SERVICE BOREHOLES MANAGEMENT PLAN

Similar documents
Gas Drainage Management Plan

Environmental Management Strategy

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Bulli Seam Operation. Waste Management Plan. Bulli Seam Operations

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT

Works, services and infrastructure code

Newstan Colliery S75W Modification Project Briefing Paper

12. STATUTORY REQUIREMENTS

TABLE OF CONTENTS. Atlas-Campaspe Mineral Sands Project Environmental Impact Statement

Construction Environment Management Plan

ENVIRONMENTAL MANAGEMENT STRATEGY DENDROBIUM MINE ENVIRONMENTAL MANAGEMENT STRATEGY

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 21 ENVIRONMENTAL MANAGEMENT AND MITIGATION

Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning & Assessment Act 1979

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

Dendrobium Mine. Waste Management Plan

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

Hunter Valley Operations South

Borrow Pit and Quarry Management Procedure Environmental

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Management Plan: Hazardous Materials Removal & Demolition

Environmental Risk Analysis

WAMBO COAL PTY LTD ENVIRONMENTAL ASSESSMENT. ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies

Water Pollution Control for Work in Sensitive Areas

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

Development Approval 211/93 (as modified) Schedule Condition Commitment Audit Finding

Manningham Works Code of Practice

Council Roadside Reserves Project. Site Management Checklists and Safeguards

Section 75J of the Environmental Planning and Assessment Act 1979

Bulli Seam Operation Noise Management Plan

APPENDIX 2 DUST AND NOISE MONITORING AND MANAGEMENT PROGRAMMES

NOISE Management Plan

STATE SIGNIFICANT DEVELOPMENT ASSESSMENT Metz Solar Farm (SSD 7931)

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

Gunlake Quarry. Noise and Blast Management Plan

CCSD#1 Stormwater Standards

Murra Warra Wind Farm Project Environmental Management Plan

Alberta Transportation The City of Edmonton The City of Calgary


Yeelirrie Uranium Project. Environmental Management

Fact Sheet: Anglesea Power Station and Mine Rehabilitation Overview

BSM SD PLN 0126 MANAGEMENT PLAN 1. COMMITMENT AND POLICY 2. BACKGROUND. 1.1 Purpose. 1.2 Scope. 2.1 Development Consent Requirements

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

H28. Special Purpose Quarry Zone

MINING OPERATION SERVICES

Stage 4 Geotechnical Investigations Information Sheet

Environment Protection Licence

Environmental Control Plan

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Section 75J of the Environmental Planning & Assessment Act 1979

ENVIRONMENTAL MANAGEMENT STRATEGY (EMS)

2.0 Description of Existing Mine Operations

Rev Reason for Revision Date Prepared Reviewed Approved. V1 Issue to Minister for Planning 29/11/17 PH/SS PL DS

Act Government Agency Responsible Area of regulation Mining Act 1992 ( Mining Act ) Department of Industry. Division of Resources and Energy,

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

TAURANGA CITY COUNCIL

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review

in brief corrs Policy What it means for developments in april 2012

Out of hours works protocol

Pollution Incident Response Management Plan - Summary. Medway Mine Medway

Environmental Assessment Chapter 8 Surface Water

Format and Guideline for the Preparation of an Annual Environmental Management Report: SMALL MINE VERSION

Site EMP Kit- Guidance Notes

Kurnell Refinery Conversion Project

Section 3 - Consultation and Issue Identification

Managing Country. Aboriginal Communities. Overview. Last updated: March 2013

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

New Administration Building

Building Better Storm Water Quality

For controlled copies of this EMS the copy number is shown below and initialled in Red by the Light Horse Business Centre Project Manager.

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

ROADS: OPERATION AND MAINTENANCE

Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016

UNDERGROUND OPERATION

Appendix X.6 Queensland Government CSG Water Management Policy

BENGALLA Mining Company. Contamination Assessment

Annex F Scoping Checklist

JW/docDM AEE for Non-Minimum Impact Activities

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Kurnell Refinery Conversion Project

Inrushes and Subsidence

Re: Erosion Control Report and Drawings Requirements Accompanying Document

ARTICLE 6 EXCAVATION OF MINERAL MATERIALS

Bill Richardson Governor. Highlights of the Pit Rule NMAC

TABLE OF CONTENTS LIST OF FIGURES. Mt Arthur Coal Open Cut Modification Environmental Assessment

Environmental Guidelines for Construction Sites

LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN

For controlled copies of this EMS the copy number is shown below and initialled in Red by Dial A Dump Industries Project Manager.

Verification of controlled wood supply according to FSC-STD (V2-1) EN Annex 3 and FSC-STD Item 5.

APPENDIX 2 DUST AND NOISE MONITORING AND MANAGEMENT PROGRAMMES

Relevant legislation (Administering Authority Commonwealth legislation

Environmental Management Plan

Section 75J of the Environmental Planning & Assessment Act 1979

NOISE MANAGEMENT PLAN

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Transcription:

Add CSG specific graphic to suit project SERVICE BOREHOLES MANAGEMENT PLAN BULLI SEAM OPERATIONS PROJECT APPLICATION NO. 08_0150 October 2012 Revision No: 0

