Operational Constraints Update 13/07/2017

Similar documents
Operational Constraints Update 27 th November 2015

Operational Constraints Update 28/03/2018

Operational Constraints Update 25/01/2019

Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland

Summary of Studies on Rate of Change of Frequency events on the All-Island System

Annual Renewable Energy Constraint and Curtailment Report 2017

Rate of Change of Frequency (RoCoF) Project Quarterly Report for Q3 2015

Annual Renewable Energy Constraint and Curtailment Report 2016

Rate of Change of Frequency (RoCoF) Project Quarterly Report for Q4 2015

System Operational Costs Reduction with Non-Conventional Reactive Power Sources.

Chapter 2: Inputs. Chapter 3: Inputs

LFC Block Operational Agreement Ireland and Northern Ireland

DS3: Rate of Change of Frequency (ROCOF) Workstream

Business Process. BP_SO_12.1 Unit Testing

Delivering a Secure, Sustainable Electricity System (DS3) Programme Overview E i r G r i d a n d S O N I, Page 1

Performance Monitoring Workshop. 6 th June Belfast 11 th June Dublin

Ensuring a Secure, Reliable and Efficient Power System in a Changing Environment

Rate of Change of Frequency (RoCoF) project Six Monthly Report for May 2015

Rate of Change of Frequency (RoCoF) project Six Monthly Report for November 2016

Consultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project

DS3 Rate of Change of Frequency Modification Recommendation to the CER

TSO Recommendation System Services. 26 th June 2013

Frequency Changes Due to Large System Disturbances. Workgroup Report and Next Steps

Analysing the Value of Pumped Storage in the 2020 Irish Power System. Aidan Cummins, Luke Dillon

All Island Tso Facilitation of Renewables Studies

Electricity Security of Supply Report 2018

Section 3 Firm Access Quantities and Associated Transmission Reinforcements

DS3 and Qualifier Trials Update. Ian Connaughton 29 September 2017

Consultation on DS3 System Services Volume Capped Competitive Procurement. DS3 System Services Implementation Project

Business Process. BP_SO_4.2 Demand Forecasting for Scheduling & Dispatch

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Alternative Connection Application and Offer Process Proposal

Consultation on DS3 System Services Enduring Tariffs. DS3 System Services Implementation Project

Appendix 3.1: The Need for a Second North South Electricity Interconnector. A4 appendix.indd 4 25/05/ :59

Rate of Change of Frequency Distribution Code Modifications. Response to the Consultation

Rate of Change of Frequency (ROCOF) Review of TSO and Generator Submissions Final Report

GSR016: Small and Medium Embedded Generation Assumptions

Balancing Market Principles Statement

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Increase of the Rate of Change of Frequency (RoCoF) and its impact to the Conventional Power Generation in the Island of Ireland

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements

ALL-ISLAND Generation Capacity Statement

I-SEM Business Liaison Group NEMO. 09 November2017

Balancing Market Principles Statement

DS3: Voltage Control Workstream

Consultation on DS3 System Services Scalar Design

Ancillary Service. the WEM System Management. June 2018

1200 MW Wind Generation: Exploratory Study

Interconnection Feasibility Study

TRANSFORMING AUSTRALIA S ELECTRICITY SYSTEM

TSOs, taking into account the following: Whereas

NETWORK CONTROL ANCILLARY SERVICE QUANTITY PROCEDURE

04 June 2010 ALL ISLAND TSO FACILITATION OF RENEWABLES STUDIES. Final Report for Lot3/ENQEIR132. prepared for. EIRGRID plc

System Impact Study for. 1 January January 2016

System Services Industry Forum. 12 October 2017

The Statement of the Constraint Cost Target Modelling Methodology Effective from 1 April 2013

SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT

APGTF Workshop: Managing the Grid of the Future

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

I-SEM Testing Tariff High Level Options Consultation

Standard MH-TPL Transmission System Planning Performance Requirements

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

Integration of variable renewables: what the market can do to help or hinder. Mark O Malley.

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

The Impact of Wind Generation on System Services in Ireland

Harmonised Other System Charges 2014/2015. Recommendations Paper

System Management Action Flagging Methodology Statement

Response to I-SEM DS3 System Services Auction Design Consultation Paper SEM

Wind Research for North Sea wind Energy. Secure sustainable electricity supply

Introduction to the PJM Markets

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

Outage Management Redesign Consultation Process (SE-109) September 4, 2013

System Management Action Flagging Methodology Statement

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study

Celtic Interconnector

The Statement of the Constraint Cost Target Modelling Methodology. Effective from 01 April 2017

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff

June 2017 Disclaimer

System Services by Wind Power Plants The industrial point of view Eckard Quitmann Head of Sales - Grid Integration Dena Symposium, November 8th 2018

