METHOD STATEMENT for INSTALLATION OF MICROPILE

Similar documents
Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction

SCOPE OF WORK FOR PILING JOB

PILING PART-VI CONSTRUCTION AND INSTALLATION OF RCC BORED CAST IN-SITU PILES

STANDARD SPECIFICATION FOR MICROPILE CONSTRUCTION

MUD ROTARY TECHNIQUES. MUD Rotary Drilling Method 12/11/2017. Roger E. Renner, MGWC MUD ROTARY DRILLING. Rotary Well Rig

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

A. Installer Qualifications: A firm shall have a minimum of five projects successfully constructed in the last ten (10) years.

Diaphragm wall Construction

ITEM 416 DRILLED SHAFT FOUNDATIONS Materials. All materials shall conform to the requirements of the pertinent items as follows:

Combined Pile Foundation System for a Residential Complex

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar

B. Extent of the Work: The Work specified in this Section shall include, but is not limited to, the following principal items:

SECTION DRILLED CONCRETE PIERS AND SHAFTS

Supervision of Piling Works

ITEM NN17 - DRILLED SHAFTS ITEM NN17 - DRILLED SHAFTS (LOW OVERHEAD CLEARANCE) ITEM TRIAL SHAFTS

Drilling of grout holes will be measured for payment on the basis of the linear feet of holes actually drilled.

CHAPTER III METHODS AND MATERIALS

Micropile Lateral Load Testing in the Charleston, SC Area

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS

SECTION CHAIN LINK FENCES AND GATES (PARK)

Assisting Energy Savings While Protecting 2009 REVISIONS TO GUIDELINES FOR THE CONSTRUCTION OF VERTICAL BOREHOLES

Drilled Shaft. Inspection. HQ Construction Office HQ Geotechnical Division

SAFE SYSTEMS FOR PILING OPERATIONS

Lesson 7 REINFORCING CAGE. Version 1-1/

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

STANDARD SPECIFICATION Section Auger-Grout Injected Piles Civil Engineering Group Revised: August, 2000

Specialising in Ground Engineering & Slope Stabilisation

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SPECIAL SPECIFICATION 4492 Tie Back Anchors

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

TP EA. Product Description. Properties and Benefits. Applications. Reaction Resin Mortar Based on Epoxy Acrylate. Approvals / Certificates:

Hilti HIT-RE 100 mortar with rebar (as anchor)

Construction. Injectable hose for sealing construction joints in watertight structures. Product Description. Product Data. Tests.

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Requirements for Measuring and Pricing of Structural Concrete

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

Construction. Universal anchoring adhesive. Product Description 1 1/7. Product Data Sheet Edition _1 Sika AnchorFix -S

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR BUY AMERICA

Quality Assurance Review for Bridge Construction

REINFORCED CONCRETE MASONRY SECTION

TERWA REBAR CONNECTION COUPLERS. CARES Technical Approval 5058 TA1B

CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS

Injectable hose with integral valves for sealing construction joints in watertight structures

CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS

Multi-Institutional Academic Health Science & Research Center Evansville, IN

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors

ISO INTERNATIONAL STANDARD. Building construction machinery and equipment Terms and definitions

Construction Technology B (CON4313)

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

Deep Foundation. Deep Foundation Applications

Injectable hose for sealing construction joints in watertight structures

PROPERTY TEST OF CONCRETE ISOLATORS

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

Hilti HIT-CT 1 post installed rebars

DESIGN AND CONSTRUCTION OF HEAVY INDUSTRIAL ANCHORAGE FOR POWER-PLANTS

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

Vibrating Wire Concrete Stress Cell User Manual

SECTION DRILLED CONCRETE PIERS AND SHAFTS

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4.

Construction. Injectable hose with integral valves for sealing construction joints in watertight structures. Product Description. Product Data.

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

Sealing products. The new Generation of sealing-products

SPECIAL INSPECTION AND TESTING AGREEMENT

Range Point Monuments

Construction. Injectable Hose for Sealing Construction Joints in Watertight Structures. Product Description. Tests. Product Data

SikaProof Bentonite Plastic DPM overlap - Compacted Backfill Scale 1:5. Detail no: SB01 - Nov 2013

Mechanical Engineer of Record: (Smoke Control Systems Only) Name & License Company. Others: Responsible Party Name & License Company

SECTION REINFORCING STEEL

TECHNICAL DATA SHEET SIKA ANCHORFIX-1 GREY 300ML (6's)

SECTION COLD-FORMED METAL FRAMING

Section REINFORCING STEEL

PC HOUSE FOR INCHEON BRIDGE PILE-CAP

Concreting (UNDER CONSTRUCTION)

WALL CANTILEVER WORK STATION JIB CRANE

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

MasterFlow 928T. High strength, non-shrink cementitious grout

Misan University - College of Engineering Civil Engineering Department

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

Project report on a deep well construction

TORQUE TESTING & INSTALLATION INSPECTION OF DRILLED - IN ANCHORS

TECHNICAL MANUAL. PEC Column Shoe. Heavy-duty Bolted Column Connections

Installation Guidelines for Flygt Pumps Pump Anchoring Recommendations

TERWA REBAR CONNECTION COUPLERS

.1 ANSI/ASME B31.1, Power Piping, (SI Edition)..2 American Society for Testing and Materials (ASTM)

TECHNOLOGY. Hydromill

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

SECTION GEOTECHNICAL INSTRUMENTATION

SECTION TIMBER FLOATS

Injectable hose with integral valves for sealing construction joints in watertight structures

