25th, 2011)

Contents of summary. 1. Introduction

WHAT HAPPENED, WHAT IS GOING ON IN FUKUSHIMA NO.1 NUCLEAR POWER STATION?

An overview of what happened at Fukushima NPPs

4. Current Status (1) Fukushima Daiichi Nuclear Power Station

Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization)

Progress Status Classified by Countermeasures

Presentation Outline. Basic Reactor Physics and Boiling Water Design Sequence of Events Consequences and Mitigation Conclusions and Lessons Learned

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations

Current radioactive concentration of the seawater in Miyagi, Fukushima, Ibaraki and Chiba

24 MARCH :00 UTC. Incident and Emergency Centre

Japanese Nuclear Accident And U.S. Response. Ellen Anderson Senior Project Manager Radiation Safety & Environmental Protection May 20, 2011

Tsunami Countermeasures at Hamaoka Nuclear Power Station

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Seismic Damage Information (the 219th Release) (As of 15:00 August 3, 2011)

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)

CNSC Staff Briefing CMD 11-M15 March 30, 2011

The Fukushima Daiichi Incident Dr. Matthias Braun - 2 April p.1

A One-year Review of Fukushima Daiichi Nuclear Power Station Steps to Achieve Stabilization

Immediate Countermeasures

Fukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011

The Accident at Fukushima: What Happened?

The Fukushima Daiichi Incident

-Update - Ministry of Economy, Trade and Industry Government of Japan

Japan s Nuclear Emergency - Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan

Annex III of Technical Volume 1 UNIT 3 SEQUENCE OF EVENTS

Measures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station

1) Order of accident progress and provisional expedient (chronological sequence)

Summary SUMMARY. Contents of Summary

Information on the earthquake in Japan on 11 March Compilation by GRS. as at 29 March 2011, 11:30 h (CEST)

A Study of Fukushima Nuclear Power Plant Accidents by the Viewpoint of PSA

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya

Seismic Damage Information (the 151st Release) (As of 12:00 May 27, 2011)

The Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station

THE FUKUSHIMA ACCIDENT: CAUSES, RESULTS AND IMPLICATIONS FOR EUROPE

PREVENTION POSSIBILITY OF NUCLEAR POWER REACTOR MELTDOWN BY USE OF HEAT PIPES FOR PASSIVE COOLING OF SPENT FUEL

Status of the Fukushima Daiichi Nuclear Power Plant Updated information ( at 1300hrs) (Prepared by Health Safety & Environment Group)

Fukushima Daiichi NPP Accident

Facts, Lessons Learned and Nuclear Power Policy of Japan after the Accident

Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka

New Safety Standards (SA) Outline (Draft) For Public Comment

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned

Annex I of Technical Volume 1 UNIT 1 SEQUENCE OF EVENTS

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Comprehensive Safety Assessment for Kashiwazaki Kariwa NPS

Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident

Information on the current status of the plants in Japan damaged by the earthquake and the subsequent tsunami on 11 March Compilation by GRS

Information on the earthquake in Japan on 11 March Compilation by GRS

X. Future Efforts to Settle the Situation regarding the Accident

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs

Information on the current status of the plants in Japan damaged by the earthquake and the subsequent tsunami on 11 March Compilation by GRS

Technical Volume 1 Description and Context of the Accident. R. Jammal P. Vincze

Japanese Nuclear Accident And U.S. Response. April 15, 2011

Experience feedback on the Fukushima NPS accident- Sanitary and environmental consequences

Radionuclide Release at Fukushima

Fukushima-Daiichi, Hurricane Sandy: NRC Standards vs. NFIP Regulations June 9-14, 2013

The Fukushima Daiichi Incident Dr. Matthias Braun - 16 November p.1

Attachment XI-1. I. Emergency Safety Measures, etc.

Understanding Energy: Emergency Preparedness for Nuclear in the US

Chapter 2 Fukushima Daiichi Unit 1, 2 and 3 Accidents

Transcription:

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations March 31, 2011 Tokyo Electric Power Company

Tohoku Pacific Ocean Earthquake Time: 2:46 pm on Fri, March 11, 2011. Place: Offshore Sanriku coast (northern latitude of 38 degrees, east longitude of 142.9), 10km in depth, Magnitude 9.0 Intensity: Level 7 at Northern Miyagi prefecture Upper 6 at Naraha, Okuma, and Fudaba, Fukushima pref. (Nuclear Power Station) Lower 6 at Ishinomaki, Onagawa, Tokai in Miyagi pref. Lower 5 at Kariwa, Nigata pref. 4 at Rokkasho, Higashidori in Aomori pref., Kashiwazaki, Niigata pref. Epicenter Issued at 14:53 on March 11, 2011 Seismic Acceleration at Fukushima Daiichi Unit 6 Horizontal 507gal Vertical 231gal Fukushima Daiichi NPS Fukushima Daini NPS Seismic Intensity epicenter Seismometer * gal: a unit of acceleration defined as cm/s². 1