Network Support and Control Ancillary Service (NSCAS) Quantity Procedure

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION

Alternative Connection Application and Offer Process Proposal

A Transmission Planning Case Study for Wind Integration CREZ in ERCOT

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

MAY 1, Variable Generation Integration Costs

Interconnection Feasibility Study

DS3: System Services Review TSO Recommendations

Standard TPL Transmission System Planning Performance Requirements

REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN

Interconnection Feasibility Study

Recommended Values for I-SEM Scheduling and Dispatch Parameters

WWSIS - 3: Western Frequency Response and Transient Stability Study

Integration of Renewable Energy Sources in the Electricity System - Grid Issues -

NORTHERN IRELAND ELECTRICITY plc APPLICATION PAPER FOR THE APPROVAL OF ADDITIONAL CAPEX IN RP4 MEDIUM TERM PLAN : PART 1

Transcription:

Operational Constraints Update 13/07/2017

Key Updates No updates Disclaimer EirGrid plc, the Transmission Operator (TSO) for, and SONI Limited, the TSO for Northern, make no warranties or representations of any kind with respect of this document, including, without limitation, its quality, accuracy and completeness. EirGrid plc and SONI Limited do not accept liability for any loss or damage arising from the use of this document or any reliance on the information it contains. Use of this document and the information it contains is at the user s sole risk. In addition, EirGrid plc and SONI Limited strongly recommend that any party wishing to make a decision based on the content of this document should consult the TSO in advance. Version 1.54_July2017 Page 2

Contents 1. Introduction... 4 1.1 Document Objective... 4 1.2 List of Terms... 4 2. Operating Reserve Requirements... 5 2.1 Operating Reserve Definitions... 5 2.2 Source of Reserve... 5 3. Constraints... 6 3.1 Tie Line Limits... 6 3.2 Non-Synchronous... 6 3.3 Permanent Constraint Tables... 6 3.3.1 Active Wide Constraints... 7 3.3.2 Active Northern Constraints... 8 3.3.3 Active Constraints... 10 Version 1.54_July2017 Page 3

1. Introduction To enable the efficient and secure operation of the system, generation is dispatched to certain levels to prevent equipment overloading, voltages outside limits or system instability. The software used to model the system is the Reserve Constrained Unit Commitment (RCUC). 1.1 Document Objective The objective of the Operational Constraints Update is to present the key system and generator constraints which are included in the scheduling process (i.e. in the RCUC software). The most common operational constraints that are modelled are: North South tie-line export / import constraint: MWR type Moyle import / export constraint: MW type Requirement to keep a minimum number of units on in an area: NB type Requirement to limit the output of the generators in an area to limit short circuit levels or overloads: MW type or NB type Requirement for a minimum output from the generators in an area to support the voltage or to avoid overloads: MW type or NB type Requirement to limit the output of stations due to fish spawning: MW type This document comprises of: (i) Operational Reserve Requirements, and (ii) Constraints. 1.2 List of Terms MW MWR NB TCG Type Limit MW output of unit or units assigned to a TCG Limits (the total MW + Primary Reserve - the area demand) from assigned resources Limit to the status (On/Off) of the unit or units assigned to a TCG E X N B Limit Flag Equality Constraint (generation = load) Export Constraint - limit output of a group of units <= max limit Import Constraint - limit output of a group of units >= min limit In-between Constraint; >= min and <= max Version 1.54_July2017 Page 4

2. Operating Reserve Requirements The following tables show the operating reserve requirements on an all-island basis and in each jurisdiction. Category All Island Requirement % Largest In-Feed Minimum 1 (MW) Northern Minimum (MW) POR 2 75% 110 / 75 50 SOR 75% 110 / 75 50 TOR 1 100% 110 / 75 50 TOR 2 100% 110 / 75 50 1. Lower values apply from 00:00-07:00 inclusive 2. Minimum values of POR in each jurisdiction must be supplied by dynamic sources 2.1 Operating Reserve Definitions Category Delivered By Maintained Until Primary (POR) 5 seconds 15 seconds Secondary (SOR) 15 seconds 90 seconds Tertiary 1 (TOR1) 90 seconds 5 minutes Tertiary 2 (TOR2) 5 minutes 20 minutes 2.2 Source of Reserve Northern Dynamic Reserve Synchronised Generating Units Synchronised Generating Units and Moyle Interconnector (up to 50 MW) Static Reserve Turlough Hill Units when in pumping mode Moyle Interconnector (up to 50MW) Interruptible Load: Standard provision: 43MW (07:00 00:00) EWIC Interconnector (up to 100MW) Negative Reserve (Defined as the MW output of a conventional generator above its minimum load) 100MW 50MW Version 1.54_July2017 Page 5

