Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Similar documents
Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Experts in tunneling with Tunnel Boring Machines

TBM Selection and Specification

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

Construction Technology B (CON4313)

Large-diameter bored piles and Large-hole drillings Applications

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Civil Engineering Construction I (CBE5031)

Pipe Jacking. Japan Sewage Works Association

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

Brief of evidence Tunnelling construction

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

1.0 Micro Tunnelling An overview

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

2 Technology of closed-face tunnelling machines

TBM rescue projects using shafts and ground freezing

Hardrock Tunnel Boring Machines

Tel: Neil: Tony: Website:

4D grouting pressure model PLAXIS

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

Grouting Bilfinger Spezialtiefbau GmbH

Prof. Eng. Daniele PEILA

4D grouting pressure model of a bored tunnel in 3D Tunnel

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Prof. Eng. Daniele PEILA & Prof. Eng. Sebastiano PELIZZA

CC1602 Microtunneling

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

Diaphragm wall Construction

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Risk Management of the Restoration of Shanghai Metro Line 4

Lesson Learned. Collapse of Diaphragm Wall Trench. Case study. Suez Canal Syphon Project

Misan University - College of Engineering Civil Engineering Department

An introduction to. pipe jacking

Water for the World. Methods of Developing Sources

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

From Colonia Jardín to Cuatro Vientos

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

Construction Technology B (CON4313)

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Tunnel Boring Machine Optimization

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling

Underground Construction Technology

NO DIG BERLIN 2015 Symposium and Exhibition March. Paper 5-3. Increasing requirements move boundaries in Pipe Jacking

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

Ching Guan Kee ABSTRACT

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

The new Standard DWA-A 125E. Pipe jacking and related techniques. published in German and English by

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

Grout properties and their influence on back fill grouting

Topic 3: 1 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt

JET GROUTING Implenia Spezialtiefbau GmbH

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

Concrete Pipe Jacking

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

Future mayor tunneling projects in the Netherlands,

Design of pipeline installation D-GEO PIPELINE

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

EOSC 547: Tunnelling & Underground Design

WORK IN PROGRESS. Technical Note. Technical description of key issues of Tunnel solutions. 1. Introduction

Design of pipeline installation. D-Geo Pipeline

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

IPC Company & DPI Presentation. February 2017

FOR HIGHWAY TUNNEL GALLERIA SPARVO.

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Structural Performance of Immersed Tunnel Element at Flexible Joint. Jian Sun Tongji University August 4, 2015

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

Fig.1: Mixshield with double--chamber system

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

Principles for Tunnel Design. 20th to 21st April 2017 Kuala Lumpur

Tunnel. Immersed Tunnels

Trenchless Pipeline Crossings

Tunnelling and Underground. Construction Technology

Pipe Jacking. Progress is built on ideas.

E-Power Pipe : A new trenchless method for underground cable installation

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

SECANT PILE. Introduction:

Tunnel Boring Machines

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

State of the Art TBM Full Face Driving

Compaction and Jet Grouting

Ten years of bored tunnels in the Netherlands; Part I, geotechnical issues

Transcription:

Tunnels content of the lecture 1st Hour Tunnels Immersed tunnels Comparison Bored Tunnels (short) Land tunnels 2nd Hour Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure Delft University of Technology, faculty of Civil Engineering Ir. S. van der Woude 20 February 2009 1 Department Vermelding onderdeel of Underground organisatie Space Technology

Immersed tunnels First immersed tunnel in the Netherlands; the Maas tunnel, 1942 20 February 2009 2

IMMERSED TUNNELS IN EUROPE 29 2 1 2 3 3 5 3 1 1 20 February 2009 3

Examples immersed tunnels in the Netherlands Calland, Piet Hein and 2nd Benelux tunnel 20 February 2009 4

Construction proces immersed tunnel Construction dock Tunnel elements (with temp. watertights bulkheads) Constructing the ramps with the transition structure Dredging the immersing trench Immersing Closure of the joints Founding and covering 20 February 2009 5

Principle immersing 20 February 2009 6

Construction dock 20 February 2009 7

Water barrier 20 February 2009 8

Transition structure 20 February 2009 9

BULKHEAD OUTSIDE VIEW Door Ballast-water pipes Air- vent pipe Nose Gina 20 February 2009 10

