Tile on Existing. Viewpoint

Similar documents
Mr. Eric Ryffel, Manager October 5, 2015 Sanibel Beach Club 626 Nerita Street Sanibel Island, Florida 33957

FUNCTIONAL REQUIREMENTS

2001 Building Failures Study

Exterior Elevated Elements Inspection Guidelines

Wall and cladding systems constructed. Coatings and Penetrants for Concrete and Masonry Walls

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure

SIKALASTIC-152 EXTERIOR WATERPROOFING MEMBRANE. Product. Scope. Appraisal No. 811 [2013] Appraisal No. 811 (2013) Amended 28 August 2017

Weatherproofing Masonry For Northern Climates

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate

CONCRETE TILE PAVERS

Included in our report are our visual observations, recommendations for follow-up evaluation, and conceptual repair recommendations.

Spec Master 5/7/ For each product requiring color and texture selection, provide full size samples.

DESIGN TIPS TECHNICAL BULLETIN #47 FLASHING, WEEP HOLES AND RELATED ANCHORAGE [1 of 8]

SECTION BRICK MASONRY ASSEMBLIES

SECTION CONCRETE PAVING SLABS SET IN MORTAR

SKYLINE HOUSE CONDOMINIUM 3711 SOUTH GEORGE MASON DRIVE FALLS CHURCH, VIRGINIA

SECTION CERAMIC TILE. B. Ceramic tile wall finishes including standard and custom designs.

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B

roofing ROOFING Design of the base ROOFING DETAILS

1.3 Work shall include all reinforcement and accessories necessary to complete installation.

SECTION mil thickness COLD FLUID-APPLIED WATERPROOFING

National Construction Code Series (NCC 2016) Building Code Of Australia (BCA)

SECTION ARCHITECTURAL PRECAST CONCRETE. C. Section Joint Sealers: Perimeter joints with sealant and backing.

Corium Brick Rainscreen System Specifications

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT

East Lyme Middle School EAST LYME MIDDLE SCHOOL

CONSTRUCTION SUMMARY REPORT

Balconies Information. How to waterproof and reduce efflorescence

DS411 Exterior. Product. BRANZ APPRAISAL No. 788 (2012) Scope. Wet-seal New Zealand Ltd P O Box Takapuna Auckland Tel:

SECTION mil thickness REINFORCED LIQUID-APPLIED WATERPROOFING

ReCote Finish System over Concrete

Superior Aluminum Guide Specification 10/4/2016 Non-Welded Aluminum Pipe Railing

CTIOA Field Report

PERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960

BITUMEN-SET PRECAST CONCRETE PAVING SLABS

FLUID APPLIED WATERPROOFING SECTION SPECIALTY COATINGS

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

Guidance Document Podium Decks & Buried Roofs

SECTION CERAMIC and QUARRY TILE

Forensics Engineering 8th Congress Forging Forensic Frontiers November 29 December 2, 2018, Austin, TX

Bush Elem. Addition & Alterations QUARRY TILE SECTION QUARRY TILE PART 1 - GENERAL

PROTECTO DECK INSTALLATION INSTRUCTIONS

SECTION mil thickness REINFORCED LIQUID-APPLIED WATERPROOFING

WATERGATE COMMUNITY ASSOCIATION 8 Captain Drive Emeryville, California Office: / Fax: WINDOW REPLACEMENT GUIDELINES

DIVISION 07 THERMAL AND MOISTURE PROTECTION ROOFING

Stone and Masonry Veneer

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

10/11/2017. Identify Processes or Materials Causing Distress or Failure. Portland Cement Association. References

SECTION UNIT MASONRY

TILE TILE

0331 Brick and block construction

SECTION COMMON WORK RESULTS FOR CONCRETE SSPECIALTY COATINGS

BALCONY REPAIR AND REPLACEMENT CASE STUDY

Building Enclosure Detailing for Balconies

Building Enclosure Detailing for Balconies

Bison Precast Flooring Specification

CCIM Central Canada Chapter. Richard Weldon, P.Eng., LEED AP Carson Dunlop Weldon & Associates Ltd. October 5,

