APPLICATION OF COLLABORATIVE SUPPORTED FRAME ACCURATE ANIMATION FOR BRIDGE CONSTRUCTION PROJECT

Similar documents
CONSTRUCTION MANAGEMENT TOOLS USING 3D-CAD, VIRTUAL REALITY, RFID, AND PHOTOGRAPHY TECHNOLOGIES

Assessment of Load Capacity of Railway RC Slab Spans with Reinforcement Losses

Kageyama Teruaki. Preliminary inspection about the profit of 3D data in public works. Kageyama Teruaki, Kawakami Masakazu & Miyamoto Katsunori

BIM APPLICATION IN PIER CONSTRUCTION by

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE

A SCHEME OF OPEN-SOURCE HYBRID PAVEMENT MANAGEMENT SYSTEM FOR AN INTERNATIONAL STANDARD

Solutions for Dealing with Changes in Logistics Operations Environment

Peggy Ryan Williams Center. Ithaca, New York. AE Senior Thesis April 14, Angela Mincemoyer. Structural Option. Advisor Dr.

New Steel Structural Design Tools Based on Knowledge Processing for Introductory Education

Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

Simulation of a bridge deck construction using precast beams supported in Virtual Reality technology

Collapse accident under New Haengju Bridge construction work [Seoul City, Korea. July 31st, 1992] Masahiko Kunishima

Types of Structures and Loads

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia.

Development of an Efficient Tapered Slip-Form System Applying BIM Technology

The Great Himiyume Bridge, Highway Entrance to Nagasaki The world first extradosed bridge using corrugated steel plate webs

Preliminary design of concrete structures 124SDP1

CSG Engineering ensures the success by leading the implementation

Bonner Bridge Replacement Update:

ENR202 Mechanics of Materials Lecture 1A Slides and Notes

STUDIES ON LONG-SPAN CONCRETE ARCH BRIDGE FOR CONSTRUCTION AT IKARAJIMA IN JAPAN

VIRTUAL REALITY TECHNOLOGY TO REPRESENT CONSTRUCTION ACTIVITIES

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge)

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

Comparison of Sway Analysis of RC Frames using Cracked Moment of Inertia

ctbuh.org/papers Optimal Combination between Concrete Strength and Sets of Forms in High-rise Building Title:

With several years of detailing experience and a vast range of knowledge, we have successfully helped clients with numerous projects, including:

Hybrid prestressed concrete bridges with steel truss webs-sarutagawa bridge and Tomoegawa bridge

When building the arch, a provisional upright must be put on the pier placed on the roots of the arch.

SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series

Selection guide for Adapt Builder:

Case Study of the Core Structure Succeeding Method for Tall Building Construction

Title. Author(s)M. KAWATANI; S. MATSUMOTO; X. HE; Y. HASHIMOTO. Issue Date Doc URL. Type. Note. File Information TRAIN LOAD

MIDAS Training Series

Schematic Design in Revit Structure: Leveraging the Value of BIM for Early Design Decisions

STRESS REDISTRIBUTION IN COMPOSITE CONSTRUCTION DUE TO CREEP 1

Mick Leso Structural Option 2006 Penn State AE Senior Thesis RESEARCH

DEVELOPING CIVIL ENGINEERING DESIGN SOFTWARE USING MS EXCEL Varsha S Danavandi 1, Shaik Kabeer Ahmed 2 1

DESIGN OF MULTILEVEL CAR PARKING BUILDING

Spatial Three-dimensional Technology of Special-shaped Pier Based on BIM

AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables

PRACTICAL APPLICATIONS OF EARTHQUAKE AND TSUNAMI SIMULATION OUTPUT FOR DISASTER MANAGEMENT

Amity Design Ltd. House #7&9, Road #9 Block #D, Section #11 Mirpur Dhaka 1216, Bangladesh (23.820N, E) 03.MARCH.2014

Dynamic Management Architecture for Project Based Production

Thesis Proposal. Matthew R Peyton

The concept of statical determinacy

Parametric Analysis and Design Engine for Tall Building Structures

JCI Activity on ISO Standard for Seismic Evaluation of Concrete Structures. Masaomi Teshigawara 1

ctbuh.org/papers Reform Measures of Korea s High-rise Buildings Construction Period Title: Ki-In Kim, Senior Manager, HanmiParsons Co., Ltd.