This Accident Description: Fukushima Daiichi All operating Units automatically shutdown. Offsite Power Supply lost by the quake (1F1-6) Diesel Generators started, however Tsunami s wave flooded all DGs but one at 1F6 Seawater Pumps failed due to the Tsunami (1F1-6) Spent Fuel Cooling Diesel Driven Fire Pump Fire truck Maku-up System (backup) Spent Fuel Pool Fuel Pool Cooling System Reactor Building Primary Containment Vessel (PCV) Reactor Pressure Vessel (RPV) High Pressure Injection System and Reactor Core Isolation Cooling System Shutdown Stop fission reaction by inserting control rods that absorb neutron. Cooling Cool down reactor water to avoid fuel damage. Containment Prevent radioactive materials from being released to the environment. Condensate Storage Tank Sea Residual Heat Removal Core Spray System Out of operation for lost System Pump power 2

Plant Status: Fukushima Daiichi Unit1-3: Automatic Shutdown Unit1-4: Offsite Power Lost due to earthquake. Diesel Generators started, however lost by Tsunami s wave Unit 1-3: Core Cooling System failed, Water injected via Fire Protection Lines. Water level reduced below the Top of Fuel. Unit 5-6: Core Cooling system was recovered Unit 1-4 Spent Fuel Pool: Seawater injected by Fire Engines external pumps. Unit2:from 3/17 fire truck pumps were injecting seawater, expanded to Unit 3 and 4 on 3/20 Unit1,3 and 4: Hydrogen explosion caused the upper half of R/B damage. Unit2 may be damaged by Suppression chamber. Unit1-3 emitted radioactive substances during Venting to reduce inner pressure of the Reactor Pressure Vessel As of 31 March After Earthquake Pre-Earthquake Status #1 #2 #3 #4 #5 #6 Operating Shutdown for Maintenance Shutdown Automatic Shutdown Cooling Reactor Containment Offsite Power Freshwater Offsite Power Freshwater Offsite Power Freshwater Offsite Power Shutdown Cold Shutdown Cold Shutdown Pool Reactor Building damaged One Blowout Panel opened Reactor Building damaged Reactor Building damaged Drilled holes on the roof of Reactor Building Drilled holes on the roof of Reactor Building :functioning : non-functioning(working progress) :non-functioning (not working) 3

Plant Status: Fukushima Daini Unit1-3: Automatic Shutdown. Unit 4-6: Units in extended outage Unit1-4: Offsite Power maintained. Diesel Generators lost by the Tsunami flooding Unit 3: Cold Shut down in 22hrs after the quake Unit 1,2 and 4: Core Cooling system recovered and successfully to achieve Cold Shutdown Fukushima Daini Nuclear Power Station As of 31 March Unit 1 Unit 2 Unit 3 Unit 4 Before Earthquake After Earthquake Status Shut down Cooling Containment Operating (Cold Shutdown) :functioning : non-functioning (working progress) :non-functioning (not working) 4

Course of EventsFukushima Daiichi Unit 3 Earthquake Loss of Offsite Power Tsunami Reactors Automatic Shutdown Diesel Generator (D/G) Automatic Start D/G and Power Centre Flood (Loss of Electricity) Unstable side Safety side Operation for mitigation Reactor Core Isolation Cooling (RCIC) System Started RCIC Failure Failure of Fuel Pool Cooling System Residual heat moved to Suppression Chamber PCV pressure abnormal increase Start PCV ventilation Decrease RPV Water level Start injecting sea water and boron Fuels have been exposed Hydrogen generated Hydrogen Explosion SF pool water vaporized Fuel damaged Fission Product released 5

Chronology of Fuel Cooling March 11, 14:46 12th 13th 14th Unit 1 Unit 2 Unit 3 Unit 4 Unit 5-6 Common SF Pool 12 Start injecting sea water 14Start injecting sea water 13Start injecting sea water SF Pool Reactor Power Supply Earthquake One survived 17th 20th 21th 22th 23th 24th 25th 26th 27th 31st 24Recover Main Control Room lighting 25 Change over from seawater to fresh water 17 Water spray into spent fuel pool 20 Seawater injection into spent fuel pool 20 Recovered power to power center from offsite 31Water spray into spent fuel pool 26Recover Main Control Room lighting 26Change over from seawater to fresh water 20Water spray into spent fuel pool 22 Received power to power center from offsite 22Recover Main Control Room lighting 23 Seawater injection into spent fuel pool 25Change over from seawater to fresh water 20Water spray into spent fuel pool 25 Seawater injection into spent fuel pool 29Recover Main Control Room lighting 20 Reactor cooling shutdown 2021 Switched from D/G to offsite power 21water injection into spent fuel pool 24Received electricity from offsite 24Start cooling Reactor water temp N.D. N.D. N.D. No fuel 47.421.4 SF Pool Temp N.D. 45 N.D. N.D. 30.627.0 32 6

