Formally accounting for variability in look-ahead planning

Similar documents
Production Management Experiences and Research at CIFE

Combating Uncertainty in the Workflow of Systems Engineering Projects

PLANNED WORK READY : A PROACTIVE METRIC FOR PROJECT CONTROL

INTEGRATING PRODUCTION AND QUALITY CONTROL: MONITORING MAKING-DO AND UNFINISHED WORK

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E.

WIP DESIGN IN A CONSTRUCTION PROJECT USING TAKT TIME PLANNING

THE COMBINATION OF LAST PLANNER SYSTEM AND LOCATION-BASED MANAGEMENT SYSTEM

A FRAMEWORK FOR INTEGRATING TAKT PLANNING, LAST PLANNER SYSTEM AND LABOR TRACKING

Lean Project Delivery Operating System

APPLYING LAST PLANNER IN THE NIGERIAN CONSTRUCTION INDUSTRY

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract

CASE STUDY: LEAN SUPPLY CHAIN MANAGEMENT IN CONSTRUCTION PROJECTS

NORTHERN CALIFORNIA CONSTRUCTION INSTITUTE MONTEREY, CA APRIL 22-24, "The Last Planner" by Glenn Ballard

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering

A New Assignment Sizing Criterion LCI White Paper-2 November 3, 1998

IMPROVING CONSTRUCTION WORK FLOW THE CONNECTIVE ROLE OF LOOKAHEAD PLANNING

Step 1 Preliminary Design and Engineering

A PROCESS MODEL FOR CONSTRUCTION SYNCHRONISATION USING TIME-SPACE PLANNING METHODS AND FIELD FORCE AUTOMATION

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams


CORNERCUBE. Lean Construction and Lean Project Delivery: Implications for Cost and Schedule CORNERCUBE. Optimizing Project Outcomes

Building Technology III New York City College of Technology. Course Day 13 Revit Day 05 (Project Day 2)

Research Facility Core and Shell 2012

OPTIMIZING JOINT OPERATION OF TWO TOWER CRANES THROUGH LOOK-AHEAD PLANNING AND PROCESS SIMULATION

Introduction to the Last Planner System

Effective Management of the Last Planner System Using vplanner

1999 by Greg Howell and Glenn Ballard. All Rights Reserved.

Three Opportunities Glenn Ballard Lean Construction Institute University of California, Berkeley

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

APPLICATION OF PRODUCTION MANAGEMENT IN INDUSTRIAL EPC AND MINING PROJECTS IN PERU

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

A SUBCONTRACTOR S LEAN JOURNEY: A CASE STUDY ON ILYANG

CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report

4D Modeling: Past, Present, and Future

CHAPTER 2 CUSTOMER-DRIVEN QUALITY AND SCHEDULING. Dr. Abdul Aziz A. Bubshait. CEM 515 Construction Quality Assurance

5D Virtual Construction

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management.

STABILIZING CRAFT LABOR WORKFLOW WITH INSTANTANEOUS PROGRESS REPORTING

Management Thinking in the Earned Value Method System and the Last Planner System

ASSIGNMENT BUFFER CONTROL FOR CONSTRUCTION PROJECTS

Trends & Developments. Trends & Developments

Operational Modeling: Informed solutions for complex problems

EXHIBIT 2-2-C SCHEDULES

Estimating and Scheduling

Turner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project.

INTEGRATING PRODUCTION AND QUALITY CONTROL WITH THE SUPPORT OF INFORMATION TECHNOLOGY

CHAPTER-8 DEVELOPMENT OF SPARCS

Heuristic Repetitive Activity Scheduling Process for Networking Techniques

A BIM-BASED FRAMEWORK FOR MATERIAL LOGISTICS PLANNING

Breakout Session: CPM Scheduling

6 BIM FAILURES. The design is complete, contracts are written, the project team is assembled and ready to build. Optimism is at its peak!

PLANNING. Ahmed Elyamany, PhD

LONG INTERNATIONAL. Long International, Inc Skytrail Drive Littleton, Colorado USA Telephone: (303) Fax: (303)

A Framework for Schedule Design Planning for Schedule Development

Model-Based Supply Chain Management and

DESIGN PROCESS PLANNING AND CONTROL: LAST PLANNER SYSTEM ADAPTATION

CONSTRAINT MODELING AND BUFFER MANAGEMENT WITH INTEGRATED PRODUCTION SCHEDULER

Drum-Buffer-Rope in PlanetTogether Galaxy

Introduction to Lean CAPTURE AND LEVERAGE THE LEAN ADVANTAGE. Introduction to Lean. Learning Objectives

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

MGT Operations Management Fall 2005 Sample Exam. Name (print clearly):

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

MAXIMIZING VALUE & MINIMIZING WASTE: VALUE ENGINEERING & LEAN CONSTRUCTION

THE KEY PERFORMANCE INDICATORS OF CONSTRUCTION

Applying Object-oriented Analysis and Design to Digital Construction Logistics Planning from a Material Flow Perspective