3. Constraints 3.1 Tie Line Limits Tie line flows in both directions have physical limits, the maximum flow that can be sustained without breaching system security rules (line overloads, voltage limits etc.) after a credible transmission or generation event. The limits are referred to as the Total Transfer Capacity (TTC) comprising of two values: N-S and S-N. When determining minimum system cost, RCUC respects the TTC values by not allowing the sum of a) the tie line flow into a jurisdiction and b) the reserve requirement of the largest single infeed in that jurisdiction and c) a percentage of the reserve holding in that jurisdiction to exceed the TTC i.e. TTC > a + b + c. 3.2 Non-Synchronous To ensure the secure, stable operation of the power system, it is necessary to limit the level of nonsynchronous generation of the system. The Non-Synchronous Penetration (SNSP) is a measure of the non-synchronous generation on the system at an instant in time i.e. the nonsynchronous generation and net interconnector imports as a percentage of the demand and net interconnector exports (where Demand includes pump storage consumption when in pumping mode). 3.3 Permanent Constraint Tables The following tables set out the system constraints: Active Wide Constraints; Active Northern Constraints, and Active Constraints. Note that the limits specified in each table represent the normal intact transmission network limit. These limits may vary from time to time due to changing system conditions. Version 1.54_July2017 Page 6

3.3.1 Active Wide Constraints Name Inter-Area Flow TCG Type Limit Type MWR X:<= 400 MW (There is a margin of 20MW on this limit for system safety) Limit Resources Description and Northern Power s Ensures that the total MW transferred between and Northern does not exceed the limitations of the North-South tie line. It takes into account the rescue/reserve flows that could occur immediately post fault inclusive of operating reserve requirements. This is required to ensure the limits of the existing North South tie line are respected. Inter-Area Flow MWR X:<= 450 MW (There is a margin of 20MW on this limit for system safety) and Northern Power s Ensures that the total MW transferred between Northern and does not exceed the limitations of the North-South tie line. It takes into account the rescue/reserve flows that could occur immediately post fault inclusive of operating reserve requirements. This is required to ensure the limits of the existing North South tie line are respected. Non- Synchronous Operational Limit for RoCoF Operational Limit for Inertia X:<= 60% Wind, MOYLE, EWIC X:<= 0.5 Hz/s and Northern Power s N:>= 20,000MWs and Northern Power s Ensures that the SNSP is kept below 60%. Ensures that RoCoF does not exceed 0.5 Hz/s. Ensures that all island Inertia does not fall below 20,000 MWs. Version 1.54_July2017 Page 7

3.3.2 Active Northern Constraints Name Stability TCG Type Limit Type Limit Resources Description NB N:>= 3 Units at B4, B5, B10, There must be at least 3 all times B31, B32, C30, machines on-load at all times K1, K2 in Northern. Required for dynamic stability. Replacement Reserve North West MW X:<= 275 MW AGU IPOWER, BGT1, BGT2, CGA, CGT8, EMPOWER AGU, KGT1, KGT2, KGT3, KGT4 NB N:>= 0 or 1 Unit C30 depending on NI system demand Combined MW output of OCGTs and AGUs must be less than 275 MW (out of a total of 400 MW) in Northern at all times. 125 MW Required for replacement reserve Coolkeeragh must be on load when the NI system demand is at or above 1260 MW. This operational constraint is required to ensure voltage stability in the northwest of Northern and to prevent possible system voltage collapse above the indicated system demand. Kilroot Moyle Interconnector NB N:>= 1 or 2 Units depending on NI system demand MW B -300 <MW <442 Current restriction is -254<MW <247 K1, K2 There must be at least one Kilroot unit on load when the NI system demand exceeds 1400 MW and 2 units are required above 1550 MW. This operational constraint is required to ensure voltage stability in the Belfast area and to prevent the requirement for an inter area flow reduction in a post fault scenario. Moyle Interconnector This applies to all units registered as Moyle Interconnector units. It ensures that all flows do not exceed an import of 442MW to Northern and an export of 300MW to Scotland (values taken from NI). This is required to ensure that the limits are respected. Current restriction is due to Version 1.54_July2017 Page 8

one pole being unavailable. Negative Reserve NB >50 MW Varies B10, B31, B32, BGT1, BGT2, B4, B5, C30, CGT8, K1, K2, KGT1, KGT2, KGT3, KGT4 Number of units on above minimum load for negative reserve. Version 1.54_July2017 Page 9

