LARGE STORAGE TANK PROJECT

Similar documents
2018 Manufactured Homes and Factory Built Housing

Scope of Work Bid Package C-8 - West Overhead Doors

Board Presentation North Slope LNG to Fairbanks Project

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

Doseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410

City of Westerville Guide to Commercial Inspections

ADDENDUM NO. 1 PRE-BID CONFERENCE: GENERAL: Great West Engineering, Inc N. Lakeharbor Lane Boise, Idaho (208)

CONSTRUCTION DRAWINGS

SECTION GROUND STORAGE TANK

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

Port KC RFP NORTHLAND PARK BUILDING V

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

Scope of Work Bid Package C-3 - West Precast Concrete

Pursuant to Condition 7 above referenced Orders, Sabine Pass is herein submitting its monthly construction progress report for April 2016.

COMPLETE REVISION October Process Industry Practices Piping. PIP PNSC0036 High Density Polyethylene (HDPE) Piping Installation Specification

NFPA 13D, Standard for the Installation of Sprinkler. One- and Two-Family ANSI/AF&PA, Wood Frame Construction Manual (WFCM) for Oneand

DIVISION 5 METALS SECTION STRUCTURAL STEEL

SECTION SLUDGE HOLDING TANK DEWATERING

ALDI STORES CONCRETE SALES FLOOR. The Fricks Company Floor Construction Quality Control Prerequisites and Details

UNIFIED FACILITIES GUIDE SPECIFICATIONS

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR BUY AMERICA

SECTION PACKAGE BOOSTER PUMP STATIONS

4-200 CONTRACTOR LICENSING; REGISTRATION. The following information must be submitted for registration:

Rapid Axial Load Testing of Drilled Shafts

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

SECTION AIR TERMINAL UNITS

REQUEST FOR PROPOSAL Engineering Design for Culinary Water Tank and Secondary Water Tank Conversion

Dick s Sporting Goods Demolition Package

April 4, ADDENDUM NO. 1 This Addendum and attachments consists of: 47-Pages. ITB Northwood ABC Elementary School Roof Replacement

SPITZER CONFERENCE CENTER BRIEFING SUITE REFRESH Addendum #2 02/22/2018 LCCC POJECT NO. SPBSR-17 BPA PROJECT NO

CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS

COMPLETE REVISION November Process Industry Practices Structural. PIP STF05530 Grating Fabrication Details

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

Capital Projects Group Mechanical Work Commissioning Specification

DUKE UNIVERSITY CONSTRUCTION STANDARDS

Thermosyphon Foundations in Warm Permafrost

SECTION TURBINE VENTILATORS

Division II Contractors

Invitation to Bid Duplin County Refrigeration Project for Villari Brothers Foods 1012 US Hwy 117 South Warsaw NC 28398

Polycrete Big Block Standard Specification

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood.

University of Delaware

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018

CITY OF CHINO HILLS. Request for Proposals (RFP) for. On-call Electrical Repair Service. On-call Electrical Repair including Water and Wastewater

Interior Energy Project: Pentex Purchase & Project Financing Agreements and Analysis. November 2017

References. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A

SECTION AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

SECTION ROOF MOUNTED ATTIC EXHAUST VENT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1

Fairfield Board of Education Proposed Capital Non-Recurring Projects

SECTION INSTALLATION OF OWNER-FURNISHED PRODUCTS

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

PLUMBING BUILDING SCOPE OF WORK

Statement. Special Inspection

TABLE OF CONTENTS. 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers

SECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck)

DIVISION 5 - STRUCTURAL STEEL AND IRON WORK

MINNESOTA STATE SECTION ADVERTISEMENT FOR BIDS

C o u n t y o f F a i r f a x, V i r g i n i a

SAN ANTONIO WATER SYSTEM University Pump Station Improvements Project SAWS Job No Solicitation No. B DD

DIVISION 33 UTILITIES SECTION PACKAGED SEWAGE GRINDER PUMPING UNITS

DG Valley Green Natural Gas, LLC EnergyNorth Set 1 to Valley Green Natural Gas, LLC

SECTION GROUND WATER STORAGE TANKS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

SECTION FUEL PIPING SYSTEM AND FUEL TANK RELOCATION

SECTION DUCTILE IRON PILES

COLQUITT COUNTY BOARD OF COMMISSIONERS 101 East Central Avenue

ADDENDUM NO. 2 to Bid Documents for Project No , Community Center Generator Enclosure. Date: March 24, 2016

SECTION COLD-FORMED METAL FRAMING

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

The University of Texas Health Science at Houston Swimming Pool Renovation Project Phase 1: New Filter System

ENGINEERING SERVICES Subaqueous Water Transmission Main Design

Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LIGHTING AND SIGNS

C. Miscellaneous Metal Fabricators are specified elsewhere in Division 5.

PRECISION INDUSTRIAL CONTRACTORS, INC

Division 03 - Concrete Section New Westminister Multi-Use Civic Facility & Office Building Project No Page 1

Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan)

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

METAL FABRICATION..1 General Conditions and Division 1 shall govern Work of this section.