USING 4D MODELS FOR TRACKING PROJECT PROGRESS AND VISUALIZING THE OWNER S CONSTRAINTS IN FAST-TRACK RETAIL RENOVATION PROJECTS

Project Management. Risk Management

STUDY ON CONSTRUCTION LABOUR PRODUCTIVITY USING LEAN PRINCIPLES

The Top Thrill Dragster

Summary for CIFE Seed Proposals for Academic Year Robust Design of Natural Ventilation Systems

Fleet Elementary School

Principles of Schedule Contingency Management

PRODUCTION MANAGEMENT IN CONSTRUCTION REQUIREMENTS AND METHODS

Lean Production Management In Design

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

GUIDE TO THE CHANGES IN PMP simpl learn i

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

Shielding Production: An Essential Step in Production Control Glenn Ballard & Gregory Howell

Trisasi Lestari

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions

Small House Extension Project

VII. RELOCATION OF UNDERGROUND STORM RETAINAGE SYSTEM (UGS)

Primavera P6 Exercise Worksheet

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

X-55A Advanced Composite Cargo Aircraft

Performance Verification Packet. Supervisor

4D Modeling: Applications and Benefits

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2017

Library In Metropolitan Washington, D.C.

Scheduling Challenges in the Industrial Construction Sector

AVOIDING 2015 MINNESOTA ENERGY CODE VIOLATIONS

Mastering Microsoft Project 2010

The Superintendent is appointed by the Area Manager and must have the following qualifications:

Risk Management As A Quality Enabler

LEVEE DEFICIENCY CORRECTION PROCEDURES

Transcription:

Formally accounting for variability in look-ahead planning PI: Martin Fischer RA: Nelly Garcia-Lopez 1

Field managers need to coordinate the different elements that make up the construction workflow Equipment Labor Workspace Materials Carry out activities 2

In a nutshell Problem: Field managers lack a method to predict impact of workflow variability on downstream activities. Solution: A method that leverages a model of construction workflow to analyze in-project activity variability and predict its impact. Approach: Develop method and model based on literature and input from field managers, validate by testing on a construction project. 3

Field managers lack methods to anticipate impact of variability Install slab rebar Install inserts Pour slab Install col. rebar Form edge of slab Date line Build slab form. 4

Field managers lack methods to anticipate impact of variability Variability factor: Manpower availability Install slab rebar Δt Variability factor: Overcrowded workspace Install inserts Δt Pour slab Install col. rebar Form edge of slab Build slab form. Date line 5

Field managers lack methods to anticipate impact of variability Variability factor: Manpower availability Install slab rebar Δt Variability factor: Overcrowded workspace? 1. What is the impact on downstream activities? Install inserts Δt Pour slab Install col. rebar Form edge of slab Build slab form. Date line 6

Field managers lack methods to anticipate impact of variability Variability factor: Manpower availability Install slab rebar Δt Variability factor: Overcrowded workspace Install inserts Δt? Buffer 1. What is the impact on downstream activities? 2. How can it be managed? Pour slab Install col. rebar Form edge of slab Date line Build slab form. 7

Update from 2014 Seed Project Case studies: 2 building projects Planning meetings 2 month period Findings: Field managers lack formal methods for managing variability and estimating its impact. They rely on their intuition and past experience managing variability. Analysis of activity variability data Building project Last Planner 30,000 activity entries Manual data cleanup (240 hrs) Activity type, sub type, Uniformat Findings: Median: 0 Mean: 2.26 days Long right tail Mgt activities > variability MEP activities < variability 8

Motivating problem: Curtain wall installation Field managers considered that the curtain wall procurement and installation activities were critical. Reasons: - Critical path activity - Opens up work (e.g., finishes) - Disrupts ongoing work (6ft staging area around the perimeter) Source: Genzyme Corp http://www.sotawall.com/portfolio/united%20states/genzymecorporation-8568/ 9

Field managers were concerned about installation outpacing fabrication Fabrication Total units Installation Key: Actual vs Planned 10

Number of units Accounting for variability in planning Line of balance view of fabrication vs. installation 800 700 Planned production rate: 12 units/day 600 500 400 300 200 100 0 120 0 10 20 30 40 50 60 70 80 Working days Planned fabrication Planned installation 11

Number of units Accounting for variability in planning Actual fabrication rate was 20% slower than planned 800 700 600 500 400 300 200 100 0 Planned production rate: 12 units/day Actual production rate: 9.6 units/day 120 96 Day 51 Buffer was insufficiently sized to absorb the upstream variability 0 10 20 30 40 50 60 70 80 Working days Planned fabrication Planned installation Actual fabrication 12