By definition, envelope is an

PROPERTY PRESERVATION AND CAPITAL PLANNING

SECTION TILING

Master Specifications for Microcotta November 2017

SPECIFICATIONS: Architectural Aluminum Railings

SECTION UNIT PAVERS

addressing the needs of our customers and the environment one high performance Liquid Applied solution at a time. Liquid Applied Systems

Building Envelope Investigation UTHSCSA - CTRC. San Antonio, Texas. June 20, 2016

Asphalt Pavement Maintenance and Rehabilitation Strategies

KEYSTONE PACIFIC PROPERTY MANAGEMENT, INC. Monarch Hills Condominium Association Dana Point, CA. Annual Maintenance Review.

CSI SECTION MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials

CHAPTER 18 - REHABILITATION AND REPAIR OF STRUCTURES

Construction Standards PAGE

BISON PRECAST FLOORING SPECIFICATION

STRUCTURAL ASSESSMENT OBSERVATION REPORT

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

HYDRATHANE INTERIOR WATERPROOFING MEMBRANE. Product. Scope. Building Regulations. Appraisal No. 957 [2017] Appraisal No. 957 (2017) BRANZ Appraisals

May 17, Mr. Fred Preuss Oak Park River Forest High School 201 North Scoville Avenue Oak Park, IL 60302

Integral Waterproofing

LATICRETE and Moisture Vapour Emission Rate, Relative Humidity and Moisture Testing of Concrete

Owners of Strata #2720 c/o

A. Submit product data sheets and literature verifying physical properties of materials.

Stucco Moisture Inspection Report

SECTION EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE. A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels.

Prepared By. Accent Building Sciences Inc. For

Student Services & Classroom Addition

AS The External Waterproofing Membranes Standard

DRYPROOF UNDER TILE EXTERNAL WATERPROOFING MEMBRANE. Product. Scope. Appraisal No. 887 [2015] Appraisal No. 887 (2015) Amended 17 September 2015

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

TABLE OF CONTENTS. 15-Year Commercial Warranty (Green Border) Year Commercial Warranty (Blue Border) 8

SECTION INTERIOR STONE INTERIOR STONE

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

1. Rubberized asphalt waterproofing membrane, reinforced. 2. Molded sheet drainage panels. 3. Insulation. 4. Plaza deck pavers.

Exterior Conditions Assessment

Metal to the metal. by W. Lee Shoemaker, Ph.D., P.E. and Vincent E. Sagan, P.E. and Dale Nelson

ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART GENERAL 1.

SECTION STRUCTURAL STEEL

***************************************************************************************************************

SPECIAL SPECIFICATION 4897 Repair Structural Concrete

SECTION Arisfor WallGuard

MUSSELMAN HOME INSPECTION LLC

Narrow Modular Pavers (NMP) for Sand-Set Installations

Moonlight Architecture, Inc. Architecture Interior Design Site Planning

Transcription:

Viewpoint Tile on Existing Exterior Reinforced Concrete BalconieS By Steven C. Turner Exterior reinforced concrete balconies are often covered by tile set in mortar beds with grouted joints. These installations are not only aesthetically pleasing but are also durable, easily cleaned, and protective. This article provides details for the proper installation of tiled surfaces over structural concrete slabs. Fig. 1: Defects in existing concrete balcony Fig. 2 (Note: 1 in. = 25.4 mm; 1 ft = 0.3 m) Overview and Existing Conditions Tile-covered balconies require positive pitch of about 0.25 in./ft (21 mm/m) and consist of a waterproofing membrane, a portland cement mortar setting bed, exterior-grade tile, and latex-modified grout joints. The purpose of these requirements and components is to protect the structural concrete by removing precipitation quickly from the balcony surface and away from the main building structure. Balcony surfaces should be sound and any cracks, delaminations, spalls, scaling, and other defects should be identified and repaired (Fig. 1). Existing balconies must be inspected prior to consideration of a tile installation to see if the aforementioned criteria can be met. Many existing balconies will not be able to receive tile installation without certain modifications. If tile is going to be considered, the aforementioned conditions should be incorporated into the proposed balcony design. Waterproofing Waterproofing beneath the tile system is necessary to protect the structural slab so that water that infiltrates the tile cannot enter cracks in the slab. This infiltration can cause spalling of the concrete and tile surface, requiring removal of the tile to allow needed access for repairs. The selected waterproofing system for an existing elevated balcony surface should be readily available and easily installed without the need for specialty equipment or highly skilled labor. When cured, the tile mortar setting bed can be applied to the finished surface of the waterproofing. Effective waterproofing measures include urethane base coats and cold-applied liquid membranes with cast-in select aggregate. 24 Concrete Repair Bulletin march/april 2013 www.icri.org