SERVICE BOREHOLES MANAGEMENT PLAN Table of Contents 1 EXECUTIVE SUMMARY... 0 2 INTRODUCTION... 0 2.1 BACKGROUND... 0 2.2 SCOPE OF PROJECT... 1 2.3 JUSTIFICATION... 3 2.4 AFFECTED PROPERTIES... 3 3 OBJECTIVES... 3 4 RESPONSIBILITIES... 3 5 LEGISLATIVE REQUIREMENTS AND PROPOSED PERFORMANCE STANDARDS... 5 5.1 LEGISLATIVE REQUIREMENTS... 5 5.2 PROJECT APPROVAL CONDITIONS... 5 5.2.1 Bulli Seam Operations Project Approvals... 5 5.3 PROPOSED ENVIRONMENTAL PERFORMANCE STANDARDS... 6 5.3.1 Noise... 6 5.3.2 Air Quality... 8 5.3.3 Soil and Water... 9 5.3.4 Vegetation... 10 5.3.5 Cultural Heritage... 10 5.4 BHP BILLITON AND OTHER POLICIES AND STRATEGIES... 10 6 CONSULTATION... 11 6.1 LANDHOLDER AGREEMENTS... 11 6.2 COMMUNICATION AND CONSULTATION PLAN... 11 6.2.1 Stakeholders... 11 6.2.2 Communication and Consultation... 12 7 ENVIRONMENTAL ASSESSMENT... 13 7.1 OVERVIEW OF GENERAL MANAGEMENT MEASURES... 13 8 REHABILITATION, MONITORING AND REPORTING... 15 8.1 LEGISLATIVE AND OTHER REQUIREMENTS... 15 8.1.0 Legislative Requirements... 15 8.1.1 Guidelines and Standards... 16 8.1.2 Proposed Closure Approach... 16 8.1.3 Post-Construction Rehabilitation... 16 8.1.4 Collection of Materials... 17 8.1.5 Post-Construction Infrastructure & Landscape Rehabilitation Outcomes... 17 8.1.6 Post-Construction General Rehabilitation Outcomes... 19 8.1.7 Final Land Use Objectives... 19 8.1.8 Monitoring & Reporting... 19 8.2 ENVIRONMENTAL MONITORING... 20 8.2.1 Noise... 20 Revision No: 0 October 2012 Page i

SERVICE BOREHOLES MANAGEMENT PLAN 8.2.2 Water... 21 8.2.3 Cultural Heritage... 22 8.3 REPORTING... 23 9 REFERENCES... 24 Tables Table 1: Construction and operation hours of the Project... 6 Table 2: Communications Plan... 12 Table 3: Overview of impacts and management measures 13 Figures Figure 1. Drill Rig... 8 Figure 2. Dust suppression during construction... 9 Figure 3. Construction phase rehabilitation... 17 Figure 4. Topsoil storage.... 18 Figure 5. Noise barriers... 21 Figure 6. Construction stormwater controls... 22 Figure 7. Protection of Aboriginal sites... 23 Revision No: 0 October 2012 Page ii

1 EXECUTIVE SUMMARY The construction and operation of service borehole infrastructure is required to be approved by the Director General of the Department of Planning and Infrastructure in accordance with Condition 4.22 of the Bulli Seam Operations Project Approval (08_1150). This condition requires preparation of a Service Boreholes Management Plan which includes details of community consultation, landholder agreements, assessment of environmental impacts, details of impact avoidance and mitigation, and site rehabilitation. Service boreholes are required to provide essential services or materials to support the safe and efficient operation of underground mining activities. In most instances, the service borehole has surface based ancillary infrastructure co-located with the top of the borehole. Examples of common service boreholes include: Services o Electrical power o Compressed air o Communications Materials o Concrete o Ballast o Fuel o Stone dust o Hydraulic oil o Water This service borehole management plan describes the generic management and performance measures that will be adopted by Illawarra Coal for the construction and operation of service borehole infrastructure. For each service borehole that is proposed, a site specific environmental assessment will be undertaken and any prescriptions for the management of that site will be made. These site specific assessments and actions will be progressively added to this management plan as they are required. New activities will require the approval of the Director General of the Department of Planning and Infrastructure in accordance with Condition 4.22 of the Bulli Seam Operations Project Approval. 2 INTRODUCTION 2.1 BACKGROUND BHP Billiton Illawarra Coal (BHPBIC) proposes to continue its underground mining at Appin and West Cliff mines (referred to as the Bulli Seam Operations or BSO), located in the Southern Coalfield of New South Wales, by extracting coal from the Bulli Seam using longwall mining techniques. Project Approval for the Bulli Seam Operations was granted by the Planning Assessment Commission on 22 December 2011. An Environmental Assessment was completed to Revision No: 0 October 2012 Page 0

support the Bulli Seam Operations Project application and was prepared by Resource Strategies in consultation with a number of specialist sub consultants. The construction and operation of service borehole infrastructure is required to be approved by the Director General of the Department of Planning and Infrastructure in accordance with Condition 4.22 of the Bulli Seam Operations Project Approval. This condition is: The Proponent shall prepare and implement a Service Boreholes Management Plan in respect of construction and use of future service boreholes (ie any service boreholes not subject to approval at the date of this instrument) to the satisfaction of the Director-General. This plan must be submitted to the Director-General for approval prior to the construction of any future service boreholes and must include details of the proponent s commitments regarding: (a) Community consultation; (b) Landholder agreements; (c) Assessment of noise, air quality, traffic, heritage, public safety and other impacts in accordance with approved methods; (d) Avoidance of significant impacts and minimisation of impacts generally; (e) Achievement of applicable standards and goals; (f) Mitigation and compensation for significant noise, air quality and visual impacts; and (g) Rehabilitation of disturbed sites. This Service Boreholes Management Plan addresses the generic requirements of this condition. Site specific environmental assessments and management recommendations will be progressively appended to this management plan as they are required. 2.2 SCOPE OF PROJECT The proposed service boreholes will generally be located above operational longwall domains within the approved Bulli Seam Operations Project Area. In many instances, service boreholes are located above development mains so that they can service ongoing mining operations. Service boreholes are required to provide essential services or materials to support the safe and efficient operation of underground mining activities. In most instances, the service borehole has surface based ancillary infrastructure co-located with the top of the borehole. Examples of common service boreholes include: Services o Electrical power o Compressed air o Communications Materials o Concrete o Ballast o Fuel o Hydraulic oil o Water o Stone dust Revision No: 0 October 2012 Page 1