Trump Taj Mahal Hotel

Research on seismic safety, retrofit, and design of a steel cable-stayed bridge

COURTYARD INFILL STRUCTURE DESIGN

Design of Izmir Bay Crossing Bridge

GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh ( , ) 22 March 2014

Basarab Cable Stayed Bridge in Bucharest

Dynamic Management Architecture for Project Based Production

midas Gen Advanced Webinar on Construction Stage Analysis with Special Emphasis on Column Shortening

Howard County General Hospital Patient Tower Addition Columbia, MD. Kelly M. Dooley Penn State Architectural Engineering Structural Option

Thesis Proposal Executive Summary Depth and Breadth Analysis

COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO. C.Sankarlingam Vice President L & T Ltd.

A THEORETICAL ATTEMPT TO REDUCE THE CONSTRUCTIONAL DEFLECTIONS OF UN-SHORED REINFORCED CONCRETE DECK-GIRDER BRIDGES

Construction and design features of the Bridge over the Danube River. Bulgaria

Pro-Con Structural Study of Alternate Floor Systems

Thesis Proposal. La Jolla Commons Phase II Office Tower San Diego, California. December 13, 2013

Monitoring of Long-Term Effects on Concrete Bridge Realised by Balanced Cantilever Method

Drawings shown within this brochure is the Preston CarPark Innovation Concept and patents filed in August 2018.

STUDY ON SOUNDNESS EVALUATION OF BRIDGE SLABS BY FALLING WEIGHT DEFLECTOMETER

DETERMINING A METHOD OF DYNAMIC ANALYSIS FOR THE VIADUCTS WITH GEOMETRIC IRREGULARITY AND INVESTIGATION OF THE SEISMIC PERFORMANCE OF NURTEPE VIADUCT

Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building

SI HOUSING PROJECT Flexsus House 22 Sustainable Housing system

I-94/I-69 Interchange Bridge Construction

Design of Tall Buildings: Trends and Achievements for Structural Performance. Conceptual Design in Structural System Development. November 7-11, 2016

DESIGN OF SLAB PANEL BY PIGEAUD S CURVES USING IRC: AND IRC:

QUALITY BEYOND CONSTRUCTION IN AN ITALIAN HOSPITAL

The construction technology of Chongqing Chaotianmen Bridge

Flexible Industrialization in Construction By Humanoid Construction Robots?

Structural Behaviors of Long-Span Cable-Stayed Bridge With A-Shaped Tower Due to Three Wind Speeds

New Troja Bridge in Prague Structural Solution of Steel Parts

Failure Detection of High-Strength Tendons in Prestressed Concrete Bridges by AE

HIGH IMPACT EXHIBITION STANDS

EXPERIMENTAL STUDY AND ACTUAL STRUCTURE DESIGNING OF LOOP JOINT USED FOR SEGMENTED PRECAST CONCRETE BRIDGE PIER AND CAISSON.

Stay Tuned! Practical Cable Stayed Bridge Design

Disaster Information Sharing System using Pictograms: Representation of Multidimensional Information

Structural assessment of the integrated steel fly-overs widening the historic multiple-arch concrete viaduct over the Pede valley

Structural Redesign Gravity System

Spatial analysis of concrete filled steel tubular tied arch bridge

Based on the performance of. Silver Spring, Maryland. David S. Finley Department of Architectural Engineering Structural Option

Torsion in tridimensional composite truss bridge decks

WEBGIS SIMULATOR FOR PROMOTION OF SEISMIC RETROFITTING AND COMMUNITY DISASTER MITIGATION ACTIVITIES

Global Journal of Engineering Science and Research Management

Analysis of Various Steel Bracing Systems using Steel Sections for High Rise Structures

STUDY ON TALL BUILDING STRUCTURE ANALYSIS

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems

PERFORMANCE-BASED OPTIMIZATION OF STRUT-AND-TIE MODELS IN REINFORCED CONCRETE BEAM-COLUMN CONNECTIONS

These systems are evaluated on the basis of serviceability issues such as:

An Integrated Methodology for Construction BIM & ERP by Using UML Tool

Transcription:

