Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Similar documents
// How Traditional Risk Reporting Has Let Us Down

// Achieving the Unachievable

// Improving Project Plans using a Schedule Maturity Framework

Understanding and Managing Uncertainty in Schedules

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Risk Practice. Darryl Townsend, PMP February 1, 2016

Schedule metric analysis: a formalized approach to more realistic planning...

an introduction to Fuse 360

How Pre-Planning Drives Project Success

THE TRUE VALUE OF PROJECT RISK ANALYSIS

Project Time Management

Project Controls for Optimal Execution

Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc.

SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS

2.0 SCHEDULE DEVELOPMENT

TRANSITIONING FROM SCHEDULING TO TRUE PLANNING

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM

Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results

Time Management PLANNING

PMP Exam Preparation Course Project Time Management

How AI is Changing the Art & Science of CPM Scheduling

Risk Driver Method Applied to Integrated Cost Schedule Risk Analysis Hulett & Associates, LLC David T. Hulett, Ph.D.

The Past and Future of CPM Project Scheduling. Dr. Dan Patterson PMP Pertmaster, Acumen, PMFocus Founder

Project Risk Management

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

RiskyProject Lite 7. Getting Started Guide. Intaver Institute Inc. Project Risk Management Software.

THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION

RiskyProject Professional 7

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

RISK Realistic and Practical Project Risk Quantification (without CPM)

Scheduling. Adapted from John Musser

Dynamic Simulation and Supply Chain Management

Probabilistic well cost and time modelling. See the unforeseen

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Simulation Analytics

Project Management. Opportunity or Oxymoron? Stacy Munechika, PMP, PMI-ACP. PMI Rochester Chapter Professional Development Day May 2017

Tips for Eliminating Unexpected Risk from Incentive Compensation Plans

R&D Performance Management

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

A Parametric Approach to Project Cost Risk Analysis

Proven Project Risk Management Techniques for Increased Project and Organizational Success

Risk Management User Guide

Scheduling 2 Day Structure

Project Risk Analysis (with Pertmaster)

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

Continuous Improvement Toolkit. Risk Analysis. Continuous Improvement Toolkit.

ECI: Two-Stage Contracts

Benefits of Integrating Schedule

THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION

// Does Better Scheduling Drive Execution Success?

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Program Evaluation and Review Technique (PERT)

Principles of Schedule Contingency Management

Project Forecast Survey Results Good Scheduling Practices June 2016

Expert Reference Series of White Papers. Managing Risk An Integrated Approach

Integral Risk Management for DBFM Tenders and Contracts in the Netherlands

Identification Selection Definition Execution. Schedule.

Schedule Compression

RiskyProject Lite 7. User s Guide. Intaver Institute Inc. Project Risk Management Software.

Chapter 3 Managing Systems Projects

Planning & Scheduling

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Dr. Richard Jerz rjerz.com

Lecture 2: Project Management, Part 1: Requirements, WBS, Scheduling, and Risk Management. Prof. Shervin Shirmohammadi SITE, University of Ottawa

Utilizing Optimization Techniques to Enhance Cost and Schedule Risk Analysis

Anticipate. Plan. Act. Adapt. Surviving and Thriving through Strategic Planning

2016 National Tribal Transportation Conference

Thus, there are two points to keep in mind when analyzing risk:

Project Controls. The art of predicting project completion. A good baseline schedule is not enough. Patrick Weaver PGCS 2016.

Corality Academy Financial Modelling for Renewable Energy Projects. 3 day duration

Integration Knowledge Area

Hector Guerrero. Excel Data Analysis. Modeling and Simulation. < J Springer

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,

Initiation Group Process. Planning Group Process

Down by the Levee. Zero Degree Constructors v. Louisiana Amazing Levee Authority

Uncertainty in transport models. IDA workshop 7th May 2014

Margin Erosion: Process Improvements to Help Close the Gap and Deliver a Profitable Project

Strategy, risk and objectives

LONG INTERNATIONAL. Robin K. Long, PMP

S O Seminar Objective

Best Practices In Integrated Resource Planning

A simulation-based risk analysis technique to determine critical assets in a logistics plan

LMS Selection in High Consequence Industries

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix

AACE Certified Cost Professional (CCP) Certification Preparation Training Course Brochure and Competency Matrix

Talent on Demand - The Future of Workforce Flexibility and Talent Acquisition in an Uncertain World

TDWI Analytics Principles and Practices

Key findings and insights of top operations management professionals

Project risk management

Sagar Khadka, MBP, Fairfax, VA Tom Hyland, Ohio DOT, Garfield Heights, OH. Tuesday, October 27, :00 AM 11:30 AM

Selection and Deployment of a Standard COTS Monte Carlo Software Tool November 18, 2009

Simulation as Support for PBL Contract Design

Estimating Project Schedule-Time and Cost

Risk and Opportunity Management - Experiences and Lessons Learned a personal insight

AASHTO Guide for Enterprise Risk Management: An Overview. Tim Henkel, Assistant Commissioner, Mn DOT NCHRP Project 08-93