SECTION CONCRETE PAVING

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS

STATEMENT OF SPECIAL INSPECTION FORM

Transcription:

METHOD STATEMENT for INSTALLATION OF MICROPILE A. MATERIAL TO BE USED 1. Grout Grout shall be mixed from Ordinary Portland Cement and clean water free from harmful substances. Usage of other cement which has a higher strength and/or workability shall also be allowed. 2. Grout Mix The proportions of grout and the minimum strength of work cubes shall comply with the following requirements : Range of water/cement ratio Target Resistance to crushing 0.42-0.50 (cube strength) 7 days 28 days (Typically 0.45) 21 N/mm 2 30 N/mm 2 The quantities of cement in the mix shall be measured by weight. The grout shall be free from segregation, slumping and bleeding. Grout shall be mixed on site and shall be pumped into its final position as soon as possible. Non-shrink admixture (SIKA Intraplast-Z TM ) shall be added at approximately 1% by weight. 3. Grout Test Two sets of three test cubes shall be taken per one grouting operation for testing purpose. Three test cubes shall be tested at 7 days and the remaining cubes at 28 days after casting. The characteristic strength of the grout shall be 21 N/mm 2 and 30 N/mm 2 at 7 days and 28 days.

4. Main Load Bearing Component Reinforcing Steel The main steel component and the grout shaft of the micropile shall be designed to support the external loads and bending to be transmitted to/from the load bearing stratum for end-bearing/tension piles, which shall consist of a top anchorage or pilecap (provided by the structural/pilecap contractor) and an axial steel component. Typical axial steel component consisting of hot rolled deformed high tensile bar with minimum yield stress of 460 N/mm 2 or API Pipe. B. FABRICATION OF MICROPILE API Pipes 1. If API Pipes are used, they shall be joint by either a pipe sleeve (screw-type) or fully butt-welded all around (see installation procedure). 2. Spacers consist of a small piece of steel plate tag-welded onto the pipe at 3m intervals, each interval in 2 direction or using PVC spacers adhered using epoxy or tie wire. Reinforcement Bars 1. The reinforcement of the piles are typically prefabricated on-site or elsewhere and brought to site. The bars and links are tied together with tie wire to form prefabricated cages. 2. To join the lengths of the cages, the reinforcement bars shall be lapped 40 times the diameter or 40D. The joining of the bars (if necessary) shall be done by tie wire or welding. 3. Spacers used shall be PVC pipes cut into small lengths and tied to the reinforcement bars. Alternatively, ready-made PVC round spacers can be clipped to the links. A second alternative consist of PVC lantern which is clipped to the main-bars.

C. METHOD FOR DRILLING / MICROPILE INSTALLATION STEP 1 : The pile point is determined by a surveyor and position the drill rig on top of the point. The first drill rod with a drill bit is placed above the drill point. Ensure verticality is achieved before starting drilling works. This is done by checking the verticality of both the first drill rod and the mast using a spirit level.

STEP 2 : DTH Hammer Drilling Technique For drilling in both soft and/or hard soils (typically SPT N>50), the hole can be drilled with the wash boring method using either using wash boring or using the DTH hammer. For drilling into soils and weathered rock above the solid rock formation, the down-the-hole hammer will also be employed. Depending on the behaviour of soil encountered on-site, the borehole may be temporarily cased. Upon reaching rock or firm soil strata, drilling can be continued without casing. Drilling in rock shall be done by the Down-the-Hole (DTH) pneumatic hammer method, used for hard rock formation. The system employs a pneumatic self-actuating hammer at the end of the drill rod that strikes the drilling surface while the drill rod is slowly rotated. An air compressor will be used for powering the hammer. The air used to drive the hammer as the hole is advanced removes cuttings continuously.

STEP 3 : Upon completion of the drilling, the borehole is cleaned by flushing out any soil particles from the inside of the casing with recirculation water or air. API pipes installation : - If a mobile crane is to be used for, move the drilling rig back. The pipe shall also be lowered segment-by-segment using a mobile crane. Cordon the area for safety reasons. If the drilling rig winch is to be used, lift the pipes up segment-by-segment using the winch. Cordon the area for safety reasons. The joints of the API Pipe, if present, shall be properly screwed together with grease to assist the tightening. If welding is used, clean the edge of the pipe and conduct a full butt-weld all over the outside of the API pipe.

STEP 4 : If in Step 3, the mobile crane is used to install the API Pipes, the same mobile crane can be used to pull/withdraw the temporary casing. Shall this cannot be done due to safety reasons (crane parked too far away), move the drill rig back. Withdraw the casing using the winch tied around the casing. Shall this be unsuccessful, reattach the adaptor and using the reverse circulation method (wash boring), flush water into the casing to loosen it while withdrawing the casing using the rotary unit.

STEP 5 : Mix the cement bag with water in a mixer according to the design mix measurement. The mixed grout shall be filtered and poured into a holding tank. Grouting of the micropile is then carried out by tremie method using a hose installed right up to the end tip of the pile rebar assembly cage or API Pipe with flow holes cut at the tip of the API pipe. Pump the grout into the pile using a piston or diaphragm pump.grouting is done until neat grout appears at the top of the borehole. Upon completion, the grout hose is extracted. Shall any leftover temporary casing is extracted, or at any time after grouting, the grout level drops below the cut-off level, top-up the hole with grout.