Service borehole project generally comprised of several stages which are described in Table 1. Table 1 Description of proposed work stages Task Description Stage 1- construction 1. Access to borehole Heavy and light vehicle access to the service borehole location will be required. Where possible, Illawarra Coal will use existing roads and access tracks. Upgrades to poorly formed access tracks may be required. Where no access exists, new access roads or tracks will be constructed. 2. Civil works for borehole The service borehole drill sites will require a levelled area for the safe operation of the drill rig. Cut and fill operations may be required to provide a level drill pad. In some instances, material may be imported to or exported from the site. 3. Borehole Construction The service borehole will be drilled according to the size specification required. It is generally expected that the size of cased borehole will be in the order of 150 500 mm in diameter (fully cased). Service boreholes are often required to hit a specific location in the mine workings. As such, a steered borehole is generally required which uses a specialised, larger drill rig than standard exploration drill rigs. Considerable ancillary equipment such as generators, pumps, air compressors, portable offices and toilets, water tanks and noise walls can also be required during service borehole construction. The type of rig used for service borehole construction often require 24/7 operation to operate efficiently and maintain integrity of the hole. Service boreholes will be lined from the surface to the mine workings and be fully grouted to the surrounding strata to avoid interference with aquifers and groundwater intrusion into the mine. 4.Works for service infrastructure Infrastructure for the provision of the service or material may be required to be constructed. This may include the: Power lines, water pipelines or communications cables; Transformers, pressure management devices, air compressors; housings; Delivery and surface storage facilities for materials; Offices and amenities; Site security (fencing, lighting, CCTV). 5. Demobilisation and construction rehabilitation Once the service borehole and ancillary infrastructure has been constructed, the construction equipment plant will be decommissioned and demobilised. In many instances, the construction footprint is considerable larger than that required for operational purposes. The disturbed area will be temporally rehabilitated (top soiled, grassed or planted with native vegetation) to provide a stable and more visually appealing surround to the operational service borehole facility. The operational footprint will be protected by security fence. Stage 2- operation 6. Deliveries Where the service borehole provides a material such as concrete, ballast, fuel etc to underground operations, these material will generally be delivered to the borehole in bulk quantities and require heavy vehicle transport. In most circumstances, these deliveries will be made during day light hours. Storage facilities will be co-located with the borehole and generally store a small quantity (say one weeks supply) to feed underground as needed. 7. Operation Boreholes that provided services (power, water, compressed air) are generally unattended and are operated remotely from the mine control room. Boreholes that provide materials (concrete, ballast, stone dust, fuel etc) may require an active presence at the site to operate the facility. This may require the operation of surface mobile equipment (e.g, front end loader), pumps or pneumatic equipment. A semi or permanent workforce may be present at the site. Materials service boreholes will generally operate during daytime hours, although night time operations may be required for some operations such as concrete pours. Revision No: 0 October 2012 Page 2

Task Description 8. Maintenance All service boreholes will require regular inspections and periodic maintenance. These activities will generally occur during day time hours. Maintenance activities may require heavy equipment such as cranes, mobile plant or drill rigs. Large maintenance overhauls may be required periodically. In some instances, overhauls are planned to coincide with underground maintenance or shutdowns of relatively short duration. Overhauls may take place on a 24/7 basis. Emergency maintenance or restarts may occur on a 24/7 basis. Stage 3- rehabilitation 9. Demobilisation and rehabilitation At the cessation of the service borehole operation, all equipment will be removed from the site. The borehole will be sealed and filled with grout to ensure that no interference with any aquifers occurs in the future. The borehole head will be removed at about 2m below the surface. The surface infrastructure pad will be reshaped and rehabilitated to a landform required by the land owner or to the pre-existing/surrounding landuse. 2.3 JUSTIFICATION The construction and operation of service boreholes is required to support the safe and efficient extraction of coal from the Bulli Seam Operations. Service boreholes that are located close to the active mining areas minimise underground travel times, congestion and the number of people that have to be supported underground. Similarly, they reduce surface activities and traffic at mine pit top facilities. 2.4 AFFECTED PROPERTIES The proposed service borehole infrastructure will generally take place on properties owned by Illawarra Coal. Where Illawarra Coal does not own the property, an access licence, lease or other arrangement will be made with the landowner to enable the construction and operation of the facility. 3 OBJECTIVES The objective of this Management Plan is to meet the requirements of Condition 4.22 of the Bulli Seam Operations Project Approval. 4 RESPONSIBILITIES It is the responsibility of all employees and contractors to undertake practices to manage and minimise potential environmental impacts according to this Service Borehole Management Plan. The Manager Approvals (Surface) is responsible for coordinating the implementation of this Management Plan and for the periodic review of the Plan during the construction period. The Manager Approvals (Surface) will also be responsible for ensuring the commitments contained within this management plan during the construction period are met. This will include: 1. Overseeing the operation and maintenance of environmental controls during construction of the service borehole; 2. Overseeing the implementation of any environmental monitoring; 3. Production and dissemination of reports and appropriate summaries of information in reports. Revision No: 0 October 2012 Page 3

The Manager Environment is responsible for coordinating the implementation of this Management Plan and for the periodic review of the Plan during the operational period. The Manager Environment will also be responsible for ensuring the commitments contained within this management plan during the operational period are met. This will include: 1. Overseeing the operation and maintenance of environmental controls during operation of the service borehole; 2. Overseeing the implementation of any environmental monitoring; 3. Production and dissemination of reports and appropriate summaries of information in reports. Project Engineers and Mine Surface Co-ordinators are responsible for the maintenance and operation of the service boreholes during the construction and operational phase, respectively. Revision No: 0 October 2012 Page 4