Fig. 3 (Note: 1 in. = 25.4 mm; 1 ft = 0.3 m) Fig. 4 (Note: 1 in. = 25.4 mm; 1 ft = 0.3 m) Fig. 6 (Note: 1 in. = 25.4 mm) Fig. 5: Accommodating existing features Tolerances Existing balconies are not always pitched positively away from the main building and although a pitch of 0.25 in./ft (21 mm/m) may be specified, it is frequently not achieved. In some balconies, positive pitch can be altered when the interior portion of the building is loaded and placed into service. This loading condition can cause the balcony surface to become flat or even create a negative pitch back toward the building (Fig. 2). Finishing techniques and available access to balcony surfaces during original construction can create birdbaths low spots where water accumulates or ponds (Fig. 3). A topping or slurry coat can be used to fill in and address these low spots and minor slab deficiencies (Fig. 4). The mortar setting bed for the tile can address some inconsistencies in slab surfaces but should not be relied on for surface leveling or to improve slope and drainage. There can be no voids or hollow sections between the topping and the structural slab. The integrity of the topping slab and the overall tile system can be compromised by the accumulation of moisture seeping into the voids through cracks or other deficiencies. The additional weight of the topping slab in conjunction with the tile Fig. 7 (Note: 1 in. = 25.4 mm) system should be evaluated by a structural engineer before installing. Constraints The feasibility of the project may be jeopardized by existing features such as door threshold height, location of storage closet doors and privacy panels, the type of railing system (Fig. 5), and the height of through-wall flashings adjacent to the tile installation. Conflicts can be resolved prior to construction by making sure the finished elevation of the selected tile system does not have an impact on the existing hard features. Figure 6 shows an incorrect installation, while Fig. 7 shows the proper accommodations for existing features. www.icri.org march/april 2013 Concrete Repair Bulletin 25

Fig. 9: Drainage outlet for existing balcony wall Closet doors and privacy panels may need to be cut or modified to provide adequate clearance for the proposed tile system. Cut components should be treated to prevent rusting and future maintenance of these altered components must be considered because of limited access between the door/panel and the tiled balcony deck (Fig. 8). Fig. 8 Fig. 10 (Note: 1 in. = 25.4 mm) Accommodating Existing Drainage Some guardrailing systems such as masonry walls (Fig. 9) can promote ponding because they inhibit drainage or because the balcony slab is not properly sloped toward scuppers, drains, or weep holes. Tile installation in such scenarios can obstruct outlets and alter drainage patterns. To prevent this from occurring, scuppers, drains, and weeps may need to be raised and resized. Masonry walls equipped with through-wall flashings can drain directly onto bare balcony surfaces. Coatings and tile installed on existing balcony decks often block these drainage points and existing flashing must be modified to allow for proper drainage (Fig. 10). One alternative that still provides drainage without the need for flashing modifications is an elevated paver installation. Provisions for drainage from hollow posts must also be considered if the point of drainage is covered by the new tile installation. Posts that cannot drain may hold water for extended periods of time and cyclic freezing and thawing of entrapped water can cause the post to bulge and crack (Fig. 11). In addition, trapped moisture can cause posts made of ferrous metal to rust from the inside out. Tile heave and delamination can also occur when embedded posts drain water into the setting bed instead of onto the tile surface. Edge Detailing A proper edge restraint supports the leading edge of the tile, prevents chipping and damage, and provides a transition point between the waterproofing membrane and the coating systems used 26 Concrete Repair Bulletin march/april 2013 www.icri.org