APPLICATION OF COLLABORATIVE SUPPORTED FRAME ACCURATE ANIMATION FOR BRIDGE CONSTRUCTION PROJECT Fukuchi, Yoshihiko, Ph.D Konoike Construction Co., Ltd. 3-6-1 Kitakyuhoji-machi, Chuo-ku, Osaka 541-0057, Japan TEL:06-244-3674,FAX:06-244-3632 E-Mail: yfukuchi@alum.mit.edu Hirai, Yujiro Kumamoto Prefecture 6-18-1 Suizenji, Kumamoto 862-8570, Japan TEL:096-384-1591 E-Mail:yujiro_hirai@email.msn.com Kobayashi, Ichiro, Dr. of Eng. Kumamoto University 2-39-1 Kurokami, Kumamoto 860-8555, Japan TEL:096-342-3536,FAX:096-342-3507 E-Mail:ponts@gpo.kumamoto-u.ac.jp Hoshino, Yuji Kumamoto University 2-39-1 Kurokami, Kumamoto 860-8555, Japan E-Mail:hoshino@gpo.kumamoto-u.ac.jp Yamamoto Kazuhiro Ministry of Construction, Government of Japan 1-19-32 Okaya, Otsu 520-2122, Japan TEL:077-545-5675, FAX:077-543-5340 E-Mail:y-kazu@mx.biwa.ne.jp

Abstract During a civil engineering construction process many types of professionals are involved, such as engineers, constructors, designers, clients and so forth. To provide mutual understanding among construction workers and unify their ideas is necessary the creation of an effective presentation. In addition, the construction process have to work relatively in harmony with the situation of the construction site. Moreover, the use of Computer Graphics (CG) can help to visualize clearly sequences of the construction process, simulate changes in the execution of the project and make it possible to be carried out smoothly before the construction begins. The paper introduces the application of Frame Accurate Animation (FAA) as an important implement for the construction management. Also explains the use of FAA in an illustrative example of the Sashiki Bridge (provisional name) construction project in Kumamoto. Our main expectation is for the work environmental become more cooperative, efficient and safely. Key words: Collaborative Work, Frame Accurate Animation (FAA), Presentation of CALS/EC in the construction business area. CG Animation (CGA) is one of these types of information technology, and has been reported with many practical uses on design drawing processes. The authors has applied Frame Accurate Animation (FAA), one of the CGA technologies, on different sequences of several construction projects so far, and distilled the application requirements and issues as follows: (1) purposes of use and objects were not clear during the use of FAA; (2) according to each purpose of the applications, FAA was not well expressed; and (3) specific role and usage of FAA were not well informed to the evaluators. In this research, FAA reproduces construction sites' condition, attempting to support the construction collaboratively. The possible usage of FAA during the construction process as a presentation tool has been observed through our second pilot project, Sashiki (provisional name) Bridge, the first extra-dosed bridge in Kyushu region in Japan, introducing the concept of the collaborative supported FAA application for construction management practice. 1. Introduction In phases of the public investment process, the construction work has to be shared and subdivided among construction workers. For this reason, exchanging design drawings, ideas and information about the construction project becomes not so simple to be done. The positive use of information technology can be observed trough the introduction 2. Presentation of Construction Process with FAA By using FAA during the construction process, two specific forms of the use have been verified. They are presentation and simulation. Whether it is presentation or simulation depends on the exact purpose of the usage. Strictly saying, however, users can adopt simulation as a tool to make presentation.

For Engineer For Worker Table-1 Usage of Collaborative Supported FAA Main Objective Tender Planning Management Explanation (Confirmation, Consensus Making) Explanation (Confirmation, Instruction) To decide construction method and sequence for tender price estimation To help examine construction planning; To examine alternatives for change order; for example construction method construction schedule site layout To instruct work conditions for subs; To instruct construction activity; for example safety instruction coaching traffic control For Client Persuasion (Recognition, Suggestion) VE Proposal Technological Promotion To get agreement on change order To propose plan in VE tender To get agreement for construction plan To inform construction plan For Local Community Persuasion (Understanding, Agreement) To publicize construction activity for example site surroundings from start to finish completion status construction outline construction method environmental impact To mitigate complaint Depending on each specific purpose of the use, FAA scenarios must be created for the effective presentation. In this paper, the presentation with FAA for expediting communication during the construction management process is called "Collaborative Supported FAA." As the FAA application impacts so many people related in public works, applications of Collaborative Supported FAA have to be categorized, and subjects and purposes have to be made clear to obtain an effective presentation. According to Kunishima, important matters and issues on the construction management process and its condition can be observed. Examples of specific uses of the Collaborative Supported FAA have been illustrated. Three main processes of the use are considered as follows: (1) acceptance of an order, (2) construction work planning, and (3) construction management. In each stage of the construction process stated above, audiences are specified and considered:. They are engineers, construction workers, clients, and local community. The Table -1 explains each position of the use. Engineers can use Collaborative Supported FAA when they seek authorization or confirmation to execute his task. In the phase of acquiring orders, the first step engineers involve in the construction project, engineers have to make a proposal in tenders with value engineering, promoting in-house technologies. In the phase of construction, thanks to the FAA's persuasiveness, the construction work sequences can be understood without enough construction management expertise or the presence of an expert. Therefore, a group of technical workers and engineers are able to carefully and easily analyze the construction work plan, making a successful decision in studying proposals of construction work plans. The Table -1 also presents the possibility of