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

REQUEST FOR QUALIFICATIONS. Design/Build Project Number CP Power Plant - Boiler 10 Gas Burner Replacement

Scope of Work Bid Package C-4 - West Polished Concrete

Division MEDICAL EQUIPMENT SUPPORT SYSTEMS PART 1 GENERAL

SPECIFICATIONS - DETAILED PROVISIONS Section Chlorination System (On-site Sodium Hypochlorite Generation System) C O N T E N T S

SITING STUDY FOR THE GRASSY POINT LNG TRANSSHIPMENT AND STORAGE TERMINAL

SECTION STRUCTURAL STEEL FRAMING

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA)

FENCING AND FENCE REPAIR

PULSED AIR MIXING SYSTEM

SECTION AIR COILS

1DIVISION 15- MECHANICAL Section Fire Pumps. A. Single Stage, Double Suction, 9100 Series Horizontal Splitcase Fire Pump (Base Mounted)

Addendum No. 1. City of Chicago Department of Water Management Bureau of Engineering Services

Transcription:

INTRODUCTION The Fairbanks Large Storage Tank is part of the Interior Energy Project (IEP) designed to expand natural gas distribution in Fairbanks and Interior Alaska. A tank with a capacity of 0.44 Bcf (5.25 million gallons) is desired. A five-million-gallon tank represents a 15 fold increase compared to FNG s current storage capacity. The new tank is part of a program that will develop new, larger capacity production facilities, larger tanker fleet, and expanded distribution system. The development of the production facility, tanker fleet, and distribution system are under separate cover. PROJECT The Fairbanks Large Storage Tank is a project ( the Project ) to design, construct and startup storage, truck offloading, and vaporization facilities at an existing FNG facility in south Fairbanks, Alaska. The existing storage tanks will be decommissioned and re-purposed after startup of the new facility. New vaporization is required to handle the planned increased volumes of gas sent out from the tank. The new tank and vaporization equipment will be tied into the existing and expanded metering run and distribution header. PROJECT DEVELOPMENT PLAN This Project Development Plan describes the means, methods, and expenditures for accomplishing project goals. This plan will be updated periodically throughout the life of the project. This development plan references other agreements, contracts, and documents. In the event of conflict between the terms, conditions, and provisions of this Project Development Plan and any referenced document, the terms, conditions, and provisions of the referenced document shall control. SCOPE Preliminary Engineering Preliminary engineering will evaluate the tank site for permit requirements, surrounding activity and zoning considerations, and vapor dispersion and thermal exclusion space. The vapor dispersion and thermal exclusion space will determine the maximum size of the tank suitable for the site. Preliminary engineering will also develop a list of qualified tank bidders, develop the contracting plan, prepare request for proposal for tank design and erection, determine site layout, conduct geotechnical

investigation, determine most cost effective foundation design, and conduct the bid for tank design and erection. Tank Design-Erect Contract The LNG storage tank is a specialty item governed by several design codes including federal 49 CFR 193 Safety Standards for LNG Facilities; NFPA 59A Standard for Production, Storage and Handling of LNG; and API-620 Standard for Design and Construction of Large, Welded, Low Pressure Storage Tanks. The tank, its foundation and the site preparation will be designed and erected on a lump sum turnkey contract basis. The bid specifications call for bidders to provide a refrigerated liquid tank suitable for storage of liquids at -325 F or warmer at a pressure of not more than 2.0 psig in general accordance with API-620 2006 edition. The successful bidder will design, provide materials, and construct on-site the tank and associated appurtenances including foundation anchors, access stairs, top platforms, and maintenance lifting gear. The successful bidder shall be responsible for testing the tank and the insulation space for leak-free condition. The successful bidder shall also provide technical personnel to supervise the initial cool-down of the tank with LNG provided by FNG. The initial cool-down is a critical step to ensure that metal shrinkage is properly controlled and the tank maintains integrity. The successful bidder shall warranty materials and workmanship for a period of two years from the date of substantial completion. The successful bidder shall also warranty the tank rate of evaporation ( Heat Leak ) at a rate mutually agreed to in the contract for a period of two years. Bidders are requested to provide a design with a rate of evaporation that approaches 0.05% at 50% tank capacity at the Fairbanks annual mean temperature of 27 F. Site Development Land clearing, access roads, and secondary containment dikes are required for the site. The work will be designed under the guidance of FNG s Owner Engineer. The work will be included in the Tank bid. Foundation CHI Engineering in collaboration with Alaska-based has completed geotechnical evaluations and studies necessary to establish a baseline for designing for permafrost conditions and sealing of drawings. The tank erector will be responsible the foundation installation.