5 LEGISLATIVE REQUIREMENTS AND PROPOSED PERFORMANCE STANDARDS 5.1 LEGISLATIVE REQUIREMENTS Legislation applicable to noise, water, biodiversity, cultural heritage, erosion and sediment control management includes but is not limited to: Protection of the Environment Operations Act 1997 (POEO Act); Environmental Planning and Assessment Act 1979; Soil Conservation Act 1938; Water Management Act 2000; Water Act 1912; National Parks and Wildlife Act 1974. Relevant technical guidelines published by NSW and Federal Government agencies as well as industry codes of practice are also relevant. Many of these guidelines are described in Section 9. 5.2 PROJECT APPROVAL CONDITIONS 5.2.1 Bulli Seam Operations Project Approvals An Environmental Assessment was submitted in October 2009 for the continuation of underground mining operations at the Appin and West Cliff Collieries (herein referred to as the Bulli Seam Operations) in accordance with Part 3A of the Environmental Planning and Assessment Act, 1979 (EP&A Act) and the Environmental Planning and Assessment Regulation, 2000 (EP&A Regulation). The Bulli Seam Operations Part 3A Project Approval was granted by the Planning Assessment Commission on 22 December and is available at www.planning.nsw.gov.au and http://www.bhpbilliton.com/home/aboutus/regulatory/pages/default.aspx. The objective of this Management Plan is to meet the requirements of Condition 4.22 of the Bulli Seam Operations Project Approval. This condition is: The Proponent shall prepare and implement a Service Boreholes Management Plan in respect of construction and use of future service boreholes (ie any service boreholes not subject to approval at the date of this instrument) to the satisfaction of the Director-General. This plan must be submitted to the Director-General for approval prior to the construction of any future service boreholes and must include details of the proponent s commitments regarding: (a) Community consultation; (b) Landholder agreements; (c) Assessment of noise, air quality, traffic, heritage, public safety and other impacts in accordance with approved methods; (d) Avoidance of significant impacts and minimisation of impacts generally; (e) Achievement of applicable standards and goals; (f) Mitigation and compensation for significant noise, air quality and visual impacts; and (g) Rehabilitation of disturbed sites. Revision No: 0 October 2012 Page 5

This document has been prepared specifically to comply with the Bulli Seam Operations Project Approval consent condition above. 5.3 PROPOSED ENVIRONMENTAL PERFORMANCE STANDARDS The following environmental standards are based on the existing consent conditions from the Bulli Seam Operations Project Approval and the criteria determined by relevant impact assessments appended to this document. Environmental Management Plans developed in accordance with the requirements of Schedule 4 of the Bulli Seam Operations Project Approval (such as those for noise, surface water, air quality and greenhouse gas and waste) may also be applicable. 5.3.1 Noise The NSW DECCW Interim Construction Noise Guidelines (ICNG) recommends the following standard hours of work. Monday to Friday 7am to 6pm Saturday 8am to 1pm No work on Sundays or Public Holiday Under the Guidelines, work conducted outside standard construction hours requires: A strong justification for the work being done at this time; Application of all feasible and reasonable work practices to meet a noise level of RBL + 5dBA; and Where this level cannot be achieved, negotiation with the community. Most service boreholes are constructed and operated in locations somewhat remote from urbanised areas. As such, extension of construction and operational hours during Saturday afternoons is required to complete the tasks as quickly as possible and to make efficient use of scarce construction equipment and personnel. Drilling steered boreholes requires specialist equipment and techniques that generally require 24/7 operations. Accordingly, it is proposed to construct and operate the project in accordance with the hours listed in Table below. Table 1: Construction and operation hours of the Project Activity Construction Site establishment of borehole site sites, including drill assembly/setup Hours Monday to Friday 7:00am to 6:00pm. Saturday 8am to 6pm. Revision No: 0 October 2012 Page 6

Activity Establishment of site infrastructure Drilling of boreholes Hours No work on Sundays or Public Holiday Monday to Friday 7:00am to 6:00pm. Saturday 8am to 6pm. No work on Sundays or Public Holiday 24 hours per day, 7 days per week (steered rigs). Operation Services borehole 24 hours per day, 7 days per week Materials borehole Monday to Friday 7:00am to 6:00pm. Saturday 8am to 6pm. No work on Sundays or Public Holiday except in emergencies or where ongoing operational works require borehole operation (e.g. concrete pours). Materials transport Monday to Friday 7:00am to 6:00pm. Saturday 8am to 6pm. No transport on Sundays or Public Holiday except in emergencies or where ongoing operational works require borehole operation (e.g., concrete pours) The operational noise (amenity, intrusiveness and project specific noise level) criteria for potentially affected receivers will be developed for each service borehole location unless relevant criteria are already specified in Conditions 4.1-4.4 of the Bulli Seam Operations Project Approval for that location. Application of all feasible and reasonable work practices (such as the erection of sound barriers) will be implemented to reduce noise levels below the relevant criteria where necessary. These noise management actions will be described in the site specific noise management plan. However if Illawarra Coal has a written negotiated noise agreement with the landowner and potentially affected neighbours, and a copy has been forwarded to the Department of Planning and Infrastructure and Environment Protection Authority, then the Illawarra Coal may exceed the noise limits in accordance with the negotiated noise agreement. Revision No: 0 October 2012 Page 7

Figure 1. Drill Rig Directional drilling, such as is occurring above, requires 24/7 operations and greater amounts of infrastructure. Where possible sites are selected to use natural contours to shield noise from any residences and/or noise barriers. 5.3.2 Air Quality Ambient air quality performance standards are specified in Conditions 4.7 4.9 of the Bulli Seam Operations Project Approval. Dust related air quality impacts may occur during the service borehole construction phase primarily due to earth moving and drilling operations. Standard dust suppression operations such as the use of a water cart and minimising the area of disturbed land will be used. Once construction of the service borehole is complete, the disturbed non-operational area will be revegetated. During the operational phase, the majority of service boreholes will have no air quality impacts. Operations such as the supply of ballast and stone dust may generate small quantities of dust. Site specific air quality management actions will be developed, if necessary, for potential dust generating operations. All plant and equipment will be appropriately maintained and operated to minimise exhaust emissions. Revision No: 0 October 2012 Page 8

