IST 302 : Project Time Management

Similar documents
Project Time Management

Project Time Management

Cambridge International AS & A Level Computer Science

PMP Exam Preparation Course Project Time Management

6 PROJECT TIME MANAGEMENT

Time has the least. amount of flexibility; Schedule issues are the main reason for

Constructing Networks

Estimating Project Schedule-Time and Cost

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

Information Technology Project Management, Seventh Edition

Project Management in Practice Fifth Edition

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

Planning & Scheduling

Week 5 Project Work Plan

Time Management PLANNING

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Chapter 3 Managing the Information Systems Project

Scheduling. Adapted from John Musser

Project Time Management

PROJECT TIME MANAGEMENT

Global Project Management, LLC

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

Modern Systems Analysis and Design Seventh Edition

Artificial Intelligence

Week 5 Project Work Plan

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Dr. Richard Jerz rjerz.com

Project Scope Management

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

Developing a Project Plan

Work Analysis and Design

Week 5 Project Work Plan

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Week 5 Project Work Plan

The recommended guided learning hours for this unit are 30 hours.

Project Planning and Estimating DJ

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

THE PMP EXAM PREP COURSE

Information Technology Audit & Cyber Security

Software Project Management

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

Scheduling Resources and Costs

Calculating and Using Float

Operations Management

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

Lecture- 11. Project Scheduling. Dronacharya College of Engineering

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Embarking new Project

Calculating and Using Float

Software Process and Management

Topic # 12. CIS Project Management: an overview

Project Scheduling: Lagging, Crashing and Activity Networks

Introduction to Project Management

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

Examinations for Semester I / 2014 Semester II

Principles of Planning for IT Projects

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Project Management Framework

EFFICIENCY OF CRITICAL PATH METHOD (CPM) AND PERT TECHNIQUE FOR YACHT CONSTRUCTION

Chapter 3 Managing Systems Projects

PROJECT TIME PLANNING. Process and Bar Chart Technique

Program Evaluation and Review Technique (PERT)

CE2353-CONSTRUCTION PLANNING & SCHEDULING

Cost Classifications. Tools and Analysis. Cost Classifications. Cost Classifications

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

CHAPTER 1. Basic Concepts on Planning and Scheduling

03/23/2016. Presented for Boston College Employee Development Office March 23, 2016 by Denise M. Guérin, JD, MS-PPM, PMP. Q&A from Session #1

Project Planning Tools

Project Management Concepts, Tools & Techniques

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim

nam I BIA Un IVERS ltv OF SCIEnCE AnD TECHnOLOGY

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Geog 469 GIS Workshop. Project Management

The Project Planning Process Group

technology management & innovation introduction to project management (ii) project planning methods & tools

Views and Layouts for Program Management

Successful Project Management

PROJECT SCHEDULING & CONTROL

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

VCE4Dumps. Latest vce dumps, valid certification dumps

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

International Association of Certified Practicing Engineers

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

ENGINEERING MANAGEMENT (GE

Sample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda

MICROSOFT PROJECT 2007 Level 1

Resource-constrained project scheduling using Relationship Diagramming Method (RDM)

Project Management Glossary of Terms

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms

A Framework for Project Management. The Project Management Institute Education Department

Project Management Techniques

Chapter-7# Project Controlling and Scheduling

PLANNING & SCHEDULING

Transcription:

IST 302 : Project Time Management Developing quality schedules is important. 1

Schedule issues are the main reason for conflicts on projects There are five core project time management process groups. Activity Definition Define specific activities to be performed to produce project artifacts Activity Sequencing Identify and document relationships between project activities Activity Duration Estimating Estimating number of work periods to complete each activity Activity Resource Estimating Estimating how many resources a team should use to perform each activity Schedule Development Using activity sequences, duration estimates and resource requirements to create project schedule Schedule Control Controlling and managing changes to the project schedule 2

Activity Definition Begins with : Results in : Activity sequencing requires identifying the dependencies between activities. Mandatory Dependencies Inherent in the nature of the work (hard logic) Discretionary Dependencies Defined by project team (soft logic) External Dependencies Relationships between project and nonproject activities 3