3.3.3 Active Constraints Name TCG Limit Limit Resources Description Type Type Stability NB N:>= 5 Units DB1, GI4, HNC, HN2, MP1, MP2, MP3, PBA, PBB, TB3, TB4, TYC, WG1 There must be at least 5 machines on-load at all times in. Required for dynamic stability. Replacement Reserve Dublin MW X:<= 473 MW AT11, AT12, AT14, ED3, ED5, MRC, NW5, RP1, RP2, TP1, TP3 NB N:>= 1 Units DB1, HNC, HN2 Combined MW output of OCGTs must be less than 473MW (out of a total of 798MW) in at all times. Required for replacement reserve. The MW values are subject to change as availability of the units change. There must be at least 1 large generator on-load at all times in the Dublin area. Required for voltage control. Dublin NB N:>= 2 Units DB1, HNC, HN2, PBA, PBB There must be at least 2 large generators on-load at all times in the Dublin area. Required for voltage control. This assumes EWIC is operational. Dublin Dublin NB N:>= 1 Unit if Demand >4200 MW NB N:>= 1 Unit if Demand > 4600 MW HNC, PBA, PBB, PBA, PBB Note that during an outage of EWIC there must be at least 3 large generators on-load at all times in the Dublin area. Requirement for HNC, PBA, or PBB to be on load when Demand is greater than 4200 MW. This operational constraint is required for load flow control in the Dublin area. Requirement for PBA or PBB to be on load when Demand is greater than 4600 MW. This operational Version 1.54_July2017 Page 10

constraint is required for load flow control in the Dublin area. Dublin North Dublin South South NB N:>= 1 Unit HNC, HN2, PBA, PBB Requirement for generation in North Dublin (for load flow and voltage control). NB N:>= 1 Unit DB1, PBA, PBB Requirement for generation in South Dublin (for load flow and voltage control). NB N:>= 1 Unit if Demand > 1500 MW NB N:>= 2 Units if Demand > 2500 MW NB N:>= 3 Units if Demand > 3500 MW AT11, AT12, AT14, MRC, SK3, SK4, WG1 AT11, AT12, AT14, GI4, MRC, SK3, SK4, WG1 AT11, AT12, AT14, GI4, MRC, SK3, SK4, WG1 Requirement for at least one Unit to be on load when Demand is greater than 1500 MW. This operational constraint is required for voltage stability in the South. Requirement for at least two Units to be on load when Demand is greater than 2500 MW. This operational constraint is required for voltage stability in the South. Requirement for at least three Units to be on load when Demand is greater than 3500 MW. This operational constraint is required for voltage stability in the South. Note that when wind is less than 500 MW one of these Units must be AT11, AT12, AT14, MRC, WG1. NB N:>= 3 Units if Demand > 4200 MW AT11, AT12, AT14, GI4, MRC, SK3, SK4, WG1 Requirement for at least three Units to be on load when Demand is greater than 4200 MW. This operational constraint is required for voltage stability in the South. Version 1.54_July2017 Page 11

Cork MW B 0 MW <MW< 1100 MW AT11, AT12, AT14, WG1 Note that when wind is less than 500 MW one of these Units must be AT11, AT12, AT14, MRC, WG1. When Demand is greater than 4200 MW one of these Units must be GI4, WG1. restriction in the Cork area determined week ahead by Grid Operations NearTime. South MW B 0 MW <MW< 1800 MW AT11, AT12, AT14, GI4, MRC, WG1 Moneypoint NB N:>= 1 Unit MP1, MP2, MP3 Hydro Smolt Protocol EWIC Interconnector NB N/A Varies ER1, ER2, ER3, ER4, LE1, LE2, LE3 MW B -526 <MW< 504 Current restriction is -300* < MW < 504 EWIC Interconnector restriction in the Southern Region. This will be determined week ahead by Grid Operations NearTime. There must be at least one Moneypoint unit on load at all times. Required to support the 400kV network. Over the spring and early summer period as the water temperature in the rivers and lakes change, the hydro stations have to be dispatched in a very specific way to allow fish to move safely. This affects the generators in Erne and Lee. This applies to all units registered as EWIC Interconnector units. It ensures that all flows do not exceed an import of 504MW to and an export of 526MW to GB (values taken from Portan). This is required to ensure that the limits are respected. Current restriction is to mitigate against impact of a high frequency event on the island in the event of a trip on EWIC. Version 1.54_July2017 Page 12

Turlough Hill MW B >0 MW by day, <0 MW by night TH1, TH2, TH3, TH4 * The trial to remove the operational export limit for all system conditons commenced on the 20th of June 2017. During the trial additional frequency response will be enabled on a number of windfarms to assist in high frequency regulation when EWIC exports are greater than 250 MW. To ensure required MW running of Turlough Hill. Negative Reserve NB >100 MW Varies AT1, AT2, AT4, DB1, ED3, ED5, GI4, HN2, HNC, MP1, MP2, MP3, MRC, NW5, PBA, PBB, RP1, RP2, SK3, SK4, TP1, TP3, TYC, WG1 Number of units on above minimum load for negative reserve. Version 1.54_July2017 Page 13