Vaporization FNG s Owners Engineer will design the vaporization equipment. The equipment will be purchased by FNG and installed by Alaskan contractors. Truck offloading FNG s Owners Engineer will design improvements to truck-offloading to allow higher transfer rates and more frequent deliveries. Equipment will be purchased by FNG and installed by Alaska contractors. Send-out pumps FNG s Owners Engineer will develop specifications for in-tank LNG send-out pumps. The pumps will be purchased by FNG and installed by Alaska contractors under factory supervision. The in-tank pumps are selected for reliability and reduced operating cost. External booster pumps can be added in the future if high-pressure delivery to future industrial users is required. CONTRACTS The contracting plan for development of the complete new storage site, including the tank is based on FNG serving as the project developer, and issuing and coordinating multiple prime contracts. In this manner, FNG can select the best value providers for portions of the scope. The contracts are: Owner s Engineer Currently CHI Engineering Services, Inc. Portsmouth, NH. o The Owner s Engineer is responsible for overall site development plans, including the vapor dispersion and thermal radiation studies, foundation design, equipment sizing Permitting Consultant Not Yet Selected o Permitting consultant responsible to identify and make application for all required permits Structural Engineer / Arctic Engineer Great Northern Engineering, Inc. Palmer, AK o The structural and arctic engineer provides the tank foundation support calculations, pile sizing, and cold weather details in support of work by Owner s Engineer. Geotechnical Engineer Golder Associates, Anchorage, AK o Geotechnical engineer provides subsurface investigation and determines soil bearing capacity for foundations and structures placed on the site Tank Designer / Erector o Tank designer / erector has responsibility for designing a tank and foundation of the specified size in compliance with all applicable codes, and Owner specifications, erecting the tank in a safe, timely manner, and testing and certifying the tank to applicable Codes and standards. Tank erector shall provide personnel to supervise the initial cooldown and commissioning of the LNG tank. Foundation scope will include supply, fabrication,

and installation of piling; installing cooling coils around foundation in accordance with final design, placement of embedded tank anchors; and completion of the tank foundation in a safe and timely manner. The Tank supplier will also be responsible to prepare, rough grade, and fine grade site in accordance with plans prepared by Owner s Engineer. This work includes preparation of the tank foundation site; construction of temporary access roads; construction of the secondary containment dike, grading and site prep for truck offloading facilities Mechanical Contractor Not yet selected. o Mechanical contractor is responsible for setting all equipment other than LNG tank; installation of piping and supports in accordance with designs by Owner s Engineer from first flange at tank to tie-in to existing distribution header; coordination of shutdowns for tie-ins; testing and commissioning of all piping and equipment. Mechanical contractor shall provide personnel to assist Owner in functional checkout and commissioning of all equipment. Electrical Contractor Not yet selected. o Electrical contractor is responsible for providing and installing all temporary and permanent electrical service to the site in accordance with designs provided by Owner s Engineer. Electrical contractor will provide conduit, supports, wiring and terminations to all equipment and devices requiring electrical or signal power or communications. Electrical contractor shall provide personnel to assist Owner in functional checkout and commissioning of all components. Other Owner shall contract for other miscellaneous services including IT interconnecting and support; fencing, site security, security cameras and other services. SCHEDULE The schedule for project development is based on the following milestones Milestones June 15, 2017 September 15, 2017 October 30, 2017 November 10, 2017 November 15, 2017 December 01, 2017 December 03, 2017 Begin Preparing Updated RFP Issue RFP for Tank Design & Erection Tank proposals received Final Investment Decision Tank contract awarded Final Foundation Design issued Order piling and commence fabrication

March 20, 2018 June 12, 2018 June 19, 2018 May 20, 2019 June 26, 2019 September 1, 2019 Begin piling installation Foundation complete and ready for tank erection Commence tank erection Tank ready for commissioning Begin Cool down Cut over to new tank send out begins Budget The total project budget is $42 MM. The AIDEA Board of directors has authorized the expenditure of up to $1.5 MM on preliminary Engineering and FEED work necessary to finalize the project budget prior to Final Investment Decision.