Gina gasket 20 February 2009 11

Coupling of the elements 20 February 2009 12

Closure joint 20 February 2009 13

Cross section B A F upwards = A * B * ρ w F downwards : Concrete Reinforcement Ballast concrete 20 February 2009 14

Design aspects immersed tunnel alignment Cross section Horizontal and vertical clearance (dredged trench) Force equilibrium Longitudinal section Ramps Joints Transition structure Horizontal and vertical curve radius Cover Maximum slopes Water barrier 20 February 2009 15

Design aspects Load cases >>>>>4780 Permanent loads dead weight, water, earth pressure Variable loads mobile loads due to transport, temperature Accidental loads earthquake explosion / fire collision falling and dragging anchors stranding ships 20 February 2009 16

Comparison bored/immersed tunnel Here we see the entrance of Bored tunnel: The Botlek railway tunnel of the Betuwe route. Immersed tunnel: The Botlektunnel Highway A15 20 February 2009 17

Comparison bored/immersed tunnel 20 February 2009 18

When to choose an immersed tunnel (with cut and cover ramps) Primarily Crossing of rivers/canals Advantages compared with a bored tunnel Shallower Shorter ramps Disadvantage compared with a bored tunnel Hindrance during construction caused by Dredging, Transport of elements, Immersing Construction of the ramps are adjacent to immersed tunnel Construction Dock 20 February 2009 19

When to choose a bored tunnel (with launch and reception shaft) Primarily Rivers Canals and any vulnerable object Historic city centre (Amsterdam) Residential areas (den Hague) Infrastructure (also C&P) Disadvantage compared with an immersed tunnel Deeper launching and reception shaft of TBM. Longer Advantages Little hindrance during construction Shafts can be located on optimal location. 20 February 2009 20

Land Tunnels Cut and cover Sheet piles or diaphragm walls Excavation with struts or anchoring Impermeable layer or dewatering or underwater concrete Construction of the tunnel In situ or prefab. Top Down method Pneumatic caissons 20 February 2009 21

Examples land tunnels in the Netherlands HSL-zuid, Betuweroute tunnel Zevenaar and tunnel Giessen 20 February 2009 22

Open building pit 20 February 2009 23

Cut and Cover Top down methode 20 February 2009 24

Cut and Cover / Top Down method Tram tunnel The Hague 20 February 2009 25

Cut and Cover Grout arch; Tramtunnel top down method>>> lecture 9 20 February 2009 26

Principle pneumatic caisson method 20 February 2009 27

Caisson method East line Metro Amsterdam 20 February 2009 28

Prefab shell tunnel Metro Rotterdam 20 February 2009 29

Bored Tunnels Introduction Tunnel-construction under the St. Clair River more than 100 years ago. 20 February 2009 30

Bored Tunnels in the Netherlands Hubertustunnel the Sophia tunnel and the Botlekrail tunnel 20 February 2009 31

Constructing a tunnel with a TBM Functions of a TBM: Controlled excavation of the ground. Support the ground/rock. (The shield) Construct the tunnel Facilitate the logistics (Transport of soil & tunnel elements & power, etc.). 20 February 2009 32

Constructing a tunnel with a TBM Pipejacking versus Tunnelling Shield and tunnel pushed Shield pushes against tunnel - D = 0,8m to ca. 3m - D > 3m - Limited length - Unlimited lengths - Lining = pipe - Lining = segmented ring - No sharp curves! - Sharp curves! - 2 additional processes 20 February 2009 33

Pipejacking >>> lecture 12 20 February 2009 34

Tunnelling 2 additional processes: Ring erection in the shield Shield tail injection (mortar injection) 20 February 2009 35

Tail-sealing-mechanisms 20 February 2009 36

Curves in pipe-jacking Øu-minimaal houten ring z gedrukte doorsnede 20 February 2009 37

Curves in Tunnelling 20 February 2009 38

Different shield types depending on the Geology and other boundary conditions Open Face (atmospheric pressure) In Rock; hard rock TBM (with grippers) In Soil conditions limited only small diameter and above ground water >>> lecture 12 Thix-shield Auger boring 20 February 2009 39

20 February 2009 40

Different shield types depending on the Geology and other boundary conditions Closed Face (support pressure) In soft soil conditions and in mixed geology Depending on soil conditions different types of support medium Support with bore fluid (bentonite) Slurry shield Hydro shield Support with excavated soil Earth pressure balance shield (EPBshield) Support with Air (only special occasions) EPB-shield Hydro-shield 20 February 2009 41