Fig. 11: Existing post with freeze damage Fig. 12 to protect the exposed face of the balcony slab. An angle support at the outside face of the tile system is one method that leaves a clean support to the edge of the tile while providing resistance to water infiltration. Another acceptable approach is a clean caulk joint (Fig. 12). This approach is less expensive than a prefabricated edge support, but will require regular maintenance to replace the sealant joint about every 7 to 10 years, or as needed. Edge detailing and integral expansion/soft joints at the periphery of the tile and in intervals about every 12 ft (3.7 m) are necessary to allow for differential expansion and contraction of the tile system and adjacent hard features (that is, building walls and guardrails). Wherever the tile system is interrupted by or adjoins a differing material type, internal expansion joints and soft joints should be provided. The detailing of the tile edge can be affected by the railing/guard configuration, the method of railing/ guard attachment to the deck, and the type of railing/ guard system. Some of the most popular railings for decks are painted steel or aluminum with embedded or surface-mounted posts. Tile can be cut to fit around posts for railings with embedded support posts (Fig. 13) and the joint between the posts and the tile at the periphery of the post should be caulked. Surface-mounted railings require proper detailing to provide the correct transition between the tile and base of the railing (Fig. 14). Drainage from the post at the base of the mounting shoe must be considered unless the post is solid or the drainage point is located above the shoe. When installing a tile system, the shoe of the mounted post must be isolated from the tile system. Enclosing the mount in a pitch pocket or isolating three sides with a finished edge and leaving the outside face open for drainage are acceptable methods for this type of installation. Durable Installations Tile installation on existing balconies is possible as long as appropriate details and existing constraints are considered. The most important concept is to Fig. 13 Fig. 14 protect the existing structure by installing waterproofing and implementing drainage systems that will quickly shed the balcony surface precipitation. Regular maintenance is required to ensure the longevity of any exterior tile system. Failure to www.icri.org march/april 2013 Concrete Repair Bulletin 27

diligently maintain sealant and grout joints and replace tile that becomes cracked or broken will allow moisture to infiltrate the setting bed, resulting in possible freezing-and-thawing damage, heaving, and local deterioration of tile. A properly installed waterproofing membrane beneath the tile will protect the slab, but the tile and membrane system may need to be partially or completely removed should inspection of the structural slab become necessary. It should be noted that matching pre-existing conditions and the costs associated with restoration of the membrane and tile following the inspection can be costly. When a single owner is involved, the distribution of costs for this work is known. In situations where condominium associations or multiple owners maintain the structural balcony component as a common element, maintenance, inspection, and repair costs of a tiled surface installed by a resident can become an intricate section in the association bylaws. Uniformity, architectural compliance, access, quality assurance during installation, maintenance, recordkeeping, and temporary inspections are some of the factors that should be considered by a condominium association when a tile system installed by an individual resident will impact a common structural element. This Viewpoint article has been selected by the editors as an offering to the interest of our readers. However, the opinions given are not necessarily those of the International Concrete Repair Institute or of the editors of this magazine. Reader comment is invited. Steven C. Turner, PE, has been involved in the construction industry since 1993 in capacities such as Structural Engineer, Senior Project Manager, Consulting Engineer, and Quality Assurance. He received his BS degrees in physical sciences and civil engineering from the University of Maryland. Turner is a certified professional engineer and maintains memberships in a number of professional associations. As an owner of Building Envelope Consultants and Scientists, LLC (BECS), he prepares, reviews, and approves design concepts for steel, concrete, masonry, and woodframed restor ation projects. He guides projects from survey to punch list, maintains client contact, estimates delivery schedules, and develops project budgets. 28 Concrete Repair Bulletin march/april 2013 www.icri.org