FAA applications in decision making process in proposals for the client. Clients expect to hedge risks and get their project done faster. To let the local community go through the construction work plan and construction site management processes enables collaborative relationship between engineers and local community. Moreover, it is necessary to give details of construction management process to all construction workers. Thus, FAA provides the capacity to explain the contents of the construction work process, gives safely directions to the workers, and allows engineers to share data and information with others. 3. Collaborative Supported Frame Accurate Animation: To make Collaborative Supported FAA, the following two points should be considered. They are entire reproduction of construction site and vis ualization of the model creation content. Entire reproduction of the construction site is very important for simulation. Forecasting construction site condition is also very important during the construction process. Collaborative Supported FAA can be expressed in two dimensions. They are spatial expression, which provides enlargement, reduction, and visual effects, and temporal expression, which is flexibility of time scale. Collaborative Supported FAA enables to reproduce both huge amount of information such as whole construction site surroundings and detail expression such as re-bars arrangement depending on the specific size of enlargement and reduction at the same time. Collaborative Supported FAA also makes it possible to visualize impossible situations as if it were in reality, simulating virtual conditions inside of the structure that a naked eye can not observe. In terms of the flexibility of time scale, Collaborative Supported FAA reproduces not only the whole work schedule from the beginning to the completion of the construction work activities but also certain complicated work schedules. Thus, what Collaborative Supported FAA can realize and forecast is summarized as follows; (1) condition and relative position of the structure through the spatial expression, and (2) construction process and any relevant activities to the work through temporal expression. Moreover, the advantage of using Collaborative Supported FAA is the faithful reproduction of the construction site circumstances and is the ability to forecast the construction site condition precisely. Repeating a series of still images makes collaborative Supported FAA. In this way, the project participants can visualize construction in three dimensions and different sequences of the construction process by just turning on and off. Also, selecting a certain frame of the animation can easily print out a still image. AutoCAD r14j and 3DStudioVIZ 1.0J were used for the modeling and each FAA's still frames, and both are from Autodesk Inc. Director 5.0J, a MACROMEDIA product, was used to script each command of action. CD-ROM was used for the distribution of Collaborative Supported FAA.

Figure 1. The CAD drawing Figure 2. Study of Arrangements Figure 3. Re-Arrangement of a Pier 4. Case Studies Sashiki Bridge (provisional name) is situated at Ashikita area in Kumamoto Prefecture, Japan. The bridge is being constructed as the second route in a wide agricultural area of Ashikita (alias: Orange Belt). Details of the Sashiki Bridge construction project can be observed as follows: Description: Construction of 3 clear span extra-dosed pre-stressed concrete bridge; Length of main span: 225m, Width of Bridge: 9.25m - 12.25m Duration of Work: March, 1998 ~ November, 2000 (Estimated Completion) The agricultural road projects of the second route in the wide agricultural area of Ashikita intend to improve the circulation and transportation systems of the district. The district of Ashikita is a prosperous area in the southernmost Kumamoto Prefecture. The project aims at the development and stability of the agricultural work by improving logistics access. The extension of the road is around 25km, and the road system is called the Orange Belt. The Orange Belt will be alternative route for the Route 3. The construction process of the Sashiki Bridge, the first extra -dosed bridge in Kyushu region, was relatively unfamiliar. The extra -dosed bridge has the normal girder bridge structure whose upper floor slab is arranged with pre-stressed cables to support the diagonal member arranged outside of the slab. The structure is an alternative solution to make use of pre-stressed concrete in the main girder and to stand the bending moment. Applications of Collaborative Supported FAA are illustrated as follows. (1) Simulation of Re-bar Arrangements of a Pier FAA visualized the re-bar arrangements of a bridge pier and helped site engineers for examining better installation processes. The animation was used to facilitate communication with re-bar placers and site engineers, allowing them to examine various ways of the re-bar arrangements. In general, re-bar arrangements of the bridge pier were designed independently among its base, column and beam. (Figure-1) Through regular designing process, the thickness of re-bars in the same part such as a base or column is taken into account although not taking others parts into consideration. Therefore, the re-bars of each part are always interfered each other. In this situation, site engineers usually redesign re-bar arrangements beforehand, and redraw re-bar arrangement drawings before making decisions in changing positions, cutting or reinforcement