Variability forces field managers to make decisions during look-ahead planning Fabricate curtain wall Frame interior walls L1 Install curtain wall East Elevation Rock interior walls L1 Frame interior walls L2 Install curtain wall North Elevation Tape & Mud interior walls L1 Rock interior walls L2 Install curtain wall West Elevation Tape & Mud interior walls L2 Install curtain wall South Elevation 1. Should the installation activity enter the weekly work plan? 2. Will the installation activity be starved? 3. What is the impact on downstream activities? 4. Etc. Frame interior walls L3 Rock interior walls L3 Tape & Mud interior walls L3 Frame perimeter tie-ins L1 Rock perimeter tie-ins L1 Tape & mud perimeter tie-ins L1 Candidate activities for weekly work plan Frame perimeter tie-ins L2 Rock perimeter tie-ins L2 Tape & mud perimeter tie-ins L2 Date line Downstream activities Frame perimeter tie-ins L3 Rock perimeter tie-ins L3 Tape & mud perimeter tie-ins L3 13

Field managers need to manage variability but lack a formal method to do so Aware of impact of variability Constraint checking during look-ahead planning Intuitive management of variability No formal methods to analyze variability and estimate impact Create inventory buffer to shield installation from variability in fabrication Will fabrication over/undersupply the site? What is the impact on downstream activities? 14

Theoretical points of departure 1. Workflow model of field construction 2. Mechanisms that cause workflow variability i. Variability factors ii. Variability in release of upstream flows 3. Conceptual model and theoretical gaps 15

Theoretical points of departure 1. Workflow model of field construction 2. Mechanisms that cause workflow variability i. Variability factors ii. Variability in release of upstream flows 3. Conceptual model and theoretical gaps 16

Workflow model Workflow: movement of information, materials, and resources through workspaces performing a sequence of activities on components (LCI 2015, Birrell 1980, Darwiche 1988) Flow view of production: 17

Theoretical points of departure 1. Workflow model of field construction 2. Mechanisms that cause workflow variability i. Occurrence of variability factors ii. Variability in release of upstream flows 3. Conceptual model and theoretical gaps 18

Mechanisms that cause workflow variability Occurrence of variability factors Large body of knowledge (delay analysis, risk management, lean construction, +40 papers reviewed) Most recent compilation Wambeke et al. (2011) 50 factors classified into: Labor Tools and Equipment Jobsite Materials and components Information and design External conditions Prerequisite work Management Matches 7 flows identified by Koskela (1999) 19

Mechanisms that cause workflow variability Variability in release of upstream flows 20

Theoretical points of departure 1. Workflow model of field construction 2. Mechanisms that cause workflow variability i. Occurrence of variability factors ii. Variability in release of upstream flows 3. Conceptual model and theoretical gaps 21

Conceptual model and theoretical gaps Gaps identified: (1) What variability factors affect which flows (2) How does flow variability lead to activity variability? (3) How to measure the components of the model? 22

Intuition for Activity Variability Method Look-ahead schedule (Ballard 1997) Weekly activity tracking Activity PS PF AS AF Reason Activity Variability Method Construction workflow model Variability predictions: - Flows - Activities (Ballard & Howell 1997) 23

Research methods and tasks Research questions: 1. What variability factors affect which flows? 2. How does variability in the flows cause variability in the activity? 3. How can and should field managers measure the variability factors, flows, and activity execution? 4. How can a computational model allow field managers to predict how variability is propagated to downstream activities? Theory + Case studies + Interviews Theory + Input from field managers + Field 5. How can field managers use the model to manage variability and its impact during lookahead planning? validation 24

Build basic model Carry out interviews Extend model Develop the Activity Variability Method (AVM Validation: field experiment Research methods and tasks Method: Theory, case study observations Result: Model representing activities and flows Test: Model verification by field managers Method: Structured interviews Result: Relationship between variability factors and variability in the flows, data availability Result: Model representing activities, flows, variability mechanisms Test: Verify using test cases from interviews Method: Theory, input from field managers Inputs: Model, look-ahead schedule, activity variability data collected (commitment tracking) Output: Variability predictions (flows, activities) Test: Verify using project variability data Method: 4-6 week implantation of method Result: Record planning interactions, carry out interview after experiment 25

Contributions: Expected findings A formal representation of construction workflow to predict the impact of workflow variability. The Activity Variability Method (AVM) which helps field managers anticipate the impact of variability during look-ahead planning. Impact: Field managers can implement targeted measures to manage variability, leading to better schedule conformance and project performance. 26

Project data Industry involvement Activity tracking data of projects using Last Planner containing planned vs. actual start and finish, reasons for non-completion Interviews with field managers Structured interviews with superintendents, project engineers, and foremen Feedback and test developed methods Field managers willing to evaluate the model representation and the method Field study of Activity Variability Method Test the AVM implementation for a period of 4-6 weeks 27

CIFE Seed 2014 Research milestones and risks 9/ 14 9/ 16 Case 11/ 15 Conceptual 4/ 15 12/ 15 Develop and Interviews studies workflow Test AVM Project data analysis 3/ 15 Workflow prototype 9/ 15 CIFE Seed 2015 Extend model 2/ 16 Risks and mitigation: Difficulty getting project data: Relationship with CIFE members Difficulty validating model using project data: Verify model with input from field managers, conduct field experiment 28

Contact: PI: Dr. Martin Fischer (fischer@stanford.edu) RA: Nelly Garcia-Lopez (ngarcial@stanford.edu) Thank you! Questions? Suggestions? 29