PETRONET LNG LIMITED, INDIA Current Activities : Agenda No. 5 44 th MEETING OF GENERAL ASSEMBLY OF THE INTERNATIONAL GROUP OF LIQUEFIED NATURAL IMPORTERS(GIIGNL) VENICE, ITLAY 5-8 October, 2014
OVERVIEW 1. Dahej LNG Terminal 2. Kochi LNG Terminal 3. Gangavaram Terminal on East Coast 4. Direct Marketing 5. Petronet & GIIGNL Technical Study Group
DAHEJ LNG TERMINAL Located at Dahej in Gujarat in the Gulf of Cambay Commencement of Operations in 2004 Capacity (mmtpa) : 5.0 10.0 15.0 (2004) (2009) (2016) LNG Cargoes unloaded : 1240 + 7.50 mmtpa LNG imported from Qatar under long term contract Terminal meets almost 25% of India s gas requirement Truck Loading facility can handle 3000 loadings/ yr. Capacity expansion to 15 mmtpa (provision for 20 mmtpa) Second Jetty : Commissioned in April, 2014 Expansion status : All EPC contracts awarded Scheduled Completion : November, 2016 Expanded Capacity contracted with GAIL, GSPC, IOCL & BPCL
DAHEJ LNG STORAGE TANKS 4
DAHEJ REGAS FACILITIES WITH AIR-HEATER
DAHEJ SECOND JETTY
TRUCK LOADING FACILITY Petronet has Implemented first LNG Truck Loading Facility (TLF)in India at its Dahej LNG Terminal for customer who do not have access to gas pipelines in year 2007 Regasification Facilities set up at Customers ends Total number of truck loaded : 7000+ Capacity of available trucks : 15 & 7.5 (Tons) Petronet is installing additional eight bays of truck loading to meet the amplified demand
SATELLITE LNG HUB & LNG BY ROAD LNG By Road VAPORISATION FACILITIES VAPORISATION FACILITIES Satellite Hub
KOCHI PLANT OVERVIEW
KOCHI LNG TERMINAL LNG Terminal located in Special Economic Zone with Codeveloper status Capacity 5.0 mmtpa Long term contract of 1.44 mmtpa LNG from Exxon Mobil s Gorgon Project (Australia) supply to commence by end 2015 - back to back GSA with GAIL, IOCL and BPCL Time Charter Party executed for 4 th vessel. Kochi terminal commissioned in September, 2013 Truck loading facility supply to commence in July 2014 Currently operating at very low capacity in absence of major part of the pipelines connecting Tamil Nadu, Bangalore & Mangalore markets
KOCHI - FACILITIES 11
KOCHI - MARINE FACILITIES
THIRD TERMINAL AT EAST COAST Proposed Capacity: 5 mmtpa Location: Gangavaram, Andhra Pradesh DFR, FEED and various other preproject activities completed. Clearances obtained. Estd. Project cost: 800 million USD Gangavaram
GANGAVARAM TERMINAL LNG terminal to be developed as SPV with GPL as partner MOEF has accorded Environmental and CRZ Clearance. State Government approval received Terminal proposed to be commissioned in 2017 Facilities to include 2 Storage tanks, marine & regasification facilities To commence earlier supplies, FSRU option being examined through which supplies can commence in 2016 Understanding reached for connectivity with East West & Mallavaram-Bhilwara pipelines. In discussions with Kakinada - Srikakulam Pipeline Actively working on Customers tie up
GANGAVARAM Proposed land for plant sitting Proposed berth location
CATCHMENT REGIONS OF PETRONET S TERMINAL Dahej LNG Terminal Gangavaram LNG Terminal Kochi LNG Terminal
DIRECT MARKETING Petronet exploring opportunities to supply LNG to Coastal area consumers through small LNG Vessels in India and neighbouring countries Direct Marketing by focusing on the following areas: Signed HOAs & supplied RLNG to bulk end consumers in Power, Refineries & Fertilizers Sectors LNG/LCNG supplies through Trucks, to LNG hubs, Satellite Stations at customer s premises in regions not serviced by pipelines under the Brand name of
PETRONET & GIIGNL TECHNICAL STUDY GROUP Petronet actively participates and contributes in the activities of Technical Study Group of GIIGNL Petronet Technical team participated in: Report on emissions to Environment from LNG import terminals Compilation of incident data base & Study on Failure on demand Integration of CCGT power plant with LNG import terminal Petronet would propose Technical Study Group to take up updating of existing standards under the programme in coordination with other LNG bodies
Thank You THANK YOU Kochi LNG Terminal