Figure 2. Dust suppression during construction Where exposed areas have dust potential water trucks will be used for suppression purposes. The frequency of movements will be adjusted based on the activities being undertaken, as well as weather conditions including wind and temperature. 5.3.3 Soil and Water Except as may be expressly provided by an Environment Protection Licence, Illawarra Coal shall comply with section 120 of the Protection of the Environment Operations Act 1997 (POEO Act 1997). As is the industry standard, an Erosion and Sediment Control Plan will be prepared which: Is consistent with the requirements of Managing Urban Stormwater: Soils and Construction manual (Landcom 2004 or its latest version); Identifies activities that could cause soil erosion and generate sediment; Describes measures to minimise soil erosion and the potential for transport of sediment to downstream waters; Describes the location, function and capacity of erosion and sediment control structures; and Describes what measures would be implemented to monitor and maintain the structures over time. A Water Management Plan will be prepared which: Describes where water used for the project will be sourced. Water will generally be sourced in accordance with a Water Access Licence, from a farm dam located on the property, from a mine water supply, or be transported to site from an authorised Sydney Water supply. Describes that all boreholes will be fully lined and grouted to avoid interaction with aquifers; Revision No: 0 October 2012 Page 9

Describes any drilling fluid additives that may be used in the drilling process; Describes that all boreholes will be comprehensively rehabilitated in accordance with prescribed standards once they are no longer required. Erosion, sediment control and water management measures for each service borehole Project will be outlined in the site specific environmental assessment appended to this Management Plan. 5.3.4 Vegetation Potential impacts from most service boreholes are confined to areas within a highly modified and disturbed environment. Where possible, Illawarra Coal will avoid clearing any native vegetation. Service Boreholes are not likely to have a significant impact on any threatened species, population or ecological community through either direct or indirect impacts. A site specific ecological assessment of each service borehole project will be undertaken. Given the nature of service boreholes it is considered unlikely that any significant ecological values will be impacted. Therefore, the following performance standards are proposed in regards to vegetation and fauna: All vehicles and machinery be restricted to the proposed access tracks and sites; Avoid shrubs, trees and fallen timber; Minimise clearance of native vegetation, Endangered Ecological Communities or Threatened Species 5.3.5 Cultural Heritage Potential impacts from most Service Boreholes are confined to areas within a highly modified and disturbed environment. Where possible, Illawarra Coal will avoid clearing any cultural heritage sites or places. Aboriginal cultural heritage issues will be assessed in accordance with the NSW Minerals Industry Due Diligence Code of Practice for the Protection of Aboriginal Objects. Where any Aboriginal sites are known to occur, specific management measured will be developed to avoid or minimise impacts on these sites. Registered Aboriginal Stakeholders will be provided site assessments and management prescription for their consideration prior to commencement of the service borehole construction. 5.4 BHP BILLITON AND OTHER POLICIES AND STRATEGIES BHP Billiton operates in accordance with Group Level Documents which covers all operational aspects and activities of its business and the standards which prescribe the mandatory environmental performance requirements that support the aspiration of zero harm across BHP Billiton. The HSEC Management System framework is consistent with internationally recognised standards. It aims to set benchmarks for the Company s diverse range of businesses to Revision No: 0 October 2012 Page 10

develop and implement their own HSEC Management Systems, to provide auditable criteria for these systems and to provide a basis from which to drive continuous improvement. The Environmental Management Plan has been developed consistent with the principles of the HSEC Management Standard and Environment Standard. Illawarra Coal maintains an environmental management system which is certified to ISO14001 standard and the BHP Billiton Environmental Standard (GLD.009) 6 CONSULTATION 6.1 LANDHOLDER AGREEMENTS Illawarra Coal will seek an Agreement with all landholders whose property will be accessed for the proposed works. The Agreements will detail: Periods during which Illawarra Coal may access the land; Indicative location, size and details of works proposed on the property and any land to be utilised; Any conditions to be adhered to by Illawarra Coal at the request of the landholder; Any compensation to be paid to any landholder; The manner of resolving any dispute arising in connection with the arrangement; And any other matters agreed to between Illawarra Coal and the landholder. 6.2 COMMUNICATION AND CONSULTATION PLAN A communication and consultation plan will be prepared and implemented for service borehole sites to provide effective and timely communication of key messages to support the approval process and to provide opportunity for stakeholder input to design and operation. 6.2.1 Stakeholders Affected landowners/occupiers; BSO Community Consultative Committee (BSO CCC); Douglas Park Advisory Panel (DPAP); Relevant local government council such as Wollondilly Shire Council; Elected representatives; Illawarra Coal employees; The wider Illawarra Coal community (Wollondilly); BHP Billiton Metallurgical Coal External Affairs. Preferred Stakeholder notification sequence All communication will occur in a sequence which aims to maintain and secure relationships with all key stakeholders. 1. Affected landowners/occupiers; 2. BSO CCC/DPAP; Revision No: 0 October 2012 Page 11

3. Elected representatives; 4. Local Government council; 5. The wider Illawarra Coal community in the BSO area of operation; 6. Media; 7. Illawarra Coal employees; 8. BHP Billiton Metallurgical Coal External Affairs. 6.2.2 Communication and Consultation Aim of initial communication: To provide timely information to key stakeholders regarding the any proposed service borehole and to incorporate input from key stakeholder to design and operation where practicable. The following steps will occur in the order as listed and as described in Table 2. Meetings with affected landowners input received and agreement reached and signed; Briefing note and holding statement to be prepared for internal approval; Meeting with relevant Local Government Council briefing provided on Illawarra Coal s activities in the region and specifics of service borehole proposal; BSO CCC & DPAP notified of project and feedback sought; Coalition News article. Table 2: Communications Plan Letter Coalition News Briefing Note and Holding Statement Presentation Slides Meeting Public Notice Advertisement Email BSO CCC / DPAP Local Govt Council Elected representative Illawarra Coal community Landowners/ Occupiers Employees Broader public CSG External Affairs Revision No: 0 October 2012 Page 12