Plant Parameters (Fukushima Daiichi) as of March 31 14:00 Reactor Pressure [MPag] Unit1 Unit 2 Unit 3 0.506-0.011 0.016 FPC Skimmer Surge Tank level [mm] Unit1 Unit 2 Unit 3 Unit 4 4,500 5,600 N.D. 5,200 RPV Temp [] Unit1 Unit 2 Unit 3 246.1 (Feedwater Nozzle) 172.4 (Feedwater Nozzle) 114.4 (bottom of RPV) Reactor water level [mm] Unit1 Unit 2 Unit 3-1,650-1,500-2,250 RPV Fuel PCV Spent Fuel Pool Spent Fuel Skimmer Surge Tank Drywell pressure [MPaabs] Unit1 Unit 2 Unit 3 0.210 0.110 0.1066 Suppression chamber Reactor Building 7

Evacuation Fri 11 March 14:46 Automatic Shutdown 19:03 Emergency Announcement (Daiichi) by the Gov t 21:23 3 km radius evacuation order and 10 km radius citizens take shelter directed by the PM Sat 12 March 5:44 10 km radius evacuation directed by the PM 7:45 Emergency Announcement (Daini) by the Gov t 3 km radius evacuation and 10 km radius (Daini) taking shelter directed by the PM 17:39 10 km radius evacuation (Daini) directed by the PM 18:25 20 km radius evacuation (Daiichi) directed by the PM Tue 15 March 11:00 20-30 km radius taking shelter (Daiichi) directed by the PM Fri 25 March am 20-30 km radius evacuation (Daiichi) recommended by the Chief Cabinet Secretary 8

Monitoring Data Source: Ministry of Education, Culture, Sports, Science and Technology 9

Monitoring Data inside the Site Boundary Solid Waste Storage Building Pu-238: 0.180.033 Bq/kg Normal: Maximum 0.15 as of 3/22 7:45 Sports Ground Pu-238: 0.540.062 Bq/kg Normal: Maximum 0.15 as of 3/21 13:30 North of #5-#6water Outlet I-131: 47 Bq/cm 3 (X1177.3) Cs-137: 12 Bq/cm 3 (X137.9) as of3/30 14:15 Unit 6 Unit 5 Unit 1 Unit 2 Unit 3 Unit 4 Main Gate I-131: 4.110-4 Bq/cm 3 (0.41) Cs-137: 4.010-5 Bq/cm3 (X0.01) as of 3/30 2:002:20 South water outlet I-131: 1.810 2 Bq/cm 3 (X4385.0) Cs-137: 47 Bq/cm 3 (X527.4) as of 3/30 13:55 :Sea area :Dust : Soil I: Iodine, Cs: Cesium, Pu: Plutonium 10

Source: Ministry of Education, Culture, Sports, Science and Technology 11

Recovery status (Main Control Room) Main Control Room Power recovered March 22 22:45 Turn on Power to the Unit 3 Main Control Room March 24 11:30 Turn on Power to the Unit 1 Main Control Room March 26 16:46 Turn on Power to the Unit 2 Main Control Room March 29 11:50 Turn on Power to the Unit 4 Main Control Room Unit 1 Main Control Room turned onthe light fixture is broken by the earthquake Unit 1 Main Control Room Recovery 12

[Reference] Reactor Feed Water System Change over from seawater to fresh water with motor driven pump Unit 1: 25 March, changed to fresh water, pump motorized on 29 March Unit 2: 26 March, changed to fresh water, pump motorized on 27 March Unit 3: 25 March, changed to fresh water, pump motorized on 28 March From Natural Water TankFresh water Fire engine Water Filtration Tank Temporary Motor driven pump Reactor Feed Water system Fire Protection system Fire Protection system piping PCV RPV PCV RPV Unit 1 Unit 2 Seawater Fresh Water Tank Fire Protection system PCV RPV Unit 3 Pit Fire engine 13

[Reference] Measure to Decrease Pressure of PCV (Ventilation) Ventilation by-passing filter was adopted in this accident Exhaust Stack a) Reactor Building Exhaust Duct Reactor Building Primary Containment Vessel b) Stand by Gas Treatment System Filter Valve Valve Reactor Pressure Vessel c) Pressure-resistant ventilation Rupture Disk Valve Valve 14

[Reference] Water spray into spent fuel pool Unit 1,3 and 4: Water Spray with Fire Engines Unit 2: Existing Fire Protection Line is used Dam Water Tank (Fresh water) Fire engine Reactor Building Until 29 March PCV Fire engine Temporary water tank Spent Fuel Pool RPV Seawater Water Pit Fire engine Concrete Pumps 15

[Reference] Water Removal Process from Turbine Building Investigating the source of the water Unit 2 surface rate is as high as 1000mSv/h Unit 1 pump up water to the condenser. The water will transferred to the Condenser Storage Tank and then to the Suppression Pool Surge Tank. Unit 2-4: Condenser Storage Tank water transferred to the Suppression Pool Surge Tank Water Paddle in Unit 2 Reactor Building T/B Basement 2.0X10 7 Bq/cm 3 Maximum depth: 1000mm As of 3/27 22:30 Paddle of water Suppression Pool Surge Tank Turbine Building Temporary Water Pump Turbine Condenser Storage Tank Motor Condenser Trench Shaft Pump Trench water I-131:6.9X10 6 Bq/cm 3, Cs-1372.0X10 6 Bq/cm 3 As of 3/30 8:50All Rights Reserved 2011The Tokyo Electric Power Company, Inc. 16