TBM: cutting elements and obstacles 20 February 2009 42

Selection criteria for type of TBM: Geological profile of the project. Groundwater pressures (support pressure is normative). Depth, horizontal- and vertical alignment of the tunnel. Surrounding area (settlements, ground-deformations). Logistic / available space. 20 February 2009 43

Slurry shield principle of support pressure Bentonite =Bore fluid (is the support medium) Functions of the bore fluid Maintaining support pressure Building a membrane and/or Creating an invasion zone (plug the pores) Transport of the soil particles to the Separation plant 20 February 2009 44

Slurry shield principle of support pressure 20 February 2009 45

Slurry shield versus Hydro shield Slurry shield Versus Hydro shield - Vulnerable for errors pumps - Air bubble levels out - More simple TBM - Accurate support pressure - Japan and pipe jacking - Europe 20 February 2009 46

Principles of slurry shield and EPB 20 February 2009 47

20 February 2009 48

Earth Pressure Balance (Elastic soil mixture from excavation face) 20 February 2009 49

Slurry 20 February 2009 50

Separation plant (cost factor) Separation plant Groene Hart, 2500m3/hr supplied by MS in 1998 20 February 2009 51

Slurry versus EPB Slurry-shield versus EPB-shield non cohesive versus cohesive 20 February 2009 52

EPB versus Slurry 20 February 2009 53

Support pressure EPB- versus Slurry Safety against excavation face collapse: P = 1,5 * σ h + 1,05 * σ w (all levels of cross section top and bottom) The bottom is normative Safety against blow out: P max = σ v / 1,1 (for all levels) the top is normative >>> CT 5305 & CT 5330 Foundation Eng. and Underground Construction >>>>CT 5305 & CT 5330 Foundation Eng. and Underground Construction 20 February 2009 54

20 February 2009 55

Sleufloze Technieken schildboringen 20 February 2009 56

Support pressure EPB- versus Slurry Ideal situation for support pressure worst case air support Support with bore fluid Support with earth paste EPB 20 February 2009 57

Summary Slurry versus EPB Slurry shield EPB-shield support with (bentonite) fluid support with the excavated soil minimum cover +/- 1 D minimum cover +/- 0,5 D in non- cohesive soil in cohesive soil extraction with pumps extraction with screw conveyor and? Pressure can be adjusted pressurre fluctuations accurateley Separation plant - simple TBM complex TBM (high torque, more wear, conveyors) overall higher costs overall lower costs 20 February 2009 58

Extend the use of EPB in unfavourable geological conditions 20 February 2009 59

Extend the use of EPB in unfavourable geological conditions 20 February 2009 60

Botlek Tunnel EPB in sandy soil 20 February 2009 61

Summary Immersed tunnels Building techniques for land tunnels. Functions of a TBM Pipe jacking versus tunneling Slurry versus Hydroshield Principle of support pressure Slurry versus EPB Extending the use of an EPB TBM >>>>chapter 7, 8, 9, 10 of the reader 20 February 2009 62

CT 3300 in relation to other courses CT 3300 Use of underground space. Broad introduction Inleiding ondergronds bouwen CT 4780 Special Topics New developments on UC CT 5305 Bored and immersed tunnels In detail CT 5330 Foundation Eng. and Underground Construction Amongst others Bored tunnels in detail CT 5740 Trenchless Technology Pipeline construction techniques In detail 20 February 2009 63

Tail-sealing-mechanisms (S1 seal) Rubber tail sealing mechanism 20 February 2009 64

Principle of the drilling fluid Clogging of the pores Air Drilling fluid Transport Filter-cake Penetration of the drilling fluid 20 February 2009 65

Slurry shield 1 Cutting wheel 2 Air bubble 3 Bentonite suspension 4 Drive unit 5 Stone crusher 6 Push cylinder 7 Air lock 8 Steering cylinder - Shield tail 9 Erector 10 Segment conveyor 11 Slurry pump 12 Segment crane 13 Main electric panel 14 Cable reeling drum 15 Discharge line 16 Feed line 20 February 2009 66

Segments tunnel lining Variation of the position of left and right segments change the dirrection of the tunnel Keystone closes the arch 20 February 2009 67

Next year, boulder clay foto TBM delfzijl. Foto groene Hart Tunnel lining Engineering 20 February 2009 68