Dependency Examples Mandatory Dependencies Discretionary Dependencies External Dependencies Inherent in the nature of the work (hard logic) Defined by project team; process related (soft logic) Relationships between project and nonproject activities Example Example Example The duration of a project is not the same as the effort required to complete the project. Duration: The time span from the moment you start work on a project or activity to the moment the activity is complete. Effort: The number of work periods required to complete the project or activity. 4

Try this! It took four people 15 (business) days to complete Activity X Person 1 : 60 hours Person 2 : 15 hours Person 3 : 72 hours Person 4 : 31 hours Identify Duration Effort Hmmm. Can duration be greater than effort? 5

The goal is to a realistic schedule. There are several tools and techniques that can aid in schedule creation. Activity resource estimating depends on the nature of the project and the organization. Questions to consider: How difficult will it be to do specific tasks on the project? Is there anything unique in this project s scope statement that will affect resources? What is the organization s history in doing similar tasks? Does the organization have or can they acquire the people, equipment, and materials that are capable and available for performing the work? 6

Controlling the schedule is fundamental to enabling project success. We now start looking at the tools and techniques that aid in schedule management. 7

A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities. Two Common Approaches Arrow Diagramming Method (ADM) Precedence Diagramming Method (PDM) Arrow Diagramming Method 1 A=1 B=2 2 3 D=4 E=5 5 H=6 6 J=3 8 C=3 4 G=6 7 I=2 Activities are arrows. Labels are <task name> = <duration> Nodes are start/ending points. 8

Sample PDM Network Diagram for Project X A Start: 6/1/05 ID: 1 Finish: 6/1/05 Dur: 1d B Start: 6/1/05 ID: 2 Finish: 6/2/05 Dur: 2d C Start: 6/1/05 ID: 3 Finish: 6/3/05 Dur: 3d D Start: 6/2/05 ID: 4 Finish: 6/7/05 Dur: 4d E Start: 6/3/05 ID: 5 Finish: 6/9/05 Dur: 5d F Start: 6/3/05 ID: 6 Finish: 6/8/05 Dur: 4d G Start: 6/6/05 ID: 7 Finish: 6/13/05 Dur: 6d H Start: 6/10/05 ID: 8 Finish: 6/17/05 Dur: 6d J Start: 6/20/05 ID: 10 Finish: 6/22/05 Dur: 3d I Start: 6/14/05 ID: 9 Finish: 6/15/05 Dur: 2d Activities are boxes. Arrows are dependencies. Create an ADM and PDM. Activity Predecessors Duration A 2 B A 2 C A 3 D A 4 E B 2 F C 3 G D 6 H E, F 2 I E, F 5 J G, I 1 K H, J 2 9

Chap. 6, Exer. 2 ADM A=2 1 2 B=2 C=3 3 4 E=2 F=3 6 I=5 H=2 K=2 8 9 D=4 5 7 G=6 J=1 Chap. 6, Exer. 2 PDM A B E H 2 2 2 2 C F I K 3 3 5 2 D 4 G 6 J 1 10

Gantt Charts map activities to a calendar. 11

Figure 6 3. Task Dependency Types Gantt Charts can also so task completion. 12

Critical Path Analysis is used to predict the total project duration. Critical path: Determining the Critical Path C=2 4 E=1 A=2 B=5 1 2 3 6 D=7 5 F=2 a. How many paths are on this network diagram? b. How long is each path? c. Which is the critical path? d. What is the shortest amount of time needed to complete this project? 13

What s the critical path? A=2 1 2 B=2 C=3 3 4 E=2 F=3 6 I=5 H=2 K=2 8 9 D=4 5 7 G=6 J=1 The start/finish times of tasks not on a critical path may be changeable. Free slack : Total Slack : 14

Determine the free slack and the total slack. Planning a schedule requires knowing schedule constraints. Forward Pass : Determines the earliest start and finish for each activity Backward Pass : Determines the latest start and finish for each activity. 15

Complete the diagram. ES EF A = 3 <task> = <duration> Start C = 5 LS LF B = 2 ES : Early Start EF : Early Finish LS : Late Start LS : Late Finish Changing activity or project duration requires additional resources. Original 16

Caution: Multitasking is not always optimal. Multitasking requires ramp up time. Some companies moving away from 5/40 work week. We ve beat this to death. 17

Duration Estimates : Fact or WAG? PERT : Program Evaluation and Review Technique 18