Building a Vendor Risk Management practice that delivers real value

Risk Management Policy

PMP TRAINING COURSE CONTENT

// An Alternate Approach to Integrating Cost and Schedule

Transcription:

Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting for unknowns... 3. Alternate scenarios: risk adjusted schedules 4. Interpreting results: exposure & drivers 5. Risk Reduction: reducing risk exposure Worked examples Q&A 2 Introduction to Project Risk Analysis Scheduling Science behind forecasting project completion Doesn t account for scope uncertainty, unknowns Project Risk Registers Becoming more prevalent Still isolated from true risk analysis Risk Analysis Gain true insight into schedule achievability Pinpoints risk hotspots that will cause delay Structured approach to reducing risk exposure 3 1

Why Bother with Risk Analysis? High Risk Non-Critical Path poses greatest risk to project completion Critical Path doesn t impact project completion Project Completion Reveals hidden critical paths Brings realism to your forecast Managed contingency Generates team buy-in to the schedule Helps with the likes of IPA certification Low Risk 4 How Does Risk Analysis Work? Based on CPM (scheduling!) Accounts for variability in the forecast Schedule uncertainty Risk events Cost-impact of time Monte Carlo simulation Essentially a brute force approach Highly prone to schedule logic & inputs 5 Importance of a Sound Schedule A schedule is a forecast used as a benchmark against which to measure performance. Means of defining & capturing scope Means of communicating the plan to stakeholders S1 S2 S3 S4 Schedule Basis Reflects latest scope/contractor updates Critiqued Schedule Structurally sound, no contingency, sound logic Risk-Adjusted Schedule Estimate uncertainty, risk events Optimized Target Scenarios Reduced hot spots, higher confidence S5 Team Validated Scenario Buy-in on mitigation plans 6 7/15/16 2

Sound Schedule 7 Building a Risk Model Alternate Approaches Pros Risk Load Critical Path Focuses the team in a workshop Based on actual schedule Cons Assumes known critical path Risk events make this approach flawed Dangerous approach to risk modeling Doesn t give true picture of risk Pros Create a Summary Schedule Excellent means by which to facilitate a workshop Easy to risk load/build risk model Cons Lose the logic integrity/calendars/ detail of a schedule Separate model to maintain to that of schedule 8 A More Effective Approach Top-Down Categorization Graphical Approach Retains true integrity of the project schedule Ensures whole schedule is categorized Very fast approach Removes complexity Eliminates crazy rankings 9 3

Step 1: Capturing Uncertainty Background Uncertainty Factor Uncertainty variability regarding durations/costs Is the duration realistic? Scope definition Complexity of work Past performance Just plain wrong! Not dates! Dates are the results of durations & logic Old school approach Min, most likely, max & distribution type 10 Step 2: Capturing Risk Events Risk Events Project Risk Register Discrete event 2 key attributes Probability Impact(s) Threats & opportunities Multiple states Current Mitigated 11 Risk Register Calibration One Size Doesn't t Fit All Risk Register Calibration # of categories 5X5 is standard Define probability scale Don t adopt HSE scale Calibrate impacts Relative or absolute? Determine thresholds Risk score is irrelevant 12 4

Mapping Risk Events Risk Register Risk Description Probability Impact ID 0001 Hurricane 25% 10 days Schedule Transportation 5 d H: 10 d 0002 Labor Strike 50% 50% Construction 30 days LS: 15 d Commissioning 20 days LS: 10 d H: 10 d 13 Step 3: Risk Adjusted Schedules Running the Simulation: Accounts for all reasonable combinations of risk & uncertainty Is true to the logic of the CPM schedule Critical path may jump Run enough iterations until results don t significantly vary 14 Step 4: Risk Exposure P-Dates I m 50% confident I will finish on Contingency How much more/less time do I need to finish by? Confidence Level What chance do I have of hitting my finish date? Risk Range Factor Much better means of determining risk exposure Contingency P- Dates Confidence 15 5

Step 4: Risk Drivers Risk Drivers High-risk activities Most impactful events Traditional Reporting % based. Total Contribution Risk Contribution Factor True measure of impact in duration & cost! Differentiates between uncertainty & risks Uncertainty/Logic/ Risk Event Contribution 16 Step 5: Risk Reduction Compare scenarios in a single workbook: Turn on or off risks Benefit of mitigation Uncertainty vs. Risk Events Schedule A vs. Schedule B Impact of schedule delay on cost risk Benefit of Mitigation 17 Schedule Impact on Cost Risk Cost Risk Distribution Schedule Risk Distribution P100 360d (120%) Deterministic: 300d $90K $100K $130K P0 280d (93%) Uncertainty Schedule Impact on Cost Risk Distribution $84K $90K $100K $130K $156K Uncertainty 6

Developing Cost Risk Models 19 More Information Product Information: deltek.com/products/ppm thomaspolen@deltek.com 20 7/15/16 CONFIDENTIAL Deltek, Inc. All Rights Reserved 7