7 ENVIRONMENTAL ASSESSMENT A comprehensive Environmental Assessment (EA) will be undertaken for each new service borehole. These EA s will identify, investigate and justify a range impacts relevant to the service borehole. These EA s will generally include (where relevant): Surface Water; Groundwater; Air Quality; Greenhouse Gas; Terrestrial Flora and Fauna; Cultural Heritage; Noise; Traffic. The site specific EA s and management prescriptions to manage the identified environmental issues will be progressively appended to the generic Service Borehole Management Plan as required. A list of relevant references and standards that may be applied in any environmental assessment is included in Section 9. 7.1 OVERVIEW OF GENERAL MANAGEMENT MEASURES Table 3 below summarises the general management measures applicable to the construction, operation and rehabilitation of service boreholes. These will be reassessed on a site by site basis. Table 3: Overview of impacts and management measures Impact Surface Water Management Measures The work sites will be well maintained and include appropriate surface water control measures to direct flow and reduce runoff velocity. The sites will include sediment filters or fences and will direct clean water around the work area. Water will be supplied in accordance with Water Access Licence, on site farm dam, or from an authorised Sydney Water supplier. Any bulk materials stored on the surface (e.g. fuel, soluble oils) will be stored in suitable tanks/bunds to prevent any contamination of surface waters. Any polluted surface waters will either; Be captured on site and treated to an acceptable standard to discharge to the environment. Preferably, discharge will be to surrounding well vegetated paddocks, rather than directly to waterways. Illawarra Coal will comply with s120 of the Protection of the Environment Operations Act or in accordance with an Environment Protection Licence; Be captured on site then transported to an appropriately licensed facility for treatment and/or discharge. Groundwater The drilling process will use water of high quality to minimise any chance of pollution of ground water. The proposed boreholes will be cased (e.g. steel or fibreglass) and grouted to prevent cross contamination of aquifers. Drilling sumps will be compacted to minimise interaction with shallow groundwater. Where possible, above ground sumps or mud handling systems will be used. Additives to drilling water (e.g. Superfoam, Potassium Chloride, drilling muds) may be used in small quantities and do not cause contamination of aquifers during drilling operations. No BTEX drilling fluids will be used. Revision No: 0 October 2012 Page 13

Impact Management Measures Boreholes will be plugged and rehabilitated including well capping, grouting and removal of surface infrastructure. Air Quality The following measures will reduce dust escape from works areas: Watering of exposed areas and spraying of excavations, operational areas; Removal of replacement of stockpiled soil without undue delay; Full or partial enclosure of product stockpiles. In some instances, product (e.g. stone dust) may be stored in silos. Modification, reduction or stoppage of dust generating activities during high wind. GHG Emissions The following measures will reduce GHG emissions: Use of well serviced machinery and plant; Use of modern equipment that is energy efficient. Terrestrial flora and fauna Clearing of native vegetation will be avoided where possible by locating service boreholes in cleared areas. Native vegetation disturbance will be minimised. Any screen plantings and rehabilitation planting will use native vegetation endemic to the area. Cultural heritage Locations containing cultural heritage will be avoided when possible and will be protected when this is not possible, by implementing the following measures: Mark locations of Aboriginal sites on all relevant site plans and work instructions; Site to be separated by a physical barrier from construction activities; Construction vehicles to be confined to designated access tracks and works areas. Noise The following measures will reduce impacts of noise: Select sites remote or naturally shielded from residential receivers; Install noise screens around any drilling rigs located in direct site to receivers; Consult with impacted noise receivers to determine suitable noise management measures to mitigate impacts; Program the loudest of the installation works away from the period 1-6pm on Saturdays; Manage the period Saturday 1pm-6pm (non-standard hours) so that works are restricted to the quietest practicable activities being undertaken; Use well maintained equipment; Manage the site so as to minimise/reduce need for trucks to reverse, therefore having their reversing alarm sound. Waste Visual Amenity Public Safety Site Rehabilitation Waste will be reused, recycled or disposed of appropriately as per regulatory requirements. Noise panels will be painted green to reduce visual impacts. Visual treatments to buildings or vegetation screens will be implemented where necessary. Project sites will be fenced temporarily during the Construction Phase, with permanent fencing installed during the Operations Phase, to restrict site access from the public or livestock. Access to sites will be via designated roads/ tracks and a Traffic Management Plan will be established prior to the commencement of works. Communication will occur with any landholders potentially affected by service borehole projects to minimise any interactions or other safety risks. Boreholes will be back filled and appropriately sealed. All work areas will be rehabilitated with appropriate pasture or native plant species following completion of works. In general, potential environmental impacts from service boreholes are relatively minor and localised, and all of the impacts are managed by relatively standard techniques or implantation of contemporary standards. Revision No: 0 October 2012 Page 14