Figure 4. Overall Construction Schedule Figure-5 Simulation of Cantilever Erection System However, the engineer often find the presence of re-bars interfered each other at the actual construction site, only to find that the re-arrangement is needed. For this reason, the engineers decided to place all re-bars of three parts altogether in advance on the computer to see where the interference was observed and how they can re-arrange them. (Figure -2) Then, they re-arranged interfered re -bars so as to interfere with each other (Figure-3). the project intuitively. For local community, it can be used to improve the image of the construction project. Thus, in this specific application, the FAA was created with the function of the bridge structure turned on or off, showing the major work schedule from start to completion (Figure-4). Through the application, the whole process of the project including the geographical features was visualized. The objects created for this application can be used for other FAA applications. (2) Overall Construction Schedule It's important for project participants, such as engineers, workers, clients and local community, to grasp the whole process of the project in the earlier stage of the construction. For example, the FAA can be used for the engineers to support the rational construction planning by grasping the whole story of (3) Simulation of Cantilever Erection System The Figure-5 shows the erection process of moving wargen in Cantilever System. The FAA can be used for the working explanation and for pointing out the dangerous part in education for inexperienced workers. Captions in each figure help understand the

Figure 6. Change Order Approval for Main Tower Figure 7. Completed Animation Figure 8. The view of a car Figure 9. CG Photo-Montage complicated erection process. It may not be effective for well skilled workers, but the complex construction which is difficult to grasp a situation only from the information of the still images. critical if engineers found any problem on the construction site with everything set up, such as working space shortage. FAA should be used to rehearse several site layout of construction by comparing the working space in advance. (4) Change Order Approval for Main Tower For explanation of changing scheme on construction sequence of the main tower and cantilever construction, FAA was created by showing both original and changed designs side by side. (Figure-6) On the process of the main tower construction, constructing main tower in advance and construct cantilevers later was the original sequence. However, engineers decided to change the order. In the proposed alternative plan, three blocks of cantilevers have to be erected before the main tower construction begins for ease of working. It would be (5) Completed Structure and CG Photo-Montage: It seems important for residents what kind of structure is going to build and how the view changes rather than the way of construction. So the animation was made which have several viewpoints such as from the sky, ship, and car. (Figure-7, 8) The contractor has to improve the image for residents, because their cooperation is needed to carry forward the construction. For example, to explain the outline of construction, it is considered that all of the processes and the completed structures help enhance

their understanding. Furthermore, it is possible to use CG photomontage. A cut of animation scenes is combined with a site photo. (Figure-9) References [1] The Ministry of Construction s internet site, http://www.moc.co.jp, 1999.4. 5. Conclusion [2] Fukuchi, Yoshihiko et al., SERIES OF APPLICATIONS OF COMPUTER GRAPHICS FOR A In this paper, authors tried to help support construction management process by reproducing the construction site and virtually performing construction activities on the computer, proposing Collaborative Supported Frame Accurate Animation. Case studies on an actual bridge construction project in Sashiki have been performed and the results from the studies have been examined. Through the case studies, the evaluation method for the Collaborative Supported FAA application in construction projects found to be necessary not only by the cost and the period of production but by some other performance evaluators such as the value chain analysis method which can expect synergy of each application. In this research, designers mainly produced the data of FAA. It will, however, be important for clients such as the Ministry of Construction in Japan, to deal with FAA by themselves since the keyword "Accountability" has been look at to carry out their duties and to explain how the public works projects are needed. DAM CONSTRUCTION SITE MANAGEMENT AND SITE SURROUNDINGS, First International Conference on New information Technologies for Decision Marking in Civil Engineering,Volume2,pp.1209-1216,1998. [3] Kunishima, Masahiko et al., The Philosophy of Construction Management., Sankai-dou, 1994.