8 REHABILITATION, MONITORING AND REPORTING Rehabilitation of the service boreholes and ancillary infrastructure will be undertaken soon after the cessation of the operation of the borehole. Rehabilitation of the service borehole will: Comply with all regulatory requirements set out in the Bulli Seam Operations Project Approval and other legislation with regards to rehabilitation management and monitoring; Ensure BHP Billiton environmental and other relevant Strategies and Policies are met and upheld; Implement progressive rehabilitation of temporary construction-phase impacts associated with construction operations; Rehabilitation of all areas at the completion of operations; Outline monitoring and performance evaluation measures that are practical; and Provide procedures associated with reporting the results of the monitoring. The following sections provide some background and details on the management measures required to ensure rehabilitation is undertaken progressively during the construction phases of the project, as well as final rehabilitation once works are completed. 8.1 LEGISLATIVE AND OTHER REQUIREMENTS 8.1.0 Legislative Requirements Legislation applicable to rehabilitation management includes but is not limited to: Mining Act 1992; Mining Amendment Act 2008; Environment Planning and Assessment Act 1979 (EP&A Act); Protection of the Environment Operations Act 1997; Water Management Act 2000. 8.1.0.1 Mining Lease Requirements Bulli Seam mining operations are governed by Consolidated Coal Lease (CCL) 767 and 724. In accordance with both CCL s it is required that, upon completion of operations, BHPBIC rehabilitate the subject area and establish vegetation to the satisfaction of the Minister and other relevant stakeholders. 8.1.0.2 Project Approval Conditions Schedule 4, Consent Condition 31 of the Bulli Seam Operations Project Approval states the Rehabilitation Objective for Project Surface Infrastructure is: To be decommissioned and removed, unless the Executive Director Mineral Resources agrees otherwise. Schedule 4, Consent Condition 31 of the Bulli Seam Operations Project Approval requires that The Proponent shall carry out the rehabilitation of the site progressively, that is, as soon as reasonably practicable following disturbance. Condition 4.22 of the Bulli Seam Operations Project Approval requires that this Service Boreholes Management Plan include details of the proponent s commitments regarding (g) Rehabilitation of disturbed sites. This document has been prepared specifically to comply with the Bulli Seam Operations Revision No: 0 October 2012 Page 15

Project Approval consent condition above. 8.1.1 Guidelines and Standards A number of guidelines and standards exist which govern and inform the mine closure and rehabilitation process. BHPBIC will always refer to the appropriate Standards and Guidelines available at the time. At present, relevant guidelines include: EDG01 Borehole Sealing Requirements on Land; EDG03 Guidelines to the Mining Rehabilitation and Environmental Management Process MREMP Guideline; Mine Rehabilitation Leading Practice Sustainable Development Program for the Mining Industry (Commonwealth of Australia); Mine Closure and Completion Leading Practice Sustainable Development Program for the Mining Industry (Commonwealth of Australia); Strategic Framework for Mine Closure (ANZMEC); Other relevant DRE NSW guidelines; Appropriate BHPBIC guidelines and procedures. 8.1.2 Proposed Closure Approach This rehabilitation and closure concept will be based on: The pre-existing environment of the proposed works; Management measures and criteria proposed in existing Environmental Management Plans; as well as Current legislation, guidelines and approvals. Site specific Environmental Management Plans for proposed service boreholes will address aspects of the progressive rehabilitation to be undertaken during the Construction and Operation Phases of the Project. The extent and scope of final rehabilitation/closure works will be more clearly defined closer to the end of the Operation Phase in consultation with landowners. However, the default position is to rehabilitate the disturbed sites to its pre-project landform and land use. 8.1.3 Post-Construction Rehabilitation 8.1.3.1 Timing of Construction and Rehabilitation Construction works will initially be focused on the access tracks, drill pads and pipelines. The amount of clearing undertaken during construction will be minimised to reduce the project footprint at any time and subsequently the area that requires rehabilitation. Where possible, rehabilitation works will be staged progressively to improve the ongoing aesthetics and environmental condition of the site, as well as limit the amount of rehabilitation required post-construction. The types of rehabilitation works that can be undertaken progressively during the Construction Phase will include: Rehabilitation of the disturbed areas alongside the access roads; Top soiling and spray grassing of drill pad batters; Rehabilitating of any Construction Phase disturbance areas once they are no longer required; Remove equipment and temporary infrastructure as it is no longer required. Revision No: 0 October 2012 Page 16

Progressive rehabilitation of the above items will include the stabilisation, re-shaping and revegetating of exposed areas. Exposed areas will typically be revegetated with spray grass. Figure 3. Construction phase rehabilitation During construction activities the maximum footprint will be exposed to enable construction of roadways and borehole construction pads. As soon as practical the exposed areas will be reduced to enhance stability and improve aesthetics. At the completion of the Construction Phase the remaining rehabilitation activities will be undertaken, including: Removing drilling equipment and temporary infrastructure not required during the operational phase; Rehabilitation of any remaining Construction Phase disturbance areas including drilling sumps and some of the drill pad area; Rehabilitating the surface of buried pipeline routes. Expected outcomes of the rehabilitation are outlined in the following sections. 8.1.4 Collection of Materials Materials for rehabilitation will be stored throughout the Construction Phase. This includes topsoil which will be stockpiled on site. 8.1.5 Post-Construction Infrastructure & Landscape Rehabilitation Outcomes At the completion of the Construction Phase, rehabilitation works associated with the sites of the proposed works will have been undertaken. At this time, the following outcomes should have been achieved: 8.1.5.1 Access Road Verges and Internal Roads As sections of road are completed the exposed verges will be shaped to facilitate controlled runoff and minimise the potential for erosion. These verges will be spray grassed to further assist in stabilising soils and to improve aesthetics. Revision No: 0 October 2012 Page 17

When any internal roads required for the Construction Phase are no longer required they will also be rehabilitated by re-shaping to fit the existing landscape and then spray grassed. However, access to the boreholes will still be needed for the operational phase. 8.1.5.2 Top soil stockpiling It is likely topsoil will be required to enable pasture to establish on access track and drill pad verges. Topsoil will generally be sourced from site as it will be stockpiled whenever clearing works are undertaken. Figure 4. Topsoil storage. Topsoil stored for final rehabilitation will be revegetated and, once vegetation is established, temporary sediment controls removed. 8.1.5.3 Removal of Infrastructure Throughout the Construction Phase a number of pieces of infrastructure and equipment will need to be stored on site. Temporary infrastructure will include demountable buildings and sheds which will be required for people, equipment and materials. As parts of the construction are completed some of these facilities will no longer be required and therefore will be removed from site as appropriate. Once drilling has been completed and the rig has been removed the construction area will be able to be reduced to the remaining infrastructure and the area outside the reduced footprint can be rehabilitated. 8.1.5.4 Drilling sumps Drilling sumps will be: Drained and all contaminated or unsuitable fill material removed or treated as appropriate; Backfilled with suitable fill material and/or material as appropriate; Revision No: 0 October 2012 Page 18

Re-profiled and compacted to create a final landform with non-erodible sustainable grades and no pooled areas, as close as possible to the original topography and/or consistent with the surrounding area; Topsoiled and revegetated (if access requirements allow). 8.1.5.5 Pad consolidation Drill pads will be: Consolidated to an area sufficient for borehole infrastructure; Fenced to provide security from people or livestock; Topsoiled and revegetated where access is not longer required for operational purposes. 8.1.6 Post-Construction General Rehabilitation Outcomes 8.1.6.1 Removal of Infrastructure At the completion of service borehole operations, all site and transmission/reticulation infrastructure will be removed. Boreholes All boreholes will be plugged with cement based grout to avoid any cross contamination or interference with aquifers. Plugging will be undertaken in accordance with EDG01 Borehole Sealing Requirements on Land: Coal Exploration. Prepared by Mineral Resources New South Wales Environmental Management Guidelines for Industry. NSW Department of Mineral Resources, 1 December 1997. The borehole will be removed approximately 2m below ground level. Landform Establishment Infrastructure pads will be contoured to match the pre-project landform, unless otherwise requested by the landowner or infrastructure owner. Pasture Establishment The re-contoured area will be covered with top soil and then spray grassed with a pasture mix. All disturbed land will be revegetated to a self supporting and stable landform. 8.1.7 Final Land Use Objectives At this stage it is anticipated that post-rehabilitation land use for the service borehole sites would be rural agricultural as that is the pre-existing use at most potential sites. However this is subject to the legislative, stakeholder and landowner requirements at the time of rehabilitation. 8.1.8 Monitoring & Reporting 8.1.8.1 Construction Phase During the Construction Phase the Approvals Advisor (Surface) and/or site Project Manager will ensure weekly inspections are undertaken to determine the success of management measures in place for aspects including sedimentation, erosion, and vegetation. These inspections will incorporate criteria extracted from key commitments in Environmental Management Plans. Criteria will include: Erosion controls in are in place and maintained to prevent erosion; Minimisation of cleared areas and the undertaking of progressive rehabilitation where appropriate; Revision No: 0 October 2012 Page 19

Soils are separated and stockpiled to enable reuse for rehabilitation works. In general the success of rehabilitation will be determined by achieving ground cover sufficient to provide a stable, non-erodible land surface that does not require routine maintenance. 8.1.8.2 Operation Phase During the Operation Phase the environment and community responsibilities for the project site will be managed by the Environment Manager/Advisor. By the Operation Phase the cleared footprint will have been reduced as the extended construction area will have been progressively rehabilitated during the Construction Phase. During the Operation Phase the rehabilitation monitoring required for the sites will have reduced significantly. Inspections will continue to be undertaken of the site and general maintenance of drainage facilities, vegetation and weed management will occur. 8.1.8.3 Project Completion At the completion of the Operation Phase final rehabilitation for the sites will occur. Inspections will continue to be undertaken of the site and general maintenance of drainage facilities, vegetation and weed management will occur until the site is deemed to be stable and self supporting. 8.1.8.4 Reporting Rehabilitation reporting will be in accordance with the consent conditions of the Bulli Seam Operations Project Approval. Rehabilitation programs undertaken for the prior year and expected for the following year will be reported in the Annual Review. 8.2 ENVIRONMENTAL MONITORING Monitoring that is described in Environmental Management Plans developed in accordance with the requirements of Schedule 4 of the Bulli Seam Operations Project Approval (such as those for noise, surface water, air quality and greenhouse gas and waste) may also be applicable. 8.2.1 Noise Due to the short term nature of the Construction Phase and the significant mitigation measures that will be implemented, it is not proposed to conduct attended noise monitoring for most service boreholes unless complaints are received. If any noise complaints are received by BHPBIC in regard to construction or operational aspects of this project, then attended noise monitoring will be undertaken to determine if additional mitigation measures will be implemented. Revision No: 0 October 2012 Page 20

Where service boreholes are co-located with more significant surface mine infrastructure (e.g. pit tops, upcast vent shafts) then regular noise compliance monitoring will be undertaken in accordance with the BSO Noise Management Plan. Figure 5. Noise barriers Noise barriers will be installed where projects may have impact on any adjacent residences. 8.2.2 Water The drilling water sumps or tanks will be inspected on a weekly basis as well as after every significant storm and rainfall event (i.e. >10mm in a 24hour period) to ensure the sumps continue to operate satisfactorily and to perform any maintenance work and repairs that may be required. Regular monitoring and maintenance will include: Weekly inspection of site drainage and erosion/sediment controls Repairs of areas which may become unstable following periods of high rainfall; and Checks on sump wall and liner integrity to ensure no leakage of water. Treatment and disposal of drilling fluid additives will be managed on a site by site basis. Illawarra Coal generally selects drilling fluid additives that have no/low levels of toxicity and are environmentally benign. No BTEX based drilling fluids are used. Where any stormwater is captured on site, monitoring for ph, Electrical Conductivity and turbidity will generally be implemented before any water is released to the environment. Site specific discharge limits will be proposed where water is discharged directly to waterways. Where water is captured and is required to be transported offsite for treatment or disposal, then a monitoring system will be implemented to ensure that the tank does not overflow. Specific water quality and flow monitoring requirement may be necessary. Revision No: 0 October 2012 Page 21